Table_A_-_Cost_Allocation_Matrix.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
PROGRESSIVE DESIGN-BUILD (PDB) GRAND AVENUE FLEET GARAGE PROJECT
Solicitation number
080-2891605-AR
Issued by
Orange County, San Diego City, California

About this file

The file is a Cost Allocation Matrix (Table A) for the Orange County Grand Avenue Fleet Garage Project, a Progressive Design-Build (PDB) procurement for a new fleet service facility. The project involves constructing a 45,756 square foot single-story facility at 1300 South Grand Avenue in Santa Ana, California, featuring 36 vehicle maintenance bays, 2 bus maintenance bays, and 7,946 square feet of staff offices and common spaces. A mandatory pre-proposal virtual meeting is scheduled for October 8, 2025, with statements of qualifications due by October 22, 2025, at 2:00 pm. The expected project completion is no later than the end of 2027, with a comprehensive design-build approach that will progress through initial design and preconstruction phases before establishing a Guaranteed Maximum Price.

The project's conceptual budget is estimated between $20,000,000 to $25,000,000, targeting the consolidation and replacement of Orange County's aging fleet service facilities. The Cost Allocation Matrix provides a detailed breakdown of cost responsibilities across project phases, including jobsite staff, construction work, temporary facilities, utilities, indirect costs, hoisting, main office expenses, and design elements. The facility will serve Orange County Fleet Services, which manages over 3,000 county-owned vehicles, and will incorporate sustainable design practices such as recycled materials, high-efficiency systems, natural lighting, water conservation, and drought-tolerant landscaping. Qualified respondents must be either a B-Licensed General Contractor or a lead design firm with at least ten years of experience, and will be evaluated using a points-based scoring system with a maximum of 5,000 points.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cost Table Construction Phase Jobsite Staff Direct Cost of Work Construction Phase Services General Requirements OH&P Paid by Owner Notes

1Project ManagerX
2Project SuperintendentX
3Project EngineerX
4Scheduling EngineerX
5Field Engineer and consultantX
6Estimating Change OrdersX
7Drafting and DetailingX
8All other GC field staff titles significantly involved in the projectX
9As-Built drawings and specificationsX
10Create and/or update Record DrawingsX
11Field AccountantX
12Time KeeperX
13SecretarialX
14Clerk/ TypistX
15Job Assigned Safety and. E.E.O. OfficerX
16Job site safety and cost of safety per OCIP standardsX
17Fringe Benefits for Job Site Services StaffX
18Vacation Time for Const. Phase Services StaffX
19Sick Leave for Const. Phase Services StaffX
20Subsistence for Const. Phase Services StaffX
21Periodic drug testingX
22Jobsite LaborersX
23Bonuses for staffX
24Reasonable suspicion and post-accident drug testingX

Construction Work Direct Cost of Work Construction Phase Services General Requirements OH&P Paid by Owner

1Wages of Construction LaborX
2Labor Fringe Benefits and BurdenX
3Subcontract CostsX
4MaterialX
5EquipmentX
6Protection of installed workX
7Small Tools – PurchaseX
8Small Tools – RentalX
9Small Tools – Purchase (General Requirement Tasks)X
10Small Tools – Rental (General Requirement Tasks)X
11Independent SurveyorX
12Warranty Work and CoordinationXNot contingency
13Corrective Work Damaged by Design-Builder or subcontractorsXNot contingency
14Corrective Work Non-Conforming with SpecsXNot contingency
15All Design-Builder Staff VehiclesXEven if used to pick-up / move materials.

Job Site Temporary Facilities Direct Cost of Work Construction Phase Services General Requirements OH&P Paid by Owner

