This is a Construction Plans and Specifications document issued by the Delaware Department of Transportation for an open-end right-of-way fence replacement contract covering the North and Canal Districts for fiscal years 2026-2028. The contract encompasses repair and replacement of damaged right-of-way fencing on state-maintained roads including I-95, I-295, I-495, Route 1, US 301, and related ramps throughout New Castle County. Work includes maintenance of traffic, removal of damaged fence and components, and repair or replacement of fence and components as directed by the Department Engineer through individual work orders. The contract includes quantities for various fence types and components, including 175 linear feet each of chain link fence, right-of-way fence, and wood vertical slat fence; 325 linear feet of chain link fence repair; 350 linear feet of right-of-way fence repair; 150 linear feet of wood vertical slat fence repair; 150 linear feet of wildlife exclusion fence; and miscellaneous gates and relocation work. The contract was approved for advertisement on August 18, 2026, with a duration of two years (730 calendar days) from the notice to proceed, plus an option to extend for one additional one-year period.
Payment will be made monthly for completed work, with the Contractor required to commence work no later than ten days after work order issuance. The Department reserves the right to adjust contract item quantities by any amount without justification for unit price adjustments, and changes do not require payment for loss of anticipated profits. An updated performance bond must be submitted at the beginning of each fiscal year, with associated costs incidental to initial expense. The Contractor is responsible for all utility coordination through Miss Utility of Delaware, environmental compliance if wetlands are impacted, traffic control in accordance with Delaware Manual of Uniform Traffic Control Devices standards, disposal of construction waste, and restoration of damaged grass and soil areas. The contract specifies tiered pricing for fence heights exceeding six feet, with multipliers of 1.25x for heights up to eight feet and 1.5x for heights up to ten feet. Work authorization is contingent upon state funding availability, and the Department reserves the right to stop operations deemed non-compliant with specifications or unsafe.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| T202680203 QA 10-14-26.pdf | ||
| T202680203 Proposal.pdf | ||
| public.ejs?command=PublicBusinessPlanholderList&projid=T202680203 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE STATE OF DELAWARE
DEPARTMENT OF TRANSPORTATION
MAINTENANCE AND OPERATIONS
CONSTRUCTION PLANS AND SPECIFICATIONS FOR
Open End, Right of Way Fence Replacement, North & Canal, FY26-28
CONTRACT NUMBER – T202680203 PRIMAVERA ID – 26-00058
FEDERAL AID NUMBER – N/A COUNTY: NEW CASTLE
CANAL DISTRICT MAINTENANCE ENGINEER DATE
APPROVED FOR ADVERTISEMENT
DIRECTOR OF MAINTENANCE AND OPERATIONS DATE
8/5/2026
8/18/26
DELAWARE DEPARTMENT OF TRANSPORTATION
CONTRACT No: T202680203 Open End, Right of Way Fence Replacement, North & Canal, FY26-28
CONTRACT DESCRIPTION
This purpose of this contract is to repair or replace damaged Right-of-Way Fence as required for all State maintained roads in North District and Canal District (depicted in the below maps), including I-95, I-295, I-495, RT 1, US 301, and related ramps. The work shall include, but not be limited to, Maintenance of Traffic, removal of damaged fence and components, and repair/replacement of damaged fence and components, as required or directed by the Engineer on individual work orders.
The specific work sites are not listed herein, but will be assigned as available by the District Maintenance office.
The duration of this open-end contract shall be for a period of two years (730 Calendar Days) from the date of initial “Notice to Proceed” letter, with the option to extend the Contract for one additional one-year period.
PROJECT GENERAL NOTES
1. This project is to be constructed in accordance with the Delaware Department of Transportation
Standard Specifications for Road and Bridge Construction dated January 2026 and the Delaware Department of Transportation Standard Construction Details dated 2026, including all revisions up to the date of advertisement.
2. An updated Performance Bond shall be submitted at the beginning of each fiscal year. Failure on the part of the Contractor to submit the Performance Bond shall result in the Contract being cancelled. It is the Contractor’s responsibility to assure that the Bond is current for the life of the Contract. Costs to be incidental to item 763000 (Initial Expense).
3. Whenever the word “Contractor” is used in this contract, it shall refer to the person or persons, company or corporation furnishing the services required.
4. Whenever the word “Department” or "Engineer" is used, it shall refer to the person or persons, representing the Delaware Department of Transportation (DelDOT).
