Tech Specs.pdf

PDF 2 MB Posted

Attached to
25-50 Fisherman's Park Pump Station Upgrades EDA Project #ED24PHI0G0302
Solicitation number
25-50
Issued by
Atlantic County, New Jersey

About this file

The document is a comprehensive technical specification file for the Fisherman's Park Pump Station Upgrades project, involving the City of Atlantic City, New Jersey, and Remington & Vernick Engineers. The project encompasses extensive electrical, structural, and infrastructure improvements at Fisherman's Park, located at Melrose Avenue and N. Rhode Island Avenue in Atlantic City. The scope of work includes installing a new stormwater flow control system, excavating existing soils, sawcutting and removing portions of an existing concrete box culvert, installing concrete beams and walls, constructing a stainless steel bar screen and netting trap system, adding access ladders and hatches, and implementing a comprehensive electrical system upgrade. The project involves disconnecting the existing 100-amp electrical service and replacing it with a new 1000-amp, 3-phase, 480V utility service, including a new automatic transfer switch, power distribution switchboard, and associated electrical infrastructure.

The project is anticipated to have a total completion time of 180 calendar days from the Notice to Proceed, with potential variations for electrical equipment delivery. Funding and procurement will be managed by the City of Atlantic City, with technical oversight by Remington & Vernick Engineers. The contract includes provisions for potential equipment lead time variations and allows for contractor-proposed alternative manufacturers, provided they meet the specified technical requirements. A pre-bid conference will be held via Zoom, and potential bidders are encouraged to review the detailed technical specifications, which include extensive requirements for materials, installation methods, testing, and quality control. The project emphasizes compliance with national electrical codes, New Jersey Department of Transportation standards, and specific environmental and structural engineering guidelines.

View the file

Other files

File Type Posted
0102U025 - Plan Set - signed.pdf PDF
BID 25-50 Fishermans Park Pump Upgrades.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

Fisherman’s Park AC

RVE #: 0102U025

BID DOCUMENTS APRIL 2025 (REVISED JUNE 2025)

TOC-1

TECHNICAL SPECIFICATIONS

SUPPLEMENTAL CONDITIONS

DIVISION 01 – GENERAL REQUIREMENTS

010000 SUMMARY OF WORK

010100 AS BUILT DRAWINGS

017100 CLEANING & RESTORATIONS

DIVISION 02 – EXISTING CONDITIONS

021400 DEWATERING AND FLOW DIVERSION

022280 EXCAVATION AND BACKFILL

022700 TEMPORARY SOIL EROSION AND SEDIMENT CONTROL MEASURES

024100 BUILDING DEMOLITION

024570 CONCRETE FILLED STEEL PIPE PILES

DIVISION 03 – CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 05 – METALS

051300 STRUCTURAL STAINLESS-STEEL FRAMING

055000 METAL FABRICATIONS

055210 PIPE AND TUBE RAILINGS

DIVISION 26 - ELECTRICAL

260450 ELECTRICAL DEMOLITION & RENOVATION

260500 COMMON WORK RESULTS FOR ELECTRICAL – MATERIALS & METHODS GENERAL

260519 CONDUCTORS & CABLES

260526 GROUNDING & BONDING

260529 HANGERS & SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS & BOXES

260553 ELECTRICAL INDENTIFICATION

262416 PANELBOARDS & SWITCHBOARDS

262816 ENCLOSED SWITCHES & CIRCUIT BREAKERS

263600 AUTOMATIC TRANSFER SWITCHES

264313 SURGE PROTECTION

DIVISION 31 – EARTHWORK

310000 HISTORIC FILL

DIVISION 33 – SITE UTILITIES

334433 STORMWATER TRASH AND DEBRIS GUARDS

APPENDIX A- GEOTECHNICAL BORING LOGS

SC-1

SUPPLEMENTAL CONDITIONS

1.0 GENERAL

1.01 DEFINITIONS

The following words and expressions used in the contract documents shall be construed as follows:

Owner ......................................... City of Atlantic City 1301 Bacharach Boulevard Atlantic City, NJ 08401

Engineer . ................................... Remington & Vernick Engineers 2819 Fire Road, 1st Floor Egg Harbor Township, NJ 08234

Contractor. ................................. Party, firm, corporation with whom or which the contract is made, or authorized agent thereof.

Day ............................................. Calendar day.

Legal Holiday............................. Days which the owner does not conduct regular business hours. The

Contractor is responsible to contact the Owner for a listing of these days.

Substantial Completion ………. The work will not reach Substantial Completion until all project systems included in the work are operational as designed and scheduled, all designated or required inspections, certifications, permits, approvals, licenses and other documents from any governmental authority having jurisdiction thereof necessary for the beneficial use and occupancy of the work are received, designated instruction of Owner’s personnel has been completed, and all final finishes within the Contract are in place. Any remaining work shall be minor in nature, so that the Owner can occupy the building on that date and the completion of the remaining work by the Contractor would not materially interfere or hamper the Owner’s (or those claiming by, through or under the Owner) normal operations.

