PWS Installation Engineering DRAFT - 18 JUN 26.pdf
PDF 568 KB Posted
- Solicitation number
- TBESS-SS-01
About this file
Performance Work Statement Summary: Tinker Air Force Base Civil Engineering Services
This is a Performance Work Statement (PWS) for comprehensive civil engineering services at Tinker Air Force Base, Oklahoma, prepared by the 72d Civil Engineer Directorate dated 12 June 2026. The Service Provider (SP) must deliver installation engineering support across three major functional areas: Project Management and Execution, Execution Support, and Operations Engineering. The contract structure combines a Firm-Fixed-Price Level of Effort (FFP-LOE) Baseline Support Team for continuous operations with Indefinite Delivery/Indefinite Quantity (IDIQ) task orders for project-specific services. The Baseline FFP-LOE scope encompasses decentralized FSRM (dFSRM) program management, Oklahoma City Air Logistics Center (OC-ALC) funded maintenance and capital improvement programs, and liaison support for centrally managed MILCON and federally-funded FSRM projects. The SP must establish comprehensive project lifecycle management including planning, programming, requirements development, design package preparation, solicitation support, construction management, inspection, and closeout for over 1,737 base buildings totaling 21 million square feet supporting more than 31,000 personnel.
The Execution Support function requires the SP to manage the installation's geospatial information and services (IGI&S)/GeoBase program, provide Computer-Aided Design and Drafting (CADD) services, and deliver general technical engineering support including formal evaluations, emergency response, and program advisory functions. Operations Engineering services focus on reimbursable customers (CSAG, Navy, DLA) and require development and maintenance of dynamic Maintenance Master Plans (MMPs), condition assessments of at least 20 percent of customer facility portfolios annually, equipment information database management, and pavement/bridge inspection coordination. Key Personnel requirements include a Civil Engineering Services Program Manager, Chief Engineer, Senior Project Managers, Project Managers, Lead Engineers across multiple disciplines (Civil, Structural, Mechanical, Electrical, Fire Protection), Lead Architects, and specialized inspectors and construction managers, all with specified minimum years of experience and professional certifications. Performance is measured through 13 Quality Performance Indicators (QPIs) covering staffing, schedule adherence, cost control, data integrity, reporting, and compliance, with Government surveillance conducted through quality assurance inspections, corrective action requests, and independent monitoring of contractor-developed records.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIVIL ENGINEERING
SERVICES
TINKER BASE ENGINEERING
SUPPORT SERVICE
PERFORMANCE WORK
STATEMENT
TINKER AIR FORCE BASE, OK
Prepared by:
72d Civil Engineer Directorate
72 ABW/CEN
7535 5th St, Ste 101
Tinker Air Force Base, OK 73145-9010
12 June 2026
PREFACE
CIVIL ENGINEERING SERVICES
TINKER BASE ENGINEERING SUPPORT SERVICE
PERFORMANCE WORK STATEMENT
72d AIR BASE WING
TINKER AIR FORCE BASE, OKLAHOMA
Base Profile and Mission
Tinker Air Force Base (TAFB) is centrally located in Oklahoma about 5 miles from downtown
Oklahoma City in southeast Oklahoma County. It occupies 5,904 acres and is generally bounded on its north perimeter by I-40. Since the early 1940s, the base has been an important part of the state with a current annual economic impact of more than $4.5 billion.
TAFB’s primary mission is to manage, store, and maintain components, end items, and major weapon systems assigned to the Oklahoma City Air Logistics Center (OC-ALC), which is one of three Air Force Sustainment Center (AFSC) depot level maintenance facilities in the Air
Force. The AFSC is headquartered at TAFB in the nearly mile-long building 3001.
The 72d Air Base Wing (72 ABW) is the host unit at TAFB. Their primary mission is to provide responsive installation and support services to HQ AFSC and 45 associate units assigned to six major commands—all of which comprise TEAM TINKER.
TAFB is home to three major flying wings to include the largest flying wing in Air Combat
Command, the 552d Air Control Wing. The Navy’s Strategic Communications Wing ONE with more than 1,300 sailors, civilians, and contractors also headquartered on TAFB. Finally, the Air Force Reserve Command’s 507th Air Refueling Wing with 1,500 members.
Other major associate units on TAFB include the 38th Cyberspace Engineering Installation
Group, responsible for planning, engineering, installing, removing and relocating communications and information systems worldwide for the Air Force. The Defense Logistics
Agency, Defense Distribution Center Oklahoma City, Oklahoma, provides TEAM TINKER with 24-hour distribution support in more than 3.1 million square feet of space.
The 72d Civil Engineer Directorate (CE) enhances TAFB’s mission capability by providing world class, efficient and effective support to sustain, restore, modernize, and protect TAFB’s facilities, infrastructure, and environment. CE and other Wing organizations support over
31,000 military, civilian, and contractor personnel. There are over 21 million square feet in
1,737 buildings and structures on TAFB.
Our objectives for this service contract reflect the above mission statement. Specifically, the provider shall:
• Maintain and repair TAFB’s facilities and infrastructure, both built and natural, to ensure the delivery of war-winning expeditionary capabilities to the war fighter;
• Continue to modernize the installation so that essential facilities and services are available to carry out assigned missions on-time and within budget;
• Encourage on-base development patterns which minimize land use conflicts;
• Continuously improve services and capabilities to meet our mission and achieve our vision.
• Contribute to energy conservation and the efficient use of real property facilities and infrastructure; and
• Promote a visually pleasing Base through implementation of architectural compatibility and landscape development.
