Technical Specifications - 191T7024Q0031.pdf

PDF 5 MB Posted

Attached to
Manhole on Via Friuli, Rome, Italy
Solicitation number
191T7024Q0031
Issued by

About this file

This document is a technical specification for a contract to install a new buried pipeline system that will connect the current medium voltage circuit along Via Friuli to the Power Building at the U.S. Embassy in Rome, Italy.

The scope of work includes excavation, installation of a new conduit and medium voltage cable, construction of a new concrete manhole, and restoration of the cobblestone road surface. The contractor must provide all labor, materials, and equipment necessary to complete the project. Key requirements include using ground penetrating radar for site investigation, employing an archaeologist to monitor earthmoving, and adhering to Italian regulations for handling excavated materials. The contractor must submit a safety plan, shop drawings, material samples, and other submittals for approval prior to beginning work. The contract will be awarded to a qualified contractor with the proper SOA certification for medium voltage electrical systems. The work is to be performed during normal weekday working hours, with any required off-hours work coordinated in advance with the Contracting Officer's Representative.

View the file

Other files

File Type Posted
191T7024Q0031 - Questions and Answers.docx DOCX document
RFQ - 191T7024Q0031.docx DOCX document
Cover Letter - 191T7024Q0031.pdf PDF
Bill of Quantities - 191T7024Q0031.pdf PDF
SF-1442 - 191T7024Q0031.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- 1 -

Embassy of The United States of America

Rome, Italy

U.S. EMBASSY ROME

VIA FRIULI NEW MEDIUM VOLTAGE PIPILINE

Facility Management

05/05/2024

- 2 -

1 FOREWORDS

2 GENERAL

Art. 2.1 DEFINITIONS

Art. 2.2 SAFETY STANDARS

Art. 2.3 DESCRIPTION OF WORK

Art. 2.4 LIMITATIONS

Art. 2.5 MATERIAL EQUIVALENTS

Art. 2.6 TENDER DOCUMENTS

Art. 2.7 QUALIFICATION OF OFFERORS

Art. 2.8 SUBMITTALS DESCRIPTION (SD)

Art. 2.9 RESIDENTIAL SMOKING POLICY

Art. 2.10 CONCLUSION PHASE

Art. 2.11 PARKING

3 SPECIFICATIONS

Art. 3.1 SITE DEMOLITION AND MASONRY WORK

Art. 3.2 BASIC ELECTRICAL MATERIALS AND METHODS

Art. 3.3 EXCAVATION

Art. 3.4 CONCRETE SLAB

Art. 3.5 ROAD REPAVING

Art. 3.6 UNDERGROUND ELECTRICAL CONDUCT

Art. 3.7 PAINTS AND COATINGS

4 MAINTENANCE PLAN

5 MATERIAL SHEETS

- 3 -

1 FOREWORDS

The Embassy of the United States in Rome needs to award a contract for carrying out a new buried piping system, that will connect the current medium voltage circuit installed along Via Friuli to the Ground Floor of the Power Building.

2 GENERAL

The work consists of installing a new buried pipeline for hosting the new medium voltage cable, a new manhole that will be place in correspondence of the interception with the existent line. In addition to this, core drilling will be carried out on the retain wall of the building to permit the entrance of the new pipes.

The excavation works will affect a narrow portion of Via Friuli attributable to the surface section between the current cable duct and the underground wall that delimits the ground floor of the "Power Building". In particular, the objective of the project is to provide a new cable duct that connects the existing medium voltage line and the building. Therefore, it is necessary to identify the route of the existing pipeline, dig until the medium voltage cables passing through that section are intercepted - presumably located at a depth of approximately 1.30 meters compared to the road level - and, once found, proceed with the excavation in the direction of the Power Building. Once the wall portion has been reached, a cut will be made in the affected wall to create an opening of adequate size to accommodate the passage of the cable ducts. Once the installation of the pipes has been completed, we will proceed, on Via Friuli, with the installation of an inspection pit at the junction point between the old and the new cable passage and, finally, the backfilling of the excavated area including the restoration of the cobblestone road pavement.

• All the following is to be understood as "minimum required performance" and, therefore, does not release the Contractor from all its own and wider responsibilities concerning both compliance with the National and International regulations applicable to the case, and the adoption of technologies more suitable for achieving the best manufacturing and management quality standards.

• Participants are obliged to carry out an inspection of the site subject to the intervention, and to take the final measurements and as regards the success of the project, since the Contractor himself is responsible for discrepancies and deficiencies.

• It shall be Contractor's responsibility to verify all the quantities and dimensions.

• The Contractor is fully responsible for any damage caused by its own actions or of its employees to people and / or things.

• The Contractor shall supply all the installation materials and equipment, skilled and unskilled labor, technical supervision, as well as logistic and administrative support.

