Technical Exhibit TE-01

DESIGN REQUIREMENTS (STATEMENT OF WORK)

Base Wide Fire Alarm Transmission System Design-Build Construction and Installation

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. The current posted/referenced version of each publication (including all posted supplementary revisions, errata, etc.) for each item listed at the time of project award shall be used.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI/SDI A250.8 Specification for Standard Steel Doors and Frames (SDI-100)

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 7 Minimum Design Loads and Associated Criteria for Buildings and Other Structures

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING ENGINEERS (ASHRAE)

ASHRAE 90.1 Energy Standard for Buildings except Low-Rise Residential Buildings

ASHRAE EQUIP IP HDBK Handbook, HVAC Systems and Equipment (IP Edition)

ILLUMINATING ENGINEERING SOCIETY (IES)

IES Lighting HandbookThe Lighting Handbook, 10th Edition INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 81Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System

INTERNATIONAL CODE COUNCIL (ICC)

IBC International Building Code

IgCC International Green Construction Code

IMC International Mechanical Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 1 (2018) Fire Code

NSSC - Base Wide Fire Alarm Transmission Natick, MA

NFPA 10 (2018) Standard for Portable Fire Extinguishers

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4) National Electrical Code

NFPA 70E (2021) Standard for Electrical Safety in the Workplace

NFPA 72 (2019; TIA 19-1; ERTA 2019) National Fire Alarm and Signaling Code

NFPA 80 (2019) Standard for Fire Doors and Other Opening Protectives

NFPA 90A (2018) Standard for the Installation of Air- Conditioning and Ventilating Systems

U.S. ACCESS BOARD (ABA)

ABA Standards Architectural Barriers Act

U.S. ARMY CORPS OF ENGINEERS (USACE)

TI 800-01 Technical Instructions Design Criteria

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC
1-200-01
DOD Building Code
UFC
1-200-02
High Performance and Sustainable Building Requirements
UFC
3-101-01
Architecture
UFC
3-401-01
Mechanical Engineering
UFC
3-410-01
Heating, Ventilating, and Air Conditioning Systems
UFC
3-600-01
Fire Protection Engineering for Facilities
UFC
4-010-06
Cybersecurity of Facility-Related Control Systems
UFC
4-021-01
Design and O&M: Mass Notification Systems

UNDERWRITERS LABORATORIES (UL)

UL 467 UL Standard for Safety Grounding and Bonding Equipment

UL 827 (2013) UL Standard for Safety; Central- Station Alarm Services

U.S. DEPARTMENT OF ENERGY (DOE)

FEMP Federal Energy Management Program

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

EISA Energy Independence and Security Act

EPAct-2005 Energy Policy Act of 2005 (Pub.L. 109–58)

1.2 SUBMITTALS NOT USED

1.3 PROJECT BACKGROUND AND SCOPE

1.3.1 Background

1.3.1.1 General

A functional fire protection system is a priority requirement for the U.S. Army Garrison Natick - Natick Soldier System Center (NSSC). The existing Simplex Fire Alarm system’s fiber optic lines are approaching 25 years of age and the existing fire panels are nearly 15 years old. Recent tests show fiber strands degraded in various areas, crushed conduit, open lines around buildings, lines that have been completely removed in various sections, intermittent signal problems between buildings, and a list of other abnormalities. Additionally, Johnson Controls/Simplex has notified the Garrison that they will no longer be able to support repairs due to the status of the existing fiber lines. Parts for panel repairs are becoming increasingly difficult to find and the Garrison has been forced to use/recycle system components from existing panels across installation that are in process of demolition or removal. Given the condition of the existing fiber loop, NSSC has determined that either system wide repairs must be conducted or some alternate means for ensured reporting is required.

The fire alarm system ultimately “belongs” to NSSC’s Department of Public Works (DPW) for installation, operation, maintenance, and repairs. The U.S. Army Corps of Engineers (USACE) New England District (CENAE) is currently working on fire suppression upgrades for several buildings across the Garrison, but relevant guidance/regulations require that all signals must be able to report locally once in place. Therefore, DPW has requested CENAE’s support to address the failing system and to make necessary panel/system upgrades/replacement/repairs.

It was determined that a decoupled, wireless fire alarm system was preferred by NSSC. The new system would require a minimum of 2 receivers, 2 decoders, and wiring - with wireless (mesh) connectivity that allows system transmission interlink (crosstalk). This type of system offers flexibility in installation, maintenance and repairs since each system component operates independently minimizing system-wide impacts/outages during installation, maintenance, or repairs. This type of system will support a phased construction approach rather than requiring a comprehensive site-wide system installation effort, which would be cost prohibitive.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

The purpose of this project is to provide Soldier Systems Center at Natick, Massachusetts, a reliable and code compliant means of transmitting fire alarm signals from existing fire alarm systems located in individual buildings to a central receiving station located in Building 1. Currently, Natick uses a fiber optic cable loop to connect their Simplex fire alarm panels to the existing Simplex central receiver. This loop is not fully functional; there are five (5) legs in the loop that are non-functioning and unable to transmit and there are four (4) building fire alarm panels which have not yet been connected to the loop.

The Contractor must design and install a radio transceiver system that consist of transmitter panels and antennae at each building and central- station receiving equipment in Building 1. This system must be totally independent of the existing system and constructed in parallel without affecting the existing system’s operation. The existing Simplex receiving equipment and fiber optic cabling/equipment must not be demolished until the new radio system is operational and formal acceptance testing is complete.

1.3.1.2 Supporting Documents Appendix A - Schematic Drawings Appendix B – NSSC FACP Locations Appendix C – NSSC Campus Map

1.3.2 Scope of Work

1.3.2.1 Contractor Responsibility

The Contractor shall be responsible for performing all design and construction as outlined in this Statement of Work (SOW) and the following attachments.

