T202501101 Plans.pdf
PDF 311 KB Posted
- Solicitation number
- T202501101
- Issued by
- New Castle County, Delaware
About this file
The document is a contract specification from the Delaware Department of Transportation, Division of Planning for Open End Pedestrian Access Routes and Sidewalk Improvements in New Castle County for fiscal years 2025-2027. The contract (number T202501101) covers construction and improvement of pedestrian access routes across New Castle County, with eight specific work orders targeting various roads and areas including New Castle Avenue, Old Capitol Trail, Milltown Road, and others. The contract is valid for one calendar year from the Notice to Proceed, with potential extensions for up to two additional one-year terms through mutual negotiation between the contractor and the Department of Transportation.
The contract is an open-end, work order-driven project where individual work locations will be assigned via work orders, allowing flexibility for the department to prioritize, add, or delete locations. The contractor may have up to three active work orders at a time and must complete each work order within the specified timeframe. Pricing adjustments may be considered upon contract extension, subject to departmental approval. The project does not require federal aid and will be funded through the state's transportation budget. The contractor will be responsible for maintaining traffic, pedestrian access, and following all Delaware Department of Transportation standard specifications and construction details dated January 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| T202501101 BOS.xlsx | XLSX spreadsheet | |
| public.ejs?command=PublicBusinessPlanholderList&projid=T202501101 | — | |
| T202501101 Location Display.pdf | ||
| T202501101 Proposal.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE STATE OF DELAWARE
DEPARTMENT OF TRANSPORTATION
DIVISION OF PLANNING
CONSTRUCTION PLANS AND SPECIFICATIONS FOR
OPEN END PEDESTRIAN ACCESS ROUTES AND SIDEWALK IMPROVEMENTS,
NCC FY25-FY27
CONTRACT NUMBER: T202501101 PRIMAVERA ID: 2025-00021
FEDERAL AID NUMBER: N/A COUNTY: NEW CASTLE
WALLACE MONTGOMERY DATE
APPROVED FOR ADVERTISEMENT
DIRECTOR OF PLANNING DATE
1/13/2025
1/22/25
PLANS & SPECIFICATIONS FOR T202501101 – OPEN END PEDESTRIAN ACCESS ROUTES
AND SIDEWALK IMPROVEMENTS, NEW CASTLE COUNTY, FY25-FY27
CONTRACT DESCRIPTION
THE PURPOSE OF THIS CONTRACT IS TO CONSTRUCT AND IMPROVE FEATURES OF THE
PEDESTRIAN ACCESS ROUTE (PAR) ACROSS NEW CASTLE COUNTY, IN ACCORDANCE
WITH APPLICABLE STANDARDS. THE LOCATION OF WORK IS LIMITED TO SITES WITHIN
NEW CASTLE COUNTY. INDIVIDUAL LOCATIONS WILL VARY IN THEIR CONTEXT AND
COMPLEXITY FROM CONSTRUCTION OF NEW SIDEWALK ON VIRGIN GROUND TO
RECONSTRUCTION OF EXISTING, NON-COMPLIANT PEDESTRIAN CONNECTIONS.
THE SPECIFIC WORK SITES ARE LISTED HEREIN AND WILL BE ASSIGNED AS AVAILABLE
VIA WORK ORDERS. THE WORK ORDERS WILL INDICATE THE WORK TO BE PERFORMED
AT EACH SITE. IT IS ANTICIPATED THAT THE CONTRACTOR SCHEDULE THEIR WORK TO
FOLLOW THE WORK ORDER NUMBERING SEQUENCE: WO #1, WO #2, WO #3, ETC., UNLESS
OTHERWISE APPROVED BY THE ENGINEER.
