TECHNICAL SPECIFICATIONS FOR BECKNER WELL PLUGGING PROJECT
This technical specifications document is issued by the West Virginia Department of Environmental Protection, Office of Oil and Gas, for the plugging and remediation of two abandoned oil and natural gas wells located in Ritchie County, West Virginia. The project encompasses the complete plugging, site reclamation, and restoration of two well sites identified as API# 47-085-01544 and API# 47-085-01559, both situated near Cairo, WV on Route 47. The scope of work includes site preparation, well cleaning and plugging operations, installation of permanent monuments, and full site reclamation in accordance with West Virginia Code 22-6-23 and 22-6-24. Well API# 47-085-01544, completed in 1954 as an oil well with a total depth of 1,170 feet, currently exhibits surface leakage of oil, gas, and saltwater. Well API# 47-085-01559, also completed in 1954 as a gas well with a total depth of 2,420 feet, currently exhibits surface leakage of gas and saltwater and requires construction of a 150-foot service road from Route 47 to the well site. The contract requires a minimum three-person rig crew and includes 36 detailed technical line items covering all equipment, materials, labor, and services necessary for project completion.
The contract structure utilizes individual line-item pricing with payment based on specific measurements including hourly rates for rig operation and equipment usage, lump-sum amounts for mobilization, demobilization, site preparation and reclamation, per-unit pricing for materials such as cement and gel, and per-ton pricing for waste disposal. Work is restricted to Monday through Friday during normal business hours with a maximum ten-hour workday. The Department of Environmental Protection will obtain and pay for all required local, state, and federal permits, with permit conditions becoming mandatory contract inclusions. The contractor is responsible for daily time and material tracking, with Department confirmation of expenditures at the conclusion of each workday. All work must comply with the West Virginia Erosion and Sediment Control Field Manual (May 2012), and disposal of waste materials must be documented with scale tickets or manifests from approved facilities. A designated DEP Project Coordinator will serve as the primary point of contact and must be notified within 24 hours of plugging commencement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BECKNER WELL PLUGGING PACKAGE
WEST VIRGINIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
OFFICE OF OIL AND GAS
COUNTY
OF
RITCHIE
API# 47-085-01544
API# 47-085-01559
TECHNICAL SPECIFICATIONS
Table of Contents
Table of Contents
I. PROJECT DESCRIPTION
1.0 Location/Site Description
1.1 API# 47-085-01544
1.2 API# 47-085-01559
2.0 Directions to site:
II. SCOPE OF WORK
III. GENERAL CONDITIONS
1.0 Administrative
2.0 Permitting
3.0 Work
IV. PROJECT DESCRIPTION
1.0 Site-based considerations:
1.1 API# 47-085-01544
1.2 API# 47-085-01559
2.0 Well-specific considerations:
2.1 API# 47-085-01544
2.2 API# 47-085-01559
V. PROJECT WORK PLAN
Site Preparation Plan
1.1 API# 47-085-01544
1.2 API# 47-085-01559
Proposed Plugging Work Plan:
1.1 API# 47-085-01544
1.2 API# 47-085-01559
Site Reclamation Plan
1.1 API# 47-085-01544
1.2 API# 47-085-01559
VI. TECHNICAL SPECIFICATIONS
1.0 Rig and Crew -Three (3) Man Crew (minimum)
2.0 Mobilization & Demobilization
2.5 Field Move
3.0 Site Preparation
4.0 Vacuum Water Truck
5.0 Heavy Equipment
6.0 Power Tongs
7.0 Casing Knife/Ripper
8.0 Casing and Tubing Purchase
9.0 Casing, Tubing, and Pipe Rentals
10.0 Tri-Cone Drill Bit
11.0 Trash Pump
12.0 On-Site Water Storage Container(s)
13.0 Disposal of Gel
14.0 Disposal of Liquid Waste
15.0 Disposal of Solid Waste
16.0 Aqua Gel
17.0 Cement
18.0 Gravel
19.0 Steel Mud Pit
20.0 Site Reclamation
21.0 Silt Fence
22.0 Monument
23.0 Welder/Cutting Torch
24.0 Oil Absorbent Supplies
25.0 Sand Pump
26.0 Cherry Picker
27.0 Casing/Tubing Spear
28.0 Overshot
29.0 Impression Block
30.0 Subs
31.0 Power Swivel
32.0 Concave Mill
33.0 Mud/mixing pump
34.0 Logging, Bond with CCL
34.5 Wireline Shot/Perforation, Collar Buster
35.0 Tie Mats
36.0 Topsoil
VII. APPENDIX A – WELL RECORDS
1.1 API# 47-085-01544
1.2 API# 47-085-01559
I. PROJECT DESCRIPTION
This project involves the plugging and/or remediation of abandoned oil and/or natural gas wells and sites at the location described below.