1.3.2.2 Design After Award

The Contractor shall comply with all requirements stipulated in Specification Section 01 33 16 DESIGN DATA (DESIGN AFTER AWARD).

1.3.2.3 Field Verification

The Contractor shall thoroughly field verify existing conditions, equipment, measurements and dimensions prior to any design and construction activities.

1.3.2.4 Specifications

It is the intent of the specifications to provide performance requirements for the Contractor's design-build team; they are not intended to be complete. The Contractor is responsible to provide full construction document specifications, as described in Section 01 33 16 DESIGN DATA (DESIGN AFTER AWARD) that meet or exceed the performance requirements of the RFP documents including NSSC and USACE requirements. The standards and codes referenced in the narrative set the minimum performance requirements for the Contractor's specifications.

1.3.2.5 NOT USED

NSSC - Base Wide Fire Alarm Transmission Natick, MA

1.3.2.6 NOT USED

1.3.2.7 Attached Drawings/Tables

The attached drawings/design tables in Appendix A are developed to a schematic level and providing programmatic information only. It is the intent of the drawings/design tables to provide preliminary direction and program for the Contractor's design build team; they are intended to communicate design intent and cannot be used as construction documents.

Code requirements must be evaluated by the Design-Build Contractor. The contractor is responsible to complete the full design and the construction documents to satisfy all requirements set by the RFP documents. These RFP documents do not relieve the Contractor from providing all requirements for a fully functional and operational system. The design must meet all applicable codes and standards as well as all requirements set by NSSC and USACE.

1.3.2.8 Notification

The Contractor shall note that research into existing underground utilities and submittal and Government approval of a report of the findings is required prior to all work involving existing ground disturbance.

1.3.2.9 Construction Site and Access Coordination

Prior to work commencement, coordinate location of job boxes and vehicle access in cooperation with the Contracting Officer and the Installation DPW, as needed.

1.3.3 General Technical Requirements

1.3.4 HVAC Mechanical System Testing and Balancing

The contractor shall perform testing and balancing (TAB) on multiple existing HVAC systems that service equipment closet 035 located in Building 1 basement including the chilled water system serving the blower coil unit, the fan coil unit serving the equipment closet, and the exhaust fan and associated distribution that serves the equipment closet. TAB shall be completed in alignment with UFGS Section 23 08 01.00 20 requirements.

The existing systems shall be modified and balanced in order to meet the design cooling and exhaust flow rates as calculated for the space per the direction of the mechanical design section. TAB shall be performed for the entire chilled water and exhaust systems serving the equipment closet pre- construction and post-construction in order to allow other spaces connected to the systems to continue to operate at the same existing pre-construction levels.

1.3.5 Architectural Scope of Work

1.3.5.1 General

An existing equipment closet located within the basement of Building 1 currently houses the existing fire alarm monitoring and communication panel. The room is currently not constructed to maintain a fire rating and as part of the scope of this project the room will be required to maintain a 2-hour fire rating for Equipment Closet 035.

1.3.5.2 Architectural Existing Conditions

The room is currently not constructed to maintain a fire rating although the walls of the room are constructed of CMU block. The walls as they exist are 2 hour rated. The existing entry door/frame does not carry a fire rating, therefore will be required to be replaced. The existing space has multiple wall penetrations that will be required to be sealed.

1.3.5.3 Accessibility

The scope of the project does not include any accessibility scope.

1.3.5.4 Architectural Demolition

The demolition scope of the project includes full demolition of the existing door/frame for the Equipment Closet 035. Additional wall hung components within the room may be designated for demolition by NSSC DPW staff.

1.3.5.5 Architectural New Work

The door/frame will be required to be replaced with a 90-minute rated door/frame and hardware, all new and existing penetrations to the room need to be fireproofed.

1.3.5.5.1.1 Openings

1.3.5.5.1.1 Door and Frame

Contractor is to provide new out swinging entry door/frame for existing Equipment Closet 035. Door/frame to match the same size as the existing door. The door/frame is to be a 90-minute rated door/frame system and is to be installed per manufacturers requirements to maintain fire rating within the wall assembly. Provide ¾” undercut on door to allow for air intake for Equipment Room 035.

Door/frame is to be painted on both the interior and exterior. Paint door and frame to match existing conditions. Contractor to verify with the COR for final paint colors.

1.3.5.5.1.2 Hardware

Provide door hardware to match existing style and color of existing door. Door hardware to meet same fire rating as door. Provide locks that are compatible with the NSSC DPW existing Best 7-pin small format core; NSSC DPW will core and key the door.

1.3.5.5.2 Interiors

1.3.5.5.2.1 Interior Walls

The existing interior walls of the room shall be cleaned and repainted after all penetrations have been sealed. Contractor to verify with COR to confirm final paint color.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

The contractor is responsible for all touch up paint on the corridor wall adjacent to the equipment closet. Contractor is to match existing color of corridor wall.

1.3.5.5.2.2 Room Penetrations

All new/existing penetrations through the through wall, ceiling, and floor shall be properly infilled with adjacent wall material and sealed with fireproofing material to maintain 2-hour fire rating. This includes where existing ducts and louvers are to be infilled.

1.3.5.5.2.3 Flooring Clean existing floor.

1.3.6 Mechanical (HVAC) Scope of Work

1.3.6.1 General

An existing equipment closet located within the basement of Building 1 contains multiple data racks that require continuous cooling. The closet is currently cooled via a blower coil unit connected to a chilled water system. Natick staff has communicated that the closet has had difficulty to maintain a set point of 75˚F and has questioned the capacity and performance of the existing blower coil unit. The chilled water distribution system currently serving the blower coil unit is currently being primarily controlled to cool the adjacent police station. The supply chilled water temperature is currently being adjusted to accommodate the cooling loads of the police station. The closet is currently ventilated by an exhaust system that pulls air from the corridor via existing door intake louver.