5. Tasking of work is contingent upon authorization of State funding.
6. It is anticipated that all work will occur within DelDOT’s existing right of way or easement areas.
Should the need occur to trespass onto private property; it will be the responsibility of the DelDOT Project Manager to secure such trespass needs.
7. It is anticipated that all work will occur within DelDOT’s right of way. Should the need occur to trespass onto railroad property, including the highway-rail crossing; it will be the responsibility of the Project Manager to contact the DelDOT Railroad Coordinator and obtain written authorization before entering.
8. No utility relocation involvement is anticipated. Should any conflicts be encountered during construction requiring adjustment and/or relocation of the agencies’ existing facilities, the necessary relocation work shall be accomplished by the respective agencies’ forces, as directed by the District Engineer. Any adjustments and/or relocations of municipally owned facilities shall be done by the State’s contractor in accordance with the respective agencies’ standard specifications as directed by the District Engineer.
9. Prosecution and Progress of Work:
The Contractor shall commence on work indicated on the work order no later than the tenth (10) day after issuance unless required materials are not available. Non-availability of materials shall be verified by at least three (3) different sources. Verification shall be formal and supplied by the Contractor in writing.
Issuance of each work order constitutes the notice to proceed with the work described on the work order.
If there is a verified non-availability of materials, time charges shall commence on the first (1st) working day following the delivery date of materials.
Failure to start assigned work orders in the allowed time constitutes “Failure to Pursue the Work” and subjects the Contractor to Liquidated damages as outlined in Section 108.8 of the Standard Specifications. If work on a specific work order is not completed within the allotted time, Liquidated Damages will be assessed in accordance with Subsection 108.9 and based on the total value of that work order.
Each work order shall be considered a separate unit of work. Upon the substantial completion of the work at an individual location, the Engineer will stop time at that location and perform a semi-final inspection for the work order location in accordance with Subsection 105.16. The Engineer reserves the right to require the Contractor to add Work or make repairs to completed locations until such a location has been accepted by the Department. The Contractor must repair all defects in the work caused by poor workmanship or materials at his/her own expense until the Department accepts the Contract after the Final Inspection.
A Final Inspection will be completed on an annual basis for work orders completed in a calendar year. Upon satisfactory completion of the Final Punchlist, the Department will accept the location and release the Contractor from responsibility for the Work at that location. If a work order is sufficiently large and complex as determined by the Engineer, a Final Inspection may be held upon the individual completion of that work order.
10. Payment will be monthly for the completed work as outlined in Section 109.7.
11. The Contractor shall not trespass on private property unless the District has acquired a "Temporary Trespass Agreement" from the property owner. If the work is within a permanent easement, the work shall not begin until the adjacent property owners have been notified. Prior to starting work on private property, the Contractor shall notify affected property owners in writing of the proposed work dates, scope of work, proposed work hours, and DelDOT contact phone number.
Compensation for notification shall be incidental to Item 763000 (Initial Expense/De- Mobilization).
12. The Contractor shall provide residents 24-hour prior written notice for all phases of Contract work.
This notice shall be given to all residents whose property is adjacent to the street on which work is to be performed. Failure to give notice will result in a suspension of work.
13. No environmental permits are required for this work provided no jurisdictional wetlands or waters are impacted. If there is any question as to whether or not a water or wetland is jurisdictional, contact the DelDOT Environmental Section at (302) 760-2264.
14. Work within waters/wetlands shall not begin on locations requiring environmental permits until all applicable permits have been obtained by DelDOT. Confirm permit status with DelDOT Engineer prior to commencement of applicable work.
15. Underground utilities may be present at all locations. Therefore, all standard practices and procedures regarding utilities shall be followed. The Contractor shall contact Miss Utility of Delaware prior to starting each work order. The Contractor is responsible for the support and protection of all utilities when excavating. The Contractor is responsible for ensuring proper clearances, including safety clearances, from overhead utilities for construction equipment. The Contractor is advised to check the site for access purposes for his equipment and make arrangements directly with utility companies for field adjustments for adequate clearances if necessary.
16. Section 101.3 “Working Day” definition is amended. There will not be a winter shutdown from December 16th to March 15th. The Department reserves the right to issue work and charge time between these dates.
17. Delete Section 104.2.B, Significant Changes in the Character of Work of the DelDOT Standard
Specifications, and replace with the following:
The Department reserves the right to, at any time prior to completion of the contract, issue plan revisions, make adjustments in Contract item quantities, or make such alterations considered necessary to satisfactorily complete the Contract.
