This Technical Specifications document outlines the requirements for the Marylhurst Sanitary Sewer Pump Station Rehabilitation project in Oregon. The project encompasses the replacement of electrical components, mechanical piping, and submersible pumps, along with the installation of a valve vault for an aging sanitary pump station. The Engineer's estimate for the project is $410,300.00, establishing the baseline budget for construction activities. The specifications detail the technical requirements and performance standards that contractors must meet when executing the rehabilitation work at this critical wastewater infrastructure facility.

The technical specifications establish the quality standards, equipment specifications, and installation procedures required for all project components. Contractors bidding on this work must demonstrate compliance with the outlined technical requirements for electrical systems, mechanical piping systems, pump installations, and valve vault construction. The specifications serve as the binding technical document that governs how contractors must execute the work and ensures that all rehabilitated infrastructure meets established industry standards and local regulatory requirements for sanitary sewer pump station operations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 10 00 – PAGE 1

SECTION 01 10 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

A. This Summary of Work supplements and amplifies certain sections of the City of West Linn Public Works Standards, General Conditions and Supplementary General Conditions. The City of West Linn Public Works Standards, General Conditions and Supplementary General Conditions shall apply except as modified herein. This Summary of Work and additional Technical Special Provisions may contain occasional requirements not pertinent to the project.

However, these specifications shall apply in all particulars insofar as they are applicable to this project.

1.2 DEFINITIONS AND APPLICABLE STANDARD SPECIFICATIONS AND PLANS

A. Definitions:

1. Wherever used in this Summary of Work or other Technical Special Provisions, the following terms have the meanings indicated which are applicable to both the singular and plural thereof.

2. OWNER: Refers to City of West Linn, a municipal corporation of the State of Oregon, with whom CONTRACTOR has entered into the Contract and for whom the work is to be performed. OWNER is also hereinafter referred to as CITY.

3. CITY: Refers to City of West Linn, a municipal corporation of the State of Oregon, with whom CONTRACTOR has entered into the Contract and for whom the work is to be performed. CITY is also hereinafter referred to as OWNER.

4. CONTRACTOR: Refers to person, firm or corporation with whom the OWNER has entered into the construction and installation Contract.

5. ENGINEER: Refers to Century West Engineering Corp, 5500 Meadows Road, Suite 250, Lake Oswego, Oregon 97035, (503) 419-2130, by whom the Project has been designed.

6. TECHNICAL SPECIFICATIONS: Refers to these specifications included in Appendix B, Technical Special Provisions. TECHNICAL SPECIFICATIONS is also hereinafter referred to as TECHNICAL SPECIAL PROVISIONS, and vice-versa.

B. Applicable Standard Specifications and Plans

1. The following references apply except as may be modified herein. In the case of discrepancy, unless noted otherwise herein, the more restrictive provisions shall apply.

2. City of West Linn, Oregon, "2018 Update, City of West Linn Public Works Standard Construction Specifications”.

SECTION 01 10 00 – PAGE 2

3. 2024 edition of the Oregon Standard Specifications for Construction, Oregon Department of Transportation, herein referred to as “Standard Specifications”.

4. Most current edition of the Oregon Standard Drawings and Details, Oregon Department of Transportation, herein referred to as “Standard Plans”.

1.3 CONTENTS

A. Section Includes:

1. Work covered by Contract Documents.

2. Site access.

3. Work by Owner or other Work at the Site.

4. Owner-furnished products.

5. Future work.

6. Work sequence.

7. Permits.

8. Specification conventions.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. Work of the Project includes removal and replacement of pumps, valves, piping, pump controls, and electrical components of the Marylhurst Sewer Pump Station and Cedaroak Sewer Pump Station. Work will also include installation of a new valve vault, connection to existing piping, bypass pumping, surface restoration, and related work. The project location and each separate Contract Bid Schedule are as indicated on the Drawings.

B. The defined Work elements are a general outline of principal features of the Work and does not in any way limit the responsibility of the Contractor(s) to perform all Work and furnish all equipment, labor and materials required by the Contract Documents.

1.5 SITE ACCESS

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings and as indicated by requirements of this Section.

B. Use of Site: Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

SECTION 01 10 00 – PAGE 3

1.6 WORK SEQUENCE

A. Construct Work in phases during construction period. Coordinate construction schedule and operations with Owner:

1. Phase 1: Marylhurst Sewer Pump Station.

2. Phase 2: Cedaroak Sewer Pump Station.

B. Sequencing of Construction Plan: Before start of construction, submit three copies of construction plan regarding phasing of demolition and new Work for acceptance by Owner.

After acceptance of plan, construction sequencing shall comply with accepted plan unless deviations are accepted by Owner in writing.

1.7 PERMITS

A. Unless provided for otherwise in these Contract Documents, all permits, licenses, and fees shall be obtained by the Contractor and all costs shall be borne by the Contractor. Contractor shall pay all plan check fees and other fees necessary to obtain permits and shall accommodate special inspections required thereof. Contractor shall be responsible for compliance with all permit provisions and shall accommodate all special inspections required thereof, all at no additional expense to the Owner beyond prices as bid.