As part of this project the chilled water system controls and system flows are to be modified as required to allow the blower coil unit to operate in a greater capacity and provide sufficient cooling to the closet. The entire chilled water system and blower fan coil unit are to have TAB performed pre- construction and post construction.

The existing exhaust air system is currently not operating due to a broken belt on the fan. The fan belt is to be replaced and the overall system is to have TAB performed pre-construction and post-construction in order to confirm ample air changes are occurring within the closet. A new fire rated entry door will be installed in order to achieve a 2-hour fire rating for the closet. The new door is to have a compliant door undercut in order to allow for transfer air into the space.

1.3.6.2 Mechanical (HVAC) Existing Conditions

The existing closet has a suspended horizontal 2-ton blower coil unit that is fed via a chilled water loop that is dedicated to the campus police station. The existing unit has a 1/3 HP blower fan. The unit drains condensate to a floor drain located on the floor below the unit. Natick staff has communicated that the current blower coil unit is unable to maintain a desired 75˚F setpoint during the summer cooling season. Upon further discussion with Natick staff, it was communicated that the operational temperatures of the chilled water loop tend to vary as they are controlled primarily for comfort cooling of the adjacent police station. The current piping connection which is believed to be located at the end of the

NSSC - Base Wide Fire Alarm Transmission Natick, MA circulation loop looks to not currently contain the ability to allow for bypass flow.

There are two data rack radiant cooling panels and associated modulating controls box located within the space that are not in use. The radiant cooling system used to also be connected to the same chilled water system. Natick staff have communicated that the systems were ineffective and can be removed as part of this project.

The closet contains the end of two exhaust duct risers. The first riser has a large tap to an exhaust grille that is on the other side of the closet wall that serves the adjacent atrium space. The first riser also has a tap for a spiral duct that runs through the space to the opposite wall where it penetrates the wall and serves room exhaust for the adjacent mechanical room. The second riser has an opening for exhaust out of the equipment closet. The exhaust duct risers are believed to route back to a roof mounted exhaust fan. The fan motor is currently operating but the fan belt is broken therefore the fan system is not currently operating.

The entry door currently contains an intake louver located on the lower portion of the door to allow for air intake to the closet.

1.3.6.3 Mechanical (HVAC) Demolition

The scope of this project includes demolition of the data rack radiant cooling panel system including modulating controller, removing the exhaust intake currently serving the adjacent atrium space, and removal of existing steam system piping within the space.

1.3.6.4 Mechanical (HVAC) New Work

The existing chilled water system and blower coil unit shall be modified and have TAB performed to accommodate the existing heat gain of the current data rack equipment and all equipment being added as part of this project. The piping connection to the new unit shall be modified to allow for bypass flow and a new control valve shall be provided for the unit.

Exhaust CFM for the closet shall be sized and balanced based on a 1 CFM/SF basis. The additional duct opening in the upper corner of the room shall be modified as required. The roof mounted exhaust fan shall be cleaned, greased, and have the belt changed as part of this project. The fan and ductwork shall be balanced to achieve design flows as part of this project’s testing and balancing.

All exhaust duct penetrations shall have a 2-hour rated fire damper installed within the ducted opening on the interior of the room in order to maintain the new 2-hour fire rating requirement. Fire caulking shall be installed at all duct penetrations to create a rated seal.

1.3.6.4.1 Equipment

Contractor shall provide all equipment, tools, materials, parts, components, and services to perform all contract requirements. All replacement parts and components shall be new, industrial grade, equal to or better than the manufacturer’s original equipment specifications and compatible with existing systems. All parts and materials shall be standard products of manufactures regularly engaged in the production of such products. If new

NSSC - Base Wide Fire Alarm Transmission Natick, MA parts are not available; the Contractor may request approval in writing from the COR to use rebuilt parts. Use of rebuilt parts before receipt of approval or without approval is at the risk of the Contractor. All parts whether new or rebuilt shall carry the full warranty as required by this contract.

All new equipment shall be factory packaged and tested. Use products of one manufacturer where two or more items of the same kind of equipment are required. Access clearance around equipment shall be per manufacturer’s requirements/recommendations. New HVAC equipment and systems shall meet the minimum requirements of ANSI/ASHRAE/IESNA Standard 90.1. The contractor shall purchase Energy Star or FEMP designated products. The term “Energy Star product” means a product that is rated for energy efficiency under an Energy Star program. The term “FEMP designated product” means a product that is designated under the Federal Energy Management Program of the Department of Energy as being among the highest 25 percent of equivalent products for energy efficiency. In the case of an electric motor of 1 to 500 horsepower the Contractor shall select only a premium efficient motor.

No part shall be utilized for any purpose other than that which it has been designed and manufactured. The Contractor shall retain all replaced parts for at least ten (10) working days and upon request make them available to the Government for inspection.

Materials containing Asbestos or PCB’s or lead based paints shall not be brought on-site.

Unless otherwise specified, equipment and component items, when fabricated from ferrous metal, shall be factory finished with the manufacturer's standard finish, except those items located outside of buildings shall have weather resistant finishes that will withstand 500 hours of exposure to the salt spray test specified in ASTM B 117 using a 5 percent sodium chloride solution. Immediately after completion of the test, the specimen shall show no signs of blistering, wrinkling, cracking, or loss of adhesion and no sign of rust creepage beyond 1/8 inch on either side of the scratch mark. Cut edges of galvanized surfaces where hot-dip galvanized sheet steel is used shall be coated with a zinc-rich coating conforming to ASTM D 520, Type I.

Design and locate all systems to be easily repaired and maintained. Allow adequate size equipment and room doors and clearances for repair, service, and component removal without it being necessary to remove other mechanical or electrical equipment and materials.

Provide identification for all equipment, piping and ductwork. Comply with ANSI A13.1 for piping. Provide valve tags for all valves and provide valve schedules framed in the existing mechanical room.