Ultimately, the Base Civil Engineering Government and Contractor team is responsible for proper stewardship and management of TAFB’s valuable resources and compliance with applicable laws, directives, and regulatory requirements. TAFB’s family housing, potable water, sanitary sewer system and primary electrical distribution systems have privatized;
therefore, the Service Provider (SP) is responsible for coordinating work requirements with the various privatization contractors. The Performance Work Statement (PWS) which follows provides specific requirements.
TABLE OF CONTENTS
1. INSTALLATION ENGINEERING
1.1. Description of Services
1.1.1. Major Functional Areas
1.1.2. Definitions
1.2. Government Imperatives
1.2.1. Project Management Imperatives
1.2.2. Operations Engineering Support Imperatives
2. PROJECT MANAGEMENT
2.1. Definitions of Program Categories
2.1.1. Baseline FFP-LOE Scope:
2.1.2. Orderable IDIQ Scope:
2.2. Project Management and Execution
2.2.1. Process Documentation and Knowledge Transfer
2.2.2. Provide Baseline Project Management & Program-Level Support (FFP-LOE)
2.2.3. Orderable Project-Specific Services (IDIQ)
2.3. Execution Support
2.3.1. Baseline Execution Support Team (FFP-LOE)
2.3.2. Orderable Surveying Services (IDIQ)
3. OPERATIONS ENGINEERING
3.1. Operations Engineering
3.1.1. Workload Baseline and Annual Reconciliation
3.1.2. Maintenance Master Plan (MMP)
3.1.3. Base Infrastructure Programs
3.1.4. Equipment Information System Database (EISD)
3.1.5. Pavement Condition and Bridge Inspection
4. SERVICES SUMMARY
4.1. Performance Standards
Table 4.1 - Performance Objectives
4.2. Government Surveillance
4.2.1. Government Quality Assurance
4.2.2. Government Observations
5. RELATED PUBLICATIONS
6. SPECIAL TRAINING, CERTIFICATIONS AND LICENSING REQUIREMENTS .. 27
6.1. Inspector Qualifications
6.1.1. Lead Inspector:
6.1.2. Journeyman Inspector:
6.2. Project Manager Qualifications
6.2.1. Senior Project Manager:
6.2.2. Project Manager:
6.3. Key Personnel
Table 6.3 – Key Personnel Requirements
7. APPENDICES LIST
1. INSTALLATION ENGINEERING
1.1. Description of Services. The engineering division
combines the requirements of comprehensive planning, programming, Comprehensive Asset Management Plan
(CAMP) integrator, and executor for base level facility/infrastructure requirements that exceed the operations division in-house capabilities and are within the engineering division capability to execute.
Responsibilities remain the same with regards to tenants and other agencies/units providing funding for maintenance, repair or capital improvement projects, or opportunities. The division is a lean cradle-to-grave project development and execution organization.
The functional organization chart is designed to provide a reference to how the Air Force Civil Engineer (CE) community organizes and labels both similar trade crafts as well as overall operations. This Performance
Work Statement (PWS) will make use of this convention to provide consistency with all other published guidance and training for civil engineers. The service provider (SP) is not required to organize their staff in this manner.
The Service Provider (SP) shall provide all personnel, supervision, and resources necessary to perform comprehensive engineering and execution support services for the 72d Civil Engineer
Directorate at Tinker Air Force Base. The objective of this contract is to provide a flexible and responsive engineering capability to execute the installation's facility and infrastructure requirements.
1.1.1. Major Functional Areas.
1.1.1.1. Project Management and Execution (Section 2.2). The SP shall provide comprehensive project management and execution services for the installation's facility sustainment, restoration, modernization, and construction programs. These services are delivered via a combination of a Baseline Support Team and Orderable Indefinite
Delivery, Indefinite Quantity (IDIQ) Services. The detailed requirements for this function are defined in Section 2.2 of this PWS.
1.1.1.2. Execution Support (Section 2.3). The SP shall provide the Baseline technical support functions necessary for all engineering operations. This includes managing the installation's Installation Geospatial Information & Services (IGI&S)/GeoBase Program, providing Computer-Aided Design and Drafting (CADD), and delivering General
Technical Support such as engineering evaluations and program management. The detailed requirements for this function are defined in Section 2.3 of this PWS.
1.1.1.3. Operations Engineering (Section 3.0). The SP shall establish an Operations and
Maintenance Engineering Capability, functioning as a dedicated Requirements and
NOT IN
CONTRACT
Optimization (R&O) element, specifically supporting facilities occupied by reimbursable customers (e.g., CSAG, Navy, DLA). This includes applying an asset lifecycle approach, executing the Sustainment Management System (SMS) BUILDER program, and developing prioritized maintenance and capital improvement plans to maximize the return on customer investments. The detailed requirements for this function are defined in
Section 3.0 of this PWS.
1.1.1.4. Information Systems & Security. The SP shall comply with all Government requirements for the use of information systems and the protection of data.
a) DAF-Mandated IT System Non-Disclosure Agreement (NDA): Without exception, all
SP and subcontractor employees requiring access to the designated Government IT system of record (currently NexGen IT) must complete and sign the DAF-standard
NDA. Signed NDAs shall be submitted to the Services COR prior to access being granted.
1.1.2. Definitions.
1.1.2.1. Services Contracting Officer’s Representative (Services COR): The Government official designated in writing by the Contracting Officer to perform specific technical and administrative functions for this Engineering Services contract. The Services COR is responsible for evaluating the SP’s overall contract performance, approving SP invoices, assessing Quality Performance Indicators (QPIs), issuing general tasking, and providing overarching contract direction.