1. Traffic control permit.

1.8 SPECIFICATION CONVENTIONS

A. These Specifications are written in imperative mood and streamlined form. This imperative language is directed to Contractor unless specifically noted otherwise. The words "shall be" are included by inference where a colon (:) is used within sentences or phrases.

1.9 PREVAILING WAGE RATES FOR PUBLIC WORKS CONTRACTS IN OREGON

A. The Contractor shall abide by ORS 279C.800 through 279C.870 which relate to the prevailing wage rates for the building and construction trades in the State of Oregon. These prevailing wage rates are shown in the Bureau of Labor and Industries document which is included elsewhere in these contract documents.

1.10 OREGON PRODUCTS

A. Contractor's attention is directed to the provisions of Oregon Law, ORS 279A.120 regarding the preference for products that have been manufactured or produced in Oregon. Contractor shall use Oregon-produced or manufactured materials with respect to common building materials such as cement, sand, crushed rock, gravel, plaster, etc., and Oregon-manufactured products in all cases where price, fitness, availability, and quality are otherwise equal.

1.11 USE OF EXPLOSIVES

A. The use of explosives shall not be allowed on this Project. Alternative methods of excavation shall be utilized.

SECTION 01 10 00 – PAGE 4

1.12 CONTAMINATED MATERIAL

A. General

1. It is possible that the Contractor may encounter contaminated material (soil and/or water) during excavation activities. This specification identifies requirements for handling and disposing contaminated media.

B. Definitions

1. “Contaminated material” is defined as soil, water, free product, Underground Storage Tanks (UST), buried abandoned utility lines containing residual or free product, solid waste, treated wood waste, chemical containers, or other solid, liquid, or gas substances with contamination levels above background levels.

2. “Hazardous substances” shall mean those substances or materials defined in the ORS 465.200, as amended.

3. “Release” shall have the meaning as defined in ORS 465.200, as amended.

4. “Environmental laws” shall mean any applicable statute, law, ordinance, order, consent decree, judgment, permit, license, code, covenant, deed, common law, treaty, convention, or other requirement pertaining to protection of the environment, health or safety, natural resources, conservation, wildlife, waste management or disposal, hazardous substances, or pollution, including but not limited to regulation of releases to air, land, water, and groundwater.

C. Execution

1. Discovery of Contaminated Material

a. In the event that the Contractor, during the course of construction or during any other activities authorized under this contract, should encounter suspected contaminated material or any other materials suspected of posing a threat to human health and the environment, the Contractor shall notify the Engineer immediately and manage according to requirements identified below.

2. Discovery of Contaminated Soil

a. Contractor shall note evidence of contamination (odor, visual staining of soil, free liquid product seeping from soil, sheen on groundwater, etc.) and note location of evidence on a sketch of the excavation and provide to the Engineer.

b. Contractor shall report the discovery to the Engineer immediately. Contractor shall stop all excavation activities and secure the site to prevent entry by the public. The excavation shall not be backfilled. Protect all open excavations with berms, plates, and fencing. Contractor may continue with work in other non-contaminated areas.

c. Contractor shall assist Engineer in collecting sample(s) of suspected contaminated media for testing and characterization. Contractor shall allow 21 days, at no cost to

SECTION 01 10 00 – PAGE 5

Owner, for testing, results, and instructions as to how to proceed with contaminated materials.

d. The Contractor shall obtain a copy of an approved soil disposal/acceptance permit (Disposal/Treatment Facility requires transporter to have a copy of the permit.)

e. Contractor will transport and dispose of contaminated material at an approved disposal/treatment facility.

f. Contractor shall provide the Engineer with a copy of the contaminated soil disposal receipt.

3. Handling of Contaminated Soil

a. After approval from the Engineer, excavate the soil in a manner that prevents commingling of contaminated and non-contaminated soil. Engineer will make determination (based on soil saturation) if contaminated soil can be directly transported to a treatment or disposal facility, or if soil needs to be stockpiled to reduce water content. Engineer will determine when stockpiled soil can be transported off-site.

b. Contractor will be responsible for stockpiling contaminated soil in containers or on impervious surface to prevent the spread of contamination. Any water runoff from the contaminated soil stockpile area(s) must be contained by Contractor and handled as contaminated water.

c. Minimize movement of excavation equipment over or through contaminated soil to prevent movement of contaminated soil into areas where no contaminated soil exists.

d. Stockpiles will be created on an approved site and shall be surrounded by a fence to limit access. The stockpiles must be covered and bermed during periods of rainfall to prevent run-on and run-off. The stockpiles shall be covered with a minimum 10-mil high density polyethylene (HDPE) plastic during periods of strong winds, nightfall, over the weekends, or during extended work stoppages. If dust is observed coming from the stockpiles, the stockpiles shall be either covered or the dust controlled with water.

e. Maintain excavation equipment in good working order. Prevent spillage of oil, fuel, or hazardous substances from equipment. In particular, promptly repair oil leaks from equipment and clean up any contaminated soil.

