TECHNICAL SPECIFICATIONS ARFQ DEP23-64 HULL WELL PLUGGING PACKAGE.pdf
PDF 5 MB Posted
- Attached to
- HULL WELL PLUGGING PACKAGE
- Solicitation number
- ARFQ 0313 DEP2300000064 2
- Issued by
- Taylor County, West Virginia
About this file
This technical specifications document for ARFQ DEP23-64 is issued by the West Virginia Department of Environmental Protection, Office of Oil and Gas, for the plugging and remediation of three abandoned oil and natural gas wells located in Upshur County, West Virginia. The project involves the plugging of wells with API numbers 47-097-03866, 47-097-00007, and 47-097-03864, along with site reclamation and erosion control measures. Two wells are located near Booney Hull Road in Buckhannon (approximately 200 and 300 yards from the road), and one well is located near Slab Camp Road (approximately 350 yards from the road). A pre-bid meeting will be held at a designated location on Slab Camp Road, with detailed driving directions provided from both the Charleston and Clarksburg areas. The scope of work includes well cleanout to total depth, installation of multiple cement plugs at specified depths to isolate water and salt water zones, pulling of various casing sizes, setting permanent monuments, site reclamation, and installation of erosion and sediment control structures in accordance with West Virginia Code 22-6-23 and 22-6-24.
The contract encompasses extensive technical specifications for equipment, materials, and services organized into 38 line items, including rig and crew operations (minimum three-person crew), mobilization and demobilization, heavy equipment (bulldozers and excavators), various specialized tools (power tongs, casing knives, spears, overshotts, mills), cement and gel supplies, waste disposal services, environmental sampling, site reclamation materials, and labor. Work will be performed Monday through Friday with a maximum ten-hour workday, and the Department will obtain all necessary local, state, and federal permits. The contract will be managed by a DEP Project Coordinator assigned at the time of the Notice to Proceed, with the Department confirming daily expenditures and resolving any disputes regarding time and material usage. Contractor invoicing will be submitted upon completion of work, with payment processed following departmental confirmation of daily expenditures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HULL WELL PLUGGING PACKAGE
WEST VIRGINIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
OFFICE OF OIL AND GAS
COUNTY
OF
UPSHUR
Hull WELL PLUGGING PACKAGE
API# 47-097-03866
API# 47-097-00007
API# 47-097-03864
TECHNICAL SPECIFICATIONS
Table of Contents
Table of Contents
I. PROJECT DESCRIPTION
1.0 Location/Site Description
1.1 API# 47-097-03866
1.2 API# 47-097-00007
1.3 API# 47-097-03864
2.0 Directions to pre-bid meeting:
II. SCOPE OF WORK
III. GENERAL CONDITIONS
1.0 Administrative
2.0 Permitting
3.0 Work
IV. PROJECT DESCRIPTION
1.0 Site-based considerations:
1.1 API# 47-097-03866
1.2 API# 47-097-00007
1.3 API# 47-097-03864
2.0 Well-specific considerations:
2.1 API# 47-097-03866
2.2 API# 47-097-00007
2.3 API# 47-097-03864
V. REMEDIATION AND/OR PLUGGING WORK PLAN
1.1 API# 47-097-03866
1.2 API# 47-097-00007
1.3 API# 47-097-00764
VI. TECHNICAL SPECIFICATIONS
1.0 Rig and Crew -Three (3) Man Crew (minimum)
2.0 Mobilization & Demobilization
2.5 Field Move
3.0 Additional Labor
4.0 Vacuum Water Truck
5.0 Heavy Equipment
5.5 Light Duty Equipment
6.0 Power Tongs
7.0 Casing Knife/Ripper
8.0 Casing, Tubing, and Pipe Rentals
9.0 Tri-Cone Drill Bit
10.0 Trash Pump
11.0 On-Site Water Storage Container(s)
12.0 Disposal of Gel
13.0 Disposal of Liquid Waste
14.0 Disposal of Solid Waste
15.0 Aqua Gel
16.0 Cement
17.0 Gravel
18.0 Steel Mud Pit
19.0 Site Reclamation
20.0 Silt Fence
21.0 Monument
22.0 Welder/Cutting Torch
23.0 Oil Absorbent Supplies
24.0 Sand Pump
25.0 Cherry Picker
26.0 Casing/Tubing Spear
27.0 Overshot
28.0 Impression Block
29.0 Subs
30.0 Power Swivel
31.0 Concave Mill
32.0 Mud/mixing pump
33.0 Tie Mats
34.0 Logging, Bond (with collar locator)
35.0 Wireline Shot/Perforation, Collar Buster
36.0 Topsoil
37.0 Environmental Sampling & Testing
38.0 Culvert
VII. APPENDIX A – REFERENCE WELL RECORDS
1.0 API# 47-097-00007
2.0 API# 47-097-00764
I. PROJECT DESCRIPTION
This project involves the plugging and/or remediation of abandoned oil and/or natural gas wells and sites at the location described below.
