U.S. GENERAL SERVICES ADMINISTRATION

Region I

PUBLIC BUILDINGS SERVICE

DESIGN AND CONSTRUCTION DIVISION

Thomas P. O’Neill Jr. Federal Building Boston, Massachusetts

91 & 93 Vital Drive, 170 Main Street, & Aztec Slab at 188 Main Street, Madawaska, ME

Building Demolition

SCOPE OF WORK

12/04/2020

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

Building Name:

Building Address: 91 & 93 Vital Drive, and 170 Main Street, Madawaska, Maine 04756-143

Statement of Work (SoW) for Demolition Services

December 045, 2020

PROJECT IDENTIFICATION

Project Name: New Madawaska Land Port of Entry Project

Project Number: NME0012

Region: 1 - New England

Building Address: BASE:

93 Vital Drive, Madawaska, Maine 04756-1439 (Tax

Parcel 5-162)

170 Main Street, Madawaska, Maine 04756-1439 (Tax

Parcel 5-161)

188 Main Street, Madawaska, Maine 04756-1439 (Tax

Parcel 4-88) Slab and Foundation on US Owned land

OPTION:

91 Vital Drive, Madawaska, Maine 04756-1439 (Tax

Parcel 5-163)

U.S. General Services Administration

Public Buildings Service

Statement of Work Writer:

Kenneth Perez Desk: (617) 531-2644 Mobile: (617) 306-7793 Email: kenneth.perez@gsa.gov

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

Table of Contents

SCOPE OF SERVICES: ………………

Project Summary…....………

Part 1 - General

1.1 Project Information

1.1.1 Base…………………

1.1.1.1 Property #1 93 Vital Drive

1.1.1.2. Property #3 170 Main Street

1.1.1.3. Slab and Foundation

1.1.2 Option

1.1.2.1. Property #2 91 Vital Drive

1.1.3 Project Name and Location

1.1.4 Project Summary Description

Work Restrictions…………

Part 1 - General

1.1 Contractor Use of Premises…

1.2 Hours

Safety and Health

Part 1 - General

1.1 Summary……………………

1.2 Safety Meetings

1.3 Safety and Health Program...…

1.4 Submittals

Part 2 - Products

2.1 Personnel Protective Equipment

Part 3 - Execution

3.1 Hazardous Materials and Conditions

3.2 Emergency Suspension of Work

3.3 Protection of Personnel

3.4 Environmental Protection

Construction Waste Management & Disposal

Part 1 - General

1.1 Summary……………………

1.2 Definitions

1.3 Performance Requirements...…

1.4 Action Submittals

1.5 Informational Submittals

Part 2 - Execution

2.1 Plan Implementation

2.2 Disposal of Waste

Selective Demolition

Part 1 - General

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.1 Summary

1.2 Submittals

Part 2 - Execution

2.1 Examination

2.2 Preparation

2.3 Disposal of Demolished Materials

Attachments

Requirements

Resources

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

SCOPE OF SERVICES:

Project Summary

Part 1 - General

1.1. Project Information

1.1.1. Base

1.1.1.1. Property #1 93 Vital Drive

1.1.1.1.1. Two-story residence with 1,116± square feet of living area and a wrap-around porch. The wood structure includes asphalt shingle roofing and painted clapboard siding. The structure includes poured concrete foundation walls and slab. The first floor contains a kitchen, a dining room, a living room, a master bedroom with a toilet and shower (no sink), and a laundry area where the stairway to the second floor is located. On the second floor are three bedrooms and a three-fixture bathroom.

The full basement is unfinished; it is used for storage, houses the mechanical systems and oil tank. A 275 gallon heating oil aboveground storage tank was identified in the basement.

There was no evidence of spills, leaks or releases in the vicinity of the AST. Additionally, no floor drains or sumps were identified in the basement. No areas of stressed vegetation, dumping, or spills were observed at the Site. During the site visit, it was observed that there is a fuel oil fill and vent line on the north side of the house. The residence has been vacant for a few years and has structural issues. Refer to the Hazardous

Material Assessment Report for 93 Vital Drive, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations.