1.3.6.4.2 Vibration Isolation

Mechanical systems shall not transmit or radiate any perceptible noise or vibration to occupied spaces.

1.3.6.4.3 Equipment Access

Locate and orient equipment and components to provide manufacturer- recommended clearances. Provide access doors in walls and inaccessible ceilings for system devices that require manual operation or maintenance.

1.3.6.4.4 Utility Penetrations

Provide sleeves for piping penetrations through walls, partitions, and elevated floor slabs. Provide water stopping material between pipes and sleeves where pipes pass through exterior roof. Provide escutcheon plates on all pipe penetrations exposed in occupied spaces. Extend pipe sleeves above the floor in mechanical rooms above grade and seal to make watertight. Any penetrations of fire-rated assemblies must utilize a fire-stop assembly or device that is UL-listed and FM-approved for a rating to match the penetrated assembly. Refer to section 1.3.9.8 for requirements for firestopping utilities.

1.3.8.4.5 Patch and Repair

The Contractor shall be required to patch and repair any damage to building finishes caused by work under this contract. Any parts, equipment or materials damaged during the performance of the contract shall be replaced or repaired by the Contractor at no additional cost to the Government.

1.3.6.4.6 Basement Building 1 Equipment Closet

The blower coil unit flows and supply temperature shall be calculated based on the heat gain of the new and existing data rack equipment within the closet. The exhaust grille and flow CFM shall be sized based on the square footage of the closet to achieve a minimum airflow rate.

1.3.6.4.7 Indoor Design Conditions

Indoor design conditions for the Comm Rooms/Electrical Room shall be: Cooling: 72°F dry bulb, maximum 50% RH

1.3.6.4.8 Ventilation / Indoor Air Quality

Indoor air quality, including ventilation rates and air filtration, shall be in accordance with ASHRAE 62.1, UFC 3-410-01, and UFC 1-200-02.

Design Exhaust Airflow Rate: Min 1 CFM/SF

1.3.6.4.9 Space Design Cooling/Heating Loads

Design heating and cooling load calculations shall be completed per requirements of UFC 3-410-01.

1.3.6.4.10 Protection of Existing Systems

Existing equipment and distribution ductwork shall be fully protected from damage and intrusion of any dust or debris resulting from construction or any other execution of this work. Contractor shall provide filter replacements to the existing air handling units every 30 days of construction at a minimum for all units that serve the renovated area of proposed spaces and all areas directly adjacent to the proposed area.

1.3.6.4.11 Serviceability and Maintainability

Locate all equipment so that service, adjustment and replacement of controls or internal components are readily accessible for easy maintenance.

Indicate on the design drawings minimum access requirements and clearance areas for major mechanical equipment.

1.3.6.4.12 Warranty

Provide a 1-year unconditional warranty on the installed systems and on all service call work. The warranty shall include labor and material necessary to restore the equipment involved in the initial service call to a fully operable condition.

1.3.6.4.13 Training

Provide training at the project site on the installed HVAC systems. Upon completion of this training, each student, using appropriate documentation which shall be provided by the Contractor, shall be able to start the system, operate the system, recover the system after a failure, perform routine maintenance and describe the specific hardware, architecture, and operation of the system.

1.3.6.4.14 Operation and Maintenance (O&M) Manual

The Contractor shall provide three (3) hardcopies of the O&M Manual for the HVAC systems installed. In addition to the three (3) hardcopies, the Contractor shall provide electronic files of the O&M manual in Adobe Acrobat (pdf) format on a CD or DVD disk. Three (3) disks containing the O&M manual files shall be provided. The Contractor shall provide laminated instruction cards for each HVAC controller provided. Instructions shall describe the operation of each button on the controller and any additional instruction needed to operate the HVAC system.

1.3.6.4.15 Energy Efficiency

HVAC systems that are part of this renovation shall achieve an energy performance in accordance with the applicable requirements of UFC 1-200-02, Section 2-3.1.3 Renovations, and that is life cycle cost effective. Energy calculation methodologies and substantiation requirements are defined in Section 01 33 16 DESIGN AFTER AWARD.

1.3.7 Mechanical (Plumbing) Scope of Work

1.3.7.1 General

No plumbing scope of work is required for the proposed scope of work.

1.3.8 Electrical Scope of Work

1.3.8.1 General

The NSSC campus consists of 28 buildings that will require to have the fire alarm transmission systems updated. Each building currently has a fire alarm panel. Provide power to all new equipment associated with the fire alarm upgrades as indicated herein. Coordinate final power requirements with all trades.

Provide power to all Government Furnished Contractor Installed (GFCI)

NSSC - Base Wide Fire Alarm Transmission Natick, MA

Equipment.

1.3.8.2 Electrical Existing Conditions

In general, all existing light fixtures, controls, receptacle devices, junction boxes, electrical equipment, telecommunication, security, and/or access control devices shall remain within the existing NSSC buildings unless otherwise indicated herein. Existing 120/208V distribution shall be utilized as indicated in Section 1.3.8.4 to support the necessary fire alarm upgrades.

1.3.8.3 Electrical Demolition

The existing basement Building 1 closet lighting fixtures and controls shall be removed and replaced with new. Existing 120V lighting branch circuit(s) shall be maintained for connection to new fixtures as controls as required. No additional demolition work is included in the current scope of the project.

1.3.8.4 Electrical New Work

Provide a dedicated 120V, 20 ampere branch circuit to the fire alarm control equipment as indicated in Table 1.3.8.4-1. The new circuit breaker(s)in existing panelboards shall be lockable, red in color, with the words LIFE SAFETY printed in white letters. New breaker(s) shall match existing infrastructure manufacturer, characteristics, and interrupting capacity.

Power wiring, operating at 120VAC minimum, must be No. 12 AWG copper, Type THWN/THHN or Type XHHW. Conductors No. 10 AWG and smaller diameter shall be solid, No. 8 AWG and larger diameter shall be stranded. Provide insulated conductors installed in rigid steel conduit or EMT, except where specifically indicated otherwise or required by NFPA 70.