- 4 -

The contractor shall also supply all accessory services such as: transportation, leasing, equipment and tools, disposal of debris, cleaning the work area and anything else necessary to complete the project in compliance with the present specifications.

• The contractor shall provide a safety plan designated for this project.

• Maximum attention is required for the safety of personnel at work on the site. The workers shall operate in compliance with standard codes. Since the work site consists of crucial technical installations, temporary safety protection measures towards third parties and workers shall be installed with care and attention, especially for the hours when site is closed.

• The Contractor shall be responsible for submitting, for approval by the COR, samples of materials and supplies to be used.

• In the event of discrepancy between the various drawings of the Project, will have value the solution that best fits the purposes for which the work was designed and, in any case, the one that best meets the criteria of reasonableness and good executive technique applies. In case of discrepancy between the drawings and the items in the Bill of Quantities, the choice of the realization of the workings will be the most favorable for the Embassy.

• Working hour will starts from 08:00-08:30 AM thru 5:00-5:30 PM during weekdays.

Due to the nature of the workplace, there will be workings to perform out of the normal working hours. These operations shall be preventively and beforehand discussed with the COR, in order to obtain the right approvals and authorizations.

• Temporary interruptions in the operation of plants and services must be scheduled with the COR with at least 5 days’ notice.

• Tests functions of plants built and deliveries of tranches of completed works will only take place in the presence of the manager of the Contracting Company and the COR. It will be the responsibility of the Contracting Company to draw up the relative delivery reports for all those works and systems performed and subject to verification and acceptance by the COR.

Art. 2.1 DEFINITIONS

A glossary of terms and relative equivalents used in the drawing up of the tender documents are indicated hereunder:

Client, Administration, Project Supervisor, COR, CO: all these denominations identify the technical administrative staff, predisposed to handle the contract on behalf of the Embassy of the United States of America.

- 5 -

Contracting Company, Contractor: all these denominations identify the subject that undertakes to carry out the work described in the contract.

Contract, Purchase Order (P.O.), Work Order: these terms identify the contract document with which the project is awarded. The Client at his indisputable judgment shall make the formal selection of the different types of documents.

For safety plan purposes, the figures of the Embassy that are key elements in the definition of roles and responsibility in the safety plan are:

"RUP RESPONSABILE UNICO DEL PROCEDIMENTO" The Contracting Officer of Tri-

Missions Rome, whose name appears in the contract or Purchase Order.

"COMMITTENTE" The Senior Facility Manager of Tri-Missions Rome, whose name shall be communicated after the award.

"RESPONSABILE DEL SERVIZIO PREVENZIONE E PROTEZIONE" and

"RESPONSABILE DEI LAVORI" The POSHO (Post Safety and Health Officer) of the

Tri-Mission Rome, whose name shall be communicated after award. The POSHO shall perform his/her duties also using an A/POSHO part of his/her staff.

"DIRETTORE DEI LAVORI" The COR nominated by the Contracting Officer after award.

Art. 2.2 SAFETY STANDARS

The contractor must fulfill all the safety legal requirements according to the D.Lgs.

81/2008 Testo Unico sulla Salute e Sicurezza nei Luoghi di Lavoro. The objective is to avoid or in any case to reduce to the minimum the workers’ exposure to risks associated with work activities. Therefore the contractor is expected to deliver the Risk Assessment

Document (Documento Valutazione Rischi, DVR) or the Operational Safety Plan (Piano

Operativo di Sicurezza, POS) when required, to provide trainings to the laborers, to supply individual and collective protective equipment and to comply with all the other requirements disciplined by the D.Lgs. 81/08.

In the solicitation process set up by the Contracting Officer (RUP), to verify the professional technical suitability, the Embassy asks the offerors a statement on the average annual workforce and on collective bargaining agreement (Contratto di lavoro)

- 6 -applied to employees, the details of the workers' complaints made to INPS, INAIL and

Casse Edili.

In the case of private works, no permission from construction and the amount of the work less than € 100,000, the verification of the suitability of the company is simplified and is considered satisfied through the presentation by the company of the certificate of registration in the Chamber of Commerce, Industry e Handicraft and the Single Document of Regularity Contribution (DURC), accompanied by self-certification in order to meet the other requirements set out in Annex XVII of the Local Consolidated Law on Finance.

The contractor shall submit with the offer a preliminary safety plan that must take into account all kind of work to be performed within the project being solicited.

The plan must be detailed sufficiently to let the team evaluating the offers that the contractor had understood correctly the nature of the work and its own typical risks, and therefore, had evaluated the relevant costs in their proposal.

The Preliminary Safety Plan must contain:

- For each sequence of work a brief description of the related risks.

- For each sequence of work brief description of the practices, the measures, the individual and collective protection devices that will be adopted by the company in order to respond, minimizing the highlighted risks.

