T2052 Optional Pre-Quote Conference 02.28.24~1.pptx
PPTX presentation 3 MB Posted
- Solicitation number
- 23DPP00909
- Issued by
- Mercer County, Trenton City, New Jersey
About this file
This document is an Optional Pre-Quote Conference presentation for Bid Solicitation #23DPP00909, a contract opportunity issued by the State of New Jersey for Second Referral Debt Collection services related to DORES-MVC Surcharges. The purpose of the conference is to address procedural questions regarding the bid submission requirements. Key dates include Q&A due by 2PM on March 20, 2024 and quotes due by 2PM on April 17, 2024. The contract term is a 5-year base term with two 1-year extension options.
The bid solicitation outlines the required quote submission documents, including forms, technical approach, management overview, resumes, firm experience, financial capability, and a price sheet. Bidders must complete all mandatory requirements, and failure to submit requested information could impact the technical score. The price sheet must be completed in its entirety without any changes to the format or additional language added.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Optional Pre-Quote Conference T2052 – Second Referral Debt Collection DORES-MVC Surcharges Bid Solicitation #23DPP00909 Date:
Q&a due by 2PM March 20, 2024 Quotes due by 2pm April 17, 2024
WELCOME & INTRODUCTIONS
Please identify yourself and the firm you represent prior to asking a question.
Please make sure you are registered in NJSTART, and that your contact information remains current.
NJSTART Vendor support email: njstart@treas.nj.gov https://www.state.nj.us/treasury/purchase/vendor.shtml
PURPOSE & GENERAL INFORMATION
The purpose of this conference is to address procedural questions only, regarding the Bid Solicitation and Quote submission requirements.
No questions relating to the Scope of Work or the services or products required in the Bid Solicitation will be addressed. Vendors should utilize the Q&A Tab of the Bid Solicitation in NJSTART to submit those questions electronically.
The Bid Solicitation will be reviewed section by section with procedural questions being entertained on that basis.
BID SOLICITATION AT A GLANCE
Cover Page:
Submission dates Set-aside requirements Bid Solicitation Title Information
Electronic Q&A Due: By 2:00pm March 20, 2024 Quotes Due: By 2:00pm April 17, 2024
Section 1: Introduction and Summary Purpose and Intent (Section 1.1) Background (Section 1.2) Order of Precedence of Contractual Terms (Section 1.4)
Section 2: Pre-Quote Submission Information Q&A (Section 2.1) Exceptions to the New Jersey Standard Terms and Conditions (Section 2.2) Bid Amendments (Section 2.3)
Please review each Section carefully:
Please review this section carefully:
Section 3: Quote submission requirements - including, but not limited to:
Forms (Section 3.13) Technical approach and experience (Section 3.14) Management Overview (Section 3.15) Resumes (Section 3.22) Firm experience (Section 3.24) Confidentiality/Commitment to Defend (Section 3.13.7) Financial capability (Section 3.25) Price sheet (Section 3.26)
Bidders shall submit (Mandatory)
Bidders should submit (Strongly Recommended)
Ownership Disclosure Form, Section 3.13.2 If your firm intends to subcontract, the Subcontractor Utilization Plan, Section 3.13.8 Affirmative Action Compliance, Section 3.13.10 (Due Before Contract Award) Business Registration, Section 3.13.13 (Due Before Contract Award)
Offer and Acceptance Page, Section 3.13.1 Disclosure of Investment Activities in Iran Section 3.13.3 Disclosure of Investigations and Other Actions Involving the Bidder Form, Section 3.13.4.
MacBride Principles, Section 3.13.5 Source Disclosure 3.13.6 Confidentiality/Commitment to Defend, Section 3.13.7 NJ Due Diligence Third-Party Information Security Questionnaire, Section 3.13.12 Certification of Non-Involvement in Prohibited Activities in Russia or Belarus, Section 3.13.14
Section 3.13 - Forms & Certifications
Technical Quote, Section 3.14 Management Overview, Section 3.15 Draft Transition and Mobilization Plan, Section 3.16.3 State-Supplied Price Sheet, Section 3.26
Please review Section 3 in its entirety for a full list of submission specifications.
Section 3 Quote Submission Requirements Bidders shall submit:
Draft Project Management Plan, Section 3.16.1 Draft Technology and Solution Roadmap, Section 3.16.2 Contract Schedule, Section 3.17
Bidders should submit:
Please review each section carefully:
Section 4: Scope of Work Section 5: General Contract Terms Contractual language including term details (Section 5.1 and 5.2) 5-Year Base Term Two 1-Year Extension Term Options Staff substitutions (Section 5.5) Ownership of materials (Section 5.4)
Please review all sections carefully:
Section 6: Data Security Requirements Section 7: Modifications to the NJ Standard Terms and Conditions (SSTCs) and supplemental indemnification Section 8: Evaluation criteria, clarifications, best and final offer Section 9: Glossary (including Contract Specific Definitions)
Reminders Review Bid Solicitation in its entirety and submit any questions prior to the deadline including exceptions. Updated documents will be posted in NJSTART and should be reviewed as posted.
Submit Quotes on time addressing all mandatory requirements including forms, or Quote may be deemed non-responsive. “Shall” denotes a mandatory requirement; however, not submitting requested information (“should”) could impact technical score Price Sheet must be completed in its entirety with no lines added or removed, or additional language or fees referenced
PRICE SHEET PITFALLS
Be sure to:
Complete all required price lines on the Price Sheet, or Quote may be deemed non-responsive. Indicate “no charge” if the cost is $0. Do not leave any price lines blank.
Do not make formatting changes to the Price Sheet. If the price line requires a dollar amount, don’t change it to a percentage, or vice versa. If the price line includes 2 decimal places, don’t change the settings to allow 4 decimals.
Confirm that you have completed all tabs on the Price Sheet.
Do not add additional language, assumptions, or fees on the Price Sheet. Do not add or remove any price lines.
Confirm you have completed the proper version of the Price Sheet; it may have been revised via Bid Amendment.
PRICE SHEET
Please submit all pricing according to the instructions in Bid Solicitation Section 3.26.
Bidders shall include pricing without assumptions, exceptions, or caveats or the Quote may be deemed non-responsive.
OTHER HELPFUL TIPS
Do NOT include language such as this:
Vendor accepts all terms and conditions of this Bid Solicitation with the following additional language: Section X - Agree, as it applies to changes that impact administrative fees as outlined in this provision, provided that Vendor reserves the right to modify Contracted Terms based on changes by the State.
Vendor reserves the right to charge additional fees for services that require extensive time and effort.
This Quote is a nonbinding expression of interest only and is not intended to create a binding commitment on either party unless and until a definitive agreement has been executed between the parties.
This Quote may include statements regarding plans for future products and services, or future versions of existing products and services. Any such statements are provided solely for your general information and are not part of this Quote unless specifically stated in writing in this Quote.
THANK YOU FOR ATTENDING
Q&A due by 2pm March 20, 2024
Quotes due by 2pm April 17, 2024 image1.jpeg image2.png image3.png image4.tmp image5.PNG image6.png image7.png