1.1.2.2. Project Contracting Officer’s Representative (Project COR): The Government official designated in writing by the Contracting Officer to administer a specific, third-party design or construction contract (e.g., SABER, MACC, A&E contract) that the SP is tasked with supporting or managing. For day-to-day project execution, the SP's project managers and inspectors report to, advise, and act on behalf of the Project COR. The SP holds no privity of contract with the third-party construction/design contractor and must route all formal direction, approvals, and contract modifications through the Project
COR.
1.2. Government Imperatives. Imperatives document the Government’s most critical priorities for this contract. The SP shall align all staffing, resources, and management efforts to ensure these imperatives are met.
1.2.1. Project Management Imperatives.
1.2.1.1. dFSRM Program Execution. The SP's primary function is the successful, on-time, and on-budget lifecycle execution of the entire annual dFSRM program. The
Government's expectation is that the SP's FFP-LOE Baseline Team will manage this workload proactively and efficiently.
1.2.1.2. OC-ALC M&R Program Execution. The SP shall provide a dedicated team for the successful, on-time, and on-budget lifecycle execution of the entire annual OC-ALC https://usaf.dps.mil/:w:/r/sites/CEPortal1/CEIT/NexGenIT/_layouts/15/doc2.aspx?sourcedoc=%7BFE254B15-C9CE-42C5-B0EC-57C7082DBDD3%7D&file=NexGen%20IT%20Contractor%20NDA.docx&action=default&mobileredirect=true https://usaf.dps.mil/:w:/r/sites/CEPortal1/CEIT/NexGenIT/_layouts/15/doc2.aspx?sourcedoc=%7BFE254B15-C9CE-42C5-B0EC-57C7082DBDD3%7D&file=NexGen%20IT%20Contractor%20NDA.docx&action=default&mobileredirect=true
M&R and CIP programs. The Government's expectation is that this dedicated element of the FFP-LOE Baseline Team will manage this workload proactively and efficiently.
1.2.1.3. Support for Centrally Funded Programs. When tasked via an IDIQ order, the SP shall provide project management or dedicated liaison services for the Government's highest-value and highest-risk projects, including all MILCON and Centrally Funded
FSRM efforts.
1.2.1.4. Foundational Execution Support. The SP shall provide responsive and accurate execution support services. This includes maintaining the authoritative IGI&S and record drawing libraries, providing timely technical evaluations, and ensuring all enabling data products are of sufficient quality to support effective portfolio planning, requirement development, and project execution.
1.2.1.5. Data Integrity and Portfolio Visibility. The SP shall maintain complete and accurate data for the entire CEN portfolio. The Government relies on the SP's timely reporting and data management in NexGen IT and the Master Project Schedule to make strategic decisions. Data accuracy is a paramount concern.
1.2.1.6. Strategic Workforce Transition and Knowledge Transfer. A critical imperative of this contract is the seamless and cooperative transition of functions to government performance. The SP shall actively support the Government's multi-year insourcing strategy by providing comprehensive knowledge transfer and process documentation.
This is not a secondary duty; it is a core performance requirement. The SP's methodology for this support shall be detailed in the Contract Transition Plan (CDRL A016), and its execution shall be documented in the Functional Area Continuity Binders (CDRL A017).
1.2.2. Operations Engineering Support Imperatives
1.2.2.1. Data-Driven Asset Management. The SP shall maintain accurate and current asset data through the rigorous execution of the Sustainment Management System (e.g., BUILDER) program. This includes meeting the mandate for assessing 20% of the customer facility portfolio annually, ensuring all condition assessments, equipment inventories, and warranty data are continuously updated in the designated Government IT systems.
1.2.2.2. Strategic Lifecycle Planning. The SP shall transition customer facility management from a reactive posture to a proactive, lifecycle-based strategy. The SP shall develop and maintain dynamic, five-year Maintenance Master Plans (MMPs) and specific infrastructure programs (e.g., roofs, HVAC) to prioritize investments and inform out-year programming.
1.2.2.3. Technical Quality Assurance and Commissioning. The SP shall act as the technical authority for customer facility investments. This imperative requires the SP to review all statements of work, design specifications, and material submittals, and to participate in final inspections to ensure the Government receives mission-capable, maintainable, and fully warranted products.
2. PROJECT MANAGEMENT.
2.1. Definitions of Program Categories. For the purposes of this PWS, all engineering project management and execution services are categorized into two primary scopes of work:
2.1.1. Baseline FFP-LOE Scope: This category represents the standing, day-to-day workload managed by the contractor's Firm-Fixed-Price Level of Effort (FFP-LOE) Baseline Support
Team. It consists of the following programs:
a) Decentralized FSRM (dFSRM) Program: Includes all projects executed with decentralized FSRM, Unfunded Requirements (UFR), and other local Operations &
Maintenance (O&M) funding streams. The Baseline Support Team is responsible for the full lifecycle management of these projects IAW Section 2.2.2. This support explicitly requires a proactive execution strategy, which includes developing Request for Proposal (RFP) packages in the fiscal year prior to execution (FY-1) to maintain an
"on-the-shelf" project pipeline, and managing those packages through the solicitation and award process during the fiscal year of funding.
b) OC-ALC Funded Program: Includes all real property projects funded by the Oklahoma
City Air Logistics Center (OC-ALC), including both their Maintenance & Repair
(M&R) and Capital Investment Program (CIP) portfolios. The Baseline Support Team shall provide a dedicated element for the full lifecycle management of these projects
IAW Section 2.2.2. This dedicated element shall execute requirements in direct alignment with the annual 3-year Integrated Priority List (IPL) published by the 76th
Maintenance Support Group (76 MXSG), preparing and advancing project packages based on the priorities established in this 1-N list to meet the ALC's programmatic requirements.
c) Centrally Managed Programs (Baseline Liaison): Includes projects funded as MILCON or designated by AFIMSC/AFCEC as Centrally Funded FSRM projects that are executed by an external agency (e.g., USACE, AFCEC). The Baseline Support Team shall provide routine technical liaison and coordination support for these projects IAW
Section 2.2.2.4, serving as the installation's representative to ensure compliance with local standards and mission requirements.