- For each sequence of work a cost-analysis of the selected measures.

The estimate must be congruous, analytical for single items, per unit or per measure.

After the tender closure, the company entitled to the work must submit a detailed

Operational Safety Plan (Piano Operativo di Sicurezza) at least 15 days before starting the operations.

The contractor has to send the list of personnel who will work on site. The workers have to be regularly registered and if there is a subcontractor this has to present the documents requested too. All workers have to understand and speak Italian.

The safety plan submitted must clearly identify the professional figures as follows:

"DIRETTORE TECNICO DI CANTIERE" The construction site technical director is the person who manages for the contractor the construction site. This role can be played by both an employee of the company and by an external professional, with a specific and formal assignment. The figure of the technical director of the construction site must not be

- 7 -confused with that of the construction manager, who is instead appointed by the client and checks that the works are carried out in accordance with the provisions of project and related specifications.

"PREPOSTO" an individual who is identified for the functions he/she performs and is therefore comparable to what with other terms is indicated as site manager, workshop manager, department head, office manager, etc. He/she must also be trained to be able to perform the functions attributed to him, as indicated in art. 19 letter g) of paragraph 1 and according to the objectives set by art. 37 of D.Lgs. 81/08. The PREPOSTO, insures continuously and effectively that the workers:

1) follow the safety regulations imparted and outlined in the safety plan.

2) use the required personal protective equipment (PPE).

3) promptly report to the employer or manager any deficiencies in the procedures, tools, personal protective equipment, and persistent protocols disregards.

Art. 2.3 DESCRIPTION OF WORK

The aim of the work is the execution of all the operations necessary to perform and complete the work which consists of the installation of a new buried pipeline to be placed between the current MV line and the Power Building for hosting the new medium voltage cable. In addition to this, core drilling will be carried out on the retain wall of the building for the creation of the hole necessary for the pipeline passage and the installation of a precast manhole for future inspections that will be place in correspondence of the interception with the existent line.

The contractor must perform the following preliminary tasks before starting the actual work:

- Close off the construction site area to ensure safety using removable fences, sight occlusion screens, worksite hazardous and warning signs, installation of road signs and night lights and all the means necessary in order to prevent mishaps.

- Creation of all temporary connections to users for site use. The Contractor must agree with the COR the derivation points from which to take the supplies.

- The COR will indicate which spaces, if any, may be used for storage and shelter of materials and tools for use on site and for the use of Contractor staff.

- 8 -

- Preparation of any additional protections that the COR will consider essential for the safety of people and the protection of goods.

- Provide an archeologist, licensed to the profession and registered, with the task of supervising all earthmoving operations and documenting in detail with photos, surveys and work log during the entire duration of the excavation work.

- Supply of a georadar technology for the ground subsurface investigations using, including site set-up and removal, that allows, according to the provisions of

UNI/PdR 26.1:2017, the execution of mapping of the subsurface at a depth that depends on the dielectric characteristics local soil, by means of electromagnetic survey performed with multichannel radar equipment, with single or arrayed antennas, of frequencies between 200 MHz and 600 MHz. The result of the survey includes cartographies the georeferenced planimetric course of the subservices surveyed at a scale of 1:100, the location of existing references, and information about other concentrated anomalies (e.g., stubs, small cavities, manholes, etc.), linear anomalies (e.g., walls or foundations) and anomalies extensive (e.g., stratifications, large structures, etc.); including sections schematic, performed at each point of significant variation in Plano altimetric layout. The cartographies and any other elaborate graphics will be produced in digital form, through the use of programs CAD/GIS, provided either on paper or magnetic media (dxf format, dwg, dgn, shapefile, kmz/kml, etc.), accompanied by a technical report summarizing of the various stages of investigation (data acquisition and interpretation, analysis of the radar sections and tomography, description of results, etc.); including any other charges for surveys, personnel and means of work and including traffic regulation, the prior placement of no-parking signs in the areas affected by the survey and any regulation of traffic flow during the phase of data acquisition. All stages of the survey, from data acquisition to interpretation and return of the final elaborates, shall comply with the requirements by the Quality Level "LQ-B-I" of P UNI/PdR

26.1:2017

The work to be carried out consists, but shall not be limited to:

• Removal of the existing Roman porphyry or flint paving cubes by hand and/or with the aid of mechanical means, including storage of the cubes at the site area, including their cleaning from mortar and sand, with removal of the bedding sand and cleaning of the bottom

• Removal of the sand layer and transportation of the result material to an authorized landfill.

• Demolition of the reinforced concrete slab and delivery of the rubbles to an authorized landfill.