Table 1.3.8.4-1: Dedicated Equipment 120V Circuit Sources

Bldg.
Branch Circuit Panel
Horizontal Run Length

(ft)

Branch Circuit Wiring
Ceiling Type(s)
Remarks
B1
Panel E –
95.61
Two (2) 2#8
Suspended/Open
Receiver in
Circuits #39
[29.14]
AWG & 1#8 AWG
Ceilings
Room 035.

& #41(Storage 32A)

GND – 3/4" C.

B1
Panel E –
104.21
2#8 AWG & 1#8
Suspended/Open
Workstation
Circuit #36
[31.7m]
AWG GND – 3/4"
Ceilings
in Room 022.

(Storage 32A)

C.

B2
Panel L3 –
47.57
2#12 AWG &
Suspended
Unable to

Circuit #41 (Corridor

[14.5m]
1#12 AWG GND –

3/4" C.

Ceilings
Locate

Existing FACP

Adjacent to

Feed.

Restrooms)

B3
Panel BC –
42.98
2#12 AWG &
Open Ceilings
Circuit #39
[13.1m]
1#12 AWG GND –

(Basement

3/4" C.

Corridor)

B4
Panel EDP1-A
44.62
2#12 AWG &
Suspended
– Circuit #8
[13.6m]
1#12 AWG GND –

3/4" C.

Ceilings

(Basement Mech. Room)

B5
Panel B5-F1- R143-PNLA –

Circuit #40 (Main Corridor)

26.25 [8.0m]
2#12 AWG &

1#12 AWG GND –

3/4" C.

Suspended Ceilings
Unable to Located Existing FACP Feed.
B7
Panel MP-1 – Circuit #42

(Mech. Room)

51.51 [15.7m]
2#12 AWG &

1#12 AWG GND –

Suspended/ Open Ceilings

B8
Panel 2 –

Circuit #12 (Room 100 Rear)

22.33 [6.81m]
2#12 AWG &

1#12 AWG GND –

Suspended Ceilings @ FACP

B14
Panel P1 – Circuit #27 (Mech. Room)
164.04 [50m]

Length of Bldg.

2#6 AWG & 1#6 AWG GND – 3/4" C.
Open Ceilings @ FACP
No Access to Fitness Area.
B15
Panel PP2 or PP4 (Basement Mech X003)
80.00 (24.38m)
2#10 AWG &

1#10 AWG GND –

3/4" C.

Unknown
Building Under Construction at Time of

Survey.

B16
Unnamed Panel – Circuit #38 (Adjacent to

Restrooms)

67.26 (20.5m)
2#10 AWG &

1#10 AWG GND –

3/4" C.

Suspended Ceilings
Unable to Located Existing FACP

Feed.

B19
Panel E – Circuit #17 (Adjacent to

FACP)

10 [3.05m]
2#12 AWG &

1#12 AWG GND –

3/4" C. (RMC)

Open Ceilings
Boiler Plant.
B20
Panel LP-7 – Circuit #26 (Adjacent to

FACP)

10 [3.05m]
2#12 AWG &

1#12 AWG GND –

Suspended Ceilings

B23
Panel L – Circuit # 6 (Elec/Telecom

106)

50.00 (15.24m)
2#12 AWG &

1#12 AWG GND –

Open Ceilings

B24
Panel LP – Circuit #15 (Electric

Room)

8.00 (2.44m)
2#12 AWG &

1#12 AWG GND –

Open Ceilings @ FACP

B25
Panel MDP (Electrical Closet)
54.13

(16.5m) to Elec.

Closet

2#12 AWG &

1#12 AWG GND –

3/4" C.

Suspended Ceilings
Electrical Closet Inaccessible at Time of

Survey.

B26
Panel PP – Circuit #2

(Warehouse)

15 (4.57m)
2#12 AWG &

1#12 AWG GND –

3/4" C. (RMC)

Open Ceilings
Warehouse.
B27
Panel A – Circuit #19

(Warehouse)

15 (4.57m)
2#12 AWG &

1#12 AWG GND –

3/4" C. (RMC)

Open Ceilings
Warehouse.
B32
Panel B1 – Circuit #1 (Mechanical

D2)

77.10 (23.5m)
2#10 AWG &

1#10 AWG GND –

Suspended/Open Ceilings

B36
Panel PL-2 – Circuit #2 (Mechanical

Room)

190.29 (58m)
2#6 AWG & 1#6 AWG GND – 3/4" C.
Suspended/Open Ceilings
B39
Panel PNL 2 – Circuit #9 (Utility

Room)

68.90 (21m)
2#10 AWG &

1#10 AWG GND –

Suspended Ceilings

B42
Panel EL1B – Circuit #5 (Corr.

Electric Closet)

114.83 (35m)
2#8 AWG & 1#8 AWG GND – 3/4" C.
Suspended Ceilings
Carefully Coordinate Transmitter Cabinet Location with Building

Manager.

B42A
Panel P2B – Circuit #14

(Corridor)

46.59 (14.2m)
2#12 AWG &

1#12 AWG GND –

Suspended Ceilings

B44
Unlabeled Panelboard (Adjacent to

Water Cooler)

38.39 (11.7m)
2#12 AWG &

1#12 AWG GND –

3/4" C.

Suspended Ceilings
No Panelboard Directory.
B45
Panel DPB – Circuit #21 (Bsmnt. Main Electric

Caged Area)

131.23 (40m)
2#8 AWG & 1#8 AWG GND – 3/4" C.
Suspended/Open Ceilings
B66
Unnamed Panel – Circuit #19

(Workshop)

17.00 (5.18m)
2#12 AWG &

1#12 AWG GND –

Open Ceilings

B86
Panel PP1 or PP2 (Basement Elec. Room)
80.00 (23.47m)
2#10 AWG &

1#10 AWG GND –

3/4" C.