1.1.1.2. Property #3 170 Main Street

1.1.1.2.1. The subject site is located along Main Street and includes a private roadway, Vital Drive. The 0.37±-acre site has 128± feet of frontage along Main Street and benefits from public utilities.

The site is improved with a single-unit residence that contains

1,274± square feet of living area. A covered porch is located along the east and south sides of the home. The first floor contains an eat-in kitchen, a den with doors to the back deck

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020 where the pool is located, a living room, and a full bathroom with a laundry area. On the second floor are three bedrooms and a two-fixture bathroom. The full basement is unfinished. It is used for storage, houses the mechanical systems and oil tank. The 275 gallon #2 heating oil above-ground storage tank

(AST) is in good condition. No staining or releases were observed. Additionally, no floor drains or sumps were identified in the basement. There are assorted petroleum based products located under the deck along the northern exterior wall. There was no apparent dumping of material over the steep bank on the north side of the site. There are typical residential petroleum chemicals stored on-site (gas, oil, etc. for lawn equipment). The site has a Crabapple tree towards the southwest corner of the property. Refer to the Hazardous

Material Assessment Report for 170 Main Street, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations.

1.1.1.3. Slab and Foundation on US Owned Property

1.1.1.3.1. Slab and Foundation left after the disposal of the metal building located at the northern edge of the USA owned property. The slab is 48 feet wide by 140 feet long. It is presumed to be a minimum of 3 feet thick. The foundation is presumed to be about 8 feet.

1.1.2. Option

1.1.2.1. Property #2 91 Vital Drive: Optioned property has not been fully acquired; no work should be performed at this site until the Option is exercised.

1.1.2.1.1. Two-story residential structure that is comprised of 822± SF of living area, as well as a 20’x28’ attached, unfinished, unheated garage that is accessible from the interior of the residence. The wood building includes asphalt shingle roofing and painted clapboard siding. The structure includes poured concrete foundation walls and slab. There is an open porch located in the southeast corner of the house and one in the northwest corner. The first floor contains a living room, eat-in kitchen, bedroom and a pantry area through which is the entrance to the one-car garage. On the second floor there are two bedrooms and a three-fixture bathroom. The full basement is unfinished. It

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020 is used for storage, houses the mechanical systems and oil tank as well as a camp shower. On the north side of the residence there are three fuel oil drums, two 55 gallon drums and one 35-gallon drum. The 55-gallon drums are empty, have multiple punctures, and the bungs are still attached. The 35-gallon drum is missing its cap, looks to be filled with water, and contains no visible punctures. Inside the north basement, there was a 5-gallon drum containing unknown contents. The container is not leaking and does not have any visible punctures. During the site visit, it was observed that there is a fuel oil fill and vent line on the east side of the house next to the garage. There is a 275 gallon AST present in the basement with no visible staining or spills to the concrete floor. Based on the observed age of the house, lead paint, asbestos containing materials and PCB caulking may be present. The residence has been vacant for a few years and has structural issues.

Refer to the Hazardous Material Assessment Report for 91

Vital Drive, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations. No areas of stressed vegetation, dumping, or spills were observed.

There is water damage, potentially from burst pipes since at least 2012, so there may be mold present.

1.1.3 Project Name and Location: Building Demolition,91 Vital Drive (Tax Parcel 5-

163); 93 Vital Drive (Tax Parcel 5-162); 170 Main

Street (Tax Parcel 5-161); 188 Main Street Slab &

Foundation, Madawaska, Maine.

1.1.3.1. Area located on Vital Drive, west of the McDonalds and north of Main

Street.

1.1.3.2. Slab and Foundation located south of Twin Rivers property, and west of

Mill Street.

