About this file

This is a Scope of Work document prepared by the City of Wheat Ridge, Colorado for final design services related to corridor improvements along Tabor Street. The project encompasses comprehensive design services from W 44th Avenue to W Interstate 70 Frontage Road North, with the primary objective of integrating traffic calming measures, bicycle infrastructure, and pedestrian amenities. The scope includes project management and administration, public involvement activities (four stakeholder meetings, two City Council presentations, and one public open house), topographic surveying, utility investigation with up to 40 test hole excavations, hydrology and hydraulic engineering, comprehensive engineering and design services, and the development of construction plans at 30%, 60%, 90%, and 100% completion levels. Additional deliverables include landscape design, right-of-way plan development, lighting design, geotechnical investigation, traffic analysis and traffic calming design, and construction support services. The project specifically excludes floodplain permitting, bridge construction, and construction of the corridor segment from the bridge to the frontage road north.

The scope assumes the utilization of CDOT Construction Specifications for cost estimating and incorporates design criteria hierarchy established by AASHTO, FHWA, CDOT standards, City of Wheat Ridge codes, and NACTO guidelines. The project will deliver opinion of probable construction cost estimates at multiple design stages (30%, 60%, 90%, and 100%), informed by CDOT bid history and recent City of Wheat Ridge construction project data. Right-of-way acquisition services are included under the Uniform Act requirements, encompassing property owner engagement, valuations, negotiations, and closings for impacted properties. The project is funded through the City's Transportation Improvement Plan (TIP) and addresses a critical multimodal connectivity need, as Tabor Street currently provides the only crossing over I-70 between Ward Road and Kipling Street, serving existing and projected employment and residential developments in the area.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A City of Wheat Ridge Tabor Street TIP Final Design Scope of Work – 6/1/2026

City of Wheat Ridge Tabor Street Traffic Improvement Plan Final Design Scope of Work – June 1, 2026

INTRODUCTION

Tabor Street provides the only opportunity to cross I-70 between Ward Road and Kipling Street and extends from the G-Line Station via Ridge Road to the Clear Creek Trail. Multimodal facilities are non-existent south of the I-70 Frontage Road North. Tabor Street and the bridge over I-70 are narrow and used by trucks leaving the nearby truck stop to access westbound I-70. Tabor south of 44th is essentially an alley with barely enough for a single vehicle. By extending the multimodal facilities south of the frontage road south over I-70 to Clear Creek, the project provides multimodal access to all residents, particularly those that don’t have a vehicle, between the G Line Station and the population and employment centers located north of I-70 and the Clear Creek Trail. This allows multimodal access to Clear Creek Crossing, which will soon have a new hospital and shopping, retail, restaurants, a fitness center, and employment destinations. Multimodal access will be provided to the population centers south of I-70 to the Station and the employment centers around the DRCOG Urban Center around the Station. There is also a medical facility on the west side of Ward Road at the frontage road. There are currently over 9,000 jobs within the project area and projected to be almost 14,000 jobs within 30 years.

BACKGROUND

Wheat Ridge, Arvada, and Jefferson County residents located near the northern end of the existing Tabor Street bike lanes will benefit from the multimodal connection to Clear Creek. The nearest multimodal connection that safely crosses I-70 is a couple of miles to the east at Garrison Street and the multimodal facilities to that crossing are not consistently available. In addition, the project will provide multimodal access to the Station for Golden residents and Wheat Ridge residents in the soon to be completed apartments in Clear Creek Crossing via the Clear Creek Trail. Multimodal facilities along Tabor Street are proposed to be installed between the Clear Creek Trail and I-70 Frontage Road North. A separate pedestrian bridge will be installed across I-70 adjacent to the existing vehicular bridge. Some level of signalization at the 44th/Tabor intersection is proposed to help cross 44th, a 4-lane street. Tabor Street provides the only crossing over I-70 between Ward and Kipling Streets, both of which currently do not have adequate multimodal facilities. Dedicated multimodal facilities along Tabor Street and over I-70 will separate users from the heavy truck traffic that uses Tabor Street to access westbound I-70 from the truck stop west of the project area on 44th Avenue. Extending the Tabor Street bike lanes from the frontage road to the Clear Creek Trail will provide multimodal access from western Wheat Ridge to the G Line Station and the Van Bibber Trail system in Arvada and from the rapidly developing area around the Station to the Clear Creek Trail, which is part of the Peaks to Plains Trail System. Over 1,000 housing units are in various stages of completion around the Station area in both Wheat Ridge and Arvada. The Clear Creek Trail is part of the Peaks to Plains Regional Trail System and provides multimodal connections to the entire Metro area.