2.1.2. Orderable IDIQ Scope: This category includes all other project-specific services that are ordered on an as-needed basis via the Indefinite Delivery/Indefinite Quantity (IDIQ) CLINs defined in this contract. These services are managed via Task Orders IAW Section 2.2.3 and typically include:
a) Centrally Managed Programs: Projects funded as MILCON or designated by
AFIMSC/AFCEC as Centrally Funded FSRM projects (CTO). These programs fall under IDIQ scope when the Government determines the project requires dedicated
"Cradle-to-Grave" execution or "Stand-Alone Liaison" support that exceeds the
Baseline Team's liaison responsibilities.
b) Reimbursable Customer Programs: Project-specific work funded by reimbursable customers (e.g., Navy, DLA) who do not maintain a programmed, multi-year pipeline of projects with the 72 ABW/CEN. Because these requirements are typically ad-hoc
"inserts" or "one-off" projects that arise unpredictably throughout the year, their execution is managed via IDIQ to protect the Baseline team's programmed workload.
c) Other Specified Efforts: Any other discrete project or acquisition support task ordered by the Government that falls outside the planned scope of the Baseline FFP-LOE services. This explicitly includes out-of-cycle "inserts," urgent requirements, and emergencies identified by the Base Civil Engineer (BCE) for package development and award within the same fiscal year they are identified.
2.2. Project Management and Execution. The SP shall provide comprehensive engineering project management and execution services under the direct oversight and authority of the designated Project COR. These services shall be delivered through an optimally sized, on-site support team responsible for executing all FFP-LOE continuous functions as well as a baseline volume of anticipated IDIQ services (based on historical workload data). To accommodate unpredictable workload surges, emergency "inserts," and specialized IDIQ task orders beyond the on-site baseline, the SP shall maintain the robust capability to dynamically scale support utilizing a mix of on-site augmentation and off-site (reachback) engineering workforce. While the SP is responsible for the day-to-day management of project execution, all actions shall be performed on behalf of the Government and are subject to Project COR review and approval.
The SP is not authorized to provide formal direction to other contractors or approve any change that affects a project's cost, schedule, or scope.
2.2.1. Process Documentation and Knowledge Transfer. All processes and standard operating procedures (SOP) used to perform the project management and execution functions described in this PWS shall be fully documented and maintained in the appropriate Functional Area
Continuity Binder IAW CDRL A017. This documentation is a core deliverable of the contract to support the Government's strategic workforce transition objectives.
2.2.2. Provide Baseline Project Management & Program-Level Support (FFP-LOE). The SP shall provide a Baseline Support Team responsible for the overall management and tracking of the entire CEN Capital Project portfolio and for performing the following routine, program-level support functions:
2.2.2.1. Portfolio Management & Reporting. The Baseline Team shall:
2.2.2.1.1. Prepare and maintain a Master Project Schedule for all active design and construction projects across the entire CEN portfolio, regardless of funding source or executing agent, IAW CDRL A001 (Master Project Schedule). The SP shall use this schedule as the basis for communicating project milestones and status to
Government PMs and customers.
2.2.2.1.2. Coordinate, schedule, and provide appropriate notification for all routine, urgent, and emergency utility outages, road closures, and facility disruptions. The
SP shall prepare and submit all required Outage Request forms through the designated Government system or, in its absence, via the Government-approved format, on behalf of the project execution agent.
2.2.2.1.3. Prepare and submit a weekly Design and Construction Status Report to the Government IAW CDRL A004 (Weekly Design and Construction Status
Report).
2.2.2.1.4. Be responsible for the timely and accurate entry and management of all project information within the designated Government IT system(s) (e.g., NexGen
IT, Kahua) IAW CDRL A005 (NexGen IT System Management Plan) and Air
Force provided guidance and direction on use of Government IT system. The standards for timeliness and accuracy are defined in the associated CDRL and will be monitored as part of the Government’s Quality Assurance program.
2.2.2.1.5. Prepare draft funding document packages (e.g., AF Form 9, MIPR) for
CE projects as directed by the Government. The SP has no authority to commit or obligate Government funds. The SP shall be responsible for tracking the status of these funding actions and reporting on them in the Weekly Design and Construction
Status Report (CDRL A004).
2.2.2.1.6. Project & Program Records Management. The SP shall be responsible for establishing and maintaining the official Government project file for all projects managed under this contract. The SP shall develop and adhere to a Government-approved Records Management Plan IAW CDRL A013. This plan will define the standard file structure, naming conventions, and location for all project documentation, including designs, reports, correspondence, and official forms. The
Government shall have unrestricted access to all project records at all times.
2.2.2.2. Data Call & Acquisition Support. The Baseline Team shall:
2.2.2.2.1. Be responsible for compiling, formatting, and delivering all required project and program data to the Government in support of Higher Headquarters
(HHQ) and local data calls (e.g., IPL, MILCON Program Call, etc.). All data shall be delivered in the format and by the suspense date specified in the Government's request.