4. Transport of Contaminated Materials

a. Contractor shall comply with all applicable Federal, State, or local laws, codes, and ordinances that govern or regulate contaminated substance transportation.

Contaminated soils placed in stockpiles shall be loaded into trucks in a manner that prevents the spilling or tracking of contaminated soil into areas of the site with uncontaminated soil. Loose material falling onto the exterior of the truck during loading shall be removed before the truck leaves the loading area. Any material collected in the loading area shall either be placed back into the truck or back into the stockpile. If loading areas are unpaved, the surface soil shall be sampled at the conclusion of the loading activities to confirm that contaminated soil is not present. If loading areas are paved, any loose soil shall be cleaned from the pavement at the conclusion of the loading activities.

b. Specific truck haul routes shall be established before beginning off-site contaminated media transport. On-site truck routes shall be established to minimize or prevent movement of trucks over contaminated soils. Off-site truck routes shall be established

SECTION 01 10 00 – PAGE 6

to reduce the risk of releases of contaminated soils and impact on local traffic. The Contractor shall be responsible for ensuring that loaded truck weights are within acceptable limits. All trucks shall be covered before they leave the loading area.

c. The Contractor shall ensure that all drivers of vehicles transporting contaminated substances have in their possession during transport all applicable Oregon State and local vehicle insurance requirements, valid driver's license, and vehicle registration and license. The Contractor shall be responsible for informing all drivers of transport vehicle about:

1) The nature of the material transported.

2) Required routes to and from the off-site thermal treatment or disposal facility.

3) Applicable County street regulations and requirements, and State of Oregon Department of Transportation codes, regulations, and requirements.

4) The County's requirement for proper handling and transportation of the substances.

d. The Contractor shall not allow contaminated substances to be spilled or tracked off-site at any time during the Project. Trucks used for the transportation of contaminated substances off-site shall be watertight, substance compatible, licensed, insured, and permitted pursuant to federal, state, and local statutes, rules, regulations, and ordinances.

e. If contaminated media is discarded prior to removal of contaminated material, the price per cubic yard of soil materials and price per 100 gallons of contaminated water will be negotiated with Owner.

1.13 WORK WITH EXISTING ASBESTOS WATER PIPELINES

A. The Contractor shall comply with all requirements of the State of Oregon, Department of Environmental Quality (DEQ) with respect to the safe handling, removal, and disposal of asbestos cement pipe, including all reporting requirements.

1.14 INADVERTENT DISCOVERY PLAN FOR CULTURAL RESOURCES

A. The Contractor shall follow this Inadvertent Discovery Plan (IDP) if cultural material including human remains are encountered during construction. In addition to the requirements below, the Contractor shall comply in all respects to the requirements of Oregon Department of Transportation (ODOT).

SECTION 01 10 00 – PAGE 7

B. The IDP for the Project is as follows:

1. Protocol for Coordination in the Event of Inadvertent Discovery

a. In the event of an inadvertent discovery of possible archaeological materials, all work will stop immediately in the vicinity of the find.

b. The area will be secured and protected.

c. The ODOT Archaeologist and Resident Project Representative (RPR) will be notified.

The Archeologist or RPR will notify the appropriate authorities which shall be the State Historic Preservation Office (SHPO). If possible human remains are encountered, the SHPO and the Clackamas County Coroner will be notified immediately. The RPR will then notify the SHPO and the appropriate Tribes. Contact names and numbers are as follows:

1) State Historic Preservation Office: Dennis Griffin, Archeologist – 503-986-0674

2) Clackamas County Coroner: 971-673-8200

d. No work may resume until the City’s Archeologist is on site and able to assess the situation.

e. If human remains are encountered, do not disturb them in any way. Do not call 911.

Do not speak with the media. Secure the location. Do not take photos.

f. The City’s Archeologist will consult with the SHPO, who will then contact the appropriate Tribal Governments and determine an appropriate course of action.

g. Additional archeological excavations may be required. This work will be handled on a case-by-case basis by the City’s Archaeologist in consultation with the SHPO and appropriate Tribes.

2. When to Stop Work

a. Construction work may uncover previously unidentified Native American or Euro- American artifacts. This may occur for a variety of reasons but may be associated with access restrictions during project development, or if the area contains impervious surfaces throughout most of the Project area which would have prevented standard archaeological site discovery methods.

b. Work must stop when the following types of artifacts and/or features are encountered:

1) Native American artifacts may include (but are not limited to):

a) Flaked stone tools (arrowheads, knives, scrapers, etc.)

b) Waste flakes that resulted from the construction of flaked stone tools.