1.0 Location/Site Description
1.1 API# 47-097-03866
Physical Address: 649 Booney Hull Rd.
Buckhannon, WV 26201
Parcel Description: HULL ROBERT NEIL
ID: 49-04-004K-0020-0000
DESC: 81.40 AC BULL RUN; SUR
Well Location: 38.922969 °N, -80.300300°W
1.2 API# 47-097-00007
Physical Address: 649 Booney Hull Rd.
Parcel Description: HULL ROBERT NEIL
ID: 49-04-004K-0020-0000
DESC: 81.40 AC BULL RUN; SUR
Well Location: 38.922184 °N, -80.300322°W
1.3 API# 47-097-03864
Physical Address: Slab Camp Road
Parcel Description: HAMNER ELIZABETH M HAMNER PAUL D
ID: 49-04-003L-0018-0000
DESC: SUR 85.12; SLAB CAMP
Well Location: 38.892193 °N, -80.325130°W
Note: DEP strongly advises using only the provided turn-by-turn directions listed below to navigate to the pre-bid meeting site and not the GPS coordinates of the well site itself.
Failure to arrive at the determined pre-bid location due to navigation errors will not warrant rescheduling another meeting.
2.0 Directions to pre-bid meeting:
Directions from the Charleston Area:
Take I-79 North to Exit 99. Turn right at the bottom of the ramp onto Rt. 33 East. Follow
Rt. 33 East for 10.4 miles, and then turn on to State Rt. 20 South on the right. Follow State
Rt. 20 South for 9.4 miles, and then turn on to to Slab Camp Road / CR 32 on the right.
Follow Slab Camp Road / CR 32 for 1.8 miles to a large green metal building on the left.
Pre-bid meeting will begin at the green metal building’s parking lot.
Directions from the Clarksburg Area:
Take I-79 South to Exit 99. Turn left at the bottom of the ramp onto Rt. 33 East. Follow
Rt. 33 East for 10.4 miles, and then turn on to State Rt. 20 South on the right. Follow State
Rt. 20 South for 9.4 miles, and then turn on to to Slab Camp Road / CR 32 on the right.
Follow Slab Camp Road / CR 32 for 1.8 miles to a large green metal building on the left.
Pre-bid meeting will begin at the green metal building’s parking lot.
II. SCOPE OF WORK
The Contractor, the Contractor’s agents, representatives, and subcontractors (“Contractor”) shall provide all equipment, materials, labor, and professional services for the plugging of the oil and/or natural gas well(s) identified herein, and the reclaiming of all land disturbed in association with those plugging operations in accordance with West Virginia Code §§ 22-6-23, 22-6-24, and all rules promulgated thereunder.