WORK ORDER 1 – NEW CASTLE AVENUE, PAPER PLACE TO RYAN AVENUE PAR &
SIDEWALK IMPROVEMENTS
WORK ORDER 2 – OLD CAPITOL TRAIL, WALMSLEY DRIVE TO DELAWARE PARK DRIVE
PAR & SIDEWALK IMPROVEMENTS
WORK ORDER 3 – MILLTOWN ROAD, SAINT JOHN CHURCH ENTRANCE TO E PARRIS
DRIVE PAR & SIDEWALK IMPROVEMENTS
WORK ORDER 4 – OGLETOWN STANTON ROAD, OLD CHURCHMANS ROAD TO STANTON
CHRISTIANA ROAD AND OLD CHURCHMANS ROAD, ROCKFORD DRIVE TO OGLETOWN
STANTON ROAD AND TWIN C LANE PAR & SIDEWALK IMPROVEMENTS
WORK ORDER 5 – N MARKET STREET, 41ST ST TO EDGEMOOR ROAD PAR & SIDEWALK
IMPROVEMENTS
WORK ORDER 6 – MARYLAND AVENUE, BOXWOOD PLAZA ENTRANCE TO BROOKSIDE
DRIVE AND DUPONT ROAD, VALLEY ROAD TO RICHARDSON LANE AND RACE STREET
AND OLD DUPONT ROAD PAR & SIDEWALK IMPROVEMENTS
WORK ORDER 7 – EDGEMOOR ROAD, PALADIN DRIVE TO BLUE ROCK ROAD AND
BRANDYWINE BOULEVARD, EDGEMOOR ROAD TO DRIVER ROAD AND RIVER ROAD PAR
& SIDEWALK IMPROVEMENTS
WORK ORDER 8 – S CHAPEL STREET, PENCADER PLAZA NORTH ENTRANCE TO SOUTH
ENTRANCE PAR & SIDEWALK IMPROVEMENTS
PROJECT NOTES
1. THIS PROJECT IS TO BE CONSTRUCTED IN ACCORDANCE WITH THE DELAWARE
DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE
CONSTRUCTION DATED JANUARY 2024, THE DELAWARE DEPARTMENT OF
TRANSPORTATION STANDARD CONSTRUCTION DETAILS, DATED 2024.
2. THIS IS AN OPEN-END WORK ORDER DRIVEN CONTRACT, WITH EIGHT LOCATIONS, TO
MAKE GENERAL IMPROVEMENTS TO ROADS, SIDEWALKS, PATHWAYS, BRIDGES AND/OR
PEDESTRIAN/BICYCLE FACILITIES LOCATED WITHIN THE BOUNDARIES OF NEW CASTLE
COUNTY. THE WORK SHALL BE ISSUED AS THE ENGINEER PROVIDES INDIVIDUAL WORK
ORDERS. THE DEPARTMENT RESERVES THE RIGHT TO PRIORITIZE, SUBSTITUTE, ADD,
AND/OR DELETE LOCATIONS AT ANYTIME DURING THE CONTRACT TERM.
3. THE WORK WILL BE SCHEDULED BY ISSUANCE OF WORK ORDERS TO THE
CONTRACTOR FROM THE DEPARTMENT. EACH WORK ORDER WILL REPRESENT AN
INDEPENDENT PROJECT LOCATION OR GROUPS OF LOCATIONS BASED ON THEIR
PROXIMITY TO EACH OTHER. WORK ORDERS WILL BE ISSUED UPON DESIGN COMPLETION
AND RECEIPT OF NECESSARY STATEMENTS & PERMITS FOR THE INDIVIDUAL SITES. IT IS
ANTICIPATED THAT EACH INDIVIDUAL WORK ORDER WILL OBTAIN THE NECESSARY
PLAN APPROVALS PRIOR TO ISSUANCE.
4. THE SCOPE OF EACH WORK ORDER WILL BE DEFINED BY A SET OF CONSTRUCTION
DRAWINGS. IN ADDITION TO THE DRAWINGS AND NOTES THE ESTIMATED QUANTITIES,
PROPERTY OWNER NOTIFICATION REQUIREMENTS, ALLOWABLE TIME TO PERFORM THE
WORK AND ANY ADDITIONAL SPECIFICATIONS AND CONSTRUCTION GUIDANCE NEEDED
FOR THE SPECIFIC WORK ORDER WILL ALSO BE PROVIDED. AS DIRECTED BY THE
ENGINEER, ADDITIONAL WORK MAY BE ADDED TO A WORK ORDER TO ADDRESS PAR
DEFICIENCIES IN THE IMMEDIATE AREA. ALL WORK WILL BE DISCUSSED WITH THE
CONTRACTOR TO VERIFY SCOPE AND QUANTITIES PRIOR TO ISSUING NOTICE TO
PROCEED FOR THE WORK.
5. UPON RECEIPT OF EACH WORK ORDER, THE CONTRACTOR SHALL SUBMIT THE
REQUIRED COPIES OF A DETAILED PROGRESS SCHEDULE (PSC) AS OUTLINED IN
STANDARD SPECIFICATIONS, SECTION 108.4 WITHIN FOURTEEN (14) CALENDAR DAYS.