Contractor recognizes that normal operations require the use and occupancy of the work area without interruption and that any punchlist or corrective work shall be done at times when the work area is not so occupied. As a further condition of reaching Substantial Completion, the Contractor shall certify that all remaining work will be completed within thirty (30) consecutive calendar days or as so agreed upon following the date of Substantial Completion. Site related projects and/or projects including facilities with site improvements shall not reach Substantial Completion until such time as all site amenities (i.e. lighting, top paving, striping, fencing, stormwater compliance, etc..) are placed into service leaving only minor improvements that will not hamper access or use to complete the project.”

Final Completion ……………...All warranties and guarantees required pursuant to the Contract

Documents shall be assembled and delivered by the Contractor to the Owner as part of the final application for payment. The final Certificate for Payment will not be issued by the Engineer until all warranties and guarantees have been received and accepted by the Owner.

SC-2

1.02 CONSTRUING THE SPECIFICATIONS

To avoid disputes and litigation, it must be distinctly understood by the Bidder/Contractor that the Engineer shall construe or interpret the specifications and explain any ambiguity therein and shall have the right to decide as to their purpose and intent and his decision upon any such ambiguity shall be final, conclusive and binding.

1.03 TIME LIMITS

Should the Owner grant the Contractor an extension of Contract time, the Contractor shall not be due any compensation for the extended contract time unless specifically indicated in writing at the time of the extension. Failure of Owner or Owner’s Representative to expressly respond to a reservation of rights letter from Contractor reserving a right to additional compensation shall in no way be deemed an admission that Contractor is entitled to additional fees. Any costs associated with increased contract time due to approved change order work must be specifically identified included in the change order at the time of submission.

1.04 REFERENCE TO THE STANDARD SPECIFICATIONS

(a) All applicable portions of the work performed under this contract shall comply with the requirements of the current New Jersey Department of Transportation Standard Specifications for Road and Bridge Construction, as amended or supplemented and whose specifications are made part of these specifications. The New Jersey Department of Transportation Standard Construction Details shall govern except insofar as same are expressly modified, amended or changed in detail drawings prepared specifically for this particular project.

(b) The Standard Specifications are made part of these specifications by this reference as if were set forth in full. It is the responsibility of the prospective bidder to be familiar with these Standard Specifications. The Contractor is required to follow only the electronic version, effective September 1, 2019, as referenced in Baseline Document Change announcement BDC19S-01 of the New Jersey Department of Transportation Standard Specifications for Road and Bridge Construction, 2019, unless modified in the technical specifications of this contract. Copies may be examined in the Engineer's office or may be obtained from the New Jersey Department of Transportation.

2.0 CONDUCT OF THE WORK

2.01 CONTRACTOR TO ACT IN AN EMERGENCY

In case of any emergency which threatens loss or injury of property, and/or safety of life, the Contractor is required to act as he sees fit. He shall notify the Engineer thereof immediately thereafter.

2.02 EXTRA WORK

The Contractor further agrees that the Engineer may make such alterations as he may see fit in the form, dimensions, plans for materials of the work, materials and supplies bid upon or any part thereof, either before or after work. If such alterations diminish the quantity of the equipment, materials and supplies to be furnished and delivered to the site or work to be executed, they shall not constitute a claim for damages for anticipated profits on the work that may be dispensed with. If the extra work, change or alteration increases the amount of work to be performed or equipment, they shall be paid for at the price bid. If prices for such extra work are not included in the lump sum prices or unit prices bid, the Contractor hereby agrees to furnish the necessary materials and perform such labor as extra work, and agrees to

SC-3

accept in full payment therefore a price which shall be fixed by the Engineer previous to its commencement. The basis of such price will be the estimated actual cost of materials, labor, equipment, and a maximum 10% overhead plus a maximum 10% profit. Contractor shall furnish a detailed cost breakdown for proposed extra work for review by the Engineer. The Owner and/or Engineer has the sole authority to unilaterally direct extra work to be performed on a force account basis. The basis of payment for force account work shall be the actual cost of the materials, labor and equipment, and a maximum 10% overhead plus a maximum 10% profit. Contractor shall furnish a detailed cost estimate of the extra work to be paid by force account previous to its commencement. Contractor shall submit daily or shift reports for actual force account costs.

Payment for markup on subcontracted work shall be at a maximum rate of 5% of the total amount for all costs on the subcontracted work, for both fixed price and force account extra work. Change Orders and Open End Contracts will be in accordance with N.J.A.C. 5:30-11 et seq.

The Contractor shall not be entitled to receive payment for any extra work unless the same is certified in writing by the Engineer.

2.03 DISPUTE RESOLUTION

For construction contracts, the Owner and Contractor agree that in the event of a dispute arising under this contract, it shall be submitted to a process of resolution pursuant to alternative dispute resolution practices, such as mediation, binding arbitration or non-binding arbitration pursuant to industry standards, prior to being submitted to a Court for adjudication. Nothing in this section shall prevent the contracting unit from seeking injunctive or declaratory relief in court at any time. The alternative dispute resolution practices shall not apply to disputes concerning the bid solicitation or award process, or to the formation of contracts or subcontracts to be entered to pursuant to N.J.S.A. 40A:11-1 et seq. (Local Public Contracts Law).

