TC Fire Station1 Project Manuel.pdf

PDF 2 MB Posted

Attached to
Construction of Troup County Fire Station #1
Solicitation number
PE-77030-NONST-2027-000000029
Issued by
Terrell County, Georgia

About this file

This file is a Project Manual for the construction of Troup County Fire Station No. 1, prepared by 2WR of Georgia for the Troup County Board of Commissioners in LaGrange, Georgia. The project involves the construction of a new 7,522 square foot fire station and associated sleeping quarters located at Burkes Chapel Road in Troup County, Georgia. The facility will be constructed as Type VB, unsprinklered/sprinklered NFPA 13R construction. The project will be executed under a single prime contract with a Guaranteed Maximum Price structure. Sealed proposals are due by 2:00 p.m. on October 1, 2026, at the Troup County Purchasing Department, 100 Ridley Avenue, Suite 3100, LaGrange, Georgia 30240. A mandatory pre-bid meeting is scheduled for August 27, 2026, at 2:00 p.m. at the jobsite location at the corner of Burkes Chapel Road and Whitesville Road. The anticipated project start date is November 2026, with substantial completion required within 300 consecutive calendar days. All proposals must include a fully executed proposal form, a 5% bid bond, two hard copies and one digital copy (on thumb/zip drive), detailed project proposals demonstrating scope compliance, contractor qualifications, and written warranty documentation covering labor, installation, and workmanship.

The contract will be awarded on a lump sum basis, with bids remaining valid for 60 days following the bid opening date. The Project Manual establishes comprehensive specifications across 28 divisions, including general requirements, concrete, masonry, metals, wood composites, thermal and moisture protection, openings, finishes, specialties, furnishings, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, and earthwork. The specifications include ten unit-cost allowances totaling approximately $15,400 for equipment such as refrigerators, ovens, washers, dryers, ice machines, microwaves, coffee makers, emergency shower stations, and a stacked gear extractor washer/dryer, plus a 5% contingency allowance for use at the Owner's discretion. The Owner will furnish and install certain items including a gas-fired exterior grill, security cameras, and an alarm and security system with card readers. The contract includes detailed requirements for contractor quality control, submittals, payment procedures, scheduling, coordination, testing and inspections, photographic documentation, and closeout procedures. Requests for clarification must be submitted via email only to Ramona Gillham, Troup County Purchasing Director.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prepared by 2WR of Georgia 11 9th Street, Suite 120 Columbus, Georgia 31901 Project Number 26-00013

TROUP COUNTY FIRE STATION NO1

BURKES CHAPEL ROAD

TROUP COUNTY, GEORGIA

26-00013 TROUP COUNTY FIRE

STATION NO 1 000101 - 1 Project Title Page

SECTION 000101

PROJECT TITLE PAGE

PROJECT MANUAL

FOR

26-00013 TROUP COUNTY FIRE STATION NO 1

TROUP COUNTY BOARD OF COMMISSIONERS

BURKES CHAPEL ROAD

TROUP COUNTY, GEORGIA

PREPARED BY:

2WR OF GEORGIA

END OF SECTION

STATION NO 1 000107 - 1 Seals Page

SECTION 000107

SEALS PAGE

STATION NO 1 000110 - 1 Table of Contents

SECTION 000110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 000101 - Project Title Page B. 000107 - Seals Page C. 000110 - Table of Contents

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 011000 - Summary B. 012100 - Allowances C. 012300 - Alternates D. 012600 - Contract Modifications Procedures E. 012900 - Payment Procedures F. 013100 - Project Management and Coordination G. 013200 - Construction Progress Documentation H. 013233 - Photographic Documentation I. 013300 - Submittal Procedures J. 014000 - Quality Requirements K. 014339 - Mockups L. 014533 - Code Required Special Inspections and Procedures M. 015000 - Temporary Facilities and Controls N. 015723 - Temporary Storm Water Pollution Control O. 016000 - Product Requirements P. 017300 - Execution Q. 017419 - Construction Waste Management and Disposal R. 017700 - Closeout Procedures S. 017900 - Demonstration and Training