1.1.4. Project Summary Description: This project includes but is not limited to the following Work:

1.1.4.1. BASE:

1.1.4.1.1. 93 Vital: Demolish and remove the two story building and wrap around porch, with the building having an approximate building area of 1,200 square feet. The demolition of all structures, down to the foundations, and inactive utilities on the property should occur. Demolish concrete foundations, finish product should be a taper that follows the contrast of the land and does

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020 not leave a hole. All foundations should be backfilled if possible, bring in fill in areas that are necessary. Once completion of the demolition of the structure, the site shall be cleared of debris and disposed of properly. All exposed dirt shall be seeded to not allow future erosion of soil. The building was designed to be used as a single family home. Building has conventional framing, gypsum drywall wall, wood studs and wood cabinetry. Electrical and mechanical systems are disconnected. Remove all fluorescent light bulbs and any mercury thermostats, properly dispose of and provide chain of custody documentation. Remove and properly dispose of the existing 275-gallon fuel oil tank in the basement of the building.

Refer to the Hazardous Material Assessment Report for 93 Vital Drive, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations.

1.1.4.1.2. 170 Main: Demolish and remove the two story building and wrap around porch, with the building having an approximate building area of 1,300 square feet. The demolition of all structures, down to the foundations, and inactive utilities on the property should occur. Demolish concrete foundations, finish product should be a taper that follows the contrast of the land and does not leave a hole. All foundations should be backfilled if possible, bring in fill in areas that are necessary. Once completion of the demolition of the structure, the site shall be cleared of debris and disposed of properly. All exposed dirt shall be seeded to not allow future erosion of soil. The building was designed to be used as a single family home. Building has conventional framing, gypsum drywall wall, wood studs and wood cabinetry. Electrical and mechanical systems are disconnected. Remove all fluorescent light bulbs and any mercury thermostats, properly dispose of and provide chain of custody documentation. Remove and properly dispose of the existing 275-gallon fuel oil tank in the basement of the building.

The site has a Crabapple tree towards the southwest corner of the property that must not be removed and remain on the site.

Refer to the Hazardous Material Assessment Report for 170 Main Street, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations.

1.1.4.1.2.1. Location of Crabapple tree that is to not be

disturbed and remain on site.

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.1.4.1.3. Slab and Foundation: Demolish and remove the slab and foundation. The finish product should be a taper that follows the contrast of the land and does not leave a hole. All foundations should be backfilled if possible, bring in fill in areas that are necessary. Once completion of the demolition of the structure, the site shall be cleared of debris and disposed of properly. All exposed dirt shall be seeded to not allow future erosion of soil.

1.1.4.2. OPTION:

1.1.4.2.1. 91 Vital: Demolish and remove the two story building and wrap around porch, with the building having an approximate building area of 900 square feet. The demolition of all structures, down to the foundations, and inactive utilities on the property should occur. Demolish concrete foundations, finish product should be a taper that follows the contrast of the land and does not leave a hole. All foundations should be backfilled if possible, bring in fill in areas that are necessary. Once completion of the demolition of the structure, the site shall be cleared of debris and disposed of properly. All exposed dirt shall be seeded to not allow future erosion of soil. The building was designed to be used as a single family home. Building has conventional framing, gypsum drywall wall, wood studs and wood cabinetry.

Electrical and mechanical systems are disconnected. Remove all fluorescent light bulbs and any mercury thermostats, properly dispose of and provide chain of custody documentation. Remove and properly dispose of the existing 275-gallon fuel oil tank in the basement of the building. On the north side of the residence there are three fuel oil drums, two 55 gallon drums and one 35-gallon drum. The 55-gallon drums are empty, have multiple punctures, and the bungs are still attached. The 35-gallon drum is missing its cap, looks to be filled with water, and contains no visible punctures. Refer to the

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

Hazardous Material Assessment Report for 91 Vital Drive, lead paint, asbestos containing materials (ACMs) and PCB caulking levels will be shown as well as locations.