Notwithstanding industry rules or any provision of law to the contrary, whenever a dispute concerns more than one contract, such as when a dispute in a contract involving design, architecture, engineering or management, upon demand of a contracting party, other interested parties to the dispute shall be joined unless the arbitrator or person appointed to resolve the dispute determines that such a joinder is inappropriate. Notwithstanding industry rules or any provision of law to the contrary, whenever more than one dispute of a similar nature arises under a construction contract, or related construction contracts, upon demand of a contracting party, the disputes shall be joined unless the arbitrator or person appointed to resolve the dispute determines that the disputes are inappropriate for joinder.

During any dispute the Contractor shall diligently proceed with completing the contract unless otherwise directed, in writing, by the Owner or Engineer.

3.0 MATERIALS

In all cases, new materials shall be used unless this provision is waived by notice from the Engineer.

4.0 INSPECTION AND TESTING

4.01 INSPECTION

Should the contractor have an emergency or need to cancel scheduled work, notification of the cancelled work must be received by the Engineer’s inspector no later than 6:00 am the morning of the cancellation.

Failure of the contractor to provide the required notification will require the contractor to pay for eight (8) hours of inspection at the rate of the Engineer’s local inspector. The costs for cancellation of inspection without the required notification will be deducted from the contractor’s payment application.

SC-4

5.0 PAYMENTS

5.01 CONSTRUCTION SCHEDULE AND PERIODIC ESTIMATES

Approval of the progress schedule by the Engineer does not modify the Contract or constitute Acceptance of the feasibility of the Contractor’s logic, activity durations, or assumptions used in creating the schedule. If the schedule reflects a completion date different than that defined by the date of Notice to Proceed and Contract Time, this does not change the specified completion date. If the Engineer approves a schedule that reflects a completion date earlier than that specified as the Contract Time, the Owner will not accept claims for additional Contract Time or compensation as the result of failure to complete the Work by the earlier date shown on the progress schedule. Float is the amount of time that an activity may be delayed from its early start without delaying Completion. Float belongs to the Project and is not for the exclusive use of the Contractor or the Owner.

6.0 DIFFERING SITE CONDITIONS PROVISIONS (N.J.S.A. 40A:11-16.7)

a. Differing Site Conditions Provisions:

(1) If the contractor encounters differing site conditions during the progress of the work of the contract, the contractor shall promptly notify the contracting unit in writing of the specific differing site conditions encountered before the site is further disturbed and before any additional work is performed in the impacted area.

(2) Upon receipt of a differing site conditions notice in accordance with Section 9.0(a)1 of this subsection, or upon the contracting unit otherwise learning of differing site conditions, the contracting unit shall promptly undertake an investigation to determine whether differing site conditions are present.

(3) If the contracting unit determines different site conditions that may result in additional costs or delays exist, the contracting unit shall provide prompt written notice to the contractor containing directions on how to proceed.

(4) (a) The contracting unit shall make a fair and equitable adjustment to the contract price and contract completion date for increased costs and delays resulting from the agreed upon differing site conditions encountered by the contractor.

(b) If both parties agree that the contracting unit’s investigation and directions decrease the contractor’s costs or time of performance, the contracting unit shall be entitled to a fair and equitable downward adjustment of the contract price or time of performance.

(c) If the contracting unit determines that there are no differing site conditions present that would result in additional costs or delays, the contracting unit shall so advise the contractor, in writing, and the contractor shall resume performance of the contract, and shall be entitled to pursue a differing site conditions claim against the contracting unit for additional compensation or time attributable to the alleged differing site conditions.

(5) Execution of the contract by the contractor shall constitute a representation that the contractor has visited the site and has become generally familiar with the local conditions under which the work is to be performed.

(6) As used in this subsection, “differing site conditions” mean physical conditions at the contract work site that are subsurface or otherwise concealed and which differ materially from those indicated in the contract documents or are of such an unusual nature that the conditions differ

SC-5

materially from those ordinarily encountered and generally recognized as inherent in the work of the character provided for in the contract.

b. Suspension of Work Provisions:

(1) The contracting unit shall provide written notice to the contractor in advance of any suspension of work lasting more than 10 calendar days of the performance of all or any portion of the work of the contract.

(2) If the performance of all or any portion of the work of the contract is suspended by the contracting unit for more than 10 calendar days due to no fault of the contractor or as a consequence of an occurrence beyond the contracting unit’s control, the contractor shall be entitled to compensation for any resultant delay to the project completion or additional contractor expenses, and to an extension of time, provided that, to the extent feasible, the contractor, within 10 calendar days following the conclusion of the suspension, notifies the contracting unit, in writing, of the nature and extent of the suspension of work. The notice shall include available supporting information, which information may thereafter be supplemented by the contractor as needed and as may be reasonably requested by the contracting unit. Whenever a work suspension exceeds 60 days, upon seven days’ written notice, either party shall have the option to terminate the contract for cause and to be fairly and equitably compensated therefore.

(3) Upon receipt of the contractor’s suspension of work notice in accordance with Section 9.0(A)2 of this subsection, the contracting unit shall promptly evaluate the contractor’s notice and promptly advise the contractor of its determination on how to proceed in writing.

(4) (a) If the contracting unit determines that the contractor is entitled to additional compensation or time, the contracting unit shall make a fair and equitable upward adjustment to the contract price and contract completion date.

(b) If the contracting unit determines that the contractor is not entitled to additional compensation or time, the contractor shall proceed with the performance of the contract work, and shall be entitled to pursue a suspension of work claim against the contracting unit for additional compensation or time attributable to the suspension.