SECTION 01 10 00 – PAGE 8

c) Ground stone tools like mortars and pestles.

d) Layers (strata) of discolored earth resulting from fire hearths. May be black, red, or mottled brown and often contain discolored cracked rocks or dark soil with broken shell

e) Human remains

f) Structural remains- wooden beams, post holes, fish weirs

2) Euro-American artifacts may include (but are not limited to):

a) Glass (from bottles, vessels, windows, etc.)

b) Ceramic (from dinnerware, vessels, etc.)

c) Metal (nails, drink/food cans, tobacco tins, industrial parts, etc.)

d) Building materials (bricks, shingles, etc.)

e) Building remains (foundations, architectural components, etc.)

f) Old wooden posts, pilings, or planks (these may be encountered above or below water)

g) Even what looks to be old garbage could very well be an important archaeological resource

h) Remains of ships or sea-going vessels, marine hardware, etc.

i) Old farm equipment may indicate historic resources in the area

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

SECTION 01 22 20 – PAGE 1

SECTION 01 22 20

UNIT PRICE MEASUREMENT AND PAYMENT

A. Measurement and payment will be on a unit price basis in accordance with the prices set forth in the proposal for individual work items. Where work is required but does not appear as a separate item in the proposal, the cost for that work shall be incidental to other unit prices named in the proposal. Contractor shall make a careful assessment when preparing the bid.

1. Mobilization: Payment for mobilization will be made at the contract lump sum amount for the item “Mobilization” and shall include costs of mobilization, bonds, insurance, and demobilization. The amounts paid for mobilization in the contract progress payment will be based on the percent of the original contract amount that is earned from other contract items, as follows:

a. When 5 percent is earned, either 50 percent of the amount for mobilization or 5 percent of the original contract amount, whichever is the least.

b. When 10 percent is earned, either 100 percent of the amount for mobilization or 10 percent of the original contract amount, whichever is the least

c. When all work is completed, amount of mobilization exceeding 10 percent of the original contract amount.

1) This schedule of mobilization progress payments will not limit or preclude progress payments otherwise provided by the contract.

2. Erosion Control: Payment for installation and maintenance of approved temporary and permanent erosion and sedimentation control (ESC) devices (including sediment fencing, inlet protection, bio filter bags, wattles, and other items as required), including all labor, materials, and equipment, will be on a lump sum basis.

3. Temporary Work Zone Traffic Control: Payment for traffic maintenance and protection, flagging, temporary fencing, and safety barricades, including all coordination, materials, and equipment, as required, will be on a lump sum basis.

4. Demolition: Payment for demolition shall be on a lump sum basis, and shall include removal and disposal of all items called out for demolition or removal as show in the contract drawings. Handling and disposal of asbestos material and/or asbestos-cement (AC) pipe shall be incidental to this work.

5. Excavation, Trenching and Backfill: Payment for excavation, trenching and backfill shall be made on a lump sum basis. Payment shall include all labor, materials, and equipment necessary to excavate, backfill, and compact earthen materials and aggregates to the limits and depths as needed for demolition of existing facilities and construction of new facilities as indicated in the contract drawings.

6. Temporary Sewer Bypass: Payment for temporary sewer bypass shall be made on a lump sum basis. Payment shall include all labor, materials, and equipment necessary to establish, operate, and maintain a temporary pumping system for the purpose of diverting existing sewage flow around work area for the duration of the work.

SECTION 01 22 20 – PAGE 2

7. Valve Vault: Payment for furnishing and installing valve vault(s) shall be on a per each basis. Payment shall include all labor, materials, and equipment to furnish, install, and adjust the valve vault and appurtenances including the access hatch, pipe penetrations, pipe supports, bracing, aggregate bedding, and all other items necessary for a complete and functioning installation, and not included in other bid items.

8. Top Slab Replacement: Payment for furnishing and installing a replacement top slab shall be on a per each basis. Payment shall include all labor, materials, and equipment to remove and dispose of the existing top slab, and furnish and install the top slab and appurtenances including the access hatch, and all other items necessary for a complete and functioning installation, and not included in other bid items.

9. Submersible Sewage Pump Replacement: Payment for furnishing and installing new submersible sewage pumps and appurtenances shall be made at the unit price per each pump installed. Payment shall include all labor, materials, and equipment to furnish, install, and adjust the submersible sewage pump and appurtenances including the discharge elbow, slide rails, lifting chain, mounting hardware, and all other items necessary for a complete and functioning installation, and not included in other bid items.

10. Mechanical Piping: Payment for furnishing and installing mechanical piping and appurtenances shall be made on a lump sum basis. Payment shall include all labor, materials, and equipment to furnish, install, and test mechanical piping as indicated on the contract drawings, including pump discharge piping, valves, joints, fittings, hardware, supports, bracing, and all other items necessary for a complete and functioning installation, and not included in other bid items.

11. Painting and Coating: Payment for painting and coating shall be on a lump sum basis, and shall include furnishing and applying paint and/or coating systems as indicated on the contract drawings. Surface preparation, environmental controls, testing, and disposal of waste materials shall be incidental to this item.

12. Level 2, ½-inch Dense HMAC Pavement: Payment for permanent HMAC replacement surfacing shall be on a per square yard basis. Payment for HMAC resurfacing shall include furnishing and installing the compacted aggregate base materials, tack coat, asphaltic concrete, compaction, process control, acceptance testing, and other incidental work required to provide permanent HMAC pavement as shown on the Drawings and specified in Section 32 12 16, Asphaltic Concrete Pavement. 6 inch “T” cut and 4 inches minimum asphalt thickness on city streets.

