Technical Exhibit TE-02

DIRECTORATE OF PUBLIC WORKS

DIRECTORATE OF PUBLIC WORKS

DESIGN-BUILD CONSTRUCTION AND INSTALLATION

BASE WIDE WIRELESS FIRE ALARM TRANSMISSION SYSTEMNATICK SOLDIERS CENTER

10 GENERAL GREENE AVENUE

NATICK MA 01760

SUBMITTAL REGISTER

Division 01 — General Requirements

• Two-Week Schedule of work activities

• Submittal Register

• Accident Prevention Plan (APP)

• Daily Reports

• Qualification Records

• Closeout Submittals o Indoor Air Quality o Commissioning: HVAC, Fire Protection, Electrical, Steam and Chilled Water

Commissioning Plan Commissioning Reports

• Waste Management Plan

• Operation and Maintenance (O&M) o O&M Manuals o O&M Training

Division 02 — Existing Conditions

• Demolition Plan

Division 03 — Concrete

• Reinforcement o Product information

• Concrete mix information

Division 04 — Masonry

Division 05 — Metals

• Cold-Formed Metal Framing / Metal Studs o Product information

Division 06 — Wood, Plastics, and Composites

Division 07 — Thermal and Moisture Protection

• Rock wool insulation o Product information

• Pipe Boots o Product information

Division 08 — Openings

• Doors o Product information o Product sample

DIRECTORATE OF PUBLIC WORKS

DESIGN-BUILD CONSTRUCTION AND INSTALLATION

BASE WIDE WIRELESS FIRE ALARM TRANSMISSION SYSTEMNATICK SOLDIERS CENTER

• Door Hardware o Product information o Hardware schedule

Division 09 — Finishes

• Interior Gypsum Board o Product Information

• Water Resistant Tile Backer Board o Product information

• Fire Rated Gypsum Board o Product Information

• Joint tape and Compound o Product Information

• Acoustical Ceilings o Product information o Product samples

• Fluid Applied Epoxy Flooring o Product information

• Paints o Product information o Paint drawdown samples

• Tile and Grout o Product information o Product samples

• Resilient Flooring o Product information o Product samples

• Carpet o Product information o Product samples

Division 10 — Specialties

Division 11 — Equipment

• Contractor Design / Build o Drawing submittal for record

Division 12 — Furnishings

Division13 — Special Construction

Division 14 — Conveying Equipment

Division 21 — Fire Suppression

DIRECTORATE OF PUBLIC WORKS

DESIGN-BUILD CONSTRUCTION AND INSTALLATION

BASE WIDE WIRELESS FIRE ALARM TRANSMISSION SYSTEMNATICK SOLDIERS CENTER

• Contractor Design / Build o Drawing submittal for record

Division 22 — Plumbing

Division 23 — Heating, Ventilating, and Air Conditioning (HVAC)

• HVAC systems o Product information

Division 25 — Integrated Automation

Division 26 — Electrical

• Electrical systems o Product information

Division 27 — Communications

Division 28 — Electronic Safety and Security

*This checklist is provided for the Contractor’s convenience. Contractor shall provide submittals as required by the documents and to execute the design intent of the drawings.

SUBMITTAL REGISTER
*This checklist is provided for the Contractor’s convenience. Contractor shall provide submittals as required by the documents and to execute the design intent of the drawings.