The Department reserves the right to increase or decrease the quantities of Pay Items specified in the Contract. Such additions or deletions shall not be cause for an increase or decrease in Contract unit bid prices. The "Change" threshold of plus or minus 25%, as described in Subsection 104.2.B of the DelDOT Standard Specifications dated June 2021 shall not apply to this Contract. Quantity increases or decreases of plus or minus 25% or greater shall not be justification for adjustments to unit prices.
The plan revisions and quantity adjustments described above do not invalidate the Contract or release the Contract surety. Payment for these changes shall exclude any amount for loss of anticipated profits alleged to result from the change.
When payment for the Contract work cannot be agreed upon by the Contractor and the Department prior to starting such work ordered, the Department may direct the Contractor to perform the work under Force Account provisions of Section 109.4. The Contractor will proceed immediately with the work so ordered and such direction shall neither invalidate the Contract, nor release the surety.
18. Work located within Municipalities requires a Town Agreement. Contact DelDOT Team Support section at (302) 760-2251 prior to commencing work within Municipalities to process a town agreement.
19. The Contractor shall guarantee all work to be free from defects for a period of one year from time of owner acceptance. Any defects occurring during this period shall be corrected by the Contractor at no additional cost to the Department.
CONSTRUCTION NOTES
20. The Contractor shall protect all driveways from damage due to Contractor’s equipment and shall be responsible for all such damage done by Contractor’s equipment.
21. The contractor shall be equipped with a tripod/chain hoist or other similar equipment capable of removing damaged steel fence posts and footings at inaccessible places that will not permit the use of the post truck or would necessitate a lane closure if an auger truck were used. If approved by the Engineer, the Contractor may use an approved bagged concrete mix for concrete footings when they are in inaccessible locations or in too small a quantity for a certified plant mix delivery.
22. Excavated material not needed on the project shall be removed from the site at the Contractor's expense.
23. Clearing and grubbing of trees, shrubs and other vegetation less than 6 inches in diameter shall be incidental to Item 763000 (Initial Expense/De-Mobilization). Grubbing activities performed in wetland areas require environmental permit approvals.
24. Grass and soil areas within State right-of-way that have been damaged by equipment during this contract, shall be restored with topsoil, seed and mulch at Contractor's own expense, and in accordance with the requirements for Special Provisions 908004 (Topsoil, 6″Depth) and 908014 (Permanent Grass Seeding, Dry Ground).
25. Proper disposal of construction related wastes shall be the sole responsibility of the Contractor and shall be performed in accordance with all applicable State regulations.
26. The new fence type and positioning of new fence shall be identical to the existing fence to be replaced, except when directed otherwise by the Engineer. The Engineer shall determine for the
Contractor if any fence components shall be reused on each work site. Any components not to be reused, as determined by the Engineer, become the property of the Contractor. Removal and legal disposal of the unused components are the Contractor’s responsibility and all costs associated with this work are incidental to the applicable repair item.
27. All right of way fence gates and chain link fence gates are swing gates.
28. New construction of wood vertical slat fence (Item 727004) with a height less than or equal to 6 feet shall be paid at the unit price bid. Wood vertical slat fence with a height greater than 6 feet up to 8 feet shall be paid at 1.25 times (1.25 x) the unit price bid. Wood vertical slat fence with a height greater than 8 feet up to 10 feet shall be paid at 1.5 times (1.5 x) the unit price bid. New construction of wood vertical slat fence greater than 10 feet shall be negotiated or performed by Force Account procedures.
29. New construction of chain link fence (Item 727010) with a height less than or equal to 6 feet shall be paid at the unit price bid. Chain link fence with a height greater than 6 feet up to 8 feet shall be paid at 1.25 times (1.25 x) the unit price bid. Chain link fence with a height greater than 8 feet up to 10 feet shall be paid at 1.5 times (1.5 x) the unit price bid. New construction of chain link fence greater than 10 feet shall be negotiated or performed by Force Account procedures.
30. Fence Repair (Item 727032) shall refer to chain link fence with a height less than or equal to 6 feet and be paid at the unit bid price. Chain link fence with a height greater than 6 feet up to 8 feet shall be paid at 1.25 times (1.25 x) the unit price bid. Chain link fence with a height greater than 8 feet up to 10 feet shall be paid at 1.5 times (1.5 x) the unit price bid. Repair of chain link fence greater than 10 feet shall be negotiated or performed by Force Account procedures.