1.1.4.3. Demolition and removal shall be completed ninety (90) days from the Notice to Proceed (NTP). Contractor shall attend a pre-demolition meeting prior to receiving the NTP and beginning any work on site. This meeting shall be scheduled between the parties after contract award.

1.1.4.4. The contractor is eligible to submit an invoice at the 50% and 100% completion, upon government inspection and acceptance. 50% completion represents the demolition, removal, backfilling, tapering of the Aztec Slab and Foundation on 188 Main Street, Madawaska, Maine.

1.1.4.5. Contractors shall pay their employees at least the wages and fringe benefits by occupation code in the attached Davis-Bacon Act WD # ME20200006. (https://beta.sam.gov/wage-determination/ME20200006/4?index=wd&keywords=&is_active=true&so rt=-modifiedDate&date_filter_index=0&date_rad_selection=date&wdType=d bra&state=ME&page=1)

1.1.4.6. Utilities: Provide a Work schedule for all utility work to be done and to give ample notice, minimum of 14 calendar days, to the residents of 170 Main Street, Madawaska, ME.

1.1.4.6.1. Electrical: Remove overhead utility lines at the pole. Coordinate with local electrical service provider, EMERA Electric.

Customer Service: Toll Free: 1855-EMERA-11 or 207-973- 2000.

1.1.4.6.2. Water: Underground water lines need to be capped and abandoned below finish grade. Coordinate with local utility (Madawaska Water District). Phone: (207) 728-3859, email:

madwaterdistrict@myfairpoint.net.

1.1.4.6.3. Sewer: Underground sewer lines need to be capped and abandoned below finish grade. Coordinate with local utility (Madawaska Public Works Department). Phone: 207-728-3607.

kdube@madawaska.com (Kevin Dube, PW Director).

PART 2 - PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

Work Restrictions

Part 1 - General

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.1. Contractor Use of Premises

1.1.1. The Government will conduct a pre-construction survey with the

Contractor to review and document the existing conditions surrounding the project premises prior to the beginning of any demolition activity.

1.1.2. During the demolition period, the Contractor shall have full use of the designated premises for demolition operations. The Contractor shall limit operations to the project site. Do not disturb portions of the site beyond the areas where demolition takes place. Schedule demolition material to be removed offsite during each workday, contractor must ensure that they do not leave an attractive-nuisance at the end of the workday

1.1.3. Coordinate with the GSA Building Manager for site access. Xavier

Ramirez, 207-922-3010, cell 207-325-1539.

1.2. Hours

1.2.1. Contractor’s General Working Hours: The Contractor working hours shall be generally 7:00 am through 5:00 pm, Monday through Friday.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

Safety and Health:

Part 1 - General

1.1 Summary

1.1.1. References: In addition to publications referenced in the Construction Contract

Clauses, the following Code of Federal Regulations (CFR), publications apply to conduct of the work. State and local safety and health regulations that apply are not cited herein. Current editions at the date of the agreement apply. The more stringent requirements apply.

1.1.1.1. 29 CFR, Part 1910: Occupational Safety and Health Administration

(OSHA) General Industry and Health Standards.

1.1.1.2. 29 CFR,Part 1926 " Safety and Health Regulations for Construction"

1.1.1.3. 40 CFR 260, "Hazardous Waste Management System"

1.1.1.4. 40 CFR 261, "Identification and Listing of Hazardous Waste."

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.1.1.5. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use

Prohibitions. [GSA Project Team: Check if any work involves sealant removal as PCBs may be present.]

1.1.1.6. National Fire Protection Association (NFPA) 70E Electrical Safety

Requirements for Workplace Safety

1.1.1.7. U.S. Army Corps of Engineers (USCOE) Safety and Health

Requirements Manual, EM 385-1-1, current edition.

1.1.1.8. Federal Standard: Fed. Std. 313A, Material Safety Data Sheets, Preparation and the Submission of.

1.1.2. Acquisition of Publications:

1.1.2.1. 29 CFR, Part 1910: Occupational Safety and Health Administration

(OSHA) General Industry and Health Standards.