1.0 Location/Site Description
1.1 API# 47-085-01544
Physical Address: Rt. 47
Cairo, WV 26337
Parcel Description: HERCEG ROBERT J
ID: 43-05-0047-0015-0001
DESC: N F H R 142.879 AC FEE
Well Location: 39.133480 °N, -81.291979 °W
1.2 API# 47-085-01559
Physical Address: Rt. 47
Cairo, WV 26337
Parcel Description: GIBSON JULIE & ANDERSON KAYLA
ID: 43-05-0047-0015-0005
DESC: SUR 60000 SQ FT NFHR
Well Location: 39.13353 °N, -81.290708 °W
Note: DEP strongly advises using only the provided turn-by-turn directions listed below to navigate to the pre-bid meeting site and not the GPS coordinates of the well site itself.
Failure to arrive at the determined pre-bid location due to navigation errors will not warrant rescheduling another meeting.
2.0 Directions to site:
Directions from the Charleston Area:
Take I-77 N toward Parkersburg for 59 miles. Take Exit 174 – Staunton Avenue. Turn left on Rt. 47 E and continue 19 miles. The well site will be on the left side of Rt. 47.
Directions from the Parkersburg Area:
Take I-77 S to Exit 174 – Staunton Avenue. Turn left on Rt. 47 E and continue 19 miles.
The well site will be on the left side of Rt. 47.
II. SCOPE OF WORK
The Contractor, the Contractor’s agents, representatives, and subcontractors (“Contractor”) shall provide all equipment, materials, labor, and professional services for the plugging of the oil and/or natural gas well(s) identified herein, and the reclaiming of all land disturbed in association with those plugging operations in accordance with West Virginia Code §§ 22-6-23, 22-6-24, and all rules promulgated thereunder.
This project is defined by, and subject to, the following documents attached hereto or included as part of supplemental documentation made available as part of the solicitation request (“Contract”):
I. Project Description
II. Scope of Work
III. General Conditions
IV. Well Description
V. Remediation and Plugging Work Plan
VI. Technical Specifications
VII. Appendix A – Well Records
III. GENERAL CONDITIONS
In addition to the Standard Terms & Conditions for Construction and Reclamation, the following conditions govern this Contract:
1.0 Administrative
A. The Contract shall be overseen by DEP by an inspector specialist/project coordinator from the Abandoned Well Plugging Program. DEP may, situationally, assign alternate or assistant coordinators as staffing needs vary.
B. The Project Coordinator for the contract will be designated at the time of the issuance of the Notice to Proceed.
C. The Project Coordinator shall serve as the first point of contact for the Contractor in all matters related to the Contract.
D. The Contractor shall notify the Project Coordinator of any work stoppages or changes to planned operators at soon as practically possible.
E. All change order requests shall be submitted to the Project Coordinator for approval prior to the initiation of any work related to that change order request.
2.0 Permitting
A. Upon award of the Contract to the successful bidder, the Department shall transfer the well to and issue the plugging permit under the responsible party name, UNKNOWN
- DEP PAID PLUGGING CONTRACT.
B. The plugging portion of the Remediation and Plugging Work Plan included herein
(Section V) shall be incorporated as part of the plugging permit. This plan is developed based on best available information. Should field observations during plugging operations necessitate deviations from this plan, the Department and Contractor shall cooperate to develop alternate plans in full compliance with all applicable rules and regulations.
C. All work performed under the Contract must be completed in accordance with the most current version of the Erosion and Sediment Control Field Manual.
D. Unless otherwise specified in the Technical Specifications and/or Bid Sheet, the
Department will obtain and pay for all Local, State, and Federal permits necessary for the completion of the Contract. Any permit conditions contained within said permits shall become mandatory inclusions in the Contract.
3.0 Work
A. Contractor shall perform Contract work (i.e., site preparation and permitted well work) during the days of Monday through Friday. Work will not be conducted on weekends or state/national holidays except with Department approval or during emergency situations. A workday is defined as a maximum of ten (10) hours; however, additional hours may be worked with Department approval or during emergency situations.