2.2.2.2.2. Provide technical acquisition support to the Government by developing
Draft Acquisition Packages IAW CDRL A010 (Acquisition Support Package) for new or follow-on local design and construction contract programs, including but not limited to SATOC, SABER, MACC, AE IDIQ, and PAVING IDIQ vehicles. This support includes developing the full documentation (PWS, specifications, IGEs, market research, etc.) as directed by the Services COR. An acquisition support package is considered contractually delivered only upon acceptance by the Services
COR and the cognizant Contracting Officer, signifying it is of sufficient quality for solicitation. The SP's support to the Contracting Office shall include, but is not limited to: (a) assisting in the development of responses to offeror questions during the solicitation period, and (b) providing technical input to the Government's evaluation of proposals, as requested by the Services COR.
2.2.2.3. Baseline Program Execution. The FFP-LOE Baseline Support Team shall be responsible for the complete lifecycle execution of the Baseline Programs defined in
Section 2.1.1 (dFSRM and OC-ALC M&R). The Baseline Team shall perform all necessary functions, including but not limited to:
2.2.2.3.1. Project Planning & Programming Support (FY-2 to FY-5): Developing
Project Assessed Amounts (PAAs) to support the planning, programming, and IPL development of future requirements. The SP shall validate the scope of work with the requestor, conduct site visits, coordinate with appropriate base agencies (safety, fire, environmental, etc.), and prepare a preliminary project cost estimate IAW UFC
3-740-05. The SP shall incorporate all required supporting documents (drawings, sketches, photos) to justify the requirement, recommend a method of contracting, and propose a construction timeline.
2.2.2.3.2. Requirements & Design Development (FY-1): Developing comprehensive requirements packages for all projects within the Baseline Programs designated for the upcoming fiscal year (FY-1). The objective is to proactively build and maintain a robust, "on-the-shelf" pipeline of executable projects prior to the year of funding. All packages shall be prepared in accordance with the specific method of execution (e.g., SABER, MACC, etc.) as directed by the Government and shall be of sufficient quality and completeness for solicitation. All packages are subject to the acceptance criteria defined in CDRL A006. As part of this package development, the SP shall develop and submit two distinct Independent
Government Estimates (IGEs) for each project: 1) A Procurement IGE ("Should-
Cost") developed strictly IAW standard estimating tools for Contracting Office use, and 2) A Programming IGE ("Will-Cost") developed by applying documented local market trends to the Procurement IGE to ensure accurate programming and funding requests. A package is considered contractually delivered only upon written acceptance by the Project COR, signifying it is of sufficient quality and completeness for solicitation by the Contracting Office. The SP shall be responsible for making all necessary corrections required during Government reviews in a timely manner.
2.2.2.3.3. Solicitation and Award Support (Year of Funding): For projects in the current year of execution, the SP shall transition accepted "on-the-shelf" packages to the active procurement phase. This includes finalizing and routing the package to the Contracting Office and providing continuous technical support through contract award. Support shall include, but is not limited to: developing draft Government responses to offeror Requests for Information (RFIs) for Project COR approval, facilitating pre-bid site visits, and providing technical evaluations of contractor proposals as requested.
2.2.2.3.4. Construction Management: Providing comprehensive, on-site construction management for all Baseline Program projects. This includes:
a) Performing on-site Quality Assurance (QA) inspections to monitor and document construction. The SP shall utilize the Three-Phase Quality Control process (Preparatory, Initial, Follow-up) for all definable features of work. The frequency of inspections shall be commensurate with the size, complexity, and risk of the project, as determined by the Project COR. Where Journeyman
Inspectors are utilized, the designated Lead Inspector shall perform documented oversight inspections at critical project milestones and major features of work.
All inspection activities shall be documented IAW CDRL A007 (Construction
Inspection Record). The SP inspector shall serve as the Government's 'eyes and ears' on the project site. The SP inspector has no authority to direct the construction contractor. All potential issues, deficiencies, or required changes identified during inspections shall be documented and immediately reported to the Project COR for formal direction.
b) Managing, tracking, and reviewing all construction submittals and RFIs and providing a formal, documented recommendation for approval or rejection to the Project COR.
c) Prepare complete, draft contract modification packages (including SOW, IGE, and technical justification) for Project COR review and approval.
d) Reviewing construction contractor progress payment requests for accuracy and completeness and providing a formal, documented recommendation to the
Project COR.
2.2.2.4. Installation Liaison for Externally Executed Programs. For all projects executed by an external agent (e.g., USACE, AFCEC) that do not have dedicated liaison support ordered via IDIQ, the Baseline Support Team shall serve as the installation's routine technical liaison. This support shall include, but is not limited to:
a) Ensuring appropriate Key Personnel attend meetings (e.g., design reviews, pre-construction conferences, progress reviews) as the installation's technical representative.
b) Performing technical reviews of design submissions and providing consolidated comments back to the executing agent on behalf of the installation.
c) Reviewing construction submittals sent to CE for input (typically includes fire and life safety systems, architectural finishes, and all equipment that will be maintained by CE) to ensure compliance with installation standards and mission requirements, and providing a technical recommendation to the Project COR.
d) Performing technical review of Requests for Information (RFIs) sent for CE input to ensure compliance with installation standards and mission, and providing a technical recommendation to the Project COR.
e) Performing site visits to monitor project progress. The frequency of site visits shall be determined by the Project COR, but shall be conducted at a minimum of once per week during active construction. All liaison site visits and significant observations shall be documented IAW CDRL A011 (Weekly MILCON/External
Agency Liaison Report).
f) Facilitating and coordinating all installation-level requirements for the executing agent, including but not limited to: required utility outages, staging, site access requests, and base civil engineer work clearance requests (e.g., AF Form 103 / Dig
Permits).
2.2.2.5. Contract by Requestor (CBR) Oversight. The Baseline Support Team shall provide technical oversight and coordination for Contract by Requestor (CBR) projects.