This project is defined by, and subject to, the following documents attached hereto or included as part of supplemental documentation made available as part of the solicitation request (“Contract”):
I. Project Description
II. Scope of Work
III. General Conditions
IV. Well Description
V. Remediation and Plugging Work Plan
VI. Technical Specifications
VII. Appendix A – Well Records
III. GENERAL CONDITIONS
In addition to the Standard Terms & Conditions for Construction and Reclamation, the following conditions govern this Contract:
1.0 Administrative
A. The Contract shall be overseen by DEP by an inspector specialist/project coordinator from the Abandoned Well Plugging Program. DEP may, situationally, assign alternate or assistant coordinators as staffing needs vary.
B. The Project Coordinator for the contract will be designated at the time of the issuance of the Notice to Proceed.
C. The Project Coordinator shall serve as the first point of contact for the Contractor in all matters related to the Contract.
D. The Contractor shall notify the Project Coordinator of any work stoppages or changes to planned operators at soon as practically possible.
E. All change order requests shall be submitted to the Project Coordinator for approval prior to the initiation of any work related to that change order request.
2.0 Permitting
A. Upon award of the Contract to the successful bidder, the Department shall transfer the well to and issue the plugging permit under the responsible party name, UNKNOWN
- DEP PAID PLUGGING CONTRACT.
B. The plugging portion of the Remediation and Plugging Work Plan included herein
(Section V) shall be incorporated as part of the plugging permit. This plan is developed based on best available information. Should field observations during plugging operations necessitate deviations from this plan, the Department and Contractor shall cooperate to develop alternate plans in full compliance with all applicable rules and regulations.
C. All work performed under the Contract must be completed in accordance with the most current version of the Erosion and Sediment Control Field Manual.
D. Unless otherwise specified in the Technical Specifications and/or Bid Sheet, the
Department will obtain and pay for all Local, State, and Federal permits necessary for the completion of the Contract. Any permit conditions contained within said permits shall become mandatory inclusions in the Contract.
3.0 Work
A. Contractor shall perform Contract work (i.e., site preparation and permitted well work) during the days of Monday through Friday. Work will not be conducted on weekends or state/national holidays except with Department approval or during emergency situations. A workday is defined as a maximum of ten (10) hours; however, additional hours may be worked with Department approval or during emergency situations.
B. Contractor is responsible for tracking daily time and material utilization for the purpose of invoicing. The Department shall confirm daily expenditures at the conclusion of each workday. Any disputes related to time and/or material usage determinations should be made in writing to the Project Coordinator.
C. All in-stream work required in association with the project shall be performed in accordance with all applicable local, state, and federal requirements.
D. Toilet facilities will be provided by the vendor but will not be a separate line item in the contract.
IV. PROJECT DESCRIPTION
1.0 Site-based considerations:
The well is located in the field between #47-097-0007 (Burrough #1) and the Booney Hull Road.
It’s located 20’ from Bull Run of French Creek of Buckhannon River. The well is approximately
200 yards off Booney Hull Road. An access road will need to be maintained through the farmer’s field. Additional erosion and sediment control structures will be added as needed.
The well is located in a farmer’s field at the edge of a wood line. Located 10’ from an intermittent stream feeding an unnamed tributary of Bull Run of French Creek of the Buckhannon River. The well is approximately 300 yards off Booney Hull Road. An access road will need to be maintained through the farmer’s field. Additional erosion and sediment control structures will be added as needed.
1.3 API# 47-097-03864
The well is located in a farmer’s field 200 or more yards from Slab Camp Fork of French Creek of the Buckhannon River. The well is approximately 350 yards off Slab Camp Road. The well sits within a fenced-in corner separating fields. Gates and the fence will need to be removed temporarily for plugging operations and then reinstalled for final reclamation. An access road will need to be maintained through the farmer’s field. Additional erosion and sediment control structures will be added as needed.
2.0 Well-specific considerations:
2.1 API# 47-097-03866
The Office of Oil and Gas does not have a driller’s log for the subject well. Well #47-097-03866 is leaking gas at the surface, and there is no production equipment or tank. A farmer broke the casing off at ground level more than 30 years ago. There is 6 ⅝” casing visible at the surface.