(5) Failure of the contractor to provide timely notice of a suspension of work shall result in a waiver of a claim if the contracting unit can prove by clear and convincing evidence that the lack of notice or delayed notice by the contractor actually prejudiced the contracting unit’s ability to adequately investigate and defend against the claim.

c. Change in Character of Work Provisions:

(1) If the contractor believes that a change directive by the contracting unit results in a material change to the contract work, the contractor shall so notify the contracting unit in writing. The contractor shall continue to perform all work on the project that is not the subject of the notice.

(2) Upon receipt of the contractor’s change in character notice in accordance with paragraph (1) of this subsection, the contracting unit shall promptly evaluate the contractor’s notice and promptly advise the contractor of its determination on how to proceed in writing.

(3) (a) If the contracting unit determines that a change to the contractor’s work caused or directed by the contracting unit materially changes the character of any aspect of the contract work, the contracting unit shall make a fair and equitable upward adjustment to the contract price and contract completion date. The basis for any such price adjustment shall be the difference between the cost of performance of the work as planned at the time of contracting and the

SC-6

actual cost of such work as a result of its change in character, or as otherwise mutually agreed upon by the contractor and the contracting unit prior to the contractor performing the subject work.

(b) If the contracting unit determines that the contractor is not entitled to additional compensation or time, the contractor shall continue the performance of all contract work, and shall be entitled to pursue a claim against the contracting unit for additional compensation or time attributable to the alleged material change.

(4) As used in this subsection, “material change” means a character change which increases or decreases the contractor’s cost of performing the work, increases or decreases the amount of time by which the contractor completes the work in relation to the contractually required completion date, or both.

d. Change in Quantity Provisions:

(1) The contracting unit may increase or decrease the quantity of work to be performed by the contractor.

(2) (a) If the quantity of a pay item is cumulatively increased or decreased by 20 percent or less from the bid proposal quantity, the quantity change shall be considered a minor change in quantity.

(b) If the quantity of a pay item is increased or decreased by more than 20 percent from the bid proposal quantity, the quantity change shall be considered a major change in quantity.

(3) For any minor change in quantity, the contracting unit shall make payment for the quantity of the pay item performed at the bid price for the pay item.

(4) (a) For a major increase in quantity, the contracting unit or contractor may request to renegotiate the price for the quantity in excess of 120 percent of the bid proposal quantity. If a mutual agreement cannot be reached on a negotiated price for a major quantity increase, the contracting unit shall pay the actual costs plus an additional 10 percent for overhead and an additional 10 percent for profit, unless otherwise specified in the original bid.

(b) For a major decrease in quantity, the contracting unit or contractor may request to renegotiate the price for the quantity of work performed. If a mutual agreement cannot be reached on a negotiated price for a major quantity decrease, the contracting unit shall pay the actual costs plus an additional 10 percent for overhead and an additional 10 percent for profit, unless otherwise specified in the original bid; provided, however, that the contracting unit shall not make a payment in an amount that exceeds 80 percent of the value of the bid price multiplied by the bid proposal quantity.

(5) As used in this subsection, the term “bid proposal quantity” means the quantity indicated in the bid proposal less the quantities designated in the project plans as “if and where directed.”

SUMMARY 011000 - 1

SECTION 011000 – SUMMARY OF WORK

1.GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work under separate contracts.

5. Access to site.

6. Coordination with occupants.

7. Work restrictions.

8. Specification and Drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: Fisherman’s Park Pump Station Upgrades.

1. Project Location: Fisherman’s Park Melrose Ave. & N. Rhode Island Ave.

Atlantic City, NJ 08401

B. Owner: City of Atlantic City, NJ

C. Engineer: Remington, Vernick Engineers – (609) 645-7110, 2819 Fire Road 1st. Floor, Egg Harbor Township, NJ 08234.

Retain "Contractor" Paragraph below only if Contractor has been selected by negotiation and if subcontracts are subsequently bid.

D. It is anticipated that electrical transformers and equipment may have significant lead times for equipment delivery. The completion time for all work on the project, except electrical work, is 180 calendar days from the Notice to Proceed. The completion time for all electrical work shall be 30 days from the receipt of all required equipment and materials.

E. No compensation will be provided to the contractor for any delay caused by any utility company/operator in installing or relocating their facilities, but the contractor will be given a time extension equivalent to the time lost.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists, but not be limited to the following:

SUMMARY 011000 - 2

1. Furnish and install Stormwater Flow Control as required to de-water construction area.

All costs for the Stormwater Flow Control including temporary cofferdam, sheathing, shoring, pumps, and dewatering trenches and excavations if necessary shall be included in the cost as a lump sum for the item “Stormwater Flow Control (Cofferdam & Dewatering)” in the Bid Form. The location, materials, equipment and design of the cofferdam and dewatering trenches are the responsibility of the contractor. Contractor shall provide an engineered design, signed and sealed by a NJ Professional Engineer, for the cofferdam, pumps, and any other sheeting or shoring required for construction.

2. Excavate existing soils on site to the top slab of the existing concrete box culvert. The existing concrete top-slab is approximately 3.70 feet below finished grade as shown on the Contract Documents. All excavated soils shall be properly disposed off-site.