THE PSC SHALL INCLUDE A DESCRIPTION OF EACH WORK ACTIVITY, THE PLANNED DAYS
OF WORK, THE NUMBER OF CREWS OR SHIFTS, AND SCHEDULED WORKING HOURS.
DURING THE CONTRACT, THE CONTRACTOR SHALL SUBMIT TWO-WEEK (OR AS
OTHERWISE REQUIRED) “LOOK AHEAD” SCHEDULES TO THE AREA ENGINEER/MANAGER
NO LATER THAN NOON OF EACH THURSDAY. FAILURE TO COMPLY WILL RESULT IN A
SUSPENSION OF ALL CONTRACT WORK WITH TIME CHARGES CONTINUING TO BE
ASSESSED.
6. EXECUTION OF EACH WORK ORDER IS TO BEGIN WITHIN TWENTY-ONE (21) CALENDAR
DAYS OF THE ISSUANCE TO THE CONTRACTOR. IN ADDITION, THE CONTRACTOR MUST
COMPLETE THE WORK WITHIN THE TIME FRAME THAT THE WORK ORDER ALLOCATES,
UNLESS THE NECESSARY MATERIALS ARE NOT AVAILABLE. THE CONTRACTOR SHALL
VERIFY THE MATERIAL’S NON-AVAILABILITY BY AT LEAST THREE (3) INDEPENDENT
SOURCES. AFTER WHICH, THE CONTRACTOR SHALL PROVIDE THE DEPARTMENT WITH
THE VERIFICATION FORMALLY PRESENTED IN WRITING WITHIN FOUR (4) DAYS OF THE
WORK ORDER ISSUANCE.
IF THE CONTRACTOR DOES NOT COMMENCE THE WORK OR DOES NOT PRESENT THE NON-
AVAILABILITY OF MATERIALS WITHIN THE ALLOTTED TIME, THIS SHALL SUBJECT THE
CONTRACTOR TO LIQUIDATED DAMAGES AS OUTLINED IN SUBSECTION 108.8 OF THE
STANDARD SPECIFICATIONS. TIME CHARGES EQUAL TO THE LIQUIDATED DAMAGES FOR
THE WORK ORDER SHALL COMMENCE. IF THE CONTRACTOR VERIFIES WITH THE
DEPARTMENT THAT NON-AVAILABILITY OF MATERIALS IS THE SITUATION CAUSING THE
NON-COMMENCEMENT OF WORK, TIME CHARGES SHALL COMMENCE ON THE FIFTEENTH
(15) CALENDAR DAY FOLLOWING THE DELIVERY DATE OF THE PREVIOUSLY NON-
AVAILABLE MATERIALS.
THE CONTRACTOR MAY HAVE UP TO THREE (3) ACTIVE WORK ORDERS AT A TIME UNTIL
ALL ASSIGNED WORK HAS BEEN COMPLETED.
THE CONTRACTOR IS TO COMPLETE EACH WORK ORDER (OR GROUP OF WORK ORDERS)
WITHIN THE SPECIFIED TIME. AT THE DISCRETION OF THE ENGINEER, ADDITIONAL ITEMS
AND/OR DAYS CAN BE ADDED TO ANY WORK ORDER AS DEEMED NECESSARY. IF THE
CONTRACTOR DOES NOT COMPLETE THE WORK ON A SPECIFIC WORK ORDER ON TIME,
THE DEPARTMENT WILL ASSESS LIQUIDATED DAMAGES IN ACCORDANCE WITH
SUBSECTION 108.9 OF THE STANDARD SPECIFICATIONS. IN SUCH A CASE AS LIQUIDATED
DAMAGES ARE ASSESSED, THE TOTAL AWARD VALUE OF THE WORK ORDER OR GROUP
OF WORK ORDERS, WHICHEVER IS APPLICABLE, WILL BE USED TO DETERMINE THE
VALUE OF LIQUIDATED DAMAGES.