Offset well records (API #47-097-00007) indicate 8 ¼” casing at 647’, water at 12’ and 140’, and salt water at 1060’ and 1070’.
2.2 API# 47-097-00007
The driller’s log for the subject well API# 47-097-00007 indicates 6 ⅝” casing with 2” tubing visible at the surface. Gas is leaking at the 2” tubing. There is a 2” production line broken off from the well. There is no production equipment or tank. All casing is deteriorated. Well records indicate 8 ¼” casing at 647’. Water is listed at 12’ and 140’, and salt water is indicated at 1060’ and 1070’.
2.3 API# 47-097-03864
The Office of Oil and Gas does not have a driller’s log for the subject well. Well 47-097-03864 is leaking gas and oil at the surface. There is a 2” production line connected to the well, and 6 ⅝” casing with 2” tubing visible at the surface. There is no production equipment or tank, and both the production and intermediate casing is deteriorated. Offset records (47-097-00764) show multiple sizes of casing at various depths (see Appendix A).
V. REMEDIATION AND/OR PLUGGING WORK PLAN
Contract work may require site remediation of the well site prior to the commencement of plugging operations.
Project will commence, generally, as follows:
1. Pre-mobilization site remediation, if necessary,
2. Site preparation,
3. Connect rig to well,
4. Clean out well to total depth,
5. Set prescribed plugs and monument,
6. Reclaim site including removal of stream crossings, and
7. Submit invoice to DEP.
Proposed Work Plan
1. Notify Project Coordinator (PC) within 24 hours of plugging commencement.
2. Move in rig up to 6 ⅝” casing.
3. Load hole with water. Check total depth (TD).
4. Run in hole to TD. Run 2 sks of gel followed by 200’ cement plug. Pull work string, wait on cement (WOC). Tag plug, add cement if needed. Shot hole.
5. Pull 6 ⅝” casing. Gel hole to 700’.
6. Set cement plug 1800’ – 1700’ to cover casing seat. Tag plug, add cement if needed.
7. Set cement plug 1500’ – 1400’ to cover elevation. Tag plug.
8. Set cement plug 1100’ – 1000’ to cover salt water. Tag plug.
9. Pull 8 ¼” casing, set cement plug from 700’ to 600’ to cover casing seat. WOC.
10. Pull 10” casing.
11. Pull 16” casing.
12. Set cement plug from 200’ to surface.
13. Set monument. Reclaim.
Note: A bond log may be required to plug this well. Class A or Class L cement required.
2. Move in rig up to 6 ⅝” casing.
3. Pull 2” tubing and packer. Load hole with water.
4. Run bond log.
5. Run in hole to TD. Run 2 sks gel followed by 200’ cement plug. Pull work string, WOC.
Tag plug, add cement if needed. Shot hole.
6. Pull 6 ⅝” casing. Gel hole to 700’.
7. Set cement plug 1800’ – 1700’ to cover casing seat. Tag plug, add cement if needed.
8. Set cement plug 1100’ – 1000’ to cover salt water. Tag plug.
9. Pull 8 ¼” casing, set cement plug from 700’ – 600’ to cover casing seat. WOC.
10. Pull 10” casing.
11. Pull 16” casing.
12. Set cement plug from 200’ to surface.
13. Set monument and reclaim.
1.3 API# 47-097-00764
2. Move in rig up to 6 ⅝” casing. Pull 2” tubing.
3. Pull 4 ½” casing.
4. Gel hole to 1000’, set cement plug 4040’ – 3840’. Pull work string, WOC. Tag plug, add cement if needed.
5. Set cement plug 3050’ – 2950’. WOC. Tag plug.
6. Run bond log.
7. Pull 6 ⅝” casing. Set cement plug 2200’ – 1900’. Tag plug, add cement if needed.
8. Set cement plug 1600’ – 1500’. WOC, tag plug.
9. Pull 8 ¼” casing, set cement plug from 1500’ to 1300’. WOC.
10. Pull 10” casing. Set cement plug from 600’ to 300’. WOC.
11. Pull 13” casing.
12. Set cement plug from 200’ to surface.
13. Set monument and reclaim.
VI. TECHNICAL SPECIFICATIONS
1.0 Rig and Crew -Three (3) Man Crew (minimum)
Description:
The rig is a mobile platform from which well work is performed. The rig crew are the persons needed to adequately operate the rig.