3. Sawcut and remove a 34’ x 12’ area of the concrete top-slab of the existing box culvert, approximately 12” thick. The existing concrete walls of the box culvert shall remain. The removed concrete top-slab and associated steel reinforcement shall be properly disposed off-site.

4. Furnish and install two (2) 20” D x 12” W cast-in-place concrete beams and associated steel reinforcement as detailed in the Contract Documents. The proposed cast-in-place concrete beams will bear on the existing box culvert walls which are to remain and also be doweled into the remaining box culvert top-slab as shown in the Contract Documents.

5. Furnish and install 12” thick cast-in-place concrete walls and associated steel reinforcement above new cast-in-place concrete beams as shown in the Contract Documents. Proposed concrete walls shall be doweled into cast-in-place concrete beams as detailed in the Contract Documents.

6. Furnish and install one (1) 14’-10” D x 10’ W Type 316L stainless steel bar screen as shown in the Contract Documents (Contractor to verify all dimensions prior to fabricating bar screen). This includes the installation of Type 316L stainless steel bottom/side connection tracks and Type 316L stainless steel W-shape members at the top of the proposed bar screen/netting trap locations and mid-span of the proposed bar screen as shown on the Contract Documents. The W-shape members shall be attached to the new cast-in-place concrete walls via stainless steel base plates and anchor bolts as detailed in the Contract Documents. Spacing of stainless steel bars for proposed bar screen shall be 2” clear.

7. Furnish and install one (1) netting trap system/bar screen as described in the Specifications. All connections to existing concrete walls shall be per manufacturer requirements. This also include the installation of a vertical bar rack system as a safety mechanism should the netting system detach.

8. Furnish and install three (3) wall-mounted Type 316 stainless steel access ladders as shown on the Contract Documents. This includes the installation of epoxy-grouted anchors as detailed in the Contract Documents.

9. Furnish and install 8” thick cast-in-place structural concrete top-slab as shown in the Contract Documents, including all associated steel reinforcement. Proposed openings for access hatches shall be installed as shown on the Contract Documents.

SUMMARY 011000 - 3

10. Furnish and install three (3) single-leaf 4’x10’ and one (1) single leaf 4’x4’ stainless steel access hatches as shown in the Contract Documents.

11. Furnish and install steel pipe piles for the proposed transformer pad as shown in the Contract Documents. Steel pipe piles shall be filled with 4000 PSI concrete and be driven to depths/capacity indicated in Contract Documents.

12. Furnish and install cast-in-place concrete grade beams for the proposed transformer pad as indicated on the Contract Documents, including all associated steel reinforcement.

13. Furnish and install cast-in-place concrete walls for the proposed transformer pad as indicated on the Contract Documents, including all associated steel reinforcement.

14. Furnish and install cast-in-place concrete structural top-slab for the proposed transformer pad as indicated on the Contract Documents, including all associated steel reinforcement.

15. Furnish and install cast-in-place concrete stair for the proposed transformer pad as indicated on the Contract Documents, including all associated steel reinforcement.

16. Furnish and install aluminum handrails around the perimeter of the proposed transformer pad as shown on the Contract Documents.

17. Disconnect and demolish the existing 100-amp, 230V phase electrical utility service and replace with a new 1000-amp 3 phase 480V. utility service, new Automatic Transfer switch and power distribution switchboard to operate the existing 500kW diesel generator, (2) 250HP Storm Water Pumps, and all associated equipment. All work shall include the necessary electrical demolition and electrical alterations to connect, restore, and provide a new electrical power distribution, new automatic transfer switch, raceways, electrical equipment, conductors, etc. as described on the contract drawings.

18. Furnish and install a new 1000-amp 3 phase 480V LSIG main circuit breaker with NEMA3R enclosure.

19. Furnish and install a new 1000-amp automatic transfer switch.

20. Furnish and install new 1000-amp 480V electrical distribution switchboard.

21. Revise and restore electrical interconnections to existing pump controllers and associated low voltage circuiting and controls.

22. Furnish and install new feeder cables, raceway, and control wiring as indicated on the contract drawings.

23. Restore all existing exterior surfaces to match existing surfaces.

24. The contractor is responsible to provide sheathing and shoring for the protection of the excavation, adjacent structures throughout all excavation and construction activities.

25. The Contractor is responsible for cleaning and restoration of the site to pre-construction conditions or better and shall provide all dumpsters as required.

B. Type of Contract:

SUMMARY 011000 - 4

1. Project will be constructed under a single prime contract.

1.4 ACCESS TO SITE

A. Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways, and Entrances: Keep driveways, standpipe, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANCY

A. Occupancy: The project location is an active storm water pump station designated to remove large volumes of storm water from the City streets. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Disruption of the utility service will need to be coordinated based on active weather conditions that are less likely to introduce high volumes of storm water. All utility electric power disruptions are to be coordinated with the local utility company and conducted in accordance with the Owner’s written permission two weeks prior to disruption, unless otherwise indicated by the owner’s representative and/or the City of Atlantic City Engineer.

1.6 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated or approved by the Owner.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two weeks in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Restricted Substances: Use of tobacco, alcoholic products, and any other controlled substances of any type or quantity on the project site and /or in possession is prohibited. Any and all legal actions will be at the discretion of the local law enforcement and at the full expense of the individual or responsible party.