13. General Surface Restoration: Payment for general surface restoration other than streets, including stripping and stockpiling topsoil, regrading to original contours, bark mulching planting areas, and cleanup following construction as required including resurfacing gravel surfaces as required, will be on a lump sum basis

14. General Electrical: Payment for General Electrical shall be on a lump sum basis, and shall include full pay for all work to furnish, install, and test all electrical equipment and related items as indicated in the Electrical Specifications. Demolition and disposal of removed electrical components shall be incidental to this item.

SECTION 01 31 00 - PAGE 1

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.01 SUMMARY

A. Section includes the preconstruction conference, construction scheduling and coordination requirements.

B. Costs associated with project management and coordination are incidental to the contract work and are included in the contract unit and lump sum costs.

1.02 PRE-CONSTRUCTION CONFERENCE AND PROGRESS MEETINGS

A. Prior to beginning construction, but following contract award, the Contractor, Subcontractors and other interested parties must participate in a Preconstruction Conference.

B. Periodically throughout the contract performance period, the Contractor and

Subcontractors shall avail themselves to project progress meetings. These meetings shall be held as often as the parties determine is necessary, but will be at least once each week (weekly).

C. Representatives from the following shall attend each meeting:

1. Prime Contractor

2. Subcontractors

3. Contracting Officer

4. Project Engineer and Inspector

5. Owner Project Manager

D. Contractor is responsible for notifying Subcontractors of meeting time and date.

E. Meeting Minutes:

1. Meeting Minutes will be recorded, typed up in a memorandum and distributed to all attendees by the Project Engineer.

2. Any attendee may question or challenge the content of the meeting minutes, in writing to the Project Engineer, prior to the next project meeting. If the meeting minutes are unchallenged, they will be accepted as an accurate representation of the meeting discussions and decisions.

3. Challenges will be resolved as “old business” at the subsequent project progress meeting.

SECTION 01 31 00 - PAGE 2

1.03 CONSTRUCTION SCHEDULE

A. Present three original signed copies to the contracting officer a written preliminary construction schedule in the form of a “critical path” diagram or equivalent chart showing the following as a minimum (all times referenced to calendar dates):

1. activity

2. activity description

3. duration

4. early start

5. early finish

6. latest start

7. latest finish

8. total float for that activity

B. Provide enough detail to allow the Engineer to evaluate work progress both on-site and off-site.

C. Review of the schedule by the Engineer shall not constitute endorsement of the Contractor’s approach, means, methods sequences or procedures nor shall it constitute assignment of the Contractor’s responsibility to provide superintendence and project management.

D. Provide the Engineer with a revised schedule whenever major changes occur to the schedule.

1.04 WEEKLY ACTIVITY SCHEDULE

A. Provide the Engineer with a written weekly activity schedule (facsimile or email is acceptable) indicating planned activities, locations, and approximate schedules.

B. Note the planned visits by manufacturer’s representatives, testing firms, or other site visitors that may be of significance to the Engineer.

C. Provide the weekly activity schedule to the engineer by noon on the last day of the workweek for activities during the following week.

SECTION 01 33 00 – PAGE 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

A. This Section contains administrative and procedural requirements for submittals for review, information, and for Project closeout.

B. Section includes:

1. Schedule of Submittals.

2. Submittal requirements.

3. Submittal procedures.

4. Engineer review.

5. Resubmittal procedures.

6. Product data.

7. Shop Drawings.

8. Samples.

9. Design data.

10. Test reports.

11. Certificates.

12. Manufacturer's instructions.

13. Manufacturer's field reports.

14. Erection Drawings.

15. Construction progress schedules.

16. Breakdown of contract price.

17. Construction photographs.

18. Operation and maintenance (O&M) instructions.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action.

B. Informational Submittals: Written and graphic information and physical Samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements.

1.3 SCHEDULE OF SUBMITTALS

A. Within 10 days after the Effective Date of the Contract, Contractor shall submit to Engineer a preliminary Schedule of Submittals, including proposed list of major products proposed for use, with specification section reference, name of Manufacturer, supplier, trade name, subcontractor, and model number of each product. Provide a schedule of specific target dates for the submission and return of submittals and shop drawings required by the Contract Documents.

B. For products specified only by reference standards, indicate Manufacturer, trade name, model or catalog designation, and reference standards.

C. The list and schedule shall be updated and resubmitted when requested by the Engineer.

SECTION 01 33 00 – PAGE 2

D. Contractor’s Schedule of Submittals will be acceptable to the Engineer if it provides a workable arrangement for reviewing and processing the required submittals.

1.4 SHOP DRAWING AND SAMPLE SUBMITTAL REQUIREMENTS

A. Before submitting a Shop Drawing or Sample, Contractor shall have:

1. reviewed and coordinated the Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents;

2. determined and verified all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto;

3. determined and verified the suitability of all materials and equipment offered with respect to the indicated application, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work; and

4. determined and verified all information relative to Contractor’s responsibilities for means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto.

