TECHNICAL_SPECIFICATIONS_FOR_SPORTS_COURT_RESURFACING.docx

DOCX document 20 KB Posted

Attached to
Sports Court Resurfacing (Bid Discount)
Solicitation number
26-P-00204
Issued by
Hillsborough County, Florida

About this file

This is a Technical Specifications document for Sports Court Resurfacing issued by the City of Tampa Parks & Recreation Department for municipal athletic facilities throughout the community. The City maintains an inventory of over 200 courts including basketball, tennis, pickleball, and racquetball facilities constructed of concrete or asphalt. The scope of work encompasses surface preparation, crack and low-area patching, application of 100% acrylic resurfacer and color coats fortified with silica sand, restriping of playing lines according to sport-specific standards, replacement or refinishing of net posts and sleeves as needed, and fiberglass overlay repairs for courts requiring structural repair. The sealed bid submission deadline is 3:00 p.m. on Thursday, April 23, 2026, with award to be made within 120 days of bid opening. The contract term is one year from the effective award date with options for two additional one-year renewal periods by mutual written agreement, plus the City's unilateral right to extend for up to three additional 30-day periods, with annual price escalation thereafter limited to the previous year's Consumer Price Index change. Bidders must provide evidence of a permanent place of business, adequate equipment inventory, current contracts with references, at least three references from similar projects completed within the past three years, documented key personnel qualifications, and proof of adequate financing.

This procurement is reserved exclusively for certified Small Local Business Enterprises (SLBEs) located in the City of Tampa, with a five percent bid discount (not to exceed $10,000) applied for evaluation purposes only. An additional two percent evaluation discount is available for bidders voluntarily complying with criminal history screening practices outlined in City Code Section 2-285. The estimated project value is $250,000. Mandatory insurance requirements include Commercial General Liability of $1 million per occurrence and $2 million aggregate, Automobile Liability of $1 million, and Workers' Compensation as required by Florida law, with the City named as additional insured. Final acceptance of the awarded contractor's work triggers a 90-day warranty period covering materials and workmanship, excluding structural cracking. The City's SLBE Availability Contact List identifies one certified vendor, Apsis Construction LLC, located in Tampa, Florida, as eligible to bid on this opportunity.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATIONS FOR SPORTS COURT RESURFACING

1. GENERAL

1.1 DESCRIPTION OF WORK Furnish all materials, equipment and labor as necessary for the preparation of existing court surfaces, patching of low areas and cracks, application of acrylic concrete adhesion promoter coat (one coat, concrete courts only), application of primer/resurfacer (one coat) and color/texture (two coats), restriping of playing lines, replacement of post sleeves when needed, replacement of net posts when needed or priming and painting of net posts if not replaced, and re-attachment of existing nets where needed, as specified herein. Based on court condition by mutual agreement of Awardee and City Representative, courts requiring fiberglass overlay repairs will require fiberglass overlay material and additional application of primer/resurfacer coats and associated labor as needed to embed fiberglass material, as specified herein. Based on posts and/or post sleeves condition by mutual agreement of Awardee and City Representative, courts requiring post replacement and/or post sleeve replacement will require additional materials and labor, as specified herein. Posts and post sleeves shall be replaced in pairs on same court.

1.2 DEFINITIONS The following words and terms or pronouns used instead shall wherever they appear in these specifications, be construed as follows, unless a different meaning is clear from the context: “Final Acceptance” shall mean that point in time when all requirements of project drawings and specifications are complete, including any punch list items, to the satisfaction of the City of Tampa representative. The awardee shall be notified in writing of final acceptance by a City of Tampa representative. “Warranty Period” shall be a 90-day beginning at Final Acceptance. Warranty shall apply to materials and workmanship except for reopening of structural cracks or new structural cracking. It is understood that resurfacing cannot address structural cracks, new or existing.

1.3 QUALITY ASSURANCE The work shall be by a single firm specializing in sports court resurfacing.

1.4 BIDDER SUBMITTALS

1.4.1 Bidder shall furnish, with their bid, evidence in writing that they maintain a permanent place or places of business.