B. Contractor is responsible for tracking daily time and material utilization for the purpose of invoicing. The Department shall confirm daily expenditures at the conclusion of each workday. Any disputes related to time and/or material usage determinations should be made in writing to the Project Coordinator.
C. All in-stream work required in association with the project shall be performed in accordance with all applicable local, state, and federal requirements.
D. Toilet facilities will be provided by the vendor but will not be a separate line item in the contract.
IV. PROJECT DESCRIPTION
1.0 Site-based considerations:
The well is currently leaking oil, gas, and salt water at the surface. The contamination from the well has not exceeded the limits of the well site. There was no casing observed above ground level.
The well appears to be open just below the surface. The well site is wooded and covered in brush.
All trees and brush that are cleared from the well site can remain on location. There is no tank or production line at the well site. OOG will contact Locate 811 to have subsurface utilities marked.
The well is located in a wooded area. All trees and brush can be cut and stacked to be left on location. A service road will be constructed from Rt. 47 to the well site at an estimated 150’ in length. The well is currently leaking gas and salt water at the surface of the well. The well surface casing is open. The contamination from the well has not exceeded the limits of the well site. There is no tank or production line at the well location. OOG will contact Locate 811 to have subsurface utilities marked.
2.0 Well-specific considerations:
2.1 API# 47-085-01544
The Office of Oil and Gas has a well record for the subject well. The record shows well total depth
(TD) at 1170’, with 41’ of 10” conductor, 331’ of 8” casing and 925” of 6 ⅝” casing. The cemented locations of the casing strings are unknown. There is no record of tubing or packer placement in the well. The record shows oil at 1100’, 805’, 209’, and 108’. There is a gas show at 530’ and a salt water show at 595’, and there is fresh water at 110’. The elevation at the well head is 640’. No coal was reported. The well was completed on 10/4/1954 as an oil well.
2.2 API# 47-085-01559
The Office of Oil and Gas has a well record for the subject well. The record shows total depth
(TD) at 2420’. The elevation of the well site is 639’. The record shows 12’ of 10” conductor, 294’ of 8” casing, 832’ of 6 ⅝” casing, and 1503’ of 2” tubing. Packer type and location are unknown. There is a gas show at 1561’, 1470’, 540’, and 325’. There is an oil show at 1020’ and
944’, and there is fresh water at 300’. No coal or salt water was reported. The well was completed in 1954 as a gas well.
V. PROJECT WORK PLAN
Contract work may require site remediation of the well site prior to the commencement of plugging operations.
Project will commence, generally, as follows:
1. Pre-mobilization site remediation, if necessary,
2. Site preparation,
3. Connect rig to well,
4. Clean out well to total depth,
5. Set prescribed plugs and monument,
6. Reclaim site including removal of stream crossings, and
7. Submit invoice to DEP.
Site Preparation Plan
One hundred (100) feet of silt fence will be installed around the well to isolate the disturbed area from the stream. The area around the well (50’ x 100’) shall be cleared of all brush and trees. All trees and brush can be stacked and left on location. A service road will be constructed from the county road to the well site with an estimated length of 200’. The service road shall be covered with tie mats and/or stone. A minimum of 24” cellar shall be installed around the well head.
Two hundred (200) feet of silt fence will be installed around the well site to isolate the disturbed area from Rt. 47. The area around the well (50’ x 100’) shall be cleared of all brush and trees. All trees and brush can be stacked and left on location. A service road will be constructed from the county road to the well site, estimated length 75’. The service road shall be covered with tie mats and/or stone. A minimum 24” cellar shall be installed around the well head.
Proposed Plugging Work Plan:
1. Notify Project Coordinator (PC) within 24 hours of plugging commencement.
2. Move in and set 24” conductor for well control.
3. Locate 8” surface casing and begin cleaning out well to total depth (TD) at 1170’.
4. Once TD has been reached and approved by PC, a bond log will be ran inside the 6 ½” casing to determine cement bond location and free points.
5. Trip in hole (TIH) to TD at 1170’ with tubing, spot 6% gel followed by cement from 1170’ to 900’. Trip out hole (TOH), wait on cement (WOC), tag top of cement plug. Add cement if needed.