CBRs are defined as projects generated, funded, and procured by other base organizations or tenants that alter, add to, or affect Tinker AFB real property, infrastructure, or industrial processes. The SP’s role is to protect the Government’s real property interests throughout the CBR lifecycle by performing the following functions:
a) Technical Design Review: The SP shall perform in-depth technical reviews of CBR design, equipment installation, and solicitation packages provided by the requesting organization. The SP shall verify the proposed work complies with the Installation
Facility Standards (IFS), UFCs, life safety codes, AT/FP, and cybersecurity requirements. The SP shall provide consolidated written comments and recommendations to the Project COR within ten (10) working days of receiving the package for review.
b) Construction Observation & Coordination: The SP shall provide on-site observation of CBR construction activities to ensure the tenant's contractor does not negatively impact existing base infrastructure or operations. The frequency of these observations shall be commensurate with the complexity of the project and the risk to base infrastructure, as determined by the Project COR. Observations shall be documented IAW CDRL A007 (Construction Inspection Record). The SP has no authority to direct the tenant's construction contractor. Any observed safety violations, unapproved utility connections, or deviations from the approved design shall be immediately reported to the Project COR.
c) CBR Closeout and Capitalization: The SP shall actively facilitate the collection of required real property documents from the requesting organization. The SP shall make and document weekly attempts to obtain final as-built drawings, O&M manuals, and draft DD Form 1354s from the requestor upon notification of construction completion. The SP shall review received documents for accuracy, process them into the appropriate CE systems (e.g., NexGen IT, drawing vault), and submit the final DD Form 1354 package to the Project COR within ten (10) working days of receiving acceptable documents from the requestor.
2.2.2.6. Portfolio Warranty and Closeout Management. The Baseline Support Team shall manage the warranty and administrative closeout processes for all completed real property projects across the entire CEN portfolio, regardless of executing agent. This function includes:
a) Managing the installation's warranty program by tracking all active warranty periods within the designated Government IT system of record (e.g., NexGen IT)
IAW current DAF playbooks. The SP shall proactively schedule and conduct end-of-warranty inspections prior to expiration (e.g., conducting a 9-to-11 month inspection for a standard 12-month warranty), and prepare all necessary warranty claim documentation for the Project COR to enforce contractor corrections.
b) Managing the project closeout process by ensuring all required deliverables (e.g., as-built drawings, O&M manuals, training certifications) are received from the construction contractor. The SP shall ensure these deliverables are correctly filed
IAW the Records Management Plan (CDRL A013) and distributed to the appropriate CE Operations (CEO) shops. The SP shall prepare the final DD Form
1354 package IAW UFC 1-300-08 and current DAF guidance for Project COR signature and submission to the Real Property Office.
2.2.3. Orderable Project-Specific Services (IDIQ). The Government may issue individual Firm-
Fixed-Price (FFP) or Labor-Hour Task Orders against the corresponding IDIQ CLIN(s) for the discrete, project-specific services defined below. These services are intended for Centrally
Managed Programs (e.g., MILCON, Central FSRM), reimbursable O&M customers, or other efforts that exceed the scope of the FFP-LOE Baseline Team.
2.2.3.1. Full-Lifecycle Project Management. This task is intended for large, complex, or high-risk projects where the installation is the primary executing agent. This task order shall NOT be used for projects where an external agency (e.g., USACE, AFCEC) is the executing agent. For projects designated by the Government as requiring dedicated management beyond the capacity of the Baseline team, a Task Order may be issued for the SP to provide comprehensive, full-lifecycle project management. When this task is ordered, it shall be priced to encompass all applicable lifecycle functions, including requirements and design development (IAW 2.2.2.3.2), solicitation support (2.2.2.3.3), construction management (2.2.2.3.4), and closeout, as a single, integrated effort for that specific project.
2.2.3.2. Stand-Alone Requirements Package Development & Solicitation Support. For projects where the Government requires a discrete requirements package but not full lifecycle management, a Task Order may be issued for the SP to develop a complete design and RFP package. The package shall be prepared in accordance with the specific method of execution (e.g., SABER, MACC Design-Build) as directed by the Government and IAW the requirements of CDRL A006. This task includes all necessary
CADD/drafting support to produce the package, as well as subsequent technical support to the Contracting Office during the solicitation phase (answering RFIs, evaluating proposals).
2.2.3.3. Stand-Alone A&E Design Management. For projects where the Government has or plans to contract directly with a third-party Architect-Engineer (A&E) firm for design services, a Task Order may be issued for the SP to act as the Government's technical representative for design management. The SP shall perform all duties IAW CDRL
A009, including conducting design reviews, managing correspondence, and providing a final recommendation for design acceptance.
2.2.3.4. Special Acquisition Support. A Task Order may be issued for the SP to provide a dedicated Draft Acquisition Package, prepared IAW CDRL A010, for either of the following non-recurring efforts:
a) The full documentation package for a new, large-scale construction contract vehicle not previously identified in Section 2.2.2.2.
b) A complex acquisition package (SOW, IGE, Market Research) to support the award of a single, uniquely complex project Task Order that exceeds the capacity of the
Baseline FFP-LOE team (e.g., an urgent, high-visibility end-of-year fallout project requiring immediate contract award).
2.2.3.5. Stand-Alone Construction Inspection Augmentation. For projects where the
Government retains overall Project Management duties but requires dedicated on-site
Quality Assurance, a Task Order may be issued for the SP to provide on-site inspection services for a specified period of performance. All inspection activities shall be documented via Daily Inspection Reports (IAW CDRL A007).
2.2.3.6. Stand-Alone External Agency Liaison. For externally-executed projects requiring a level of dedicated, on-site support that exceeds the baseline liaison function described in Section 2.2.2.4, a Task Order may be issued for the SP to provide dedicated liaison and
QA support. The SP shall provide Weekly Liaison Reports to the Services COR IAW
CDRL A011 (Liaison Report).