2.02 DIVISION 03 -- CONCRETE

A. 032000 - Concrete Reinforcing B. 033000 - Cast-in-Place Concrete

2.03 DIVISION 04 -- MASONRY

A. 042000 - Unit Masonry

2.04 DIVISION 05 -- METALS

A. 051200 - Structural Steel Framing

2.05 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

A. 060000 - Woods & Plastics B. 061000 - Rough Carpentry C. 061600 - Sheathing D. 061753 - Shop-Fabricated Wood Trusses E. 064116 - Plastic-Laminate-Clad Architectural Cabinets

STATION NO 1 000110 - 2 Table of Contents

2.06 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

A. 072100 - Thermal Insulation B. 072119 - Foamed-In-Place Insulation C. 072500 - Weather Barriers D. 073113 - Asphalt Shingles E. 074646 - Fiber-Cement Siding F. 076200 - Sheet Metal Flashing and Trim G. 077100 - Roof Specialties H. 077200 - Roof Accessories I. 079200 - Joint Sealants

2.07 DIVISION 08 -- OPENINGS

A. 081113 - Hollow Metal Doors and Frames B. 081213 - Hollow Metal Frames C. 081416 - Flush Wood Doors D. 083323 - Overhead Coiling Doors E. 085113 - Aluminum Windows F. 087100 - Door Hardware G. 088000 - Glazing

2.08 DIVISION 09 -- FINISHES

A. 090561 - Common Work Results for Flooring Preparation B. 092900 - Gypsum Board C. 092013 - Ceramic Tiling D. 095123 - Acoustical Tile ceilings E. 096513 - Resilient Base and Accessories F. 096519 - Resilient Tile Flooring G. 096813 - Tile Carpeting H. 099114 - Exterior painting (MPI Standards) I. 099124 - Interior Painting (MPI Standards) J. 099300 - Staining and Transparent Finishing K. 099723 - Concrete and Masonry Coatings

2.09 DIVISION 10 -- SPECIALTIES

A. 101419 - Dimensional Letter Signage B. 102800 - Toilet, Bath, and Laundry Accessories C. 104413 - Fire Protection Cabinets D. 104416 - Fire Extinguishers E. 105123 - Plastic-Laminate-Clad Lockers F. 105143 - Wire Mesh Storage Lockers G. 107300 - Aluminum Canopy H. 107516 - Ground-Set Flagpoles

2.10 DIVISION 12 -- FURNISHINGS

A. 122513 - Window Roller Shades

STATION NO 1 000110 - 3 Table of Contents

B. 123661 - Simulated Stone Countertops

2.11 DIVISION 21 -- FIRE SUPPRESSION

A. 210100 - Sprinkler System

2.12 DIVISION 22 -- PLUMBING

A. 220100 - Plumbing

2.13 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

A. 230100 - Heating, Ventilation, and Air Conditioning

2.14 DIVISION 26 -- ELECTRICAL

A. 260500 - General Requirements B. 260533 - Raceways C. 260600 - Electrical Submittals D. 260800 - Equipment Identification E. 260900 - Construction Reviews and Testing F. 262000 - Wire and Cable G. 262700 - Pull and Junction Boxes H. 262900 - Devices I. 262920 - Panelboards J. 262930- Motor and Circuit Disconnects K. 262940 - Grounding L. 265000 - Lightning Systems M. 263212 - Spark Ignited Engine-Driven Generator Sets

2.15 DIVISION 27 -- COMMUNICATIONS

A. 270000 - Telephone/Data Raceway System

2.16 DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

A. 283100 - Fire Alarm System

2.17 DIVISION 31 -- EARTHWORK

A. 313116 - Termite Control

STATION NO 1 010000 - 1 General Requirements

SECTION 010000

GENERAL REQUIREMENTS

PART 1 GENERAL

1.01 NOT USED

A. Not used.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

STATION NO 1 011000 - 1 Summary

SECTION 011000

SUMMARY

PART 1 GENERAL

1.01 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work performed by Owner.