6. TIH to 900’, shoot/cut 6 ½” casing at free point and pull.
7. TIH with tubing, spot gel from 900’ to 850’ followed by cement from 850’ to 600’. TOH, WOC, tag top of cement plug. Add cement if needed.
8. TIH free point and shoot/cut 8” casing. If 8” casing cannot be retrieved, perforate casing at 300’ and 100’.
9. TIH with tubing, spot gel from 600’ to 300’ followed by cement from 300’ to surface.
10. Rig down and install monument, and reclaim site.
1. Notify Project Coordinator (PC) within 24 hours of plugging commencement.
2. Move in and rig up to existing 8 ¼” casing.
3. Trip in hole (TIH) pull all 2” tubing and packer if found.
4. TIH and check total depth (TD) at or below 2420’. If TD cannot be reached begin cleaning out hole to approved depth/TD by inspector.
5. Once TD has been reached / approved, a bond log will be ran inside the 6 ⅝” casing to determine cement bond location and free points.
6. TIH to TD at 2420’ with tubing, spot 6% gel followed by cement from 2420’ to 2000’.
Trip out hole (TOH) and wait on cement (WOC), then tag top of plug. Add cement if needed.
7. TIH with tubing, spot 6% gel from 2000’ to 1600’ followed by cement plug from 1600’ to
1300’. TOH, WOC and tag top of plug. Add cement if needed.
8. TIH and free point the 6 ⅝” casing.
9. TIH with tubing, spot gel from 1300’ to 1100’ followed by cement plug from 1100’ to
900’. TOH, WOC and tag top of cement plug. Add cement if needed.
10. TIH with tubing, spot gel from 900’ to 700’ followed by cement plug from 700’ to 300’.
TOH, WOC and tag top of cement plug. Add cement if needed.
11. TIH and free point 8 ¼” casing.
12. TIH with tubing, pump cement from 300’ to surface.
13. Rig down and install monument, reclaim site.
NOTE.. Any casing found in the well without cement in the annulus that cannot be retrieved must be perforated and cemented at all saltwater, freshwater, coal, oil, gas, casing shoe and elevation points.
Site Reclamation Plan
All production equipment shall be removed and disposed of. The silt fence shall be removed. All tie mats and/or shall be removed from the well site and service road. The cellar shall be removed from around the well head. All disturbed areas will be smoothed, seeded, and mulched per DEP code. A well monument will be installed at the well head, minimum 6” diameter and 42” above final grade.
All production equipment shall be removed and disposed of. The silt fence shall be removed. All tie mats and/or shall be removed from the well site and service road. The cellar shall be removed from around the well head. All disturbed areas will be smoothed, seeded, and mulched per DEP code. A well monument will be installed at the well head, minimum 6” diameter and 42” above final grade.
VI. TECHNICAL SPECIFICATIONS
1.0 Rig and Crew -Three (3) Man Crew (minimum)
Description:
The rig is a mobile platform from which well work is performed. The rig crew are the persons needed to adequately operate the rig.
Functional/performance requirements:
The rig must be a mobile rig, capable of pulling 150 percent of the heaviest hook load anticipated. Rig shall have the ability to use both cable tools and rotary type equipment.
Rig will be equipped with a walking beam and cable tools such as stinger, drill stem, jars, bailers of various sizes, an assortment of cable tool bits, a sinker bar, and well control devices. The rig crew will consist of, at a minimum, three persons – a rig operator, two hands, and a pickup truck.
Measurement and Payment:
Item is bid per hour of operation. Hours charged will be for on-site work only. Daily transportation to and from the job site is not included and will not otherwise be charged separately. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Heavy Equipment.’)
Hours for Rig and Crew are payable only after the point in time in which the rig has been set up and connected to the well. Rig set up prior to well connection is considered under the line item for “Site Preparation.”
2.0 Mobilization & Demobilization
Mobilization and demobilization, collectively, encompasses the labor and equipment necessary to transport all contract equipment, tools, and materials to and from the project site. Mobilization and demobilization pricing includes all equipment on the contract at the time of the bid. Transportation costs for any other unanticipated equipment needs that may arise will be resolved through the Change Order process, if necessary.
Functional requirements:
All necessary trucking must include operator with a valid Commercial Driver’s License
(CDL).
Item is bid as a service, with half the total bid amount payable after mobilization has occurred (50.0%), and the remainder payable with the final invoice.