2.3. Execution Support.
2.3.1. Baseline Execution Support Team (FFP-LOE). The SP shall provide a Baseline
Execution Support Team responsible for performing all routine Installation Geospatial
Information & Services (IGI&S), CADD/Drafting, and general engineering support functions.
This is a Firm-Fixed-Price (FFP) Level-of-Effort (LOE) requirement. All processes and standard operating procedures used to perform the portfolio management functions described in this section shall be fully documented and maintained in the appropriate Functional Area
Continuity Binder IAW CDRL A017.
2.3.1.1. IGI&S / GeoBase Management. The Baseline Execution Support Team shall perform all necessary activities to manage the installation's GeoBase program IAW all applicable directives. All geospatial data management shall adhere to the standards defined in CDRL A012 (IGI&S Management Plan). This includes:
2.3.1.1.1. Maintaining the authoritative installation geospatial data in the designated
Air Force IT system (e.g., AFGIMS) and ensuring compliance with SDSFIE standards.
2.3.1.1.2. Developing, updating, and maintaining all required utility, infrastructure, and facility data layers, including space utilization data in a format compliant with
NexGen IT and any other DAF-mandated enterprise systems.
2.3.1.1.3. Performing QA/QC on, and recommending Government acceptance of, all geospatial data from other sources (e.g., A&E firms, construction as-builts) to ensure compliance with standards and checklists defined in the Government-approved IGI&S Management Plan (CDRL A012).
2.3.1.1.4. Performing routine data conversions and preparing maps for Government and authorized external entities upon request. Routine map and data requests shall be completed within one (1) working days of receipt, unless a different timeline is mutually agreed upon with the requestor based on complexity. Map requests shall be tracked and completed IAW CDRL A003 (Map & Data Request Log).
2.3.1.1.5. Supporting the installation Geospatial Integration Office (GIO) working group, to include assisting with scheduling meetings and providing draft meeting minutes to the Services COR.
2.3.1.2. CADD & Drafting Services. The Baseline Execution Support Team shall:
2.3.1.2.1. Perform all routine drafting services, manage the CE drawing vault, and maintain all master facility plans and infrastructure drawings IAW CDRL A013
(Records Management Plan). This includes digitizing records, providing copies upon request, and providing drafting support for all locally developed project efforts.
2.3.1.2.2. As-Built Drawing Quality Control. The Baseline Execution Support Team shall perform a quality control review of all as-built drawing submittals received from the Project Management and Execution element to ensure they are complete, legible, and adhere to the standards defined in the Records Management Plan
(CDRL A013) before they are formally accepted into the master record set.
2.3.1.2.3. Be responsible for updating all as-built drawing data into the CADD and
GIS systems within 60 days of receipt from the Project Management and Execution element. Performance against this timeline shall be tracked and reported in the
Weekly Status Report (CDRL A004).
2.3.1.3. General Technical Support. The Baseline Execution Support Team shall provide general engineering support to the 72d Civil Engineer Directorate and its customers. This support includes, but is not limited to, the following functions:
2.3.1.3.1. Engineering Evaluations (Formal Work Requests). For all engineering evaluation requests received as formal work tasks through the designated
Government IT system (e.g., NexGen IT), the SP shall:
a) Manage and maintain a prioritized backlog. The SP shall work with the
Services COR to prioritize all open evaluation requests based on mission impact, life-safety, and other Government priorities.
b) Perform engineering evaluations to assess facility deficiencies and conduct code compliance reviews (e.g., Life Safety Analyses), providing a comprehensive written report IAW CDRL A002. These evaluations require the SP to identify the root cause of the deficiency or compliance issue, formulate technical solutions, and assess downstream system impacts. This support is for determining the viability and scope of a potential follow-on project or ensuring safe facility utilization and is distinct from routine maintenance troubleshooting (which is the responsibility of the CE
Operations Contractor).
2.3.1.3.2. General Engineering Assistance (Ad-Hoc Support). For all other requests for technical assistance that are not formal work tasks, the SP shall provide SME support to the CE Operations Division, other base customers, and other SP elements as tasked by the Services COR. This support may include, but is not limited to, answering technical questions, attending meetings, or providing other consultation requests. Report the status of all active assistance requests in the Weekly Status
Report (CDRL A004).
2.3.1.3.3. Installation Facility Standards. The SP Chief Engineer shall coordinate and co-chair an annual review working group to develop and provide annual updates to the Installation Facility Standards (IFS) for Government review and approval IAW CDRL A014. The SP’s key personnel SMEs shall provide technical recommendations to the Chief Engineer for inclusion. The SP shall ensure the latest version of all approved IFS documents is maintained in the Government system of record (currently WBDG.org).
2.3.1.3.4. Installation Program Support. The SP shall provide technical management and advisory support for various installation programs. This includes preparing and delivering meeting minutes, position papers, or technical recommendations as required for the Traffic Safety, AT/FP, Corrosion Control, and other engineering programs as designated by the Services COR. The status and level of effort for this advisory support shall be tracked and reported in the Weekly Status Report (CDRL
A004).
2.3.1.3.5. Emergency Response Support. The SP shall provide emergency response support, including on-call availability for damage assessment surveys, within 60 minutes of initial notification to respond from the CE Damage Control Center
(DCC) or designated Government representative. All assessment activities shall be documented and delivered in a Damage Assessment Report IAW CDRL A015.