• Cross sectional excavation for undergrounding of the new medium voltage cable duct

- 9 -

• Excavation of the ground using any means and workforce, storage of the soil, rocks, and any kind material next to the trench, treated and cleaned up in such a way for being reused during backfilling operations. Excavation shall meet the requested depth required to reach the buried MV cables currently installed.

• Carry out the cutting of the wall by using an electrical core drilling machine or other tools, both mechanical or manual, performed inside the building or within the trench, to obtain the right space for the insertion of the piping system.

• Installation of the new conduit composed by PVC pipe or similar materials resistant to the soil compression (crushing greater than 750 N to CEI standards), buried inside a concrete layer, protected by an impact-resistant material and marked by special plastic warning strip.

• Laying of a new medium voltage cable in the duct without interfering with the old cable, still in service, which ensures the energy supply to the entire Embassy including the connection in accordance with current legislation.

• Supply and installation of the reinforced concrete inspection manhole 100x100cm and the related driveway manhole at the point where the junction between the new and the old cable duct takes place after installing a reinforced concrete support slab with a thickness of at least 20 cm. The manhole cover must be made up of prefabricated elements as far as possible and only where not otherwise possible cast or modified on site, with holes of suitable width made in correspondence with the electrical passages and the new pipe. The manhole cover must be made of cast iron class D400 dim. 1000x1000 mm height 200 mm suitable for intense traffic, periodic openings with triangular openings - see attached technical data sheet.

• Substrate screed in reinforced concrete conglomerate with electro-welded mesh of the portion of road pavement affected by the excavation.

• Carry out backfilling operations with material coming from the excavation, previously selected and stored on the edge of the excavation, with the use of mechanical means or carried out manually, compacted every 30cm with special equipment until the desired volume and height is reached. Excess material will be loaded onto means of transport and transported to authorized landfills.

• Backfilling and repositioning operations of the Roman pavement flooring sealed in the joints with the use of polymeric sand.

The main work of the tender will therefore be the excavation, followed by the subsequent work of cutting the masonry, the installation of the new cable duct including the ancillary works and finally the backfilling and restoration phase of the road surface.

The preliminary phase of the works involves the identification, using ground penetrating radar equipment, of the underground services present in the excavation area, which is essential for a preliminary assessment in order to extrapolate their correct location, sizing and distance from the building.

Once the exact position of the existing system has been verified, we will proceed to trace the portion of the area to be excavated and then remove the Roman pavement paving, clean the removed cobblestones and, to ensure security, store them in a locked metal

- 10 -case or a container on site for future re-use.

Subsequently we will proceed with the dismantling of the laying surface composed of a layer of sand with a thickness of approximately 10cm and the reinforced concrete base, with a thickness of 10cm, placed at a depth of 30cm.

The phase following the removal involves the forced section excavation until the discovery of the cable duct, which is assumed to be at a depth of approximately 1.50 meters from the walking surface. Once the pipe has been identified, we proceed with the excavation work until we reach the retaining wall of the building. Given the particular nature of the site, the excavation operations will be carried out mainly by hand and, only when necessary, with the aid of mechanical instruments, under the careful supervision of the works management and of a qualified archaeologist.

Once the portion of masonry has been demolished and the pipes have been installed, the underground operations will end with the backfilling of the trench carried out with material from the excavation with the aid of mechanical and manual means. In correspondence with the power line, a concrete well will be inserted with a cast iron driveway cover, to allow for any further passages of medium voltage cables and related technical inspections in the future.

However, it cannot be ruled out that during the excavations it may be necessary to make changes to the project route due to the presence of any currently undetectable elements, and which will be evaluated jointly with the works management.

Given the presence of numerous underground services and archaeological elements in the Via Friuli area, it was decided to build the cable ducts using a mixed technique, including both the reuse of existing cable ducts and the construction of traditional cable ducts. The installation plan will be established and decided by the surveillance archaeologist who will supervise the execution of the excavations.

Inside the power building you will have to proceed with closing the openings, smoothing and painting the entire wall involved. Are also included various completion works such as masonry assistance for the individual interventions, minor touch ups to the plastering, touch-ups to paintwork, interventions and supplies that cannot be estimated in quantities such as leasing and scaffolding, removal and disposal of all debris, final cleaning of worksite, etc.

There are included in this contract all the works, the performances, and the supplies necessaries to deliver the work fully accomplished, according to the established conditions by the present specifications, with the technical characteristics, qualitative and quantitative expected by the work executive project and relatives to the attachments from which contractor declares to have taken full and exact knowledge. There are also included, only if accepted by the COR, improvements and additional operations contained

- 11 -in the technical specifications presented by the contractor without any additional charges for the government.

All the material should be of primary brands and samples should be submitted to the COR for approval. All samples should be submitted within 15 days from the notice to proceed.

All the debris from the work shall be loaded and disposed outside the building on the very same day, and only a small internal area will be set up to deposit the material to be installed.