Functional/performance requirements:
The rig must be a mobile rig, capable of pulling 150 percent of the heaviest hook load anticipated. Rig shall have the ability to use both cable tools and rotary type equipment.
Rig will be equipped with a walking beam and cable tools such as stinger, drill stem, jars, bailers of various sizes, an assortment of cable tool bits, a sinker bar, and well control devices. The rig crew will consist of, at a minimum, three persons – a rig operator, two hands, and a pickup truck.
Measurement and Payment:
Item is bid per hour of operation. Hours charged will be for on-site work only. Daily transportation to and from the job site is not included and will not be charged separately.
At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Additional Labor’ or ‘Heavy Equipment.’)
Labor hours for Rig and Crew are payable only after the point in time in which the rig has been set up and connected to the well. Rig set up prior to well connection is considered
Mobilization.
2.0 Mobilization & Demobilization
Mobilization and demobilization, collectively, encompasses the labor and equipment necessary to transport all contract equipment, tools, and materials to and from the project site. Mobilization and demobilization pricing includes all equipment on the contract at the time of the bid. Mobilization of the rig includes all setup up to the point that the rig is connected to the well. Transportation costs for any other unanticipated equipment needs that may arise will be resolved through the Change Order process, if necessary.
Functional requirements:
All necessary trucking must include operator with a valid Commercial Driver’s License
(CDL).
Item is bid as a service, with half the total bid amount payable after mobilization has occurred (50.0%), and the remainder payable with the final invoice.
2.5 Field Move
A field move is the complete relocation of field equipment and/or materials between successive project sites contained within the same contract. The field move includes all the labor, equipment, and materials necessary to demobilize from one site, transport all equipment and/or materials to the next location, and setup the rig to the point that the rig is connected to the next well.
All necessary trucking must include operator with a valid Commercial Driver’s License
(CDL).
Measurement and payment:
Item is bid as a lump sum inclusive of all labor, equipment, and materials.
3.0 Additional Labor
Additional labor is general labor performing tasks not included in the rig crew bid. This labor may be assisting by performing tasks the rig crew does not have time to complete or may be performing tasks not included in the actual well work.
This item is bid per worker per hour. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy Equipment.’)
4.0 Vacuum Water Truck
A vacuum truck is a tank truck that has a pump and a tank designed to pneumatically suck liquids, sludges, slurries, or similar fluids into the tank of the truck for the purposes of transporting that material to another location. In this contract, the vacuum water truck will be used to deliver water to site, dispose of plugging fluids and may assist in controlling fluid returns from the well bore site.
Vacuum water truck must include all hoses and connections needed as well as operator.
This item is bid per hour of operation and includes operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy
Equipment.’)
5.0 Heavy Equipment
Heavy equipment shall be used in construction and reclamation of site and access road, and in the moving of tools and equipment during the plugging operations. The use of heavy equipment requires a qualified operator.
Bulldozer must have winches and tilt blades and will be used for grading and the spotting of equipment. Excavator must be a tracked machine. Note: horsepower and weight will be verified by reviewing the specifications of the model(s) selected by the vendor.
1. Bulldozer (minimum 85 horsepower and minimum weight 16,000 pounds.)
2. Excavator (minimum 85 horsepower and minimum weight 25,000 pounds.)
This item is bid per hour of operation and includes labor. At no time may an individual labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew or ‘Additional
Labor.’)