Suspended Ceilings
No Spares Visible in PP1 at Time

of Survey.

B92
Panel LPA – Circuit #19 (Electrical

105)

60.00 (18.29m)
2#10 AWG &

1#10 AWG GND –

Suspended Ceilings

B110
Panel B2 – Circuit #34 (Mechanical

Room)

100.72 (30.7m)
2#8 AWG & 1#8 AWG GND – 3/4" C.
Suspended/Open Ceilings

Note: Electrical contractor shall verify existing conditions to confirm exact run lengths of intended branch circuits.

New high efficiency LED lighting fixtures shall be provided within Building #1 Battery Room 035 to replace existing. New lighting shall be pendant, or wall mounted as required to achieve lighting levels requirements within UFC 3-530-01 INTERIOR AND EXTERIOR LIGHTING SYSTEMS AND CONTROLS. New lighting controls shall meet the minimum requirements of UFC 1-200-02 and its ASHRAE

90.1 requirements.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

1.3.8.4.1 Materials and Equipment

Materials, equipment, and devices shall, as a minimum, meet the industrial grade requirements of Underwriters Laboratories (UL) where UL standards are established for those items. Materials and associated design and installation shall meet or exceed the minimum standards specified in the applicable UFCs. The Designer of Record (DOR) shall use the Unified Facility Guide Specifications (UFGS) as template to prepare the project specific specifications. Use the latest editions or where applicable the superseding documents. The designers of record shall edit and expand the appropriate specifications to ensure that all project design requirements, current code requirements, regulatory requirements, and UFCs are met.

Specifications shall clearly identify, where appropriate, specific products chosen to meet the contract requirements such as manufacturers' brand names and model numbers or similar product information. The use of shop or field fabricated electrical equipment assemblies that are not manufacturer's standard catalog products or do not conform to the industry and technical society standards are not acceptable.

Electrical systems, including, but not limited to, interior building mounted lighting, shall be designed to comply with the documents listed in applicable criteria. Use utilization voltages for lighting to match the existing. Voltage drop shall not exceed the maximum allowed per ASHRAE 90.1.

1.3.8.4.2 General Purpose Power

Electrical equipment and installation shall adhere to the latest National Electrical Code, NFPA and UFC requirements.

Coordinate with UFC 3-501-01, UFC 3-520-01, and UFC 3-550-01.

1.3.8.4.3 Electrical Service

The existing service(s) to each building within the project scope of work on the NSSC campus shall remain. Distribution equipment throughout all buildings is existing to remain.

New circuit breakers shall be provided as required. New circuit breakers shall be coordinated with the existing equipment. Series circuit breakers are unacceptable. AIC rating of new circuit breakers shall match that of existing circuit breakers. New circuit breakers shall be of the same manufacturer and match characteristics of the existing circuit breakers.

Provide all new branch circuit wiring as required.

1.3.8.4.4 Interior Raceway and Wiring

Install all wiring in raceways unless specifically required otherwise by code or UFC. Minimum size conduit permitted is 3/4-inch. Conduit shall be galvanized rigid steel only. Provide an insulated green equipment grounding conductor for all circuits installed in raceways. Raceways must be all surface mounted. Refer to Table 2-1 in UFC 3-520-01 for approved raceway types and their limitations of use. Unless otherwise required by code or UFC, wiring shall be insulated stranded copper conductors in conduit.

Branch circuit conductors shall not be smaller than No. 12 AWG. Conductor

NSSC - Base Wide Fire Alarm Transmission Natick, MA terminations, as well as conductors, must be rated for the operating temperature of the circuit.

1.3.8.4.5 Lighting

The design and construction of interior and exterior lighting shall be in accordance with but not limited to, NFPA 70, UFC 3-530-01 Interior and Exterior Lighting Systems and Controls, franchise requirements and the fundamentals and recommendations of the IES Lighting Handbook, EPAct-2005 and Federal Energy Management Program (FEMP) for lighting products.

Interior light fixtures shall be 48-inch, lensed, industrial strip, pendant or wall mounted, with multi-volt driver. LED lamp source shall be 3500K color temperature with an 80CRI.

New lighting fixtures shall be industrial grade with LED lamp source. The Contractor shall provide fixture, lamp, driver, and switch/control device that ensure compatibility and operability between devices.

Lighting levels shall be in accordance with UFC requirements and IESNA (Illuminating Engineering Society of North America) recommendations.

1.3.8.4.6 Miscellaneous Equipment

Power shall be provided to all equipment that will be addressed in the design development phase.

Provide power as required to the HVAC transfer fan within the building #1 basement battery closet. Coordinate all power requirements and quantity of units with the mechanical designer.

Coordinate power requirements with all trades.

Provide power to all Government Furnished Contractor Installed (GFCI) Equipment.

1.3.8.4.7 Grounding and Bonding

Interior wiring grounding shall comply with UFC 3-520-01, exterior grounding shall comply with UFC 3-550-01. Size of grounding electrode and equipment grounding conductors shall be in accordance with NFPA 70.

Ground exposed, non-current-carrying metallic parts of electrical equipment, metallic raceway systems, grounding conductors in metallic and nonmetallic raceways, and neutral conductors of wiring systems.

Provide ground rods where required and measure the resistance to ground using the fall-of-potential method described in IEEE 81. Do not exceed 25 ohms under normally dry conditions for the maximum resistance of a driven ground.

Make grounding connections which are buried or otherwise normally inaccessible by exothermic weld or high compression connector.

a) Make exothermic welds strictly in accordance with the weld manufacturer's written recommendations. Welds which are "puffed up"

NSSC - Base Wide Fire Alarm Transmission Natick, MA or which show convex surfaces indicating improper cleaning are not acceptable. Mechanical connectors are not required at exothermic welds.