The supply of the materials, as listed in the bill of quantities, shall be fully charged to the contracting company.

The contractor shall provide professional cleaning of the premises at final completion of the work.

The contract has to prepare and submit all design details necessary for correct execution of the project (Shop Drawings), before carrying out the work, following the methodology and times determined in the chapter entitled "Times and Penalties".

Art. 2.4 LIMITATIONS

The accomplishment of the project shall be circumscribed to the specific requests described in the Tender Documents.

Art. 2.5 MATERIAL EQUIVALENTS

The contractor shall verify and ensure that all the materials supplied are new and without defects and that their use and/or installation is carried out using the best techniques and fully respecting the instructions supplied by the manufacturers.

Special parts shall be manufactured solely by workshops that are highly qualified in that specific sector.

The makes indicated in this SOW (Scope of Work) are intended as a point of reference and therefore, the words or approved equivalent are implicit.

Therefore, the makes and products listed are to be deemed equivalent to each other.

Different selections implemented by the Contractor shall be approved in advance by the

- 12 -

COR, after submission of samples and technical cards.

Special products must be processed only to workshops highly qualified in the field of specific realization.

Paints

SIKKENS

Art. 2.6 TENDER DOCUMENTS

The following documents shall form an integral part of the contract:

➢ The present Special Tender Document

➢ General Conditions in use by the Client

➢ Drawings AR 101

➢ Bill of quantities

Art. 2.7 QUALIFICATION OF OFFERORS

SOA CERTIFICATION

The offeror shall demonstrate that it meets the project classification requirements (SOA’s certification). The SOA certificate is a qualifying system established by the current Italian laws and implemented through private qualifying agencies.

In the event two SOAs are required, an offeror with the intent to subcontract the effort must have at least one of the SOAs and its subcontractor must possess the other SOA.

The applicable SOA(s) for this project is: OG 10

OG 10: SYSTEMS FOR HIGH TO MEDIUM VOLTAGE TRANSFORMATION AND

ELECTRICITY DISTRIBUTION IN ALTERNATING AND DIRECT CURRENT, AND

PUBLIC LIGHTING INSTALLATIONS

It concerns the construction, maintenance or renovation of electrical installations necessary for the distribution at high and medium voltage and for the transformation and distribution at low voltage to the final user of electricity, complete with any related

- 13 -complementary or accessory building work, local or networked, and the construction, maintenance and renovation of public lighting installations, to be carried out outside buildings. Includes but is not limited to transformer stations and substations, pylons necessary for the transport and distribution of any voltage, the supply and laying of electrical cables for any number of line phases on pylons or underground, the supply and laying of equipped channels and voltage cables, and public lighting installations on ports, viaducts, tunnels, roads, motorways and parking areas.

Art. 2.8 SUBMITTALS DESCRIPTION (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

• SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portions of the work are requested by the cor. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

• SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

• SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Requested by the the Cor

- 14 -

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards ensuring work can be judged. Includes assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.

• SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

• SD-06 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer, or

Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

Material Testing.

• SD-07 Manufacturer's Instructions

Preprinted material describing installation of a product, system, or material, including special notices and (SDS) concerning impedances, hazards, and safety precautions.

• SD-08 Operation and Maintenance Data

Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.

Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

Data incorporated in an operations and maintenance manual or control system.

- 15 -

• SD-09 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principal Validation (GPV) or Third-Party Certification

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

Approving Authority

Office or designated person authorized to approve the submittal.

Art. 2.9 RESIDENTIAL SMOKING POLICY

U.S. Tri-Mission Rome Employee Smoking Policy

Tri-Mission services are performed by direct-hire LES. and Embassy contractors.

This smoking policy has been established for the following reasons:

To protect individuals from second-hand smoking

To avoid setting off alarms and smoke detectors

To maintain a clean workplace

To avoid fires from discarded cigarettes

Any LES or Embassy Contractor working in/on a Government Owned residential compound/property or in an owned or leased residence will follow the rules listed below:

No smoking is allowed on the compound or inside any government-owned residence outside of the dedicated areas.

No smoking is allowed inside a government owned or leased residence.

No smoking is allowed on terraces, in common areas, or parking lots.

No smoking is allowed in any enclosed spaces.

Smoking is allowed outside the gates of a compound or in dedicated areas only. Any person found to be in violation of the above rules will be escorted off the property immediately, reported to the Facility Manager and or GSO, and face immediate disciplinary action.

- 16 -

For questions, concerns, or reporting of a violation please call Facility Management or

GSO at X2132 or RomeFacilMaint-DL@state.gov.

Art. 2.10 CONCLUSION PHASE

Once the project is completed, a final inspection shall be carried out with representatives of the contractor and the Embassy, in order to verify that the project has been carried out correctly, that it is in compliance with the technical specifications and that the systems operate correctly.