4. Multiple Work Packages.

5. Work under Owner's separate contracts.

6. Owner-furnished/Contractor-installed (OFCI) products.

7. Owner-furnished/Owner-installed (OFOI) products.

8. Contractor's use of site and premises.

9. Work restrictions.

10. Specification and Drawing conventions.

11. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

2. Section 017300 "Execution" for coordination of Owner-installed products.

1.02 DEFINITIONS

A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.

1.03 REFERENCE STANDARDS

A. NFPA 13R - Standard for the Installation of Sprinkler Systems in Low-Rise Residential Occupancies; 2025.

1.04 PROJECT INFORMATION

A. Project Identification: Troup County Fire Station Number 1.

1. Project Location: Burkes Chapel Road, Troup County, Georgia.

B. Owner: Troup County Board of Commissioners. Lagrange, Georgia.

1. Owner's Representative: James (Jay) Anderson

a. Assistant County Manager

b. 100 Ridley Avenue, Lagrange, GA 30240

c. (706)298-3792

C. Architect: 2WR + Partners.

1. Architect's Representative: Alex Griggs

2. 11 Ninth Street, Suite 120, Columbus, GA 31901

3. (706) 571-6923

D. Architect's Consultants: Architect has retained the following design professionals, who have prepared designated portions of the Contract Documents:

1. Structural Engineering: Wright Engineering, Inc.

a. 7413 Whitesville RD Suite 800, Columbus, GA 31904

b. (706) 507-0232

1) Structural Engineer Representative: Matt Pearson

2) Scope of Service: Structural Engineering

2. MEP Engineering: Peach Engineering

a. 1214 1st Ave, Columbus, GA, 31901

b. (706)596-1840

STATION NO 1 011000 - 2 Summary

E. Contractor: T.B.D. has been engaged as Contractor for this Project.

1. Contractor Representative: T.B.D.

F. Construction Manager: T.B.D..

1. Construction Manager Representative: T.B.D..

2. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner and each Contractor, according to a separate contract between Owner and Construction Manager.

1) Construction Manager also serves as Project coordinator, as defined in Section 011200 "Multiple Contract Summary."

3. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous.

G. Web-Based Project Software: Project software will be used for purposes of managing communication and documents during the construction stage.

1. See Section 013100 "Project Management and Coordination" for requirements for using web-based Project software.

1.05 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. Construction of a new 7,522 SF Fire Station and associated sleeping quarters. Type VB, unsprinklered / Sprinklered NFPA 13R construction and other Work indicated in the Contract Documents.

B. Type of Contract:

1. Project will be constructed under a single prime contract with a Guaranteed Maximum

Proce.

2. Project will be constructed under coordinated, concurrent multiple contracts. See Section

011200 "Multiple Contract Summary" for a list of multiple contracts, a description of work included under each of the multiple contracts, and the responsibilities of Project coordinator.

1.06 WORK PERFORMED BY OWNER

A. Cooperate fully with Owner, so work may be carried out smoothly, without interfering with or delaying Work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.

B. Preceding Work: Owner will perform the following construction operations at Project site. Those operations are scheduled to be substantially complete before Work under this Contract begins.

1. Owner to engage Geotechnical engineer and Civil engineer.

C. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract.

1. Owner to engage city vendor for installation CCTV security cameras and alarm system.

1.07 WORK UNDER OWNER'S SEPARATE CONTRACTS

A. Work with Separate Contractors: Cooperate fully with Owner's separate contractors, so work on those contracts may be carried out smoothly, without interfering with or delaying Work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under Owner's separate contracts.