5.5 Light Duty Equipment
Certain light duty equipment may be necessary to move dirt, debris, and equipment at the well site. Light duty equipment generally does not require a qualified operator.
1. Skid Steer (minimum 24 HP, 700# rated capacity or equivalent.)
This item is bid per hour of operation and does not include specific operator labor. Labor while using this equipment is to be billed under “Additional Labor.”
6.0 Power Tongs
Power tongs are large-capacity self-locking wrenches used to grip drill string components and apply torque. Power tongs are used to assemble and disassemble tubulars and casings.
The following sizes may be needed for this project.
1. Up to 4 ½ inches
2. Over 4 ½ inches up to 8 ⅝ inches
This item is bid per day of use.
7.0 Casing Knife/Ripper
A casing knife/ripper is a cable tool used in association with jars to affect the separation or severance of tubing or casing found in the well bore.
Knife block assembly size will be determined by the well bore. All assembly components will be provided by the contractor.
This item is bid per knife per day.
8.0 Casing, Tubing, and Pipe Rentals
Casing and tubing are pipes of a specified diameter lowered into the borehole to serve as a conduit for fluids or to provide borehole structural stability. The casing, tubing, drill pipe, and drill collar rentals are needed when tubing and casings may be used in the well bore and recovered in such instances.
This will include various sizes that will be determined by the well bore. Slips and elevators will be provided by the contractor.
1. Tubing: 1 ½ inches to 2 3/8 inches
2. Drill Collar: 2 7/8 inches
3. Casing: 24-inch conductor casing
This item is bid per foot.
9.0 Tri-Cone Drill Bit
The drill bit is the tool used to cut or crush rock during well drilling. A Tri-cone bit will be used to drill out fill-up found in the well bore.
Tri-cone bit include bit sub and a float.
1. 4 ¾ inches – 6 ¼ inches
Drill bit shall be in used condition.
This item is bid per bit.
10.0 Trash Pump
The trash pump is used to transfer water and other plugging fluids between locations.
Functional and Performance requirements:
The trash pump must be a minimum three (3) inches and shall be of industrial grade with all hoses and fittings included.
This item is bid per hour of use.
11.0 On-Site Water Storage Container(s)
The water storage container(s) must hold at a minimum one hundred (100) barrels and will be used for the storage of fresh water for use in the plugging operation.
This item is bid per container.
12.0 Disposal of Gel
There are instances where gel fluids from the plugging operations may need to be disposed of, in which case they shall be hauled to an approved solid waste facility.
This item is bid per barrel and does not include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.
13.0 Disposal of Liquid Waste
There are instances where saltwater or other Class II fluids are returned to the surface due to the plugging operations and must be disposed of at an Underground Injection Control
(UIC) well. The contactor will transport the saltwater or other Class II fluids to a UIC well for disposal.
This item is bid per barrel and does not include trucking cost. Manifest and invoice from an approved disposal facility shall be provided to the Department.
14.0 Disposal of Solid Waste
Solid waste, including contaminated soil, disposal will be the responsibility of the contractor.
This item is bid per ton and does include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.
15.0 Aqua Gel
Gel is a mixture of water and bentonite clay mixed to desired weight. Aqua gel will have dual use, it will be used to increase the viscosity of the drill fluid and as spacers between the cement plugs. The Aqua Gel will be mixed, pumped, and delivered to site.
This item is bid per fifty (50) pound sack. Larger unit quantities of gel may be used on-site but bid prices should be standardized to the fifty (50) pound sack.
16.0 Cement
Portland Class A Cement shall be used to cement casings and tubulars in the well bore and for cement plugs.
Performance requirements:
Cement will be a Portland Class A cement with no other additives.
This item is bid per standard ninety-four (94) pound sack delivered to site. Pricing is to include mixing and pumping. Larger unit sizes of cement may be used on-site (i.e., “Super
Sacks”), but bid prices and payment shall be standardized to the ninety-four-pound sack equivalent.