THE DEPARTMENT WILL PERFORM AN INITIAL INSPECTION FOR EACH WORK ORDER OR
WORK ORDER GROUP AFTER THE CONTRACTOR PROVIDES NOTICE TO THE DEPARTMENT
OF COMPLETION OF THE WORK ORDER. THE CONTRACTOR’S WORK MUST MEET THE
DEPARTMENT'S SPECIFICATIONS, THE REQUIREMENTS AS THESE NOTES DEFINE AND
REQUIREMENTS OF THE WORK ORDER. THE CONTRACTOR MUST COMPLETE ANY
PUNCHLIST WORK WITHIN THIRTY (30) CALENDAR DAYS OF THE INITIAL INSPECTION,
UNLESS THE ENGINEER APPROVES OTHERWISE. THE CONTRACTOR MUST REPAIR ALL
DEFECTS IN THE WORK AT THEIR OWN EXPENSE UNTIL THE DEPARTMENT PERFORMS A
PRIMARY INSPECTION. A PRIMARY INSPECTION WILL BE PERFORMED FOR EACH WORK
ORDER OR GROUP OF WORK ORDERS. UPON SATISFACTORY COMPLETION OF THE
PRIMARY PUNCHLIST, THE DEPARTMENT WILL CONDUCT AN ACCEPTANCE INSPECTION.
ONCE DELDOT’S MAINTENANCE AND OPERATIONS VERIFIES THAT ALL PRIMARY
INSPECTION PUNCHLIST ITEMS HAVE BEEN SATISFACTORILY ADDRESSED, THE
CONTRACTOR WILL BE RELEASED FROM MAINTENANCE RESPONSIBILITY FOR ALL
LOCATIONS COMPRISING THE INSPECTED WORK ORDER OR GROUP OF WORK ORDERS.
PAYMENT WILL BE MADE MONTHLY FOR THE COMPLETED PAY ESTIMATES AS
OUTLINED IN SECTION 109.8 OF THE STANDARD SPECIFICATIONS.
7. THE DEPARTMENT RESERVES THE RIGHT TO ADD OR DELETE LOCATIONS AND/OR
QUANTITIES TO THIS CONTRACT. SUCH ADDITIONS OR DELETIONS SHALL NOT BE CAUSE
FOR AN INCREASE OR DECREASE IN ANY CONTRACT UNIT BID PRICES. NO ITEM PRICES
ARE TO BE RENEGOTIATED DUE TO EITHER AN INCREASE OR DECREASE IN QUANTITY
USAGE RESULTING FROM SAID ADDITIONS OR DELETIONS. THE DEPARTMENT RESERVES
THE RIGHT TO, AT ANY TIME DURING THE CONTRACT TERM, ISSUE PLAN REVISIONS,
MAKE ADJUSTMENTS IN CONTRACT ITEM QUANTITIES, OR MAKE SUCH ALTERATIONS
CONSIDERED NECESSARY TO SATISFACTORILY COMPLETE THE CONTRACT.
IF AN ITEM OF WORK IS ADDED TO THE CONTRACT, AND THE BID PRICES ARE NOT
AVAILABLE, PRICES WILL BE NEGOTIATED OR PERFORMED BY FORCE ACCOUNT
PROCEDURES IN ACCORDANCE WITH SUBSECTION 109.4 OF THE STANDARD
SPECIFICATIONS. THE CONTRACTOR WILL PROCEED IMMEDIATELY WITH THE WORK SO
ORDERED AND SUCH DIRECTION SHALL NEITHER INVALIDATE THE CONTRACT, NOR
RELEASE THE SURETY.
8. THE PERIOD OF THIS CONTRACT SHALL BE VALID FOR ONE (1) CALENDAR YEAR FROM
THE “NOTICE TO PROCEED”. THE CONTRACT MAY BE EXTENDED FOR UP TO TWO (2)
ADDITIONAL, ONE-YEAR TERMS THROUGH NEGOTIATION BETWEEN THE CONTRACTOR
AND THE DEPARTMENT OF TRANSPORTATION. NEGOTIATION SHOULD BE INITIATED NO
LATER THAN NINETY (90) DAYS PRIOR TO THE TERMINATION OF THE CURRENT
AGREEMENT. EACH ONE-YEAR EXTENSION MUST BE APPROVED BY BOTH PARTIES IN
WRITING, AT LEAST 30 DAYS PRIOR TO THE EXPIRATION OF THE EXISTING CONTRACT.