B. Each submittal shall bear a stamp or specific written certification that Contractor has satisfied Contractor’s obligations under the Contract Documents with respect to Contractor’s review of that submittal, and that Contractor approves the submittal.

C. With each submittal, Contractor shall give Engineer specific written notice of any variations that the Shop Drawing or Sample may have from the requirements of the Contract Documents.

This notice shall be set forth in a written communication separate from the Shop Drawings or Sample submittal; and, in addition, in the case of Shop Drawings by a specific notation made on each Shop Drawing submitted to Engineer for review of each such variation.

1.5 SUBMITTAL PROCEDURES

A. Contractor shall submit Shop Drawings and Samples to Engineer for review in accordance with the accepted Schedule of Submittals.

B. Transmit each submittal with Engineer-accepted transmittal form certifying compliance with requirements of Contract Documents.

C. Sequentially number transmittal forms. Mark transmittal forms for resubmittals with original number and sequential alphabetic suffix.

D. Show each Submittal with the following numbering and tracking system:

1. Submittals shall be numbered according to specification section. For example, the first product submittal for Section 05 50 00 would be “05 50 00-1”. Resubmittals of that submittal would be “05 50 00-1.1”, followed by “05 50 00-1.2”, and so on. The second product submittal for that Section would be “05 50 00-2”.

2. Submittals containing product information from multiple sections of the specifications will not be reviewed. Contractor and/or their supplier shall divide submittals in a manner that meets the numbering and tracking system requirements stated herein.

SECTION 01 33 00 – PAGE 3

3. Alternative method of numbering may be used if acceptable to Engineer.

E. Identify: Project, Contractor, subcontractor and supplier, pertinent drawing and detail number, and specification Section number appropriate to submittal.

F. Apply Contractor's stamp, signed or initialed, certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is according to requirements of the Work and Contract Documents.

G. Coordinate submission of related items.

1. All shop drawings for interrelated items shall be scheduled for submission at the same time.

2. The Engineer may hold shop drawings in cases where partial submission cannot be reviewed until the complete submission has been received or where shop drawings cannot be reviewed until correlated items affected by them have been received. When such shop drawings are held, the Engineer will advise the Contractor in writing that the shop drawing submitted will not be reviewed until shop drawings for all related items have been received.

H. When hard copies of submittals are provided by the Contractor, six copies of all materials shall be provided to the Engineer. Two copies of reviewed submittals will be kept by the Engineer, two copies of reviewed submittals will be transmitted to the Owner, and two copies of reviewed submittals will be returned to the Contractor. If the Contractor requests that more than two copies of the reviewed submittal be returned, then the Contractor shall submit the appropriate quantity of submittals.

I. When electronic transmittals of submittals are provided by the Contractor under established protocols described elsewhere in the Contract Documents or as jointly developed by the Owner, Engineer and Contractor, provide electronic submittals in portable document format (PDF) in addition to the source document format (Word, Excel, AutoCAD, etc.). Reviewed submittals will be returned to the Contractor as PDF electronic files.

J. For each submittal for review, allow not less than 14 days for Engineer review, excluding delivery time to and from Contractor.

K. Identify variations in Contract Documents and product or system limitations that may be detrimental to successful performance of completed Work.

L. Allow space on submittals for Contractor and Engineer review stamps or comments.

M. When revised for resubmission, the Contractor shall identify changes made since previous submission. A narrative of changes shall be provided, and shop drawings or calculations shall indicate that a revision was made.

N. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with review comments.

O. Submittals not requested will not be recognized nor processed.

P. Incomplete Submittals: Engineer will not review. Complete submittals for each item are required. Delays resulting from incomplete submittals are not the responsibility of Engineer.

SECTION 01 33 00 – PAGE 4

1.6 ENGINEER REVIEW

A. Informational submittals and other similar data are for Engineer's information, do not require Engineer's responsive action, and will not be reviewed or returned with comment.

B. The Engineer’s review of submittals and shop drawings is not a check of any dimension or quantity and will not relieve the Contractor from responsibility for errors of any sort in the submittals and shop drawings.

C. Submittals made by Contractor that are not required by Contract Documents may be returned without action.

D. The Engineer will review the submitted data and shop drawings and return to the Contractor with notations thereon indicating "No Exception Taken", "Make Corrections Noted", "Rejected", "Revise and Resubmit", or "Submit Specified Item".

E. If more than two submissions of an item are required to meet the Project specifications, Contractor shall be responsible for Engineer’s charges to Owner for its review time, and Owner may impose a set-off against payments due to Contractor to secure reimbursement for such charges, unless the need for such change is beyond the control of Contractor.

F. Engineer will provide timely review of Shop Drawings and Samples in accordance with the Schedule of Submittals acceptable to Engineer. Engineer’s review will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents.

G. Engineer’s review will not extend to means, methods, techniques, sequences, or procedures of construction or to safety precautions or programs incident thereto.