17.0 Gravel
Gravel is used for a variety of applications including roadbuilding and site stabilization.
Functional requirement:
Gravel will be limestone and size will be determined by the application for which it is being used.
This item is bid per ton delivered to site. This price will include trucking to site.
18.0 Steel Mud Pit
The mud pit is a large tank that contains drilling fluids on-site. Mud pits may also be used to store plugging fluids from the well.
Functional requirement:
The mud pit shall be constructed of steel and have a divider to expedite the settling of cuttings and debris flushed from the well bore.
This item is bid per mud pit.
19.0 Site Reclamation
Site reclamation is the process of restoring the well site area back to original condition.
Site reclamation generally requires earth work and a combination of lime, fertilizer, seed, and mulch, as appropriate.
Performance Requirements:
Site reclamation shall be completed in accordance with the provisions described in the
West Virginia Erosion and Sediment Control Field Manual – May 2012. Note that Section
III of this manual establishes minimum quantities for reclamation materials including lime, fertilizer, seed, and mulch based on site acreage. Site reclamation performance will be evaluated against these parameters.
https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.
https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf
This item is bid as a lump sum for all materials needed to complete site reclamation including the soil borrow area, if applicable. Labor for the completion of site reclamation activities shall be billed as ‘additional labor.’
20.0 Silt Fence
A silt fence is a temporary sediment control device used on construction sites to protect water quality in nearby streams, rivers, lakes, and seas from sediment in stormwater runoff.
Silt Fence shall be supplied with stakes pre-attached and will be installed prior to site construction. Silt fence will also be removed at the completion of reclamation.
This item is bid per foot.
21.0 Monument
The monument is the permanent marker indicating the location of the plugged well.
Monument and its installation will meet all the requirements in 35 CSR 4 – 5.5.b.
• The monument will be a minimum of six (6) inches in outside diameter.
• The monument will extend minimum of thirty (30) inches above final grade and not less than ten (10) feet below the surface.
• The monument will have the well’s API Number attached.
http://apps.sos.wv.gov/adlaw/csr/readfile.aspx?DocId=16899&Format=PDF.
This item is bid per monument.
22.0 Welder/Cutting Torch
A welder/cutting torch is necessary for the fusing or cutting of metal components.
This item is bid per hour of use and includes operator. At no time may an individual labor-based item allowing for hourly rate payments (e.g., ‘Additional Labor’ or ‘Heavy
Equipment.’)
23.0 Oil Absorbent Supplies
Oil Absorbent Supplies are used to absorb and contain oil as directed by the DEP.
1. Booms will be bid per boom and must be a minimum of ten (10) feet in length.
2. Absorbent pads will be bid by the bundle; pads must be a minimum of two
(2) feet by two (2) feet.
3. Peat sorb will be bid per fifty (50) pound bag.
4. Plastic Roll – (100 feet by 50 feet), twenty (20) mil (0.02 inch) minimum thickness, bid per roll.
Items are bid as described above.
24.0 Sand Pump
A sand pump is a syringe-type cable tool typically between four (4) and six (6) inches in diameter used to pump sand and cuttings from the well bore.
The well bore size will determine the size of the sand pump used.
Item is bid per pump.
25.0 Cherry Picker
A cherry picker is a tool used to retrieve items from the well bore and drill out wooden plugs. This tool is run on the stem and is used in conjunction with jars.
The cherry picker will be a four (4) to eight (8) in diameter tubular four (4) feet in length with a tapered hole and slot. The well bore diameter will determine the precise size of cherry picker.
Item is bid per cherry picker.
26.0 Casing/Tubing Spear
Casing/Tubing Spear is a grapple tool that will go inside of tubing that is inside of the well bore.
Size will be determined by tubing encountered.
1. Tubing Spear 1 inch to 3 ½ inches
2. Casing Spear up to 10 ¾ inches
Item is bid per spear.