1Office Trailers, including Inspectors and OwnersX
2Storage Trailer and Tool ShedX
3Office Furniture and EquipX
4Copy machine and PrinterX
5Postage/UPS/FedExX
6Project PhotographsX
8Project SignX
7Temporary ToiletsX
9ScaffoldingX
10Temporary Fencing and EnclosuresX
11Covered WalkwaysX
12BarricadesX
13Temporary StairsX
14Opening ProtectionX
15Safety Railing and NetsX
16Drinking Water/Cooler/CupX
17Safety/First Aid SuppliesX
18Fire Fighting EquipmentX
19Security GuardsX
20Watchman / Service (Day or Night) incl. Fire WatchX
Temporary Utilities And CleaningDirect Cost of WorkConstruction Phase ServicesGeneral RequirementsOH&PPaid by Owner
1Telephone InstallationX
2Telephone Monthly ChargesX
3Electric Power InstallationX
4Electric Power Distribution WiringX
5Electric Power Monthly ChargesX
6Water Service – InstallationX
7Water Service - Monthly CostsX
8Heating and Cooling CostsX
9Light BulbsX
10Final CleanX
11Periodic Job Site Clean-UpX
12Dump Permits and FeesX
13Trash Removal and HaulingX
14Flagman and Traffic ControlX
15Dust ControlX
16SWPP Installation and MaintenanceX
17SWPP InspectionX
18Temporary Road ConstructionX
19Temporary Road MaintenanceX
20Trash Chute and HopperX
Indirect and Miscellaneous CostsDirect Cost of WorkConstruction Phase ServicesGeneral RequirementsOH&PPaid by Owner
1Performance and Payment Bond premiums for Design-Builder’s bondsX
2Design-Builder Insurance PremiumsX
3Builders Risk Insurance PremiumsX
4Trade Contractor Performance and Payment Bond PremiumsX
5Insurance premium for trade contractors enrolled in any Design-Builder sponsored program such a CCIPX
6Trade contractor default insurance PremiumsX
7Any other premium associated with any sort of product related to additional risk mitigationX
8Insurance deductible by Design-Builder or trade contractorX
9Printing plans and specificationsX
10Initial Soils InvestigationX
11Hydraulic Testing for dewateringX
12Testing and InspectionX
13Maintenance after occupancyX
14Facility operator training by Design-Builder or trade contractorsX
15Fees- Plan CheckX
16Fees- Building PermitX
17Fees- Sidewalk PermitX
18Fees- Water Connection PermitX
19Fees- Water MeterX
20Fees- Sanitary SewerX
21Fees- Storm DrainX
22Fees- Gas ServiceX
23Fees- Power ServiceX
24Fees- Curb and Gutter permitX
25Fees- SignsX
26Elevator Inspection and PermitsX
27Fees, assessments, licenses, inspections required for ConstructionX
28Business Licenses and FeesX
29LEED registrationX
30LEED certificationX
31Commissioning CoordinationX
32County Health Department FeeX

Hoisting (multi-trade) Direct Cost of Work Construction Phase Services General Requirements OH&P Paid by Owner Specialty hoisting for single trades may be included in subcontracts however, the Design-Builder shall consolidate general jobsite equipment to the extent feasible and efficient with consideration of the amount of available space on the jobsite.

1Hoist and Tower RentalX
2Hoist Landing and FrontsX
3Hoist OperatorX
4Hoist Material Skips/ HoppersX
5Erect and Dismantle Cranes and HoistsX
6Crane RentalX
7Crane OperatorsX
8Crane Raising/ Jumping CostsX
9Temporary Elevator RentalX
10Elevator Operation CostsX
11Cage Rider at ElevatorX
12Forklift RentalX
13Forklift OperatorX
14Hoisting Safety InspectionsX
15Fuel, Repairs, Maintenance, ServiceX

Main Office Direct Cost of Work Construction Phase Services General Requirements OH&P Paid by Owner

1Corporate ExecutivesX
2Principal in ChargeX
3Operation ManagerX
4Project ExecutiveX
5EstimatingX
6Value EngineeringX
7SchedulingX
8Drafting and DetailingX
9Purchasing and Writing ContractsX
10Accounting and BookkeepingX
11Safety and E.E.O OfficerX
12SecretarialX
13Clerk/TypistX
14Computer/Data ProcessingX
15Legal - General and Pertaining to ProjectX
16Travel and SubsistenceX
17Fringe Benefits and BurdenX
18Vacation Time/Main OfficeX
19Bonuses/Main OfficeX
ItemDesign ElementsInclude in Design FeeInclude in Direct CostOH&POwner Allowance
(inc. in GMP)Owner Other

(outside of GMP)

1ArchitecturalX
2StructuralX
3MechanicalX
4ElectricalX
5PlumbingX
6Design-Build Trade Partner Design & Preconstruction FeesX
7Design-Assist Trade Partner Design & Preconstruction FeesX
8Data and Tel-com design and coordinationX
9Data and Tel-com Equipment SelectionX
10AV DesignX
11Interior DesignX
12AcousticalX
13LightingX
14Code AnalysisX
15Civil/UtilitiesX
16Distributed Antenna System and Two Way Communications design and rough-in coordination.X
17Distributed Antenna System and Two Way Communications system designX
18Fire ProtectionX
19Fire AlarmX
20Security - Access Control/CCTVX
21Curtain Wall SystemsX
22Pre-Engineered Pipe SystemsX
23Seismic BracingX
24Pre-Engineered ProductsX
25Manufacturer's Proprietary Eng.X
26<Specialty Design added by OCPW Project Manager>X
27Elevator Design CoordinationX
28Elevator EngineeringX
29LandscapeX
30<OCPW Project Manager add specialty equipment description> Design CoordinationX
31<OCPW Project Manager add specialty equipment description> SelectionX
32FFE Design CoordinationX
33FFE SelectionX
34Energy Modeling (Title 24)X
35BMS ControlsX
36OFOI EquipmentX
37Commissioning Agent - Enhanced for LEEDX
38Commissioning CoordinationX
39Foundation Structural DesignX
40Dewatering System EngineeringX
41Environmental (Branding) Graphics/ Signs – Coordination, scope and solicitation. Allow 4 design meetings with user groups.X
42Environmental (Branding) Graphics/ Signs – DesignX
ItemPhase 1 Site InvestigationInclude in Design FeeInclude in Direct CostOH&POwner Allowance
(inc. in GMP)Owner Other

(outside of GMP)

1Subsurface Utility MappingX
2Potholing / trenchingX
3Survey / scanningX