H. Engineer’s review of a separate item as such will not indicate approval of the assembly in which the item functions.

I. Engineer’s review of a Shop Drawing or Sample shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Paragraph 1.4.C and Engineer has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample. Engineer will document any such accepted variation from the requirements of the Contract Documents in a Field Order.

J. Engineer’s review of a Shop Drawing or Sample shall not relieve Contractor from responsibility for complying with the requirements of this Section.

K. Engineer’s review of a Shop Drawing or Sample, or of a variation from the requirements of the Contract Documents, shall not, under any circumstances, change the Contract Times or Contract Price, unless such changes are included in a Change Order.

L. Neither Engineer’s receipt, review, return of a Shop Drawing, Sample, or other submittal shall result in such item becoming a Contract Document.

SECTION 01 33 00 – PAGE 5

M. Contractor shall perform the Work in compliance with the requirements and commitments set forth in returned Shop Drawings and Samples, subject to the provisions of Paragraph 1.6.I.

1.7 RESUBMITTAL PROCEDURES

A. Contractor shall make corrections required by Engineer and shall return the required number of corrected copies of Shop Drawings and submit, as required, new Samples for review.

Contractor shall direct specific attention in writing to revisions other than the corrections called for by Engineer on previous submittals.

B. Contractor shall furnish required submittals with sufficient information and accuracy to obtain required review of an item with no more than two submittals. Engineer will record Engineer’s time for reviewing a third or subsequent submittal of a Shop Drawings, sample, or other item requiring review, and Contractor shall be responsible for Engineer’s charges to Owner for such time. Owner may impose a set-off against payments due to Contractor to secure reimbursement for such charges.

C. If Contractor requests a change of a previously reviewed submittal item, Contractor shall be responsible for Engineer’s charges to Owner for its review time, and Owner may impose a set-off against payments due to Contractor to secure reimbursement for such charges, unless the need for such change is beyond the control of Contractor.

PART 2 PRODUCTS

2.1 CONSTRUCTION PROGRESS SCHEDULES

A. Within 10 days after the Effective Date of the Contract, prepare and submit to the Engineer a practicable schedule showing the order in which the Contractor proposes to carry out the Work, the dates on which the important features of the work will start, and the contemplated dates for completing same. A time-scaled bar chart schedule shall include the following:

1. Construction activities

2. Submittal and review of critical material samples and shop drawings

3. Procurement and delivery of critical materials

4. Duration of work, including completion times of all stages and their sub-phases

B. Attention is drawn to typical local climatic weather patterns and Work shall be coordinated accordingly.

C. Complete Project schedule shall be revised and resubmitted to the Engineer at a minimum occurrence of every 4 weeks for review.

D. Three Week Lookahead Schedules: Provide each week at the weekly construction meeting. The previous week’s completed work shall be shown on the schedule for a total of 4 weeks shown.

2.2 BREAKDOWN OF CONTRACT PRICE

A. Within 10 days after the Effective Date of the Contract, submit a complete breakdown of all lump sum bid items showing the value assigned to each part of the work, including an allowance for profit and overhead adding up to the total lump sum contract price. Breakdown of lump sum bids shall be coordinated with the items in the schedule and shall be in sufficient detail to serve as the basis for progress payments during construction.

SECTION 01 33 00 – PAGE 6

B. Engineer will review the contract price breakdown and may request items to be further broken down or for more items be added in order to facilitate tracking of work progress for payment.

C. Preparatory work, bonds, and insurance required in setting up the job will be allowed as a separate entry on the cost breakdown but shall not exceed 5 percent of the total base bid.

D. Upon acceptance of the breakdown of the contract price by the Engineer, it shall be used as the basis for all requests for payment.

2.3 PRODUCT DATA

A. Product Data: Action Submittal: Submit to Engineer for review for assessing conformance with information given and design concept expressed in Contract Documents. Submitted data shall be sufficient in detail for determination of compliance with the Contract Documents.

B. Mark each copy to identify applicable products, models, options, and other data. Supplement Manufacturers' standard data to provide information specific to this Project.

1. Note submittal will be returned to Contractor without review of submittal if products, models, options, and other data are not clearly marked or identified.

C. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

D. After review, produce copies and distribute according to Paragraph 1.5.M and for record documents.

2.4 SHOP DRAWINGS

A. Shop Drawings: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. When required by individual Specification Sections, provide Shop Drawings signed and sealed by a professional Engineer licensed in the state of Project, responsible for designing components shown on Shop Drawings.

1. Include signed and sealed calculations to support design.

2. Submit Shop Drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.

3. Make revisions and provide additional information when required by authorities having jurisdiction.

D. All dimensioned shop drawings shall be scalable and provided as full-sized (22-inch x 34-inch) sheets. PDF electronic files shall print as scalable full-sized sheets.