PAST PLANNING EFFORTS Comment by Ashley Holland: Added this section Improvements to the Tabor Street corridor have been identified as a priority through several city planning and community engagement efforts over the past decade. The 2017 Bicycle and Pedestrian Master Plan recommended the addition of sidewalks and bike lanes along Tabor Street between the Clear Creek Trail and W I-70 Frontage Road North to improve multimodal connectivity and access throughout the area.

In 2023, residents reaffirmed the importance of these improvements through the city’s neighborhood engagement initiative, Let’s Talk North I-70. During that process, creating a safe bicycle and pedestrian connection between the Ward Road RTD Station and Clear Creek emerged as the top-ranked action item identified by participants.

Most recently, the 2025 City Plan identified Tabor Street north of Clear Creek as a Neighborhood Bike Connector. This designation calls for implementation of the best feasible bicycle facility and may include improvements such as bike lanes, traffic calming measures, shared lane markings, signage, and related pedestrian and bicycle enhancements.

Together, these planning efforts and community priorities have established a strong foundation for the current final design process and demonstrate ongoing support for improved multimodal connections on the corridor.

SCOPE OF WORK Comment by Lauren Mikulak: I recall talking about minimum sidewalk widths with DRCOG when we revised the TIP. Are those in the TIP agreement so we can include them here? Comment by Logan Huffaker: @Lauren Mikulak The city standard would be a 6ft detached sidewalk here. I have a note from our meeting for “bike lane and sidewalk up to 8ft width where possible” but I don’t remember where we wanted that in the scope. I assume here with the minimum sidewalk width.

The City seeks the Consultants expert guidance to perform Final Design services for corridor improvements along Tabor Street from W 44th Avenue to W Interstate 70 Frontage Road N in the City of Wheat Ridge. This project must integrate three key elements—traffic calming, bicycle infrastructure, and pedestrian amenities. The scope includes the following assumptions and exclusions:

· Floodplain permitting is excluded.

· Final design of the Tabor Street bridge crossing over I-70 is included in this scope for bridge configuration and pedestrian accommodation. Bridge construction and construction phase improvements are excluded from this scope.

· Final design, right-of-way, and construction of a bike lane and sidewalk, up to 8 feet in width, on Tabor Street from 49th Avenue to Clear Creek Trail and the I-70 Frontage Road North are included in this project. All elements of this segment will be constructed as part of this project, except for the Tabor/I-70 Bridge.

· Construction of the Tabor Street corridor from the bridge to W Interstate 70 Frontage Road N is excluded from this scope.

· No new traffic signal design is included along this portion of the Tabor Street corridor.

0.0 PROJECT MANAGEMENT & ADMINISTRATION

0.1 Administer the contract per City of Wheat Ridge requirements

0.2 Prepare monthly invoices and progress reports.

0.3 Schedule & conduct a project kick-off meeting with project staff and bi-weekly progress meetings with project staff and prepare meeting minutes and/or summaries.

1.0 PUBLIC INVOLVEMENT

1.1 Plan, coordinate, and hold small group stakeholder meetings with properties most impacted (assume 4 separate meetings).

1.2 Develop materials to support City staff presentations to City Council (assume 2 presentations).

1.3 Plan, coordinate, and hold one public open house meeting and online engagement opportunity. Develop informational flyers & invites. City will develop mailing list and send mailings. Provide public engagement results to staff for use on the City website.

2.0 TOPOGRAPHIC SURVEY

2.1 Perform traditional detailed topographic survey of critical areas (sidewalk ramps, tie-in curb/gutter, pavement tie-in points, etc. Includes QC and CAD Processing of line features in Civil 3D). Survey Control shall be City of Wheat Ridge Datum, Central Zone, NAD 83 US Feet.

3.0 UTILITY INVESTIGATION

3.1 Review existing utility reports, records, maps, and plans from study phase.

3.2 Perform and mark on-site designating & locating of existing UG utilities (QLC). Perform survey of marked locations (QLB) and process into topographic survey CAD files.

3.3 Develop preliminary utility plan sheets & potential locations for QLA Test Holes.

3.4 Perform preliminary utility coordination with up to 10 impacted utility owners. Develop preliminary utility conflict plans for up to 5 separate utility owners.