Make high compression connections using a hydraulic or electric compression tool to provide the correct circumferential pressure. Provide tools and dies as recommended by the manufacturer. Use an embossing die code or other standard method to provide visible indication that a connector has been adequately compressed on the ground wire.

1.3.9 Fire Protection

1.3.9.1 General

The purpose of this project is to provide Soldier Systems Center at Natick, Massachusetts, a reliable and code compliant means of transmitting fire alarm signals from existing fire alarm systems located in individual buildings to a central receiving station located in Building 1. Currently, Natick uses a fiber optic cable loop to connect their Simplex fire alarm panels to the existing Simplex central receiver. This loop is not fully functional; there are five (5) legs in the loop that are non-functioning and unable to transmit and there are four (4) building fire alarm panels which have not yet been connected to the loop.

The Contractor must design and install a radio transceiver system that consist of transmitter panels and antennae at each building and central- station receiving equipment in Building 1. This system must be totally independent of the existing system and constructed in parallel without affecting the existing system’s operation. The existing Simplex receiving equipment and fiber optic cabling/equipment must not be demolished until the new radio system is operational and formal acceptance testing is complete.

1.3.9.2 Acronyms

ABA
Americans with Disabilities Act
ADA
Architectural Barriers Act
AFF
Above Finished Floor
BFP
Backflow Preventer
CO
Carbon Monoxide
COR
Contracting Officer’s Representative
DFPE
Designated Fire Protection Engineer, Government, see UFC 3-600-01
EMT
Electrical Metallic Tubing
FA/MNS
Fire Alarm / Mass Notification System
FACP
Fire Alarm and Mass Notification Control Panel
FDC
Fire Department Connection
FSCP
Fire Suppression Control Panel
FT
Foot
GPM
Gallons per Minute
IDC
Initiating Device Circuit
LOC
Local Operating Consoles
LSC
Life Safety Code (NFPA 101)
NAC
Notification Appliance Circuit
NFPA
National Fire Protection Association
NRTL
Nationally Recognized Testing Laboratory
NTP
Notice to Proceed
OS&Y
Outside Stem and Yoke
O.C.
On Center (dimension)
PIV
Post Indicator Valve
PPM
Part Per Million
PSI
Pounds per Square Inch
QC
Quality Control
QFPE
Qualified Fire Protection Engineer, Contractor see UFC 3-600-01
RF
Radio Frequency
SLC
Signal Line Circuit
SOW
Scope of Work
SQFT
Square Foot
TYAD
Tobyhanna Army Depot
UFC
Unified Facilities Criteria
UFGS
Unified Facilities Guide Specifications
UPS
Uninterruptible Power Supply
USACE
US Army Corps of Engineers
ZCA/FCA
Zone Control Assembly / Floor Control Assembly

1.3.9.3 FP System Outages

The Contractor shall coordinate all fire protection system outages through the COR 14 calendar days in advance.

1.3.9.4 Demolition and Salvage

Selective demolition of FP systems for re-routing and making new connections will be required. This contract has no salvage requirements for FP systems.

1.3.9.5 Equipment and Listings

All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. The Contractor shall provide fire protection products in accordance with UL standards; provide UL label on each product. The Contractor shall provide fire protection products and installations in accordance with Factory Mutual (FM) standards. All products shall be listed for fire protection service. The fire protection systems shall be in conformance with all Federal, State, and Local requirements.

All equipment and components shall be new, and the manufacturer’s current model. All equipment and components shall be installed in strict compliance with manufacturer’s recommendations. All equipment shall be attached to walls and ceiling/floor assemblies and shall be held firmly in place.

Fasteners and supports shall be adequate to support the required load.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

1.3.9.6 Contractor Roles and Qualifications

QFPE: The project qualified fire protection engineer (QFPE) must be a registered professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES), or a registered P.E. in a related engineering discipline with a minimum of 5 years’ experience, dedicated to fire protection engineering that can be verified with documentation. During design, the QFPE shall be responsible for the duties listed in UFC 3-600-01. During construction the QFPE shall be responsible for shop drawing and submittal review, responding in writing to formal requests for information, conducting periodic quality assurance site visits (minimum 1 per month), and attending acceptance testing of fire systems.

Fire Alarm Specialist: The design of the FAMNS system must be accomplished by a NICET IV technician certified by the system manufacturer. The construction of the FAMNS system must be done under the supervision of a NICET III technician certified by the system manufacturer.

1.3.9.7 FP Equipment Access

Locate and orient equipment and components to provide manufacturer- recommended clearances. Provide access doors in walls and inaccessible ceilings for system devices that require manual operation, inspection, testing, and maintenance.

1.3.9.8 Firestopping Utility Penetrations

Any penetrations of fire-rated assemblies must utilize a fire-stop assembly or device that is UL-listed and FM-approved for a rating to match the penetrated assembly. The Contractor must also firestop all existing floor openings in the neighboring electrical room, including a large opening with multiple conduits.

1.3.9.9 Existing Conditions

Existing Receiving Equipment: The central receiving equipment is located in the basement of Natick Building 1. Two (2) fiber optic cables terminate at a Simplex Comark Model 06-UL864-002 Digital Alarm Communication Receiver (DACR) located in Room 035. The DACR is rack-mounted in a rack with spare space above and below. There are two Simplex desktop workstations. One workstation is located in Room 035 and the second is located across the hall in DES Dispatch Room 022.

Existing Vertical Raceway in Building 1: There is an existing vertical raceway on the corridor side of the Stair 3 wall. This raceway is recessed into the CMU block wall with a removable steel cover and runs the full height of the building.