2.3.1.3.6. Airfield Maintenance Contract Support. As directed by the Services COR, prepare and deliver the complete solicitation package for the annual Runway
Rubber Removal and Pavement Marking contract (which typically includes both
Spring and Fall execution phases). Upon contract award, provide technical oversight and quality assurance support during execution in coordination with the designated Government representative.
2.3.1.3.7. Excavation Permit Program Management. The SP shall manage the installation's excavation permit program. This includes receiving and processing all
AF Form 103s, coordinating with all required base agencies, and issuing the final, approved permit on behalf of the Government. The SP shall also be responsible for developing and providing training to base contractors on the proper procedures for submitting excavation permits.
2.3.1.3.8. Reimbursable Customer Program Support. The Baseline Execution
Support Team shall provide general technical support to reimbursable customers
(e.g., Navy, DLA) as defined in a separate Inter-Service Support Agreement
(ISSA). This support is limited to general engineering evaluations (CDRL A002) and program-level assistance. All project-specific requirements package development, design management, and construction management for these customers shall be executed via the Orderable IDIQ Services defined in Section
2.2.3.
2.3.2. Orderable Surveying Services (IDIQ). The Government may issue an IDIQ Task Order for the SP to perform specialized or large-scale engineering surveys. All routine, minor survey work required to support the Baseline Team's drafting and design package development (e.g., locating a single utility manhole, verifying dimensions for a small concrete pad) is included in the FFP-LOE CLIN. This IDIQ CLIN is for discrete survey efforts, including but not limited to:
a) Large-area topographic or boundary surveys (e.g., a topographic survey for an entire project site greater than one acre).
b) Formal aircraft mishap investigation support.
c) Other specialized engineering surveys or studies as defined in the specific Task
Order.
3. OPERATIONS ENGINEERING
3.1. Operations Engineering.The Contractor shall establish an Operations and Maintenance
Engineering Capability for CSAG, Navy, and DLA occupied facilities listed in Appendix 4.4.6.
Work closely with Operations personnel to provide analysis of built and natural infrastructure asset data. Apply an asset lifecycle approach to continually measure the performance of assets with respect to predicted lifecycle performance and use that analysis to ensure the CE's investment plans minimize risk to the mission and maximize the Air Force's return on investment. The Government will review and approve/disapprove all long range plans directed by the Government. Work with Government Requirements and Optimization (R&O) to align and de-conflict all investments for example, preventive maintenance, in-house repair or replacement, and renovation/replacement by contract investments. Ensure facility and infrastructure systems changes, including in-house repair or replacement, and as-built update recommendations based on findings from facility assessments are updated to as-built drawings, in SMS BUILDER database, and Equipment Information System Database (EISD) within 60 days after transfer and acceptance of DoD real property. Review SOWs, contract specifications, requests for proposal, and material submittals for construction/repair projects to ensure the Government receives mission capable/high performing/maintainable/warranted products. Provide on-demand technical expertise to COR for any contract project. Attend pre-final inspections, final inspections, and BOD’s to ensure proper construction, code compliance, and maintainability checks are complete. Analyze customer work orders with respect to planned investments on assets to validate the requirement and inform investment timing.
Support coordination on planned in-house work orders through CE R&O. Input and maintain warranty data for RPIE installed under CEO portfolio. Provide engineering technical support to
CEO for execution of a preventive maintenance program. Through design review, ensure the reliability and maintainability of reimbursable customers’ real property equipment. Meet the intent of AFI 32-1001 and PAD 12-03 Operations Engineering Element, Requirements &
Optimization section. Contractor shall execute the following requirements:
3.1.1. Workload Baseline and Annual Reconciliation. The scope of Operations Engineering services is directly tied to the total gross square footage (SF) of the facilities occupied by the designated reimbursable customers. To ensure fair compensation and accurate workload management, the SP and the Government shall utilize the following reconciliation process:
3.1.1.1. Initial Baseline: The initial FFP-LOE pricing for this section is based on the facility list and associated square footage provided in Appendix C. This appendix represents the Day 1 baseline.
3.1.1.2. Multi-Use Facilities: For facilities occupied by both a supported reimbursable customer and an unsupported tenant (e.g., a standard Air Force unit funded via 3400-
O&M), the SP's workload and the associated square footage shall be calculated on a pro-rata basis. The SP shall utilize the official Air Force Real Property records (NexGen IT) to determine the exact percentage of the facility assigned to the reimbursable customer and apply that percentage to the total facility SF to determine the supported workload.
3.1.1.3. Annual Reconciliation Process: The total supported square footage will fluctuate over the life of the contract due to new construction, demolitions, and mission realignments.
a) No later than the end of the 10th month of each period of performance (Option
Year), the SP shall submit a consolidated Facility Footprint Reconciliation Report.
b) This report shall detail all additions and deletions to the supported facility list
(Appendix C) that occurred during that period of performance, citing the official
DD Form 1354 or Real Property record update as justification.
c) The report shall calculate the net change (positive or negative) in supported square footage.
d) Upon Government COR review and Contracting Officer approval, the net change in square footage shall be multiplied by the pre-negotiated, per-square-foot adjustment rate established in the contract Pricing Matrix. The resulting value shall be used to adjust the FFP-LOE CLIN for the subsequent Option Year.
3.1.2. Maintenance Master Plan (MMP). Contractor shall maintain and manage a MMP to ensure execution of an effective preventive maintenance program. Contractor shall provide capital improvement planning recommendation to maintain the industry standard for life cycle costs for each customer’s facilities. Contractor shall develop, implement and manage an effective MMP as a dynamic database with monthly updates to production control. (reference
CDRL A011 Appendix 4.6) The MMP shall include the following tasks:
3.1.2.1. Contractor shall apply engineering evaluations with considerations…
This is the start of the file's text. The full file is on GovTribe.