SUMMARY 011000 - 5

E. Sanitary Facilities: Contractor is responsible for providing temporary bathroom facilities for contractor personnel.

F. Equipment and Material Storage: The contractor is fully responsible for all equipment and material stored at the project site. The general site is not a secure area. The contractor shall provide their own secure storage methods at no additional cost to the project.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by the Contractor unless specifically stated otherwise.

3. The word ‘provide’ means all inclusive (labor, materials, equipment, tools, etc.).

2.PRODUCTS (Not Used)

3.EXECUTION (Not Used)

END OF SECTION

AS-BUILT DRAWINGS 010100-1

SECTION 010100

AS-BUILT DRAWINGS

1.01 GENERAL

The Contractor shall assist the Owner in providing a set of reproducible as-built drawings prior to final payment in accordance with N.J.A.C. 7:14-2.2.

2.01 MATERIALS

A. As-builts shall be a reproducible of the original contract drawings including any additional sheets required. All deviations from the original contract drawings shall be on the as-builts. The drawings shall be legible, neat, and of a quality acceptable to the Engineer.

B. The Engineer shall provide a set of reproducibles at the beginning of the project.

3.01 EXECUTION

A. The Contractor shall be responsible for keeping the as-built up-to-date as the project progresses.

B. Sewer service connections shall be indicated by distance from the previous downstream manhole and a right or left distance off of the main. Locate the end of the lateral with tie dimensions to two permanent features and indicate depth of burial to the top of the pipe.

C. Water Services: Services shall be indicated by means of triangulation off of the front of the building. If no building exists, then by three permanent features.

D. Sewer Mains: Actual distance installed from center of manhole, actual elevations of manholes and rims shall be indicated on the drawings. Indicate slope, pipe size and type, and inverts.

E. Water Main and Force Mains: Actual distance installed, actual inverts at each bend, and high and low points. At each fitting, bend and gate valve, tie dimensions shall be provided to three permanent features.

F. Storm Sewer: Any change in invert, location, grate elevation, pipe size, class, or type, and any utility sleeves shall be indicated on the drawings.

G. Pump Stations/Building Construction: Actual installation with all items clearly identified shall be indicated. Location of installed items and any deviations from contract documents shall be so shown with boxes around the as-built numbers or labels.

H. This section is intended to provide a minimum level of acceptance. Any section with more stringent requirements shall have precedence over this section.

AS-BUILT DRAWINGS 010100-2

4.01 PAYMENT

No separate payment will be made for work performed under this section.

END OF SECTION 010100

CLEANING AND RESTORATIONS 017100-1

SECTION 017100

CLEANING AND RESTORATIONS

1.01 DESCRIPTION

A. Contractor shall provide all equipment, labor & materials required to clean and restore the site to at least the existing condition.

B. Maintain premises and public properties free from accumulations of waste, debris and rubbish caused by work operations.

C. At completion of work, remove waste materials, rubbish, tools, equipment, machinery and surplus materials; clean all sight exposed surfaces; leave project clean and ready for occupancy.

D. At completion of work, restore or replace, when and as directed by the Engineer, any public or private property disturbed or damaged by Contractor's work operations to a condition at least equal to that existing prior to beginning work, or as otherwise specified. Materials, equipment and methods shall be approved by the Engineer.

2.01 MATERIALS

A. For restorations all materials shall comply with the following Articles of the New Jersey Department of Transportation Standard Specifications latest revision and these specifications.

B. Grass restorations:

1. Topsoil shall conform to Subsection 909.10.

2. Seed Type "A" conforming to Subsection 909.06.

3. Fertilizer and lime shall conform to Subsection 909.02 & 909.03.

C. Pavement restorations: See Section 903 "Bituminous Concrete".

D. Restoration of curbs and other concrete structures:

1. Concrete:

a. Shall conform to Section 605 for Curbs, Section 607 for sidewalks and driveways, and Section 405 for concrete surface course.

b. Compressive Strength: 4,000 psi at 28 days.

CLEANING AND RESTORATIONS 017100-2

c. Air-entrained.

2. Joint Fillers: Section 908, bituminous cellular type.

3. Curing Compound: Section 905.03, white-pigmented liquid.

E. Driveway Restoration: Driveway Aprons shall be replaced in kind with Portland Cement Concrete, Bituminous Concrete or 3/4 inch stone. Dirt driveway aprons are to be upgraded to stone.

F. All other Materials: As approved by the Engineer or authorities having jurisdiction.

3.01 METHODS OF CONDUCTING WORK – CLEANING

A. Requirements of regulatory agencies:

The Contractor shall comply with all Federal, State, and local anti-pollution laws, ordinances, codes and regulations when disposing of waste materials, debris and rubbish. All excess material shall be removed from the site and disposed of by the Contractor. Cost to be included in the unit price bid for all items.

The disposal site shall be in permanently established licensed OSWA (Office of Solid Waste Administration, New Jersey Department of Environmental Protection) landfills or a NJDEP certified recycling center if applicable.