1.4.2 Bidder shall provide a list to demonstrate that they have adequate equipment; a list of owned and/or leased equipment that is available to be used on this award.

1.4.3 Bidder shall provide a list of current contracts, their value, and a contact person with phone number & email address, with each firm.

1.4.4 Bidder shall provide at least three references who can verify work of a similar nature done by your firm in the last three years. Must include contact person with phone number & email address with each reference.

1.4.5 Bidder shall provide a list of key personnel and a brief summary of their qualifications, which are to provide services under this award.

1.4.6 Bidder shall have adequate finances to provide the specified services, City Representative may request proof, if needed. Failure to provide the listed material may cause the Bidder to be deemed non-responsive. The City also reserves the right to solicit references in making judgment on any Bidder’s ability to perform said services.

1.5 AWARDEE SUBMITTALS Awardee shall submit the following prior to commencing with the work:

1.5.1 Submit schedule showing scheduled dates for each aspect of the work two weeks prior to beginning work.

1.5.2 Submit manufacturers or vendors data substantiating that materials comply with specified requirements.

1.6 DELIVERY, STORAGE AND HANDLING Deliver materials in original, unopened, and undamaged containers showing weight, analysis, and name of manufacturer. Store in manner to prevent deterioration.

1.7 JOB CONDITIONS

1.7.1 Work notification: Notify the City Representative at least seven working days prior to start of work.

1.7.2 Protect existing utilities, paving, irrigation, landscaping, fencing, site furnishings, and other facilities from damage caused by resurfacing operations. Awardee shall verify all above ground utility locations prior to the start of work. Notify the City Representative of any unsatisfactory conditions or pre-existing damage on site prior to the start of work. Start of work will indicate acceptance of conditions and full responsibility of completed work. Awardee is responsible for repairing any damage done by court resurfacing process.

1.7.3 Examine the existing courts, verify the existing playing lines of each individual court’s based on the sport(s) played on that court, observe the conditions under which the work is to be completed, and examine unsatisfactory conditions before proceeding with the work. Any question by the Awardee on court condition that requires repair using fiberglass overlay method, replacement of tennis post sleeves, or replacement of tennis posts shall be brought to the attention of the City Representative prior to the ordering of materials, and such repairs shall only proceed upon mutual agreement by Awardee and City Representative. Any question by the Awardee regarding a specific court’s usage and subsequent striping needs shall be clarified with the City Representative prior to starting work. Some courts may require additional striping for alternative sports or underage sports.

2. MATERIALS

2.1 MATERIALS

2.1.1 City Representative shall approve all products to be used prior to starting to work.

2.1.2 Primer/Resurfacer Coat: 100% acrylic resurfacer of pigmented concentrated emulsion fortified with silica sand (60-80 mesh).

2.1.3 Color/Texture Coat: 100% acrylic color fortified with silica sand (60-80 mesh). Color(s) as noted in 3.3 INSTALLATION.

2.2 ACCESSORIES

2.2.1 Refer to specifications for accessories specifically used on this project. City Representative shall approve all products to be used prior to starting work.

2.2.2 Herbicide: An herbicide to remove all grass and weeds on the sports courts. Herbicide shall be applied in a liquid medium to penetrate into cracks and along court edges. Treat all courts per manufacturer’s recommendation.

2.2.3 Patch Mix: Provide acrylic patch mix to remove low places and fill cracks.

2.2.4 Concrete Promoter: 100% acrylic concrete adhesion promotor. Only required for concrete courts.

2.2.5 Fiberglass Overlay: 10x20 resin coated fiberglass mat as overlay material.

2.2.6 Striping Paint: 100% acrylic striping paint fortified with silica sand (60-80 mesh) for playing lines.

2.2.7 Net Post Primer and Paint: Rust-Oleum Professional High Performance Enamel primer spray and paint spray. Primer color to be Gray. Paint color to match existing posts (Hunter Green (flat/matte) or Black (flat/matte)). Coordinate color with City Representative prior to ordering.