3.5 Verify Test Hole locations, perform up to 40 test hole excavations with survey and field reports,

3.6 Finalize Utility Plans with QLA information.

3.7 Perform final utility coordination with up to 10 impacted utility owners. Develop relocation plans for up to three utility facilities. Develop and assist the City with executing up to 3 utility agreements.

4.0 HYDROLOGY AND HYDRAULIC ENGINEERING

The H&H engineering that will be developed as part of the final design stage will consist of the following tasks and assumptions. Evaluate current stormwater infrastructure and recommend necessary improvements for better performance and flood mitigation. No floodplain impacts are anticipated as part of this project; therefore, floodplain permitting is not included as part of this scope.

The specific H&H related tasks and descriptions are provided here:

4.1 Task management & coordination

a. This covers internal management of this task within the hydraulic discipline and coordination meetings with clients, stakeholders, and internal staff as needed.

4.2 H&H Modeling, Design, and Reporting

a. Updates to existing conditions H&H from comment review or due to new survey information

b. Complete H&H drainage design including minor and major storm criteria:

i. Determine locations, sizes, and alignment based on conceptual hydraulic design. Identify locations by highway station or coordinates, as appropriate.

ii. Determine the allowable headwater and roadway spread.

iii. Assess the degree of sediment and debris problems to be encountered

iv. Update per roadway comment and review changes after 30%, 60%, and 90% review periods.

4.3 Preliminary (30%) Plans

i. 30% plans will consist of general layout of the system with preliminary plan and profile sheets for the proposed drainage system. This will be used to highlight potential conflicts with ROW and Utilities.

4.4 60% Plans

i. Refinements to the 30% plans will be implemented based on 30% city review comments and conflict resolution between ROW and Utilities. Major redesign of the roadway and general layout of the system are not anticipated past the 60% design stage.

4.5 90% Plans, Details, and Specifications

i. 60% city review comments will be addressed, and plans will be refined to the 90% level, minor changes to pipe elevations and alignment are included.

ii. Necessary details and specifications will be provided at this stage.

4.6 100% Plans, Details, and Specifications

i. 90% city review comments will be addressed, and plans will be refined to the 100% level. Only very minor changes to pipe alignment or elevations are anticipated at this level. Plans will be reviewed for standardization across disciplines.

ii. Final refinements to the details and specifications will be provided at this stage.

5.0 ENGINEERING & DESIGN

5.1 Develop alignment and profile for roadways, curbs, and ramps.

5.2 Perform comprehensive 3D modeling and cross sections of the project template to develop plan sheets.

Design Criteria to be followed (in order of precedence and hierarchy):

· AASHTO; A Policy on Geometric Design of Highways & Streets

· AASHTO Roadside Design Guide

· FHWA Manual of Uniform Traffic Control Devices (MUTCD)

· CDOT M&S Standards

· City of Wheat Ridge Zoning and Development Code

· NACTO Urban Street Design Guidelines

· AASHTO Guide for the Development of Bicycle Facilities

6.0 PLAN DEVELOPMENT AND PRODUCTION

6.1 Develop 30% construction plans for roadway, bicycle facilities, sidewalks, and drainage facilities to include:

· Title sheet

· Survey Control Diagram

· Geometric Control

· Typical Section

· Removals

· Roadway Plan & Profiles

· Preliminary Intersection Details

· Preliminary ADA Ramp Details

· Preliminary Drainage Plan & Profiles

· Preliminary Drainage Details

6.2 Develop 60% construction plans for roadway, bicycle facilities, sidewalks, and drainage facilities to include 30% Plan elements plus:

· Standard Plans List

· General Notes

· SAQ & Quantity Tabulations

· Intersection Details

· ADA Ramp Details indicating compliance with the latest version of CDOT “Curb Ramp” standards M-608-1 Comment by Lauren Mikulak: Is this meant to be a black bullet as part of 60% plans instead of 6.3?

· Preliminary Driveway Details

· Drainage Plan & Profiles

· Drainage Details

· Preliminary Lighting Plans & Details

· Preliminary Signing & Striping Plans, Details, and Quantities

· Preliminary Construction Stormwater/Erosion Control Sheets (SWMP or ECS)

· Utility Plans

· Preliminary Construction Phasing/MOT Plans

6.3 Develop 90% construction plans to include 60% Plan elements plus:

· Driveway Details

· Lighting Plans & Details

· Signing & Striping Plans, Details, and Quantities

· Construction Stormwater/Erosion Control Sheets (SWMP or ECS)

· Utility Plans

· Construction Phasing/MOT Plans

· Miscellaneous Details

· Cross Sections

6.4 Finalize 100% PS&E construction plans.

6.5 Develop Preliminary Construction Specifications at 60% and final Specifications at 90% and 100%. It is assumed CDOT Construction Specifications will primarily be utilized.