Requirements with regard to the location and control of stockpile, storage and disposal areas, whether provided by the project sponsor or the contractor, must conform to the following:

1. Only environmentally suitable stockpile sites may be used for the purposes of staging or storing materials, equipment and suitable trench backfill material. Environmentally suitable sites must be level, and devoid of mature stands of natural vegetation. Drainage facilities and features, wetlands, vernal habitats, and stream corridors are not environmentally suitable sites.

2. The boundary of the stockpile area shall be clearly marked by hay bales, silt fencing or another appropriate method. Where fill is to be stored in excess of 10 days, a suitable means of protecting excavated material from wind and water erosion shall be employed. Erosion control methods may include one or more of the following: mulching, sprinkling, silt fencing, haybaling and stone covering.

3. Excess excavated material which is not considered to be solid waste pursuant to N.J.A.C. 7:26-

1.6 shall be graded on-site only to the extent needed to achieve pre-construction grade, unless otherwise specifically approved by the Department. The project sponsor shall ensure that the contractor removes the remainder from the site and disposes of it at a site approved by the project sponsor in accordance with the following:

CLEANING AND RESTORATIONS 017100-3

i. Disposal sites selected by the contractor shall be evaluated and approved by the project sponsor prior to their use. Disposal sites may also be selected by the project sponsor. The project sponsor shall conduct periodic inspection of disposal sites to ensure compliance with the requirements of this subsection during the off-site disposal operation.

ii. The disposal of excess excavated material in wetlands, vernal habitats, stream corridors and floodplains is strictly prohibited, even if the permission of the property owner is obtained. The contractor shall be responsible to remove any fill improperly placed by the contractor at the contractor's expense and restore the area impacted.

iii. If excess excavated material is placed on private property, a hold harmless release in favor of the project sponsor and the Department shall be obtained from the property owner.

iv. Prior to approval of a site for excess excavated material disposal, where the site exceeds 5,000 square feet, the project sponsor shall obtain, or shall ensure that the contractor or property owner has obtained, the appropriate certification of the soil erosion and sediment control plan in accordance with the State's standards for soil conservation (N.J.S.A. 4:24-1 et seq., also referred to as Chapter 251). Where the site is less than 5,000 square feet, the project sponsor shall advise the property owner of the need for erosion and sediment control and obtain a statement that the property owner accepts complete responsibility for implementation of appropriate methods to prevent erosion and sedimentation.

B. Cleaning during construction:

Provide periodic cleaning to keep the work, the site, and adjacent properties free from accumulations of waste materials, rubbish and windblown debris resulting from construction operations.

Provide on-site containers for the collection of waste materials, debris and rubbish. Maintain containers as required.

C. Dust Control:

The Contractor will be required to maintain all excavations, embankments, stockpiles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which would cause a hazard or nuisance to others. Approved temporary method of stabilization consisting of sprinkling will be permitted to control dust. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor must have sufficient competent equipment on the job to accomplish this if sprinkling is used. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs. If any dust control is not done within twenty-four (24) hours after written notice is given by the Engineer, the work may be done by Owner and charged to the Contractor.

CLEANING AND RESTORATIONS 017100-4

In order to control dust, as often as required during each working day, and particularly prior to the conclusion of each working day areas under immediate construction (including access roads and other areas affected thereby) shall be swept and wet down with water sufficiently to lay dust. In addition, these areas shall be wet down during non-working hours (including weekends) as often as required to keep the dust under control. The use of calcium chloride or petroleum products or other chemicals for dust control is prohibited.

D. Prohibited construction procedures include, but are not limited to, the following:

1. Dumping of spoil material into any stream corridor, any wetlands, any vernal habitats, any surface waters, any sites listed or eligible for listing on the New Jersey or National Registers of Historic Places, or at unspecified locations;

2. Indiscriminate, arbitrary or capricious operation of equipment in any stream corridors, wetlands, vernal habitats or surface waters;

3. Pumping of silt-laden water from trenches or other excavations into any surface waters, stream corridors, wetlands or vernal habitats;

4. Damaging vegetation adjacent to or outside of the access road or the right-of-way;

5. Disposal of trees, brush or other debris in any stream corridor, wetlands, vernal habitats, surface waters or at unspecified locations;

6. Permanent or unspecified alteration of the flow line of any stream.

7. Open burning of project debris.

8. Use of calcium chloride, petroleum products or other chemicals for dust control; and

9. Use of asphaltic mulch binders; and

10. Any unpermitted discharge of sewage.

3.02 METHODS OF CONDUCTING WORK - RESTORATIONS

A. General: All existing structures, unpaved areas and paved areas disturbed or damaged during the work under this contract shall be restored or replaced to a condition at least equal to that existing prior to beginning work, or as otherwise specified. The methods of conducting this work shall, as a minimum, conform to the New Jersey Department of Transportation Standard Specifications, latest revision but shall not contradict the Department’s regulations, N.J.A.C. 7:22-10.11 and 10.12.

B. Grass Restorations:

See Section 808 "Fertilizing & Seeding" and Section 810 "Sodding".

CLEANING AND RESTORATIONS 017100-5

C. Pavement Restorations:

The methods of construction employed shall conform to the requirements set forth in Section 208, 304, 305 & 404 of the Standard Specifications as applicable to the type of material being utilized.

Restoration type and thickness shall be as shown on the contract drawings.