Art. 2.11 PARKING

No parking is allowed inside the Compound. The Contractor's vehicles shall be allowed to enter only for loading and unloading materials.

Loading and unloading operations shall be carried out using only one vehicle at a time.

Consequently, during the accomplishment of the project the Contractor shall ensure that its vehicles are parked at its own expense outside the Government property.

3 SPECIFICATIONS

Art. 3.1 SITE DEMOLITION AND MASONRY WORK

References

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

National Fire Protection Association (NFPA):

• NFPA No. 241 (2000) Standard for Safeguarding Construction, Alterations, and

- 17 -

Demolition Operations.

• Safety at Work Places:

• Law Decree 14 August 1996 “Construction Site Regulations”, Supplements and

Amendments.

• Trash Disposal:

• Law Decree 15 November 1993.

• Law Decree 5 February 1997 No. 22 (Decreto Ronchi).

• Law Decree 8 November 1997 No. 389.

• Decree 1 April 1998 No. 145.

• Decree 28 April 1998 No.406, Environmental Department.

• Decree 24 June 1998 No. 261.

• Circular 4 August 1998 No. GAB/DEC/812/98.

General requirements

The work includes the demolition and/or the removal of all construction indicated or specified. All materials resulting from demolition work, except as indicated or specified otherwise, shall become the property of the Contractor and shall be removed from the limits of Government property. Trash and debris shall be removed from the station daily, unless otherwise directed, and shall not be allowed to accumulate on the site. Such materials which, in the opinion of the Contracting Officer’s Technical Representative, cannot practically be removed daily shall be neatly stored on the site where directed by the Contracting Officer.

Dust and debris control

Dust resulting from salvage, demolition and removal work shall be controlled to prevent the spread of dust and avoid creation of a nuisance in the surrounding area. Use of water will not be permitted when it may result in, or create hazardous or objectionable conditions such as ice, flooding and pollution.

Protection

• Protection of Existing Work from Damage:

Protecting workplace from damage:

Protect the working environment and all items present by appropriate means if there is no possibility of removing them temporarily. Repair items damaged during the execution of the work or replace them with new ones. Do not overload structural elements. Provide

- 18 -new supports or bracing for existing structures weakened by demolition or removal works.

• Weather Protection

The interior of the building and all materials and equipment shall be always protected from the weather. Where removal of existing roofing is necessary to accomplish work, materials, and workmen necessary to provide adequate and approved temporary covering of exposed areas shall be kept in readiness at all times. Temporary coverings shall be attended as necessary to ensure their effectiveness and prevent displacement.

• Protection of the Trees and Shrubs

Protect trees and shrubs within the project site that might be damaged during demolition, and that are indicated to be left in place. Restore trees scarred or damaged by Contractor equipment or operations to a satisfactory condition or replace them as determined by the

Contracting Officer’s Representative.

• Facilities

Protect all electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas and temporary services or connections for electrical and mechanical utilities.

• Protection of Personnel

Where pedestrians’ and drivers’ safety is endangered in the area of work removal, barricades for traffic shall be used and advance notice shall be given to the Contracting

Officer prior to beginning any such work.

Use of explosives

Use of explosives will not be permitted.

Burning

Burning will not be permitted.

Relocations

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair items to be relocated which are damaged or replace damaged items with new undamaged items as approved by the Contracting Officer’s

Representative.

Disposition of material

• Title to Materials

- 19 -

Title to all materials and equipment to be removed, except as specified otherwise, is vested in the Contractor upon receipt of notice to proceed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.

• Material to be salvaged.

Salvaged material shall be stored as directed by the Contracting Officer.

• Reuse of materials and equipment

Carefully remove and store materials indicated to be reused or relocated to prevent damage and reinstall as the work progresses.

Clean-up

• Debris and Rubbish Control

Debris and rubbish shall be removed each day and transported in a manner that will prevent spillage on streets or adjacent areas. Clean up spillage from streets and adjacent areas.

• Regulations

National, Provincial, and local regulations regarding hauling and disposal shall be complied with.

Products

Water, Limes, Cements and agglomerates cementitious, Pozzolanes, Plaster

a) Water - The water for the dough with hydraulic binders must be clear, free of oils or organic substances and free of salts (particularly sulphates and chlorides) in harmful percentages and not be aggressive to the resulting conglomerate.

b) Limes - Aerial and hydraulic limes must meet the acceptance requirements set out in Decree 16-11-1939, n. 2231; hydraulic couplings must also meet the requirements contained in Law 26-5-1965, n. 595 (Technical characteristics and requirements of hydraulic binders) as well as the acceptance requirements contained in Ministerial Decree

31-8-1972 (Rules on acceptance requirements and test methods of cement agglomerations and hydraulic limes).

c) Cements and cement agglomerates:

1. Cements must meet the acceptance limits contained in Law 26-5-1965, n. 595 and in Ministerial Decree 3-6-1968 (New rules on acceptance requirements and methods of testing cements) and subsequent amendments. Cement agglomerations will have to meet the acceptance limits contained in Law 26-5-1965, n. 595 and in the Ministerial

- 20 -

Decree 31-8-1972.