27.0 Overshot
Overshot is a grapple tool used to retrieve tubular pipe and casing by going over the outside of item being fished.
Size to be determined by the size of the fish. All grapples and working components must be included.
1. 1 inch to 3 1/2 inches
Item is bid per tool.
28.0 Impression Block
The impression block is a wax block affixed to the bottom of fishing tools to allow for the creation of an impression of hole contents to assist in fishing operations.
Item is bid per impression block.
29.0 Subs
A sub is a short, threaded piece of pipe used to adapt parts of the drilling string that cannot otherwise be screwed together because of differences in thread size or design. Subs may be needed to change over to drill pipe or to retrieve casing from the well bore.
This item is bid per sub.
30.0 Power Swivel
The power swivel is a mechanical device that suspends the weight of the drill string. It is designed to allow rotation of the drill string beneath it, conveying high volumes of high-pressure drilling mud between the rig's circulation system and the drill string.
The power swivel must be a minimum of a twenty-five (25) ton hydraulic unit. The Power
Swivel must include the Power Unit with hoses and connections, also includes two Saver
Subs (one for Drill Pipe and one for Drill Collars).
This item is bid per hour of use.
31.0 Concave Mill
A mill is a tool that grinds metal downhole, typically to remove junk or parts of a casing string.
Mills will include subs needed.
1. 4 ¾ inch mill
Item is bid per mill.
32.0 Mud/mixing pump
A mud pump is a reciprocating piston/plunger pump designed to circulate drilling fluid under high pressure down the drill string and back up the annulus.
This pump must have a minimum of five (5) inch diameter with a seven (7) inch stroke length or larger, and able to supply volumes and pressure as needed. It will include hoses and connections capable of handling the pump output.
Item is bid per hour of use.
33.0 Tie Mats
Tie mats are portable structures used to support the weight of heavy equipment.
Minimum size 4’ x 12’. Tie mats may be constructed of natural or synthetic materials.
Item is bid per mat for the duration of the project.
34.0 Logging, Bond (with collar locator)
Description
Logging includes all labor, equipment, and material necessary to determine various characteristics of the well and using probative tools suspended from a wire line. Bond logs with casing collar locator (CCL) allows for a determination of the cement bond quality behind the casing and identify the free point of any casing strings present in the well.
Logging includes all labor, equipment, and materials required to complete logging run.
Item is bid per log.
35.0 Wireline Shot/Perforation, Collar Buster
The cutting of pipe by mechanical tools is the preferred method; however, in cases where that is impossible or impractical, severance by wireline tools equipped with shots (i.e., collar busters, perf balls) in conjunction with a bond log may be acceptable.
Functional Requirements:
The sizes listed below may be needed for this project.
1. 3 ½ inches or smaller
2. up to 8 ⅝ inches
This item is bid per successful perforation.
36.0 Topsoil
The excavated area may need to be backfilled with topsoil. The quantity of topsoil will be based on the quantity of soil disposed minus the amount of gravel that is placed along the well.
Item is bid per ton and includes excavation from the borrow area, if applicable, transportation to the site and equipment and labor to level the site. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or
‘Heavy Equipment.’)
37.0 Environmental Sampling & Testing
Description
Although this contract does not directly require any characterization or permitting of wastes prior to disposal, it is likely that analysis of solid wastes may be required by the approved solid waste facilities.
Functional requirements
In the event analysis or permitting are required, the solid waste facility will identify the testing parameters.
Measurement and Payment
Environmental sampling and testing are bid per well.
38.0 Culvert
A culvert is a pipe intended to channel water.
It is anticipated that culverts of the following size will be needed (diameter x length):
1. 24” x 20’ (twenty-four inches by twenty feet)
Culvert may be metal or HDPE.
Item is bid for each culvert.
VII. APPENDIX A – REFERENCE WELL RECORDS
1.0 API# 47-097-00007
2.0 API# 47-097-00764