B. Subsequent Work: Owner will award separate contract(s) for the following additional work to be performed at site following Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract.

1. Closed Circuit Security Camera and Alarm: To: T.B.D for Installation of Security Cameras and Security system.

STATION NO 1 011000 - 3 Summary

1.08 OWNER'S PRODUCT PURCHASE CONTRACTS

A. Owner has negotiated Product Purchase contracts with suppliers of material and equipment to be incorporated into the Work. Owner will assign these Product Purchase contracts to Contractor. Include costs for purchasing, receiving, handling, storage if required, and installation of material and equipment in the Contract Sum unless otherwise indicated.

1. Contractor's responsibilities are same as if Contractor had negotiated Product Purchase contracts, including responsibility to renegotiate purchase and to execute final purchasing agreements.

1.09 OWNER-FURNISHED/OWNER-INSTALLED (OFOI) PRODUCTS

A. The Owner will furnish and install products indicated.

B. Owner-Furnished/Owner-Installed (OFOI) Products:

1. Gas fired exterior grill.

2. Security Cameras.

3. Alarm and security system with card readers.

1.10 CONTRACTOR'S USE OF SITE AND PREMISES

A. Unrestricted Use of Site: Each Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. Restricted Use of Site: Each Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

C. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or for storage of materials.

1) Schedule deliveries to minimize use of driveways and entrances by construction operations.

2) Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.11 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

1.12 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

STATION NO 1 011000 - 4 Summary

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

PART 2 PRODUCTS (NOT USED)

STATION NO 1 012100 - 1 Allowances

SECTION 012100

ALLOWANCES

PART 1 GENERAL

1.01 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

B. Types of allowances include the following:

1. Unit-cost allowances.

2. Contingency allowances.

C. Related Requirements:

1. Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders.

2. Section 014000 "Quality Requirements" for procedures governing the use of allowances for field testing by an independent testing agency.

1.02 DEFINITIONS

A. Allowance: A quantity of work or dollar amount included in the Contract, established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.

1.03 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.

B. At Architect's request, obtain proposals for each allowance for use in making final selections.

Include recommendations that are relevant to performing the Work.

C. Purchase products and systems selected by Architect from the designated supplier.

1.04 ACTION SUBMITTALS

A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.

1.05 INFORMATIONAL SUBMITTALS

A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.

B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.

C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

1.06 UNIT-COST ALLOWANCES

A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site.

B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.

C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted.

1. If requested by Architect, retain and prepare unused material for storage by Owner.

Deliver unused material to Owner's storage space as directed.

STATION NO 1 012100 - 2 Allowances

1.07 CONTINGENCY ALLOWANCES

A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by

Change Orders that indicate amounts to be charged to the allowance.

B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.

C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit.

D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.

1.08 ADJUSTMENT OF ALLOWANCES

A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, required maintenance materials, and similar margins.

1. Include installation costs in purchase amount only where indicated as part of the allowance.

2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.

3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.

4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

B. Submit claims for increased costs due to a change in the scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.

1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.

2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.01 EXAMINATION

A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

3.02 PREPARATION

A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.03 SCHEDULE OF ALLOWANCES

A. Allowance No. 1: Unit-Cost Allowance: Include the sum of $3,000.00 per unit for (3) upright reach-in refrigerators with no ice or water as shown on Drawings.

B. Allowance No. 2: Unit-Cost Allowance: Include the sum of $3,000.00 per unit for residential style electric oven with cook top with vent hood including a retrofit Ansul system.

C. Allowance No. 3: Unit-Cost Allowance: Include the sum of $1,000.00 per unit for Residential style Washing Machine

STATION NO 1 012100 - 3 Allowances

D. Allowance No. 4: Unit-Cost Allowance: Include the sum of $1,000.00 per unit for Residential style Dryer.

E. Allowance No. 5: Unit-Cost Allowance: Include the sum of $5,000.00 per unit for Ice Machine with bin. Model number KMC-H-530-A 30” by Avantco Ice.