Existing Fire Alarm Control Panels and Transmitters: The existing fire alarm control panels have Digital Alarm Communication Transmitters (DACTs) capable of sending fire alarm signals through the fiber optic pathway to Building 1. The existing panels are all Simplex panels (only Simplex panels can be connected to the fiber network). The majority of the panels are Simplex 4200U model and were installed in 2006. See Table 1.3.12-1.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

Existing Fiber Optic Loop: The fiber optic loop pathway is shown in Fig. 1.3.9-1 below. The red shaded areas are legs of the fiber loop that are currently non-functioning (there are five legs currently inoperable). Also shown in Fig. 1.3.9-1 are the four (4) existing fire alarm systems not currently integrated into the campus fiber optic loop. As a result of the above issues, many buildings on campus cannot send fire alarm signals to B1 at this time.

NSSC - Base Wide Fire Alarm Transmission Natick, MA

Fig. 1.3.9-1

NSSC - Base Wide Fire Alarm Transmission Natick, MA

1.3.9.10 New Work – Building 1 (Central-Station Receiving)

1. Antenna: Mount a 6 dB omni-directional radio antenna at the roof level of the West-facing exterior wall of the Stair Enclosure 3 of Building 1, adjacent to the existing antennae for other systems.

2. Antenna Wiring: Install a coaxial cable to connect the new antenna to the new receiving equipment to be installed in the Basement Room 035. Provide a lightning arrestor inside of the building at the point where the antenna cable and raceway enters the building envelope. Install a ground cable routed from the antenna lighting arrestor to a building ground terminal. Cable must within its listed pull length.

3. Radio Receiver: Provided a rack-mount AES model 7705-II receiver within an existing rack in Room 035 in the Basement of Building 1. If the newer “virtual receiver” model is available at the time of construction that would be preferred over the 7705-II.

4. Power: See primary and secondary power sections of this section, 01 10 10.

5. Workstations, Automation Platform, and Displays: Provide two (2) PC workstations with an automation platform to translate the signals from the receiver to a workstation with a graphical user interface. Locate one laptop in Room 035 and the second in Dispatch Room 022. Provide a 42” wall-mounted monitor in Dispatch Room 022. Provide all necessary auxiliaries to use the workstation and automation platform (chargers, mouse, keyboard, speaker, etc.). At no point in time can these workstations be connected to the internet or local network.

6. Room 035: Firestop all existing and new penetrations in the room enclosure using assemblies listed by an NRTL for a 2-hour F and T rating. Provide a portable fire extinguisher in Room 035.

1.3.9.11 New Work – 28 Buildings (Buildings 2, 3, 4, 5, 7, 8, 14, 15, 16, 19, 20, 23, 24, 25, 26, 27, 32, 36, 38, 39, 42, 42A, 44, 45, 66, 86, 92, and 110)

1. Antenna: Provide the factory-mounted 2.5 dB “rubber duck” antenna on the AES fire alarm transmitter (see next section).

2. Antenna Wiring: Provide factory wiring fully enclosed in transmitter cabinet to the cabinet-mounted antenna.

3. Fire Alarm Radio Transmitter: Provide an AES 7177H-88-ULP IntelliNet

2.0 Hybrid Subscriber configured for RF communication. Locate the transmitter adjacent to, or as near as possible to, the existing fire alarm control panel (refer to Table 1.3.9-1 for existing FACP locations in each building). The transmitter must be provided in a lockable steel cabinet.

4. Power: See primary and secondary power sections of this RFP.

5. Signal Zones: In each building, connect the new RF transmitter to the existing FACP and program the unit to group signals into the following eight (8) zones:

NSSC - Base Wide Fire Alarm Transmission Natick, MA

1) Waterflow Switch

2) Manual Pull Station

3) Smoke Detector

4) Duct Smoke Detector

5) Heat Detector

6) Carbon Monoxide

7) General Supervisory

8) General Trouble

Table 1.3.9-1: Existing FACP Locations

Bldg.
FACP Location
Year
Notes
B1
Dispatch in Room 022 Receiver in Room 035

FACP in Central Stair Enclosure

B2
FACP located in North vestibule.
2006
B3
FACP located in central stair.
2006
Serves 78+80
B4
FACP located in central stair.
2006
B5
FACP located in East vestibule.
2006
B7
FACP located in East near vestibule.
2006
B8
FACP located in Main (south) vestibule
2006
B14
FACP located in Northwest vestibule.
2006
B15
Under construction, to be located in main

(east) vestibule

2006
Note 1
B16
FACP located in East vestibule.
2006
B19
Main Boiler Room, west wall
2006
B20
Northeast visitor entrance vestibule
2006
B23
South warehouse entrance on office wall
---
B24
Inside east warehouse on office wall
2015
Not on Ex. Loop
B25
FACP located in East vestibule.
2020
Not on Ex. Loop
B26
FACP located in fire pump room.
2020
Not on Ex. Loop
B27
FACP located in warehouse.
2018
Not on Ex. Loop
B32
Inside closet, lower-level office
2006
B36
FACP located in East vestibule.
2006
B38
FACP located in South vestibule.
2006
B39
FACP located in North vestibule.
2006
B42
FACP located in West vestibule.
2006
B42A
FACP located in Southwest vestibule.
2020
B44
FACP located in Northeast vestibule.
2006
44/66/77/94/111
B45
FACP located in East vestibule.
2006
B66
FACP located in Northwest vestibule.
2006
44/66/77/94/111
B86
FACP located in West vestibule.
2006
B92
FACP located in South vestibule.
2006
B110
FACP located in North vestibule.
---

Notes:

1. B15 is a Barracks. There are local smoke alarms that do not activate general alarm individually but to signal the FACP. All FACP alarm, supervisory, and trouble signals, including the local room smoke alarms, need to be transmitted to the central receiving station.

1.3.9.12 Portable Fire Extinguishers

Extinguishers provided in unfinished areas should be hung on hooks. Extinguishers provided in finished areas must be provided in semi-recessed cabinets. Semi-recessed cabinets located on fire walls, barriers, or partitions must have a fire resistive rating matching the wall on which they are installed.

Coordinate the size and type of…