2.5 Field Move
A field move is the complete relocation of field equipment and/or materials between successive project sites contained within the same contract. The field move includes all the labor, equipment, and materials necessary to demobilize from one site, transport all equipment and/or materials to the next location, and setup the rig to the point that the rig is connected to the next well.
All necessary trucking must include operator with a valid Commercial Driver’s License
(CDL).
Measurement and payment:
Item is bid as a lump sum inclusive of all labor, equipment, and materials.
3.0 Site Preparation
Site preparation is the process of readying the well site location for plugging activities.
Site preparation may include clearing and grubbing, tree-cutting, construction, installation of erosion and sediment controls, tie-mat installation, cellar installation, and roadbuilding and maintenance thereof. Site preparation includes all setup up and staging of well plugging equipment to the point that the rig is connected to the well and plugging operations are ready to commence.
Any heavy equipment used during site preparation must meet the functional requirements identified in Item 5. Heavy Equipment.
Performance Requirements:
Any construction activities conducted during site preparation shall be completed in accordance with the provisions described in the West Virginia Erosion and Sediment
Control Field Manual – May 2012. Note that Section A of this manual establishes relevant criteria for road construction.
https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.
This item is bid as a lump sum for all labor, equipment, and tools needed to complete site preparation, as described in the ‘Site Preparation’ project description in Section V. Any materials needed will be bid separately under their respective line items. (e.g., stone, silt fence, tie mats, culverts).
4.0 Vacuum Water Truck
A vacuum truck is a tank truck that has a pump and a tank designed to pneumatically suck liquids, sludges, slurries, or similar fluids into the tank of the truck for the purposes of https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf transporting that material to another location. In this contract, the vacuum water truck will be used to deliver water to site, dispose of plugging fluids and may assist in controlling fluid returns from the well bore site.
Vacuum water truck must include all hoses and connections needed as well as operator.
This item is bid per hour of operation and includes operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy
Equipment.’)
5.0 Heavy Equipment
In addition to site preparation, heavy equipment may be used during well plugging operations for purposes including the movement of tools and equipment. The use of heavy equipment requires a qualified operator.
Bulldozer must have winches and tilt blades and will be used for grading and the spotting of equipment. Excavator must be a tracked machine. Note: horsepower and weight will be verified by reviewing the specifications of the model(s) selected by the vendor.
1. Bulldozer (minimum 85 horsepower and minimum weight 16,000 pounds.)
2. Excavator (minimum 85 horsepower and minimum weight 25,000 pounds.)
3. Skid Steer (minimum 24 HP, 700# rated capacity or equivalent.)
This item is bid per hour of operation and includes labor by a qualified operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and
Crew).
6.0 Power Tongs
Power tongs are large-capacity self-locking wrenches used to grip drill string components and apply torque. Power tongs are used to assemble and disassemble tubulars and casings.
The following sizes may be needed for this project.
1. Up to 4 ½ inches
2. Over 4 ½ inches up to 8 ⅝ inches
3. Over 8 ⅝ inches up to 10 ¾ inches
This item is bid per day of use.
7.0 Casing Knife/Ripper
A casing knife/ripper is a cable tool used in association with jars to affect the separation or severance of tubing or casing found in the well bore.
Knife block assembly size will be determined by the well bore. All assembly components will be provided by the contractor.
The following sizes may be required:
1. Up to 3 ½”
2. Up to 8 ⅝”
This item is bid per knife per day.
8.0 Casing and Tubing Purchase
Casing and tubing are pipes of a specified diameter lowered into the borehole to serve as a conduit for fluids or to provide borehole structural stability. The casing and tubing purchase is necessary when casing and tubing must be left in the well bore, and when casings need to be lengthened to nipple up for physical connection to the rig. Slips and elevators will be provided by the contractor.
The following sizes may be needed:
1. 24” Casing
2. 8 ¼” Casing
3. 7” Casing
This item is bid per foot.
9.0 Casing, Tubing, and Pipe Rentals
Casing and tubing are pipes of a specified diameter lowered into the borehole to serve as a conduit for fluids or to provide borehole structural stability. The casing, tubing, drill pipe, and drill collar rentals are needed when tubing and casings may be used in the well bore and recovered in such instances.
This will include various sizes that will be determined by the well bore. Slips and elevators will be provided by the contractor.
1. Tubing: 1 ½ inches to 2 ⅜ inches
2. Drill Collar: 2 ⅞ inches
3. Drill Pipe: PAC 50 or equivalent
This item is bid per foot.