2.2.8 Net Post Sleeves: Galvanized post sleeves to match existing. Coordinate style and size with City Representative prior to ordering and installing sleeves. Replace both sleeves.

2.2.9 Net Posts: Standard tennis net posts to match existing posts. Coordinate style, size, and color with City Representative prior to ordering and installing new posts. Posts shall be polyester powder-coating – color to be determined per existing court posts. Replace both posts.

2.2.10 Fill Dirt: Naturally occurring, reasonable well-graded soil with organic content of less than 5%, pH range between 5.5 and 7.6, reasonably free of rocks and gravel. Material should pass 100% through a 75mm screen, 50% through a 2mm screen and 20% through a 0.075mm screen.

2.2.11 Concrete: Portland Cement ANSI/ASTM C 150, Type I (fly ash is permitted) with normal weight aggregate ANSI/ASTM C 33 from a single source. Reinforcement shall be synthetic fiber reinforcement such as Fibermesh® 150 or approved equivalent at the rate of 1 ½ pounds of material per cubic yard of concrete, mixed in accordance with mixing time and speed of ASTM C 94 to ensure uniform distribution and random orientation of fibers throughout concrete. Concrete shall have compression strength of 3000 psi within 28 days.

2.2.12 Asphaltic Concrete: Type S-III. Conform to FDOT Standard Specifications for Road & Bridge Construction, current edition. 17 9.2.13 Asphalt Tack Coat: Type RS-1 or RS-2 or approved equal. Conform to FDOT Standard Specifications for Road & Bridge Construction, current edition. Tack coat to be applied as a binder to compacted base layer prior to application of asphaltic concrete. 10. EXECUTION

3.1 INSPECTION

Awardee shall examine the sports court(s) and surrounding area. Do not start work until unsatisfactory conditions are corrected, and until extent of repair needed (need of fiberglass overlay, replacement of tennis posts sleeves or replacement of tennis court posts) and extent of restriping (based on sports to be played on the court(s)) have been clarified with City Representative. Any pre-existing damage to site or surrounding areas shall be documented by the Awardee. Failure of Awardee to document pre-existing damage(s) on site may result in an expectation by the City of Tampa that the damages are the result of the resurfacing work and as such would need to be repaired by Awardee.

3.2 PREPARATION

3.2.1 Remove and store existing nets, if applicable.

3.2.2 Remove all grass and weeds. Wash courts to remove all dirt, oil, mildew, and foreign matter. Treat cracks and edges with herbicide per manufacturer’s recommendation to inhibit future organic growth.

3.2.3 Machine sand court to remove crack edges and minor elevations.

3.3 INSTALLATION

3.3.1 If tennis post sleeves require replacement (by mutual agreement with City Representative), Awardee shall remove existing posts (store as needed) and excavate existing sleeves and footers. Remove only enough court area to access footer and conduct removal and replacement of same. Compact subgrade under replacement footer to 95% density per AASHTO-T-180. Install new sleeves per manufacturer’s recommendation with appropriate footer (18” diameter round at top tapering down to square bottom minimum 30” per side, and minimum 42” deep overall). Repair court as indicated below based on existing court surfacing material.

3.3.1.1 For concrete courts, top of footer shall be level with court playing surface. Add any necessary fill dirt between edge of footer and underside of court, and compact to 95% density. Top of added fill dirt shall be level with bottom of undisturbed court when compaction is complete. Place sufficient depth concrete as needed over compacted fill dirt to match level of existing court and new footer. Court area immediately adjacent to sleeve shall be repaired to smooth, level surface after sleeve replacement is complete.

3.3.1.2 For asphalt courts, top of footer shall be ¾” below level of court playing surface. Add any necessary fill dirt between edge of footer and underside of court, and compact to 95% density. Top of added fill dirt shall be level with existing compacted soil level under layer of crushed subgrade material beneath asphalt layer when compaction is complete. Add layer of crushed material to match existing base layer under asphalt and compact as needed: top of crushed material shall be level with bottom of undisturbed court when compaction is complete. Apply tack coat over compacted base layer and concrete footer as a binder prior to application of asphaltic concrete. Add sufficient depth of Type S-III Asphaltic Concrete over compacted base to match level of existing court and cover top of concrete footer. Court area immediately adjacent to sleeve shall be repaired to smooth, level surface after sleeve replacement is complete.