1.1.2.2. 29 CFR,Part 1926 " Safety and Health Regulations for Construction"

1.2 Safety Meeting

1.2.1. Prior to commencing demolition, representatives of the Contractor, including the principal on-site project representative and one or more safety representatives, shall meet with designated representatives of the government for the purpose of reviewing the Contract's safety and health requirements. The safety and health program shall be reviewed, and specific implementation of safety and health provisions pertinent to the Work shall be discussed.

1.3 Safety and Health Program

1.3.1. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work, and shall hold the Government harmless for any action on the Contractor's part, or that of the Contractor's employees or subcontractors, that results in illness, injury or death.

1.3.2. Site Safety and Health Officer: A trained and experienced individual shall be delegated in writing as the Site Safety and Health Officer (SSHO).

1.3.3. First Aid and Emergency Response Requirements: The Contractor shall provide for emergency first aid equipment. Additionally, a 20-pound ABC-rated fire extinguisher shall be maintained on-site as well as absorbent material of

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020 sufficient quantity to collect any spill which might occur during this project. A listing of emergency phone numbers and points of contact for fire, hospital, police, ambulance, and other necessary contacts shall be posted at the

Contractor’s site.

1.3.4. Contractor shall provide for site visitors Personal Protective Equipment (PPE) per

OSHA for use during their visits. Provide a minimum of 10 sets with replacements for items not suitable for re-use.

1.3.4.1. In accordance with the attached Memorandum from the GSA

Administrator, and consistent with the CDC’s recommendations, contractors are required to wear cloth face coverings when gaining access to and working within GSA-controlled facilities. Exceptions may apply for reasons such as impracticality, health or other bases, and shall be approved by the Contracting Officer. Cloth face coverings will not be provided to contractors by the Government.

1.3.5. The following Code of Federal Regulations (CFR), publications apply to conduct of the work. State and local safety and health regulations that apply are not cited herein. Current editions at the date of the agreement apply. The more stringent requirements apply.

1.3.5.1. 29 CFR, Part 1910: Occupational Safety and Health

Administration (OSHA) General Industry and Health Standards.

1.3.5.2. 29 CFR, Part 1926 " Safety and Health Regulations for

Construction"

1.3.5.3. 40 CFR 260, "Hazardous Waste Management System"

1.3.5.4. 40 CFR 261, "Identification and Listing of Hazardous Waste."

1.3.5.5. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use

Prohibitions. [GSA Project Team: Check if any work involves sealant removal as PCBs may be present.

1.3.5.6. National Fire Protection Association (NFPA) 70E Electrical Safety

Requirements for Workplace Safety

1.3.5.7. U.S. Army Corps of Engineers (USCOE) Safety and Health

Requirements Manual, EM 385-1-1, current edition.

1.3.5.8. Federal Standard: Fed. Std. 313A, Material Safety Data Sheets, New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

Preparation and the Submission of.

1.4 Submittals

1.4.1. The Contractor shall submit for approval to Project Manager copies of the project safety and health programs, as applicable to the work scope or required as a result of the safety meeting prior to commencing demolition.

1.4.1.1. Occupational Noise Exposure.

1.4.1.2. Fall Protection.

1.4.1.3. Personal Protective Equipment.

1.4.1.4. Control of Hazardous Energy.

1.4.1.5. Electrical Safety Related Work Practices.

1.4.1.6. Lead.

1.4.1.7. Asbestos.

1.4.1.8. Polychlorinated Biphenyls (PCBs)

1.4.1.9. Respirator Protection.

1.4.1.10. Confined spaces.

1.4.2. Contractor's Safety Plan: In addition to specific safety and health programs applicable to the project, Contractor shall submit the firm's general safety plan at the pre-construction conference listing emergency procedures and contact persons with home addresses and telephone numbers. The Safety Plan shall be sent to the Project Manager prior to commencing demolition.