2. In accordance with the provisions of the decree of the Ministry of Industry of 9-3-

1988, n. 126 (Regulation of the cement quality control and certification service), the cements referred to in art. 1 letter A) of Law 26-5-1965, n. 595 (i.e. normal and high-strength portland, pozzolanic and blast furnace cements), if used to package the normal cement conglomerate, reinforced and prestressed, must be certified at the laboratories referred to in art. 6 of Law 26-5-1965, n. 595 and art. 20 of Law 5-11-1971, n. 1086. For imported cements, the control and certification procedure may be carried out at the production sites by similar foreign analysis laboratories.

3. Cements and cement agglomerates must be stored in covered warehouses, well protected from moisture and other agents capable of degrading them before use.

d) Pozzolans - Pozzolans will be obtained from layers of cappellaccio worlds and free from heterogeneous substances or inert parts; whatever the origin must meet all the requirements prescribed by Royal Decree 16-11-1939, n. 2230.

e) Gypsum - The gypsum must be recently cooked, perfectly dry, at the end of grinding so as not to leave residues on the fence of 56 meshes per square centimeter, free from heterogeneous materials and without altered parts due to spontaneous extinction. Gypsum should be stored in covered rooms, well protected from moisture and degrading agents.

For acceptance, the general criteria of the article "Materials in General" apply.

Mortars for Masonry

The water and sand for the preparation of the dough must meet the requirements and technical characteristics referred to in the articles "Materials in General" and "Water, Limes, Cements and Cement Agglomerations". The use of ready-made pre-mixed and pre-mixed mortars is permitted, provided that each supply is accompanied by a supplier's declaration certifying the group of mortar, the type and quantity of binders and any additives. If the type of mortar does not match within those indicated below, the supplier must certify with official tests also the strength characteristics of the mortar itself. The procedures for determining the compressive strength of mortars are set out in the

Ministerial Decree 13-9-1993.

Types of mortar and their classes are defined in relation to the composition in volume;

mortars of different proportions in composition also packaged with additives, previously tested, can be considered equivalent to those indicated if their average compressive strength is not lower than the values referred to in Ministerial Decree 20-11-1987, n. 103.

Inert materials for cement conglomerates and mortars

- 21 -

1. Aggregates for cementitious conglomerates, natural and crushing, must consist of non-frosty and non-friable elements, free of organic, silty and clayey substances, etc., in proportions not harmful to the hardening of the conglomerate or to the preservation of the reinforcements. Gravel or crushed stone must have maximum dimensions commensurate with the geometric characteristics of the carpentry of the casting and the size of the reinforcements. The sand for mortars must be free of organic, earthy or clayey substances, and have a maximum grain size of 2 mm for masonry in general, 1 mm for plasters and parameter masonry or in cutting stone.

2. Additives for cementitious mixtures are classified as follows: fluidifiers; aerants;

retardants; accelerants; fluidifiers-aerants; fluidifiers-retardants; fluidifiers- accelerants;

antifreeze-superfluidifying agents.

3. Cement conglomerates for reinforced concrete structures must comply with all the requirements of Ministerial Decree 14-2-1992 and related explanatory circulars.

Brick and concrete elements

The artificial resistant elements to be used in the masonry (brick and concrete elements) can be made of normal brick, lightened brick paste, normal concrete, lightened concrete.

When used in the construction of load-bearing masonry, they must meet the requirements contained in Ministerial Decree 20-11-1987 (Technical standards for the design, execution and testing of masonry buildings and for their consolidation).

In the case of non-load-bearing masonry, the requirements can be a useful reference, together with those of the UNI EN 771-1:2004.

The resistant elements of brick and concrete may contain punctures that meet the requirements of the Ministerial Decree 20-11-1987.

The mechanical strength of the elements must be demonstrated through certifications containing test results and conducted by official laboratories in the production plants, in the manner provided for in the ministerial decree above.

The Director of Works should request an acceptance check, with the aim of ascertaining whether the elements to be implemented have the characteristics declared by the manufacturer.

General materials

The materials, products and components needed, made with traditional and / or artisanal materials and technologies, for the construction of the works, will come from those

- 22 -locations that the Contractor deems of its convenience, provided that, at the sole discretion of the management of the works, they respond to the characteristics / performances indicated below.