F. Allowance No. 6: Unit Cost Allowance: Include the sum of $500.00 per unit for countertop Microwave. Similar to Panasonic Model # NN-SN96JS 2.2 cu ft.

G. Allowance No. 7: Unit Cost Allowance: Include the sum of $900.00 per unit for Plumbed autofill Coffee Maker: Similar to BUNN CWTF-DV-TC

H. Allowance No. 8: Unit-Cost Allowance: Include the sum of $1,500.00 per unit for Emergency Shower Station with Eyewash. Similar to Guardian G1902.

I. Allowance No. 9: Unit-Cost Allowance: Include the sum of $30,000.00 per unit for Stacked Gear Extractor Washer/Dryer. Basis of Design product : UniMac UST50

J. Allowance No. 10: Contingency Allowance: Include a contingency allowance of 5% of total construction cost for use according to Owner's written instructions.

STATION NO 1 012300 - 1 Alternates

SECTION 012300

ALTERNATES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Description of Alternates.

1.02 ACCEPTANCE OF ALTERNATES

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option.

Accepted Alternates will be identified in the Owner-Contractor Agreement.

B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.

1.03 SCHEDULE OF ALTERNATES

A. Alternate No. 1 - Widen the Apparatus Bay to Accommodate a Third bay.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

STATION NO 1 012600 - 1 Contract Modification Procedures

SECTION 012600

CONTRACT MODIFICATION PROCEDURES

PART 1 GENERAL

1.01 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

1.02 MINOR CHANGES IN THE WORK

A. Architect will issue through Construction Manager supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710 form included in Project Manual.

1.03 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the

Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

1.04 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

STATION NO 1 012600 - 2 Contract Modification Procedures

PART 2 PRODUCTS (NOT USED)

STATION NO 1 012900 - 1 Payment Procedures

SECTION 012900

PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.02 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Owner's name.

c. Owner's Project number.

d. Name of Architect.

e. Architect's Project number.

f. Contractor's name and address.

g. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

3. Provide a separate line item in the schedule of values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

4. Schedule of Values Revisions: Revise the schedule of values when Change Orders or Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.

1.03 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Architect and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the

Owner/Contractor Agreement. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G703 and AIA Document G732 as form for Applications for Payment.

1. Other Application for Payment forms proposed by the Contractor may be acceptable to

Architect and Owner. Submit forms for approval with initial submittal of schedule of values.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

STATION NO 1 012900 - 2 Payment Procedures

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices.

Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of date of previous

Applications for Payment.

b. Value of previously stored materials put in place after date of previous Application for

Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Combined Contractor's construction schedule (preliminary if not final) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor.

5. Products list (preliminary if not final).

6. Sustainable design action plans, including preliminary project materials cost data.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

13. Initial progress report.

14. Report of preconstruction conference.

STATION NO 1 012900 - 3 Payment Procedures

15. Certificates of insurance and insurance policies.

16. Performance and payment bonds.

17. Data needed to acquire Owner's insurance.

I. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures."

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for

Owner occupancy of designated portions of the Work.

J. Final Payment Application: After completing Project closeout requirements, submit final

Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Certification of completion of final punch list items.

3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

4. Updated final statement, accounting for final changes to the Contract Sum.

5. AIA Document G706.

6. AIA Document G706A.

7. AIA Document G707.

8. Evidence that claims have been settled.

9. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

10. Final liquidated damages settlement statement.

11. Proof that taxes, fees, and similar obligations are paid.

12. Waivers and releases.

PART 2 PRODUCTS (NOT USED)

STATION NO 1 013100 - 1 Project Management And

Coordination

SECTION 013100

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Web-based Project management software package.

6. Project meetings.

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

2. Section 019113 "General Commissioning Requirements" for coordinating the Work with

Owner's Commissioning Authority.