9. PRICE ADJUSTMENT: UPON EXPIRATION OF THE INITIAL CONTRACT TERM OR FIRST
CONTRACT EXTENSION (IF APPLICABLE), THE SUBSEQUENT ONE-YEAR CONTRACT
EXTENSION MAY ADJUST PRICING BY MUTUAL WRITTEN AGREEMENT. THE PRICING
MUST COVER THE FULL TERM OF THE CONTRACT EXTENSION PERIOD. IF THE PRICE
DIFFERENCE FOR ANY EXTENSION PERIOD EXCEEDS THE PREVIOUS ONE-YEAR PERIOD,
APPROVAL OF THE PRICE ADJUSTMENT SHALL BE AT THE DISCRETION OF THE
DEPARTMENT. THE DEPARTMENT RETAINS THE RIGHT TO REJECT A REQUEST FOR
FUTURE YEAR EXTENSIONS AT ANY TIME.
10. THE BID PROPOSAL INDICATES ESTIMATED QUANTITIES FOR THE CONTRACT. INITIAL
LOCATION LIST WITH DESCRIPTIONS WILL BE PRESENTED IN A SEPARATE DOCUMENT.
11. ANY DAMAGE TO ITEMS NOTED TO BE RELOCATED OR RESET BY THE CONTRACTOR,
AT THE DISCRETION OF THE ENGINEER, SHALL BE REPAIRED AND/OR REPLACED IN KIND
AT THE CONTRACTOR’S EXPENSE.
12. NO ENVIRONMENTAL PERMITS ARE REQUIRED FOR THIS WORK PROVIDED NO
JURISDICTIONAL WETLANDS OR WATERS ARE IMPACTED. IF THERE IS ANY QUESTION AS
TO WHETHER OR NOT A WATER OR WETLAND IS JURISDICTIONAL, CONTACT THE
RELEVANT NORTH CONSTRUCTION DISTRICT WHO WILL COORDINATE AS NEEDED WITH
THE DELDOT ENVIRONMENTAL STUDIES SECTION AT (302) 760-2264. IF AT ANY POINT IT
IS DETERMINED THAT A PERMIT IS REQUIRED, NO WORK WITHIN WATERS/ WETLANDS
SHALL BEGIN UNTIL ALL APPLICABLE PERMITS HAVE BEEN OBTAINED BY DELDOT. THE
CONTRACTOR SHALL NOT BE HELD LIABLE FOR DELAYS TO THE COMMENCEMENT OF
WORK OR IMPACTS TO THE CONSTRUCTION PROGRESS SCHEDULE DUE TO OBTAINING
PERMITS. TIME CHARGES SHALL COMMENCE ON THE FIFTEENTH (15) CALENDAR DAY
FOLLOWING THE CONTRACTOR’S RECEIPT OF APPLICABLE PERMITS.
13. IT IS ANTICIPATED THAT ALL WORK WILL OCCUR WITHIN DELDOT’S EXISTING RIGHT
OF WAY OR EASEMENT AREAS. SHOULD THE NEED OCCUR TO TRESPASS ONTO PRIVATE
PROPERTY; IT WILL BE THE RESPONSIBILITY OF THE DEPARTMENT TO SECURE SUCH
TRESPASS NEEDS.
14. NO WORK NEAR OR WITHIN RAILROAD RIGHT-OF-WAY IS ANTICIPATED. SHOULD THE
NEED OCCUR TO TRESPASS ONTO RAILROAD PROPERTY, INCLUDING HIGHWAY-RAIL
CROSSINGS; CONTACT THE RELEVANT NORTH CONSTRUCTION DISTRICT WHO WILL
COORDINATE AS NEEDED WITH THE DELDOT RAILROAD COORDINATOR AT (302) 760-4882
TO COORDINATE THE EXECUTION OF THE APPROPRIATE AGREEMENTS AND
AUTHORIZATIONS REQUIRED FROM ANY RAILROAD COMPANY INVOLVED.