10.0 Tri-Cone Drill Bit
The drill bit is the tool used to cut or crush rock during well drilling. A Tri-cone bit will be used to drill out fill-up found in the well bore.
Tri-cone bit include bit sub and a float.
1. 2 ¾ inches up to 4 ¾ inches
2. 4 ¾ inches up to 6 ¼ inches
3. 6 ½ inches to 8 ¼ inches
Drill bit shall be in used condition.
This item is bid per bit.
11.0 Trash Pump
The trash pump is used to transfer water and other plugging fluids between locations.
Functional and Performance requirements:
The trash pump must be a minimum three (3) inches and shall be of industrial grade with all hoses and fittings included.
This item is bid per hour of use.
12.0 On-Site Water Storage Container(s)
The water storage container(s) must hold at a minimum one hundred (100) barrels and will be used for the storage of fresh water for use in the plugging operation.
This item is bid per container.
13.0 Disposal of Gel
There are instances where gel fluids from the plugging operations may need to be disposed of, in which case they shall be hauled to an approved solid waste facility.
This item is bid per barrel and does not include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.
14.0 Disposal of Liquid Waste
There are instances where saltwater or other Class II fluids are returned to the surface due to the plugging operations and must be disposed of at an Underground Injection Control
(UIC) well. The contactor will transport the saltwater or other Class II fluids to a UIC well for disposal.
This item is bid per barrel and does not include trucking cost. Manifest and invoice from an approved disposal facility shall be provided to the Department.
15.0 Disposal of Solid Waste
Solid waste, including contaminated soil, disposal will be the responsibility of the contractor.
This item is bid per ton and does include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.
16.0 Aqua Gel
Gel is a mixture of water and bentonite clay mixed to desired weight. Aqua gel will have dual use, it will be used to increase the viscosity of the drill fluid and as spacers between the cement plugs.
This item is bid per fifty (50) pound sack delivered to site. Pricing is to include mixing and pumping. Larger unit sizes of aqua gel may be used on-site (i.e., “Super Sacks”), but bid prices and payment shall be standardized to the fifty-pound sack equivalent. The use of any heavy equipment to assist in the mixing and pumping of aqua gel (i.e., excavator to lift a super sack) shall be considered in this line item.
17.0 Cement
Portland Class A Cement shall be used to cement casings and tubulars in the well bore and for cement plugs. Class L cement may be used in place of Class A if explicitly allowed by permit.
Performance requirements:
Cement will be a Portland Class A or L cement, as identified in the permit, with no other additives.
This item is bid per standard ninety-four (94) pound sack delivered to site. Pricing is to include mixing and pumping. Larger unit sizes of cement may be used on-site (i.e., “Super
Sacks”), but bid prices and payment shall be standardized to the ninety-four-pound sack equivalent. The use of any heavy equipment to assist in the mixing and pumping of cement
(i.e., excavator to lift a super sack) shall be considered in this line item.
18.0 Gravel
Gravel is used for a variety of applications including roadbuilding and site stabilization.
Functional requirement:
Gravel will be limestone and size will be determined by the application for which it is being used.
This item is bid per ton delivered to site. This price will include trucking to site.
19.0 Steel Mud Pit
The mud pit is a large tank that contains drilling fluids on-site. Mud pits may also be used to store plugging fluids from the well.
Functional requirement:
The mud pit shall be constructed of steel and have a divider to expedite the settling of cuttings and debris flushed from the well bore.
This item is bid per mud pit.
20.0 Site Reclamation
Site reclamation is the process of restoring the well site area back to original condition.
Site reclamation generally requires earth work and seeding of grass utilizing a combination of lime, fertilizer, seed, and mulch, as appropriate. The minimum quantities of these materials are specified in the reclamation plan. Site reclamation also includes the removal of any well production equipment, installed erosion and sediment controls, tie mats.
Any heavy equipment used during site preparation must meet the functional requirements identified in Item 5. Heavy Equipment.
Performance Requirements:
Site reclamation shall be completed in accordance with the provisions described in the
West Virginia Erosion and Sediment Control Field Manual – May 2012. Note that Section
III of this manual establishes minimum quantities for reclamation materials including lime, fertilizer, seed, and mulch based on site acreage. Site reclamation performance will be evaluated against these parameters.
https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.
