TAFB_400 Ramp Ph 5_8_IFB Acq_Bid Schedule_20250707 (BLANK)v2.xlsx
XLSX spreadsheet 258 KB Posted
- Solicitation number
- FA8903-25-B-0002
About this file
This is a pre-solicitation notice and bid schedule for a design-bid-build construction project at Travis Air Force Base, California. The solicitation (FA8903-25-B-0002) seeks a contractor to demolish and replace approximately 60,000 square yards of concrete pavement and associated underground drainage utilities at the 400 Aircraft Parking Ramp, covering Phases 5 and 8. The project is a total small business set-aside with a price range of $25M-$100M, using NAICS code 237310 (Highway, Street, and Bridge Construction), and has a size standard of $45M.
Key project details include a site visit scheduled for 03 June 2025, with attendee registration due by 20 May 2025. The solicitation will be posted on SAM.gov on 23 July 2025, with sealed bids due on 25 August 2025 at 11:00 AM Central Time. The contractor will be required to establish an on-site staging area with a batch plant capable of producing 250 cubic yards of concrete per hour. Project completion time is 420 days for the base bid and 510 days if including the Phase 8 option. Contracting points of contact are Mr. David Foote and Ms. Monica Gallegos from the Air Force Installation Contracting Agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CSI Summary
| Contractor's Name | |
| Project No.: | XDAT06100105 & XDAT06100108 |
| Project Title: | Repair 400 Aircraft Parking Ramp Phases 5 & 8 |
| Project Location: | TRAVIS AFB, CA |
| Contracting No.: | TBD |
| Task Order No.: | N/A |
| Date: | 09 July 2025 |
| CSI SUMMARY |
MasterSpec Divisions Total
| Division 01 — General Conditions | |||
| Division 02 — Existing Conditions | |||
| Division 03 — Concrete | |||
| Division 04 — Masonry | |||
| Division 05 — Metal | |||
| Division 06 — Wood, Plastics, and Composites | |||
| Division 07 — Thermal and Moisture Protection | |||
| Division 08 — Openings | |||
| Division 09 — Finishes | |||
| Division 10 — Specialties | |||
| Division 11 — Equipment | |||
| Division 12 — Furnishings | |||
| Division 13 — Special Construction | |||
| Division 14 — Conveyance | |||
| Division 21 — Fire Suppression | |||
| Division 22 — Plumbing | |||
| Division 23 — Heating Ventilating and Air Conditioning | |||
| Division 25 — Cybersecurity | |||
| Division 26 — Electrical | |||
| Division 27 — Communications | |||
| Division 28 — Electronic Safety and Security | |||
| Division 31 — Earthwork | |||
| Division 32 — Exterior Improvements | |||
| Division 33 — Utilities | |||
| BASE BID ITEMS | |||
| CLIN # | CLIN Description | UI | CLIN Price |
| BASE BID ITEMS | |||
| 0001 | Base Bid Item 1 400 Aircraft Parking Ramp Phase V | LS | |
| 0002 | Option Item #1 400 Aircraft Parking Ramp Phase VIII | LS | |
| Base Bid Items Subtotal | $ - | ||
| OPTIONS | |||
| N/A | $ - | ||
| Bid Options Subtotal | $ - | ||
| Grand Total for All CLINs | $ - |
| Project Completion Time (Base Bid Only): | 420 | days from Award Date. |
| Project Completion Time (Base Bid + Option 1): | 510 | days from Award Date. |
&"-,Bold"&A
&"-,Bold"Page &P of &N
Col C - CSI Subtotal from each Base Bid Item and Bid Option Tabs
File details come from the government source that posted it. Updated .