31. New construction of a chain link fence gate / right of way fence gate (Item 727011 / 727010) with a height less than or equal to 6 feet shall and a width less than or equal to 6 feet shall be paid at the unit price bid. New construction of a chain link fence gate / right of way fence gate with a height greater than 6 feet up to 10 feet or a width greater than 6 feet shall be paid at 1.5 times (1.5 x) the unit price bid. New construction of chain link fence gate / right of way fence gate with a height greater than 10 feet shall be negotiated or performed by Force Account procedures.
MAINTENANCE OF TRAFFIC
32. All work shall be performed in a manner that will reasonably provide the least practicable obstruction to all road users, including vehicular, pedestrian, and bicycle traffic, and shall conform to the requirements of the Delaware Manual of Uniform Traffic Control Devices (MUTCD), Part 6, including revisions up to the date of advertisement for bids.
33. All shoulder or travel lane closures shall be performed at times directed by the Engineer with direction from the Canal or North District Safety Officer. Any deviation from the time restriction must be approved by the Canal or North District Engineer and Canal or North District Safety Officer prior to commencement of work.
34. No lane closures will be permitted on holidays or holiday weekends, unless approved by the
Engineer with consultation with DelDOT Safety Section. This requirement applies to all roads impacted in this Contract.
35. The Project Manager is responsible for ensuring any required documents and analysis as part of the adopted Work Zone Safety and Mobility Procedures and Guidelines has been completed prior to any work starting on this contract.
36. Traffic control devices shall be provided and placed in accordance with the Delaware Manual on
Uniform Traffic Control Devices (MUTCD). The Contractor shall prepare and submit a Traffic Control Plan for each bridge site to DelDOT for approval. The Traffic Control Plan must clearly indicate orientation of traffic control devices to be used for each site. The plan must be approved by the DelDOT Safety Officer and DelDOT Engineer prior to commencement of work on each bridge. Maintenance of Traffic Typical Applications is described in the Delaware MUTCD. The Contractor shall be responsible for determining the applicable Typical Application for each work application. The proposed Traffic Control Plan must be submitted to DelDOT a minimum of ten
(10) working days prior to commencement of work at each location. All costs associated with preparing the Traffic Control Plan are included in the cost of bid item 763000 (Initial Expense).
37. No lane closures or shoulder closures will be permitted unless applicable work activity is taking place.
38. All repair/maintenance equipment shall be removed from the job sites on a daily basis, except when approved by the Engineer. Contractor shall follow guidelines set forth by the Delaware MUTCD for storage of materials.
39. No separate payment shall be made for use of traffic cones. Traffic cones and/or work associated with their use, such as set up, removal, cleaning, etc., shall be incidental to the work for which they protect.
40. All open excavations shall be secured with plastic drums with retroreflective fluorescent orange and white prismatic sheeting. If the construction activity results in a vertical difference along, adjacent to, or across a travelway, the Contractor shall eliminate or remedy this hazard by the methods detailed in Table 6G-1 of the Delaware Manual on Uniform Traffic Control Devices (DEMUTCD), or as directed by the Engineer.
41. All permanent warning signs shall be retroreflective, and constructed of rigid material complying with NCHRP 350 and/or MASH requirements.
42. The safety measures outlined within this Contract and the Delaware MUTCD are not necessarily sufficient in every instance to guarantee the protection of the traveling public or the persons working on the project. Therefore, the provisions of this Contract do not relieve the Contractor of the sole responsibility for the safety of all persons working within or traveling through the work zone throughout the duration of the project. The Contractor shall implement any additional safety measures that are not expressly required by the Contract and are necessary to ensure the safety of all persons. The Contractor shall submit to the Engineer justification for deviations from the Traffic Control Plan or Traffic Management Plan. Final approval of the deviations or additions shall rest with the Engineer with guidance from the Traffic Safety Section.
43. The Department reserves the right to stop the Contractor's operations, if in the opinion of the Engineer the Contractor's operations are not in compliance with the Delaware MUTCD, the specifications, or the Plans. The Department also reserves the right to stop the Contractor's operations if the Engineer deems the operations to be unsafe.
44. The Department will not make payment to the Contractor for any and all temporary traffic control devices where the Contractor sets up temporary traffic control to perform work, but fails to perform any work.