In the case of industrial products, compliance with these specifications may result from a certificate of conformity issued by the manufacturer and proven by appropriate documentation and / or certification.

All switches by 160 cm from the faucets or water point, must be covered by waterproof plate IP55.

Execution

Demolitions and removals

The demolition of masonry, concrete, both partial and complete, must be carried out in order and with the necessary precautions, so as not to damage the residual walls, to prevent any injury to workers and to avoid inconvenience or disturbance.

It is therefore forbidden to throw away the materials in general, which instead must be transported or guided down, and to raise dust, so both the walls and the resulting materials must be properly wet. In demolitions and removals, the Contractor must also provide for any necessary shoring to support the parts that must remain and arrange so as not to deteriorate the resulting materials, which must still be able to be used within the limits agreed with the management of the works, under penalty of recourse for damage in favor of the contracting authority. Demolitions should be limited to the prescribed parts and dimensions. When, also due to lack of shoring or other precautions, other parts are demolished or the limits set are exceeded, the parts unduly demolished will also be rebuilt and restored at the expense of the Contractor, without any compensation. All reusable materials, at the sole discretion of the management of the works, must be properly cleaned, guarded, transported and ordered in the places of storage that will be indicated by the management itself, using precautions not to damage them both in cleaning, both in transport, and in their settling and to avoid dispersion. These materials all remain the property of the contracting authority, which may order the Contractor to use them in whole or in part in the contracted works, pursuant to art. 40 of the current General Specifications, with the prices indicated in the list of these Specifications.

• Demolition

Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.

• Deconstruction

- 23 -

Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.

• Demolition Plan

Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.

• Deconstruction Plan

Deconstruction Plan is the planned steps and processes for dismantling all or portions of a structure or assembly, to include managing sequencing activities, storage, re-installation activities, salvage, and disposal mechanisms.

• Demolition/Deconstruction Plan

Prepare a Demolition Plan and Deconstruction Plan and submit proposed demolition, deconstruction, and removal procedures for approval before work is started. The plan includes procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Coordinate with Waste Management Plan. Include statements affirming Contractor inspection of the existing roof deck and its suitability to perform as a safe working platform or if inspection reveals a safety hazard to workers, state provisions for securing the safety of the workers throughout the performance of the work. Provide procedures for safe conduct of the work in accordance with PSC Plan shall be approved by the Contracting Officer prior to work beginning.

• General Requirements

Do not begin demolition or deconstruction until authorization is received from the

Contracting Officer. Remove rubbish and debris from the daily, do not allow accumulations inside or outside the buildings. The work includes demolition, deconstruction, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from the property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the C.O.R.

• Items to remain in place

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer Representative. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload

- 24 -structural elements pavements to remain. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

Masonry works

In the constructions of the walls in general the perfect execution of the edges, vaults, plates, arches will be taken care of, and all the necessary recesses, backgrounds, reeds and holes will be left for:

• receive the keys and keycaps of the vaults: the anchors of the chains and double

T beams; the heads of the beams (wooden, iron); cutting stones and anything else that is not put in place during the formation of the walls

• the passage of vertical ducts (rain pipes, drinking water pipes, stove and chimney pipes, used water discharge, garbage, etc.)

• for the passage of electrical, telephone and lighting pipes

• the plinths, devices for stopping doors and windows, anchors, thresholds, ironwork, railings, windowsills, etc.

What has been said, so that there is never a need to chisel the masonry already carried out. The construction of the walls must begin and continue evenly, ensuring the perfect connection both with the existing walls and between the parts of them. The bricks, before their use, must be wetted to saturation by prolonged immersion in the water and never by sprinkling. They will have to be put in place with the alternating joints and in regular and normal courses to the external surface; they will be laid on top of an abundant layer of mortar and pressed on top of it so that the mortar flows back to fill all the connections. The mortars to be used for the execution of the masonry must be sieved to prevent the joints between the bricks from being higher than the tolerance limit set. The cladding walls will be made in well-aligned courses and must be properly connected with the inner part.

If the masonry were to be carried out with exposed facing (cortina) care must be taken to choose for the external faces the bricks of best firing, better formed and of more uniform color, arranging them with perfect regularity and recurrence in the horizontal connections, alternating with precision the vertical joints.

In this kind of facing the joints must not have a width greater than 5 mm and, after their scraping and cleaning, must be profiled with hydraulic or cement mortar, diligently compressed and smoothed with special iron, without deburring.

The crooks, arches, plates and vaults must be built so that the bricks are always arranged in the normal direction at the curve of the intrados and the width of the joints must never exceed 5 mm at the intrados and 10 mm at the extrados.

- 25 -

At the junction with walls to be built later, appropriate clamps must be left in relation to the material used.

Masonry work, whatever the construction system…

This is the start of the file's text. The full file is on GovTribe.