1.4.3. Contractor’s Work Plan & Demolition Schedule: Contractor shall submit a detailed schedule of work to the Contracting Officer and Project Manager for review and acceptance within two (2) days of contract award, and prior to the project kickoff meeting.

1.4.4. Contractor’s Employee and Subcontractor List: Contractor shall submit a list of employees and subcontractors working on site during the contract, identifying the main points of contact within two (2) days of contract award, and prior to the project kickoff meeting.

1.4.5. Contractor’s Insurance: Contractor shall submit to the Contracting Officer proof of

General Liability and Worker’s Compensation…

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.4.6. Permits: If hazardous materials are disposed of off-site, submit to the Project

Manager the copies of shipping manifests and permits from applicable federal, state or local authorities and disposal facilities, and submit certificates that the material has been disposed of in accordance with regulations. Contractor shall be responsible for obtaining the Environmental Protection Agency’s (EPA)

Hazardous Waste Generator ID Number for disposal of contractor generated hazardous waste; submit to GSA PM or COR within 7 days of receiving

Generator ID Number from the EPA.

1.4.7. Accident Prevention Plan (APP): Submit an electronic copy of the APP to the

Project Manager. Plan shall include all activities for which the contractor is responsible but not be limited to:

1.4.7.1. Emergency Action Plan

1.4.7.2. Emergency Equipment

1.4.7.3. Incident/Accident Investigation, Reporting and Record keeping

1.4.7.4. Safety Inspection Procedures

1.4.7.5. Means of Egress

1.4.7.6. Hazardous Materials

1.4.7.7. Confined Space

1.4.7.8. Demolition

1.4.7.9. Electrical Safety

1.4.7.10. Excavations

1.4.7.11. Fall Protection

1.4.7.12. Fire Prevention

1.4.7.13. Hazard Communication and Right to know

1.4.7.14. Ladders and Stairways

1.4.7.15. Heavy Equipment

1.4.7.16. Machine and Equipment Guarding

1.4.7.17. Personal Protective Equipment

1.4.7.18. Power Tools

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.4.7.19. Site Security

1.4.7.20. Weather Conditions

1.4.7.21. Employee Training

1.4.8. Accident Reporting: Submit an electronic copy of each accident report to the

Project Manager, which the Contractor or Subcontractors submits to their insurance carriers, within seven (7) calendar days after the date of the accident.

1.4.9. Emergency call down tree: Include an emergency call down tree containing contact info for all team members as part of the Contractor Safety Plan.

1.4.10. If the contractor brings hazardous materials onto the property, the contractor shall submit a hazardous material management plan which shall, at a minimum, identify and provide the Material Safety Data Sheet (MSDS) for each material, describe proper handling and storage procedures for each material, and describe the contractor's plan for responding to a spill or release of the material(s).

Part 2 - Products

2.1 Personal Protective Equipment

2.1.1. Special facilities, devices, equipment and similar items used by the Contractor in execution of the Work shall comply with the applicable regulations, including PPE related to Covid-19 as outlined in Section 1.3 Safety and Health Program line

1.3.4.1.

Part 3 - Execution

3.1 Hazardous Materials and Conditions

3.1.1. The Contractor shall advise GSA of any hazardous material and/or hazardous condition encountered during execution of the work. GSA shall determine if the

Contractor must perform additional tests and if the work for the particular material or condition shall cease. Work shall recommence at the direction of GSA. The

SSHO shall take measures to protect personnel until GSA has rendered its decision

3.2 Emergency Suspension of Work

3.2.1. When the Contractor is notified by GSA of non-compliance with the safety or health provisions of the Contract, the Contractor shall immediately cease work in the subject area unless otherwise instructed, and correct the unsafe or unhealthy condition.

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

3.2.1.1. If the Contractor fails to comply promptly, all or part of the Work will be stopped by notice from GSA.

3.2.1.2. When GSA determines that satisfactory corrective action has been taken by the Contractor, work shall resume.

3.2.1.3. The Contractor shall not be allowed any extension of time or compensation for damages in connection with a work stoppage for an unsafe or unhealthy condition.