3.3.2 All cracks shall be scraped and ground. All cracks of 1/8” width or more shall be patched with an acrylic patch mix and leveled with surrounding area.

3.3.3 Flood courts with water. After one hour, any areas with water still standing with a depth of 1/16” or more shall be patched with an acrylic patch mix.

3.3.4 Machine sand all patched areas and low areas (“bird baths”) to a smooth level surface.

3.3.5 For concrete courts only, apply one coat of acrylic concrete adhesion promoter over the entire court surface.

3.3.6 Over the entire court surface, apply one coat of acrylic resurfacer fortified with silica sand to provide leveling and filler coat for succeeding color coats.

3.3.7 For courts that do not require a fiberglass overlay, apply two texture/color coats of multi-purpose acrylic fortified with silica sand over entire court surface, to provide a tough, durable, textured sport surface. Court colors shall be as follows: tennis courts shall have dark blue court areas with green out-of-bounds areas; multi-purpose courts shall have dark green courts with maroon keys at the goal post areas and beige out-of-bounds areas (if present). If existing court colors differ from this color scheme, confirm desired court color(s) with City Representative prior to ordering color coat material.

3.3.8 If fiberglass overlay method is required, place fiberglass material using a minimum of two additional coats of acrylic resurfacer fortified with silica sand over entire court surface. Adjacent panels shall be overlapped a minimum of 3”. Wrinkles in the fiberglass material shall be corrected prior to application of the acrylic resurfacer. Completely mask and embed fiberglass material to hide the texture of the fiberglass membrane. Apply two texture/color coats of multipurpose acrylic fortified with silica sand over fiberglass overlay layer. Court colors shall be as noted in INSTALLATION 3.3.6.

3.3.9 According to the governing body of the sport(s) to be played on the surface, accurately locate, mark, and paint 2” wide playing lines using acrylic paint fortified with silica sand, as clarified by Awardee for each individual court with City Representative prior to start of work. Standard playing lines for adult players shall be white in color on all courts for all sports. Playing lines for alternative sports and underage sports, such as Pickleball or Under 10 tennis courts (as identified by City Representative), shall be light blue in color.

3.3.10 If existing net posts are not being replaced, prepare net posts as needed for priming and painting per manufacturer’s recommendation. Apply one coat of spray primer. Cover with two costs of spray paint, color to match existing posts. Allow first coat to dry per manufacturer’s recommendation prior to application of second coat. Allow posts to dry thoroughly.

3.3.11 Install new net posts if existing posts are mutually agreed by Awardee and City Representative to require replacement. Re-install existing net posts, if removed for sleeve replacement and in acceptable condition. Reinstall existing nets, if applicable.

3.4 ACCEPTANCE

3.4.1 Inspection to determine acceptance of court resurfacing work will be by the City of Tampa Representative upon Awardee’s request. Provide notification at least three working days before requested inspection date.

3.4.2 The City Representative will prepare a “punch list” of those items which must be corrected before re-inspection for final acceptance. The Awardee shall have no more than a one-week time period in which punch list items must be corrected. Provide 48-hour notification of need for re-inspection.

3.4.3 The City Representative shall notify the Awardee in writing of Final Acceptance; at which time the warranty requirements shall apply.

3.5 WARRANTY Awardee shall warrant materials and workmanship for 90 days after Final Acceptance.

3.6 CLEANING

3.6.1 Perform cleaning daily during installation and upon completion of the resurfacing work. Remove from site all excess materials and equipment. Do not leave uninstalled materials or equipment on site overnight unless arrangements have been made to do so with the City Representative. Repair damage resulting from resurfacing operations.

3.6.2 Keep adjacent walkways open and free of debris at all times.