This item is bid as a lump sum for all labor, equipment, tools, and materials including lime, fertilizer, seed, and mulch needed to complete site reclamation of the well site (including the soil borrow area, if necessary), as described in the ‘Site Reclamation’ project description in Section V. Topsoil, where necessary, shall be bid separately; however, all labor associated with that soil will be considered in this bid item. Site reclamation shall also include the removal of all production equipment, installed erosion and sediment controls, and tie mats.
21.0 Silt Fence
A silt fence is a temporary sediment control device used on construction sites to protect water quality in nearby streams, rivers, lakes, and seas from sediment in stormwater runoff.
Silt fence shall be supplied with stakes pre-attached and will be installed during site preparation. Silt fence will also be removed at the completion of reclamation.
This item is bid per foot. Installation and removal of silt fence shall be included in the site preparation and reclamation line items, respectively.
https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf
22.0 Monument
The monument is the permanent marker indicating the location of the plugged well.
Monument and its installation will meet all the requirements in 35 CSR 4 – 5.5.b, including:
● The monument will be a minimum of six (6) inches in outside diameter.
● The monument will extend minimum of thirty (30) inches above final grade and not less than ten (10) feet below the surface.
● The monument will have the well’s API Number permanently attached.
http://apps.sos.wv.gov/adlaw/csr/readfile.aspx?DocId=16899&Format=PDF.
This item is bid per monument installed.
23.0 Welder/Cutting Torch
A welder/cutting torch is necessary for the fusing or cutting of metal components.
This item is bid per hour of use and includes operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Heavy Equipment.’)
24.0 Oil Absorbent Supplies
Oil Absorbent Supplies are used to absorb and contain oil as directed by the DEP.
1. Booms will be bid per boom and must be a minimum of ten (10) feet in length.
2. Absorbent pads will be bid by the bundle; pads must be a minimum of two
(2) feet by two (2) feet.
3. Peat sorb will be bid per fifty (50) pond bag.
4. Plastic roll – (100 feet by 50 feet), twenty (20) mil (0.02 inch) minimum thickness, bid per roll.
Items are bid as described above, and shall include installation or deployment costs.
25.0 Sand Pump
A sand pump is a syringe-type cable tool typically between four (4) and six (6) inches in diameter used to pump sand and cuttings from the well bore.
The well bore size will determine the size of the sand pump used.
Item is bid per pump.
26.0 Cherry Picker
A cherry picker is a tool used to retrieve items from the well bore and drill out wooden plugs. This tool is run on the stem and is used in conjunction with jars.
The cherry picker will be a four (4) to eight (8) in diameter tubular four (4) feet in length with a tapered hole and slot. The well bore diameter will determine the precise size of cherry picker.
Item is bid per cherry picker.
27.0 Casing/Tubing Spear
Casing/Tubing Spear is a grapple tool that will go inside of tubing that is inside of the well bore.
Size will be determined by tubing encountered.
1. Tubing Spear 1 inch to 3 ½ inches
2. Casing Spear up to 10 ¾ inches
Item is bid per spear.
28.0 Overshot
Overshot is a grapple tool used to retrieve tubular pipe and casing by going over the outside of item being fished.
Size to be determined by the size of the fish. All grapples and working components must be included.
1. 1 inch to 3 ½ inches
2. Up to 8 ⅝ inches
Item is bid per tool.
29.0 Impression Block
The impression block is a wax block affixed to the bottom of fishing tools to allow for the creation of an impression of hole contents to assist in fishing operations.
Item is bid per impression block.
30.0 Subs
A sub is a short, threaded piece of pipe used to adapt parts of the drilling string that cannot otherwise be screwed together because of differences in thread size or design. Subs may be needed to change over to drill pipe or to retrieve casing from the well bore.
This item is bid per sub.
31.0 Power Swivel
The power swivel is a mechanical device that suspends the weight of the drill string. It is designed to allow rotation of the drill string beneath it, conveying high volumes of high-pressure drilling mud between the rig's circulation system and the drill string.
The power swivel must be a minimum of a twenty-five (25) ton hydraulic unit. The Power
Swivel must include the Power Unit with hoses and connections, also includes two Saver
Subs (one for Drill Pipe and one for Drill Collars).
This item is bid per hour of use.
32.0 Concave Mill
A mill is a tool that grinds metal downhole, typically to remove junk or parts of a casing string.