15. UNDERGROUND AND AERIAL UTILITIES MAY BE PRESENT AT ALL WORK ORDER
LOCATIONS. THEREFORE, ALL STANDARD PRACTICES AND PROCEDURES REGARDING
UTILITIES SHALL BE FOLLOWED. AS PER THE DELDOT STANDARD SPECIFICATIONS, NO
ADDITIONAL COMPENSATION WILL BE ALLOWED FOR ANY DELAYS, INCONVENIENCE,
OR DAMAGE DUE TO ANY INTERFERENCE FROM THE UTILITY FACILITIES AND
APPURTENANCES OR THE OPERATION OF MOVING THEM, EXCEPT THAT THE
CONTRACTOR MAY BE GRANTED AN EQUITABLE EXTENSION OF TIME. SHOULD ANY
CONFLICTS BE ENCOUNTERED AS A RESULT OF THE CONTRACTOR’S MEANS AND
METHODS DURING CONSTRUCTION REQUIRING ADJUSTMENT AND/OR RELOCATION, THE
NECESSARY RELOCATION WORK SHALL BE ACCOMPLISHED BY THE RESPECTIVE UTILITY
COMPANY AND FUNDED BY THE STATE’S CONTRACTOR AS DIRECTED BY THE DISTRICT
ENGINEER. THE CONTRACTOR SHALL CONTACT DELMARVA811 OF DELMARVA, A
MINIMUM OF TWO WORKING DAYS PRIOR TO STARTING EACH WORK ORDER. SHOULD
ANY CONFLICTS BE ENCOUNTERED DURING CONSTRUCTION REQUIRING ADJUSTMENT
AND/OR RELOCATION OF THE AGENCIES’ EXISTING FACILITIES, THE NECESSARY
RELOCATION WORK SHALL BE ACCOMPLISHED BY THE RESPECTIVE AGENCIES’ FORCES,
AS DIRECTED BY THE ENGINEER. ANY ADJUSTMENTS AND/OR RELOCATIONS OF
MUNICIPALLY OWNED FACILITIES SHALL BE DONE BY THE STATE’S CONTRACTOR IN
ACCORDANCE WITH THE RESPECTIVE AGENCIES’ STANDARD SPECIFICATIONS AS
DIRECTED BY THE DISTRICT ENGINEER. THE CONTRACTOR IS RESPONSIBLE FOR THE
SUPPORT AND PROTECTION OF ALL UTILITIES WHEN EXCAVATING. THE CONTRACTOR IS
ADVISED TO CHECK THE SITE FOR ACCESS PURPOSES FOR HIS EQUIPMENT AND MAKE
ARRANGEMENTS DIRECTLY WITH UTILITY COMPANIES FOR FIELD ADJUSTMENTS FOR
ADEQUATE CLEARANCES IF NECESSARY. 16 DEL. C. § 7405B REQUIRES NOTIFICATION TO
AND MUTUALLY AGREEABLE MEASURES FROM THE PUBLIC UTILITY OPERATING THE
ELECTRICAL FACILITIES FOR ANY PERSON INTENDING TO CARRY ON ANY FUNCTION,
ACTIVITY, WORK OR OPERATION WITHIN DANGEROUS PROXIMITY OF ANY HIGH
VOLTAGE OVERHEAD ELECTRIC LINES. ALL CONTRACTORS/OTHER UTILITIES MUST
ALSO MAINTAIN A DISTANCE OF 10 FEET FROM ALL OVERHEAD ENERGIZED LINES.
16. SEASONAL RESTRICTIONS MAY EXIST AT SELECT LOCATIONS TO BE PERFORMED
UNDER THIS CONTRACT. THE DEPARTMENT WILL NOTIFY THE CONTRACTOR UPON
ISSUANCE OF A NEW WORK ORDER OF ANY RESTRICTIONS.
17. ALL PORTLAND CEMENT CONCRETE MUST BE RECEIVED FROM AN APPROVED
PRODUCTION PLANT. ONLY CALIBRATED VOLUMETRIC CONCRETE TRUCKS WILL BE
PERMITTED TO PROVIDE ON-SITE MIXTURES. THIS PERTAINS TO BOTH WORK OCCURRING
DURING NORMAL WORKING HOURS AND NIGHTTIME RESTRICTED WORK.
18. THE DELDOT PROJECT MANAGER SHALL BE RESPONSIBLE FOR COORDINATING WITH
THE TRAFFIC SIGNAL CONSTRUCTION SECTION RELATING TO ANY IMPACTS TO TRAFFIC
SECTION FACILITIES (INCLUDING BUT NOT LIMITED TO TRAFFIC LOOPS, JUNCTION
WELLS ETC.) AT LEAST 4 WEEKS IN ADVANCE OF THE START OF THE ACTIVITY.