3.3 Protection of Personnel

3.3.1. The Contract shall take necessary precautions to prevent injury to the public, occupants, and work forces. The public and occupants includes all persons not employed by the Contractor or a subcontractor

3.3.2. The work area shall be fenced, barricaded or otherwise blocked off from the public or occupants to prevent unauthorized entry into the work area. Control by authorized personnel shall be done where passage through is necessary for the work.

3.3.2.1. Provide traffic barricades and traffic control signage where construction activities occur in vehicular areas.

3.3.2.2. Corridors, aisles, stairways, doors and exitways shall not be obstructed or used in a manner to encroach upon routes of ingress or egress utilized by the public or occupants, or to present an unsafe or unhealthy condition to the public or occupants.

3.3.2.3. Store, position and use equipment, tools, materials, in a manner that does not present a hazard to the public or occupants

3.3.2.4. Store and transport refuse and debris in a manner to prevent unsafe and unhealthy conditions for the public and occupants. Cover refuse containers, and remove refuse on a frequent regular basis acceptable to

GSA. Use tarpaulins or other means to prevent loose transported materials from dropping from trucks.

3.4 Environmental Protection

3.4.1. Dispose of solid, liquid and gaseous contaminants in accordance with applicable federal, state, and local codes, laws, ordinances and regulations.

3.4.2. Comply with applicable federal, state and local noise control laws, ordinances and regulations, including but not limited to 29 CFR 1910.95 and 29 CFR

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1926.52.

3.4.3. All on-site inquiries about the GSA or MaineDOT project shall be directed to the

COR and Project Manager.

Construction Waste Management & Disposal:

Part 1 - General

1.1 Summary

1.1.1. Section includes administrative and procedural requirements for the following:

1.1.1.1. Salvaging nonhazardous demolition waste.

1.1.1.2. Recycling nonhazardous demolition waste.

1.1.1.3. Disposing of nonhazardous demolition waste.

1.2 Definitions

1.2.1. Disposal: Remove site demolition waste and deposit in a landfill or incinerator acceptable to authorities having jurisdiction.

1.3 Performance Requirements

1.3.1. General: Practice efficient waste management in the course of the Work.

1.4 Action Submittals

1.4.1. Waste Management Plan: Submit plan within (14) days of date established for the Notice to Proceed, prepare and submit a Solid Waste Management Plan including, but not limited to, the following:

1.4.1.1. List of the recycling facilities, reuse facilities, municipal solid waste landfills and other disposal area(s) to be used. Include:

1.4.1.1.1. Name, location, and phone number.

1.4.1.1.2. Copy of permit or license for each facility.

1.4.1.2. Identify materials that cannot be recycled or reused. Provide chain of custody documentation. Submit a plan as required by Owner.

1.4.2. Approval of Contractor’s Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.5 Informational Submittals

1.5.1. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them.

Include manifests, weight tickets, receipts, and invoices.

1.5.2. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

1.5.3. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.

Part 2 - Execution

2.1 Plan Implementation

2.1.1. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement a waste management plan during the entire duration of the Contract.

2.2 Disposal of Waste

2.2.1. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

2.2.2. Burning: Do not burn waste materials.

Selective Demolition:

