TE -03 Measurement and Payment.docx
DOCX document 17 KB Posted
- Solicitation number
- W911QY-23-R-1021
View the file
Other files
| File | Type | Posted |
|---|---|---|
| TE -02 Submittal Register.pdf | ||
| TE -06 Temporary Construction Facilities and Controls.docx | DOCX document | |
| TE -05 Quality Control Program (QCP).docx | DOCX document | |
| TE -07 Operation and Maintenance Data.docx | DOCX document | |
| TE -01 (SOW) Design Requirements Statement of Work.docx | DOCX document | |
| TE -04 Administrative Requirements.docx | DOCX document | |
| Appendix B NSSC FACP Locations.pdf | ||
| Appendix A Ground Floor Plan Bld 1.pdf | ||
| Appendix C NSSC Campus Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Exhibit TE-03 Measurement and Payment Base Wide Wireless Fire Alarm Transmission System
| 1.1 | CONTRACT COST BREAKDOWN |
| The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its job pays items or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. | This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor. |
| 1.2 | JOB PAYMENT ITEMS |
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job payment item shall be included in the listed item most closely associated with the work involved.
A. Item Number 0001, "Design of Base Wide Fire Alarm Upgrade".
All costs for labor, equipment, and materials for the design of the base wide fire alarm upgrade, as shown on the contract drawings and in accordance with the specifications. This item includes all design work of this project.
Unit of Measure: Job.
B. Item Number 0002, "Construction of the Base Wide Fire Alarm Upgrade, Building #1” All costs for labor, equipment, and materials for the construction of the base wide fire alarm upgrade, as shown on the contract drawings and in accordance with the specifications. This item includes all construction work of this project.
Unit of Measure: Job.
A. C. Item Number 0003, "Construction of the Base Wide Fire Alarm Upgrade, All” All costs for labor, equipment, and materials for the construction of the base wide fire alarm upgrade, as shown on the contract drawings and in accordance with the specifications. This item includes all construction work of this project.
-- End of Section --
File details come from the government source that posted it. Updated .