19. IN ORDER TO MAINTAIN EFFECTIVE COMMUNICATION WITH THE TRAVELING PUBLIC,
ONLY PLACE SIGNS, BANNERS, FLAGS, OR OTHER DISPLAYS WITHIN THE PROJECTS
LIMITS THAT MEET THE REQUIREMENTS OF THE LATEST VERSION OF THE DELAWARE
MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES. ANY SIGNS OR OTHER MATERIALS
WHICH DEVIATE FROM THE MUTCD, MUST BE PREAPPROVED BY THE ENGINEER. THE
ONLY SIGNAGE AND MATERIALS WHICH MAY BE DISPLAYED UPON VEHICLES AND
EQUIPMENT WITHIN THE PROJECT AREA ARE SIGNS DENOTING THE NAME OF THE
CONTRACTOR AND ANY SUBCONTRACTORS AND OTHER SIGNS AND/OR MATERIALS
REQUIRED AND APPROVED PURSUANT TO THE MUTCD AND THE ENGINEER.
CONTRACTOR SHALL IMMEDIATELY REMOVE ANY SIGNS OR MATERIALS WITHIN THE
PROJECT THAT DOES NOT MEET THESE REQUIREMENTS IMMEDIATELY UPON
NOTIFICATION BY THE ENGINEER. FAILURE TO REMOVE SIGNS OR OTHER MATERIALS
FOLLOWING NOTIFICATION FROM THE ENGINEER WILL RESULT IN LIQUIDATED
DAMAGES BEING ASSESSED IN THE MANNER AND AMOUNT SPECIFIED IN THE STANDARD
SPECIFICATIONS SECTION 108.9.A.
CONTRACT NOTES
1. ITEM 763622 CONSTRUCTION ENGINEERING, PAR REHABILITATION WILL COMPENSATE
THE CONTRACTOR FOR SURVEY ACTIVITIES. INCLDUING COLLECTION OF SURVEY
INFORMATION, PERFORMING COMPUTATIONS, LAYOUTS ASSOCIATED WITH ADA
IMPROVEMENTS, PROVIDING GRADES FOR UTILITY ADJUSTMENTS, IF NECESSARY, THE
LAYOUT OF LANE LINES FOR PAVING, GRADES FOR THE INSTALLATION OF DRAINAGE
STRUCTURES OR OTHER ITEMS OF WORK AS DETERMINED BY THE ENGINEER. THE
HOURLY PAYMENT WILL BE BASED UPON ACTUAL HOURS OF SURVEYING WORK
PERFORMED IN THE OFFICE OR FIELD. THE SURVEY CREW WILL BE RESPONSIBLE UPON
ARRIVAL AND DEPARTURE ON THE JOBSITE TO CONTACT A MEMBER OF THE INSPECTION
STAFF SO THAT HOURS CAN BE TRACKED FOR PAYMENT. THE CONSEQUENCE FOR NOT
COORDINATING WITH INSPECTION STAFF PRIOR TO PERFORMING FIELD SURVEY WORK
WILL BE NON-PAYMENT FOR THE SURVEYING SERVICES. ALL HOURS MUST BE
SUBSTANTIATED THROUGH INVOICING THAT DOCUMENTS THE NUMBER OF HOURS, THE
LOCATION(S) BY WORK ORDER NUMBER, AND/OR PLAN REFERENCE AND DESCRIPTION
OF THE SPECIFIC OFFICE OR FIELD TASKS PERFORMED.
2. TRASH, RUBBISH, DEBRIS, BRUSH OR OTHER OBSTRUCTIONS THAT HAMPERS REPAIR /
MAINTENANCE WORK IN THIS CONTRACT AS DETERMINED BY THE ENGINEER, SHALL BE
REMOVED WITHIN THE PROJECT LIMITS AND SHALL BE INCIDENTAL TO PAY ITEM 763531
– WORK ORDER MOBILIZATION AND DEMOBILIZATION.
3. GRASS AND SOIL AREAS EITHER OUTSIDE OF THE LIMITS OF CONSTRUCTION OR
REASONABLE LIMITS OF DISTURBANCE THAT HAVE BEEN DAMAGED BY THE
CONTRACTOR'S EQUIPMENT DURING THIS CONTRACT SHALL BE RESTORED WITH
TOPSOIL, SEED AND MULCH AS DIRECTED BY THE ENGINEER AT THE CONTRACTOR'S
EXPENSE.
4. THE CONTRACTOR WILL CONTACT THE DELAWARE TMC AT 302-659-4600 PRIOR TO ANY
UNMANNED AIRCRAFT VEHICLE (UAV) FLIGHTS. THE CONTRACTOR WILL BE REQUIRED
TO PROVIDE THE FOLLOWING INFORMATION: THE REGISTRATION NUMBER OF THE UAV,
THE FLIGHT TIME, LOCATION OF THE FLIGHT, THE PILOT’S NAME AND THE PILOT’S
CONTACT NUMBER DURING THE FLIGHT.