Mills will include subs needed.
1. 4 ¾ inch mill
2. Up to 8 ⅞ inches
Item is bid per mill.
33.0 Mud/mixing pump
A mud pump is a reciprocating piston/plunger pump designed to circulate drilling fluid under high pressure down the drill string and back up the annulus.
This pump must have a minimum of five (5) inch diameter with a seven (7) inch stroke length or larger, and able to supply volumes and pressure as needed. It will include hoses and connections capable of handling the pump output.
Item is bid per hour of use.
34.0 Logging, Bond with CCL
Description
Logging includes all labor, equipment, and material necessary to determine various characteristics of the well and using probative tools suspended from a wire line. Bond logs with casing collar locator (CCL) allows for a determination of the cement bond quality behind the casing and identify the free point of any casing strings present in the well.
Logging includes all labor, equipment, and materials required to complete logging run.
Item is bid per log.
34.5 Wireline Shot/Perforation, Collar Buster
The perforation, severance, or separation of pipe by wireline tools equipped with explosive shots (i.e., collar busters, perf balls) or other wireline mechanical means (i.e., jet-cutter), typically in conjunction with a bond log.
Functional Requirements:
The following sizes may be needed:
1. Up to 3 ½”
2. Up to 8 ⅝”
This item is bid per run.
35.0 Tie Mats
Tie mats are portable structures used to support the weight of heavy equipment.
Minimum size 4’ x 12’. Tie mats may be constructed of natural or synthetic materials.
Item is bid per mat for the duration of the project.
36.0 Topsoil
The excavated area may need to be backfilled with topsoil. The quantity of topsoil will be based on the quantity of soil disposed minus the amount of gravel that is placed along the well.
Item is bid per ton and includes excavation from the borrow area, if applicable, transportation to the site and equipment and labor to level the site. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy Equipment.’)
VII. APPENDIX A – WELL RECORDS
| Table of Contents |
| I. PROJECT DESCRIPTION |
| 1.0 Location/Site Description |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |
2.0 Directions to site:
| II. SCOPE OF WORK |
| III. GENERAL CONDITIONS |
| 1.0 Administrative |
| 2.0 Permitting |
| 3.0 Work |
| IV. PROJECT DESCRIPTION |
| 1.0 Site-based considerations: |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |
| 2.0 Well-specific considerations: |
| 2.1 API# 47-085-01544 |
| 2.2 API# 47-085-01559 |
| V. PROJECT WORK PLAN |
| Site Preparation Plan |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |
| Proposed Plugging Work Plan: |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |
| Site Reclamation Plan |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |
| VI. TECHNICAL SPECIFICATIONS |
| 1.0 Rig and Crew -Three (3) Man Crew (minimum) |
| 2.0 Mobilization & Demobilization |
| 2.5 Field Move |
| 3.0 Site Preparation |
| 4.0 Vacuum Water Truck |
| 5.0 Heavy Equipment |
| 6.0 Power Tongs |
| 7.0 Casing Knife/Ripper |
| 8.0 Casing and Tubing Purchase |
| 9.0 Casing, Tubing, and Pipe Rentals |
| 10.0 Tri-Cone Drill Bit |
| 11.0 Trash Pump |
| 12.0 On-Site Water Storage Container(s) |
| 13.0 Disposal of Gel |
| 14.0 Disposal of Liquid Waste |
| 15.0 Disposal of Solid Waste |
| 16.0 Aqua Gel |
| 17.0 Cement |
| 18.0 Gravel |
| 19.0 Steel Mud Pit |
| 20.0 Site Reclamation |
| 21.0 Silt Fence |
| 22.0 Monument |
| 23.0 Welder/Cutting Torch |
| 24.0 Oil Absorbent Supplies |
| 25.0 Sand Pump |
| 26.0 Cherry Picker |
| 27.0 Casing/Tubing Spear |
| 28.0 Overshot |
| 29.0 Impression Block |
| 30.0 Subs |
| 31.0 Power Swivel |
| 32.0 Concave Mill |
| 33.0 Mud/mixing pump |
| 34.0 Logging, Bond with CCL |
| 34.5 Wireline Shot/Perforation, Collar Buster |
| 35.0 Tie Mats |
| 36.0 Topsoil |
| VII. APPENDIX A – WELL RECORDS |
| 1.1 API# 47-085-01544 |
| 1.2 API# 47-085-01559 |