D. Restorations of Curbs and Other Concrete Structures:

1. Curbs: Section 605

2. Other concrete structures: Restore in accordance with applicable Sections of the Standard

Specifications.

E. Fence Restorations:

Contractor shall remove all concrete from existing fence posts and appurtenances before reinstalling fence in kind.

F. The aim of restoration is to restore the disturbed area to a condition as nearly equal to pre-disturbance conditions as possible. At a minimum, restoration measures shall conform to the following:

1. Final restoration shall be undertaken as soon as an area is no longer needed for construction, stockpiling or access. Excavated material unsuitable for backfill as set forth at N.J.A.C. 7:14-

2.13 and considered to be solid waste pursuant to N.J.A.C. 7:26-1.6 shall be removed from the construction site and disposed of at a sanitary landfill approved and licensed by the Department.

Excess excavated material which is not considered to be a solid waste pursuant to N.J.A.C.

7:26-1.6 shall be graded and removed in accordance with N.J.A.C. 7:22-10.11(l)3. When access roads are no longer needed, road fill shall be removed and the access area shall be restored to pre-disturbance conditions. Care should be taken to avoid damage to adjacent vegetation and to prevent the formation of depressions that would serve as mosquito pools.

2. Topsoil shall be replaced with adequate amounts of topsoil material to restore the disturbed area to its original, pre-disturbance grade and depth of topsoil.

3. Rates and types of fertilization, liming, and seeding shall be as recommended by the local Soil

Conservation District based on soil tests and local conditions. Seed mixtures shall be selected that are best suited for the particular site conditions. Seed selection shall provide for a quickly germinating initial growth, to prevent erosion, and for a secondary growth that will survive without continuing maintenance. Mulching shall occur immediately after seeding and in no case shall be more than five days elapse between seeding and mulching.

CLEANING AND RESTORATIONS 017100-6

4. In wooded areas, for a 50-foot wide construction easement, generally 10 trees should be planted for every 100 feet of length of the easement. More trees would be required in wider easements or densely wooded areas. Plans shall include a restoration schedule specifying the quantity, common and botanic names, sizes and spacing of trees to be planted and the type of seed mixtures to be used from station to station. Trees to be replaced should be trees native to New Jersey suitable for the particular site and generally should conform to the list of trees found in the “Standards for Soil Erosion and Sediment Control in New Jersey,” prepared by the New Jersey State Soil Conservation Committee, 1999, incorporated herein by reference, as amended and supplemented.

5. In landscaped areas, environmental features shall be replaced or restored to pre-disturbance condition or better. This includes sodding, replacement of trees and shrubs, fencing, drives, and other landscape features in kind.

G. All Other Restorations:

Restore in accordance with applicable Sections of the Standard Specifications, or as approved by the Engineer or authorities having jurisdiction.

4.01 QUANTITY AND PAYMENT

All costs for Site Restorations shall be included in the Lump Sum item bid as listed in the Proposal.

END OF SECTION 017100

DEWATERING AND FLOW DIVERSIONS 021400-1

SECTION 021400

DEWATERING AND FLOW DIVERSIONS

A. Dewatering of sheet piling, trenches and excavations.

1. A New Jersey Pollution Discharge Elimination System (NJPDES) Discharge to Surface Water (DSW) permit will be needed for any water from construction dewatering that may be discharged to surface water, regardless of the amount of water. Provided that the discharge is not contaminated, the appropriate discharge permit is the Category B7 – Short-term De-Minimus Discharge General Permit (see http://www.state.nj.us/dep/dwq/pdf/B7_RFA_Checklist.pdf). The contractor is responsible to obtain this permit.

2. Dewatering in excess of 100,000 gallons per day will require the contractor to obtain a temporary dewatering permit from the New Jersey Department of Environmental protection.

B. Bypass pumping of stormwater sewer system.

1. Bypass pumping operations are required by the Contractor whenever the following are being conducted:

a. Work which would disrupt the existing stormwater canal system 's operation.

2. The Contractor shall schedule the work in such a manner that work requiring by pass pumping is not scheduled within 12 hours after a rainfall or when rain is forecast to occur during the work.

3. The Contractor is responsible for providing adequate pumping capacity (with spare units) at the site.

4. Contractor shall provide an engineered design, signed and sealed, by a NJ Professional Engineer, for the cofferdam, pumps, and any or sheeting or shoring required for construction.

1.02 MATERIALS

Furnish pumps, carrier pipe, hoses, plugs, temporary lighting, and other equipment required for dewatering and flow diversion work.

1.03 METHODS OF WORK

A. Performance:

1. General:

a. Contractor shall prevent water to enter existing canal during construction.

http://www.state.nj.us/dep/dwq/pdf/B7_RFA_Checklist.pdf

DEWATERING AND FLOW DIVERSIONS 021400-2

2. Dewatering:

a. Prevent stormwater, surface water and subsurface or groundwater from flowing into excavations and from flooding project site and surrounding area.

b. Keep excavations and structures dry until all work is completed and pipe joints have satisfactorily hardened, and to extent that introduction of water in system will not damage either new or existing structures. Do not use trench excavations as temporary drainage ditches.

c. Dispose of water in suitable manner, without damage to work site or adjacent property.

d. Any sediment laden water from trench dewatering shall be filtered through approved sediment barriers prior to discharging into the…