1.02 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.03 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

STATION NO 1 013100 - 2 Project Management And

Coordination

b. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.

Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Review: Architect will review coordination drawings to confirm that, in general, the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make suitable modifications and resubmit.

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format:

a. Same digital data software program, version, and operating system as original Drawings.

b. DWG, Version, operating in Microsoft Windows operating system.

2. File Submittal Format: Submit or post coordination drawing files using PDF format.

1.04 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Owner name.

3. Name of Architect

4. Architect's Project number.

5. Date.

6. Name of Contractor.

7. RFI number, numbered sequentially.

8. RFI subject.

9. Specification Section number and title and related paragraphs, as appropriate.

10. Drawing number and detail references, as appropriate.

11. Field dimensions and conditions, as appropriate.

12. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

13. Contractor's signature.

14. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: AIA Document G716.

STATION NO 1 013100 - 3 Project Management And

Coordination

1. Attachments shall be electronic files in PDF format.

D. Architect's and Construction Manager's Action: Architect will review each RFI, determine action required, and respond. Allow three days for Architect's response for each RFI. RFIs received by Architect or Construction Manager after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect or Construction Manager of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the

Contract Sum, notify Architect and Construction Manager in writing within 5 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect and Construction Manager.

4. RFI number, including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's and Construction Manager's response was received.

F. On receipt of Architect's and Construction Manager's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect and Construction Manager within three days if Contractor disagrees with response.

1.05 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Architect's Data Files Not Available: Architect will not provide Architect's BIM model CAD drawing digital data files for Contractor's use during construction.

B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:

1. Assemble complete submittal package into a single indexed file, incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.06 PROJECT MEETINGS

A. General: Construction Manager will schedule and conduct meetings and conferences at Project site unless otherwise indicated.

B. Preconstruction Conference: Construction Manager will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.

STATION NO 1 013100 - 4 Project Management And

Coordination

1. Attendees: Authorized representatives of Owner, Construction Manager, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Phasing.

d. Critical work sequencing and long lead items.

e. Designation of key personnel and their duties.

f. Lines of communications.

g. Use of web-based Project software.

h. Procedures for processing field decisions and Change Orders.

i. Procedures for RFIs.

j. Procedures for testing and inspecting.

k. Procedures for processing Applications for Payment.

l. Distribution of the Contract Documents.

m. Submittal procedures.

n. Preparation of Record Documents.

o. Use of the premises

p. Work restrictions.

q. Working hours.

r. Owner's occupancy requirements.

s. Responsibility for temporary facilities and controls.

t. Procedures for moisture and mold control.

u. Procedures for disruptions and shutdowns.

v. Construction waste management and recycling.

w. Parking availability.

x. Office, work, and storage areas.

y. Equipment deliveries and priorities.

z. First aid.

aa. Security.

bb. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other Sections and when required for coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect, Construction Manager of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Sustainable design requirements.

i. Review of mockups.

STATION NO 1 013100 - 5 Project Management And

Coordination

j. Possible conflicts.

k. Compatibility requirements.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written instructions.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations of authorities having jurisdiction.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Project Closeout Conference: Construction Manager will schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Owner, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of Record Documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Procedures for completing and archiving web-based Project software site data files.

d. Submittal of written warranties.

e. Requirements for completing sustainable design documentation.

f. Requirements for preparing operations and maintenance data.

g. Requirements for delivery of material samples, attic stock, and spare parts.

h. Requirements for demonstration and training.

i. Preparation of Contractor's punch list.

j. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

k. Submittal procedures.

l. Coordination of separate contracts.

m. Owner's partial occupancy requirements.

n. Installation of Owner's furniture, fixtures, and equipment.

o. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting will record and distribute meeting minutes.

STATION NO 1 013100 - 6 Project Management And

Coordination

E. Progress Meetings: Construction Manager will conduct progress meetings at monthly intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Owner, Construction Manager, and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so.

Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next…