45. Immediately prior to the implementation of any lane or roadway closures, the Engineer shall notify the DelDOT TMC at (302) 659-4600. Notifications shall also be given to the TMC when the closure is lifted. The Engineer shall notify the TMC and the DelDOT Safety Officer if lane closures cannot be removed prior to the end of the allowable work hours.
46. Any deficiencies related to temporary traffic control that are reported to the Contractor in writing shall be corrected within 24 hours or as directed by the Engineer. Corrective actions on severe deficiencies shall be taken immediately unless otherwise directed by the Engineer. Failure to comply will result in non-payment for those devices that are found to be deficient for the duration of the deficiency. Serious deficiencies that are not corrected immediately could result in possible suspension of work until items identified are brought back into compliance and/or the holding of the pay estimate until the serious deficiencies are corrected.
47. Pedestrian Maintenance of Traffic: This work shall consist of providing and maintaining an accessible pedestrian route throughout the project’s limits in accordance with the Americans with Disabilities Act of 1990 (ADA) Title II, paragraph 35.130.
The contractor shall be required to review each curb ramp location and submit the appropriate maintenance of traffic detail and devices to the Engineer for each location at least 2-weeks before construction for review, comment, and approval.
The following considerations shall be taken into account when addressing accessible pedestrian maintenance of traffic:
• All pedestrians, including persons with disabilities, shall be provided with a reasonably safe, convenient and accessible path that replicates as much as practicable the existing pedestrian facilities.
• Maintain access to all business and residents at all times.
• Provide pedestrian access thru or around the work zone. If a detour is deemed necessary the Contractor must submit the detour route to the Engineer for review and approval by the Traffic Safety Section. The detour route must meet or exceed the current conditions.
• Work should be phased so that all areas of an intersection/sidewalk path are not under construction at the same time unless a clear path is provided and identified.
• Traffic control devices and other construction materials and features shall not intrude into the usable width of the sidewalk, temporary pathway or other pedestrian facility.
• Signs and other devices mounted lower than 7 ft above the temporary pedestrian pathway shall not project more than 4 in. into accessible pedestrian route.
• A smooth, continuous hard surface shall be provided throughout the entire length and width of the pedestrian route throughout construction.
• There shall be no curbs or vertical elevation changes greater than ¼ in. in grade or terrain that could cause tripping or be a barrier to wheelchair use.
QUANTITY SUMMARY
ITEM # ITEM DESCRIPTION UNIT QUANTITY
727000 Chain Link Fence LF 175 727001 Right-of-Way Fence LF 175 727004 Wood Vertical Slat Fence LF 175 727010 Chain Link Fence Gate EA 3 727011 Right-of-Way Fence Gate EA 3 727030 Fence Relocation LF 50 727031 Gate Relocation EA 2 727032 Fence Repair (chain link only) LF 325 727033 Gate Repair (chain link only) EA 15 727529 Wildlife Exclusion Fence LF 150 727518 Right-of-Way Fence Repair LF 350 727519 Wood Vertical Slat Fence Repair LF 150 763000 Initial Expense / Demobilization LS 1 826001 Permanent Wood Barricade EA 5
| T202680203 Open-End, Right of Way Fence Replacement, North & Canal, FY26-28 Plans Signed.pdf |
| T202680203 Open-End, Right of Way Fence Replacement, North & Canal, FY26-28.pdf |
| T202680203 Open-End, Right of Way Fence Replacement, North & Canal, FY26-28.pdf |
| CONTRACT DESCRIPTION |
| 13. No environmental permits are required for this work provided no jurisdictional wetlands or waters are impacted. If there is any question as to whether or not a water or wetland is jurisdictional, contact the DelDOT Environmental Section at (302) 7... |
| 14. Work within waters/wetlands shall not begin on locations requiring environmental permits until all applicable permits have been obtained by DelDOT. Confirm permit status with DelDOT Engineer prior to commencement of applicable work. |
| 15. Underground utilities may be present at all locations. Therefore, all standard practices and procedures regarding utilities shall be followed. The Contractor shall contact Miss Utility of Delaware prior to starting each work order. The Contractor ... |
| 16. Section 101.3 “Working Day” definition is amended. There will not be a winter shutdown from December 16th to March 15th. The Department reserves the right to issue work and charge time between these dates. |
| 25. Proper disposal of construction related wastes shall be the sole responsibility of the Contractor and shall be performed in accordance with all applicable State regulations. |