Part 1 - General

1.1 Summary

1.1.1. This Section includes the following:

1.1.1.1. Demolition and removal of wood frame building.

1.1.1.2. Demolition of concrete slab and foundation walls to 6 inches below grade

1.1.1.3. Compact, backfill, and level with clean fill or gravel the area disturbed by removal of concrete slab

1.1.1.4. Asphalt areas are to remain.

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

1.2 Submittals

1.2.1. Proposed dust-control measures.

1.2.2. Proposed noise-control measures.

1.2.3. Schedule of Selective Demolition Activities: Indicate the following:

1.2.3.1. Sequence of selective demolition and removal work, with starting and ending dates for each activity.

1.2.3.1.1. Demolition and removal shall be completed ninety (90) days from the Notice to Proceed (NTP).

1.2.3.1.2. Contractor shall attend a pre-demolition meeting prior to receiving the NTP and beginning any work on site.

1.2.3.1.3. This meeting shall be scheduled between the parties after contract award.

1.2.3.2. Coordination for shutoff, capping, and continuation of utility services.

1.2.4. Landfill Records: Indicate receipt and acceptance of all wastes, hazardous and otherwise. In accordance with EPA regulations hazardous materials must be disposed of at a landfill facility licensed to accept hazardous wastes.

1.2.5. Qualification Data: For certified refrigerant recovery technician."

1.2.6. Statement of Refrigerant Recovery: Signed by the certified refrigerant technician responsible for recovering the refrigerant; stating that all refrigerant and used refrigerant oil that was present was recovered and that the recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant and used refrigerant oil was recovered. Include the name of the person or facility that received the recovered refrigerant for reuse. If disposal occurred per RCRA regulations, provide copies of disposal/incineration documentation.

Part 2 - Execution

2.1 Examination

2.1.1. Verify that utilities have been disconnected and capped.

2.1.2. Survey existing conditions and correlate with requirements indicated to determine extent of demolition required

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

2.2 Preparation

2.2.1. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

2.3 Disposal of Demolished Materials

2.3.1. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

2.3.2. Do not allow waste materials that are to be disposed of to accumulate on-site.

Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

Attachments:

● Madawaska _US LPOE_MADAWASKA_Final BCD_C102.PDF

● Madawaska ESA Phase I (5-162, 93 Vital Dr)

● Madawaska ESA Phase I (5-163, 91 Vital Dr)

● Madawaska ESA Phase I (5-161, 170 Main St)

● Madawaska ESA Phase I (4-86, 4-87, 5-164, USA Owned Lands)

● ALTA/NSPS Land Title Survey of Land 19-177 Clavette

● ALTA/NSPS Land Title Survey of Land 19-177 Baille

● ALTA/NSPS Land Title Survey of Land 19-177 Combined (91 Vital, 93 Vital, 170 Main, 180

Main)

● 91 Vital Drive 2019 Photos

● 93 Vital Drive 2019 Photos

● 170 Main Street Photos

● 188 Main Street Slab & Foundation Photos

● Hazardous Materials Assessment Report - 91 Vital Drive

● Hazardous Materials Assessment Report - 93 Vital Drive

● Hazardous Materials Assessment Report - 170 Main Street

Requirements:

• GSA PBS P100 2018 Facilities Standards for the Public Buildings Service:

https://www.gsa.gov/cdnstatic/2018%20P100%20Final%205-7-19_0.pdf

• GSA PBS P120 P-120, Public Buildings Service Cost and Schedule Management Policy

Requirements: https://www.gsa.gov/cdnstatic/PBS_1000.6_P-

120__Public_Buildings_Service_Cost_and_Schedule_Management_Policy_%28Post._Ver._- _8-4-

2016%29_%23CC033801_Rev.__5-31-2017.pdf

New Madawaska Land Port of Entry in coordination with The Maine Department of Project Number: NME0012

Transportation’s Madawaska-Edmundston International Bridge Replacement Project Building Number: Demolition

Services in Madawaska, Maine

Statement of Work, December 04, 2020

Resources:

• GSA Project site: www.gsa.gov/madawaskalpoe

• MaineDOT Project Site: https://www.maine.gov/mdot/projects/madawaska/internationalbrg/ https://www.maine.gov/mdot/grants/infra/

● Madawaska StructionSite Virtual Site Walk: https://app.structionsite.com/vp/dae2130c-94c2-

4556-95c9-d6b4af0542f4

● Madawaska+Virtual+Site+Walk+Instrustions+README.pdf