E. After review, produce copies and distribute according to Paragraph 1.5.M and for record

SECTION 01 33 00 – PAGE 7

2.5 SAMPLES

A. Samples: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Samples for Selection as Specified in Product Sections:

1. Submit to Engineer for aesthetic, color, and finish selection.

2. Submit Samples of finishes, textures, and patterns for Owner selection.

C. Submit Samples to illustrate functional and aesthetic characteristics of products, with integral parts and attachment devices. Coordinate Sample submittals for interfacing work.

D. Include identification on each Sample, with full Project information.

E. Submit number of Samples specified in individual Specification Sections; Engineer will retain one Sample.

F. Reviewed Samples that may be used in the Work are indicated in individual Specification Sections.

G. Samples will not be used for testing purposes unless specifically stated in Specification Section.

H. After review, produce copies and distribute according to this Section and for record

2.6 DESIGN DATA

A. Informational Submittal: Submit data for Engineer's knowledge as Contract administrator or for Owner.

B. Submit information for assessing conformance with information given and design concept expressed in Contract Documents.

2.7 TEST REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge and records as Contract administrator or for Owner.

B. Submit test reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

2.8 CERTIFICATES

A. Informational Submittal: Submit certification by Manufacturer, installation/application Subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or product but must be acceptable to Engineer.

SECTION 01 33 00 – PAGE 8

2.9 MANUFACTURER’S INSTRUCTIONS

A. Informational Submittal: Submit Manufacturer's installation instructions for Engineer's knowledge as Contract administrator or for Owner.

B. Submit printed instructions for delivery, storage, assembly, installation, startup, adjusting, and finishing, to Engineer in quantities specified for Product Data.

C. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

2.10 MANUFACTURER’S FIELD REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge and records as Contract

B. Submit report within 48 hours of observation to Engineer for information.

C. Submit reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

2.11 ERECTION DRAWINGS

A. Informational Submittal: Submit Drawings for Engineer's knowledge and records as Contract

B. Submit Drawings for information assessing conformance with information given and design concept expressed in Contract Documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or Owner.

2.12 OTHER REQUIRED SUBMITTALS

A. Other required submittals include the items listed below. This list is provided for Contractor’s convenience only and may not be complete in all respects. Contractor shall provide all submittals specified or required, whether or not listed here.

1. Contractor Emergency Contact List.

2. Erosion and Sediment Control Plan.

3. Traffic Control and Protection Plan.

SECTION 01 45 00 – PAGE 1

SECTION 01 45 00

QUALITY CONTROL

1.1 DESCRIPTION

A. This Section covers quality control requirements supplementary to those of the General Conditions and Technical Specifications.

1.2 PROVISIONS

A. Contractor’s Responsibility for Testing

1. The Contractor shall be responsible for the cost of all testing as specified in this section.

Additional information has been provided regarding the payment responsibility for the Owner with regards to the Project.

B. Owner’s Right to Perform Additional Tests

1. The Owner or Engineer reserves the right to complete additional testing. In such cases, the Contractor shall provide safe access for the Owner or Engineer and their inspectors to adequately inspect the quality of work and the conformance with Project specifications.

1.3 QUALITY ASSURANCE

A. Testing Requirements

1. An independently owned and operated laboratory approved by the Engineer shall perform all testing as specified herein.

B. Testing

1. General

a. All required testing of work and/or materials shall be conducted in the presence of the Engineer. The Contractor shall provide 48-hour notification to the Owner and Owner’s representative prior to conducting any and all quality assurance testing. Where applicable, work and materials shall only be buried with the consent of the Engineer.

b. Where such inspection and testing are to be conducted by an independent laboratory or agency, the sample, or samples of material to be tested shall be selected by such laboratory or agency or by the Engineer. The Contractor shall furnish such samples of all materials without charge to Owner.

c. The results from any and all tests are made for the information of the Owner.

Regardless of any test results, the Contractor is solely responsible for the quality of workmanship and materials and for compliance with the requirements of the Drawings and Specifications.

SECTION 01 45 00 – PAGE 2

2. Costs of Testing

a. The Contractor shall be responsible for and shall pay for all tests as specified in Part 3 of this Section. Additional information has been provided regarding the payment responsibility for the Owner with regards to the Project.

b. With regards to all materials to be tested, where test results demonstrate that the material or workmanship does not meet the minimum requirements of the Contract Documents, additional testing shall be completed and shall be paid for by the Contractor with no reimbursement by the Owner.

1.4 SPECIAL INSPECTIONS

A. Special inspections and testing as required by Chapter 17 of the IBC shall be conducted by Owner-retained Special Inspectors and Testing Agencies as required and as indicated in the Contract Documents.

1. Special Inspectors and Testing Agencies Responsibilities

a. Verify that manufacturers maintain detailed fabrication and quality control procedures and review the completeness and adequacy of those procedures to perform the Work.

b. Promptly notify Owner and Contractor of irregularities and deficiencies observed in the Work during performance of their services.

c. Submit certified written report of each test, inspection and similar quality control service to Owner, Contractor, and jurisdictional authorities. Interpret test results and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

d. Submit final report of special inspections at Substantial Completion, including a list of…

This is the start of the file's text. The full file is on GovTribe.