6.6 Develop opinion of probable construction cost estimate at 30%, 60%, 90%, and 100%. CDOT bid items will be utilized in the plans and CDOT bid history will be utilized to develop the opinion of probable cost, with adjustments based on recent City of Wheat Ridge construction projects.

6.7 Develop Project Manual for Advertisement and Contract

6.8 Provide Bid & Award Support for selection and award of construction contract.

7.0 LANDSCAPE DESIGN

7.1 Develop preliminary corridor streetscape design & cost estimate (per SF) for 30% plans.

7.2 Facilitate discussion and selection of surface water quality elements (i.e. bioswales) where feasible for 60% plans.

7.3 Develop detailed streetscape design and planting & irrigation quantities for 60% plans.

7.4 Develop detailed planting & irrigation plans, quantities, and specifications for 90% and 100% plans.

ROW PLAN DEVELOPMENT

Develop parcel tracking spreadsheet and calculate estimated property impact polygons (acquisition and TCE’s) for use on 30% plans and in tracking spreadsheet (with opinion of acquisition costs).

Develop Preliminary ROW Plans with detailed acquisition and easement shapes (no exhibits or legal descriptions).

Develop Final ROW Plans with detailed acquisition and easement shapes. Develop exhibits and legal descriptions for fee acquisitions.

Perform 1-on-1 coordination with affected landowners.

Field stake acquisition and easement impacts at the request of landowners. Limited to one staking per parcel; parcels will be combined and staked in groups to minimize cost.

9.0 LIGHTING DESIGN

In general, this scope is to perform necessary lighting design for roadway projects. Gather available data and review existing lighting conditions, equipment and delivery systems.

9.1 Coordinate with City staff to determine needs/desires for future corridor lighting.

9.2 Develop a photometric plan for review and discussion with City Staff.

9.3 Develop plans at 60%, 90% and Construction Documents. Plans will include the following information:

· Lighting Layouts

· Conduit and other electrical delivery infrastructure needs

· Lighting details

· Electrical connection design/details

· Opinion of probably cost of equipment for each submittal

10.0 GEOTECHNICAL INVESTIGATION

In general, this scope is to perform necessary geotechnical investigations for roadway projects. See the RMG detailed Scope of Work for exact tasks to be performed.

10.1 In consultation with the project team, develop preliminary investigation map of boreholes and soils samples, depths, and required tests.

10.2 Perform field investigation, including appropriate and approved traffic control and laboratory testing.

10.3 Perform pavement design & recommendations.

10.4 Develop draft and final geotechnical report with findings and recommendations.

11.0 ROW ACQUISITION SERVICES

In general, this scope is to perform necessary Right-Of-Way notice, negotiation, closing, and acquisition services meeting the requirements of the Uniform Act. See the WSLS detailed Scope of Work for exact tasks to be performed.

11.1 Perform initial property owner engagement at 60% design level. This applies only to impacted property owners within the included project limits.

11.2 Draft & send notice of intent letters to impacted property owners. This applies only to impacted property owners within the included project limits.

11.3 Perform property valuations. This applies only to impacted property owners within the included project limits.

11.4 Draft & send offer letters to impacted property owners. This applies only to impacted property owners within the included project limits.

11.5 Perform negotiations.

11.6 Draft & send final offer letters to impacted property owners.

11.7 Perform closings.

12.0 TRAFFIC ANALYSIS & TRAFFIC CALMING DESIGN

12.1 Conduct existing conditions traffic analysis including speed data review, traffic volume review, crash history review, and multimodal conflict evaluation.

12.2 Evaluate and recommend traffic calming measures including curb extensions, mini traffic circles, raised crossings, speed cushions, median treatments, advisory bike lanes, and intersection visibility improvements.

12.3 Prepare signing and striping concepts consistent with MUTCD and City standards.

13.0 CONSTRUCTION SUPPORT SERVICES

13.1 Provide engineering support during construction including responses to RFIs, review of submittals and shop drawings, and preparation of design clarifications.

13.2 Attend preconstruction meetings and periodic construction progress meetings

13.3 Review contractor requests for information and substitution requests.

13.4 Prepare plan revisions or supplemental sketches as required due to field conditions.

13.5 Conduct substantial completion punch list walkthrough and final acceptance review.