5. THE CONTRACTOR SHALL REMOVE AND RESET ALL MAILBOXES TO MAINTAIN MAIL
SERVICE AS DIRECTED BY THE ENGINEER. THE CONTRACTOR SHALL RELOCATE
MAILBOXES AS REQUIRED BY ANY ISSUED WORK ORDERS AND AS DIRECTED BY THE
ENGINEER. WHEN RELOCATING MAILBOXES IN CURBED SECTIONS, THE FACE OF THE
MAILBOX SHALL BE FLUSH WITH THE BACK EDGE OF CURB. WHEN RELOCATING
MAILBOXES IN OPEN SECTIONS, THE FACE OF THE MAILBOX SHALL SET BACK 8 INCHES
FROM THE EDGE OF THE PAVED SHOULDER. THE BOTTOM OF THE MAILBOX SHALL BE
POSITIONED IN ACCORDANCE WITH LATEST VERSION OF THE UNITED STATES POSTAL
SERVICE GUIDELINES. MAILBOXES LOCATED AT DRIVEWAY ENTRANCES SHALL BE
PLACED ON THE FAR SIDE OF THE DRIVEWAY IN THE DIRECTION OF TRAVEL. POSTS
BEING RESET IN CONCRETE SIDEWALK SHALL BE PLACED IN AN APPROPRIATE SIZE PVC
SLEEVE. ACCEPTABLE POST SHALL BE 4-INCH X 4-INCH WOOD POST OR 4-INCH DIAMETER
WOOD POST. FOR RELOCATING MULTIPLE MAILBOXES TOGETHER ALL POST SHALL BE
SEPARATED BY A DISTANCE OF NO LESS THAN ¾ OF THEIR FULL HEIGHT ABOVE THE
GROUND. MULTIPLE MAILBOXES ATTACHED TO A SINGLE HORIZONTAL BOARD SHALL
NOT BE LOCATED INSIDE THE CLEAR ZONE. EACH MAILBOX SHALL BE PLACED ON AN
INDIVIDUAL POST MEETING THE CRITERIA ABOVE. ALL MAILBOXES SHALL BE SET NOT
TO IMPEDE THE MINIMUM PAR (PEDESTRIAN ACCESS ROUTE) WIDTH AS DETERMINED BY
THE CURRENT EDITION OF THE PEDESTRIAN ACCESSIBILITY STANDARDS FOR FACILITIES
IN THE PUBLIC RIGHT OF WAY. COSTS FOR ALL WORK AND MATERIALS FOR RESETTING
OF THE MAILBOXES SHALL BE INCIDENTAL TO THE CONTRACT.
6. THE PAVEMENT SECTION FOR FLEXIBLE PAVEMENT RESIDENTIAL DRIVEWAYS SHALL
BE 2” BITUMINOUS CONCRETE, TYPE ‘C’ OVER 8” GRADED AGGREGATE BASE COURSE,
TYPE ‘B’ UNLESS OTHERWISE NOTED ON THE PLANS OR AS DETERMINED BY THE
ENGINEER IN THE FIELD AS NEEDED TO MATCH EXISTING.
7. STATION AND ELEVATION DATA GIVEN FOR DRAINAGE STRUCTURES ARE TO BE
APPLIED TO THE CENTER OF THE GRATE FOR INLETS AND TO THE CENTER OF THE
STRUCTURE FOR JUNCTION BOXES AND MANHOLES.
8. IN AREAS WHERE PROPOSED CURB MEETS EXISTING CURB AND THE TWO CURB TYPES
ARE NOT SIMILAR, THE PROPOSED CURB SHALL BE TRANSITIONED IN 10 LINEAR FEET,
UNLESS OTHERWISE DIRECTED BY THE ENGINEER. PAYMENT FOR THIS WORK,
INCLUDING SAW CUTTING EXISTING CURB SHALL BE INCIDENTAL TO THE PROPOSED
CURB ITEM.
9. WHERE PROPOSED CONCRETE SIDEWALK IS CONSTRUCTED TO MEET EXISTING
SIDEWALK, THE EXISTING SIDEWALK SHALL BE SAWCUT AT THE TIE-IN POINT OR MEET
THE NEAREST EXISTING SIDEWALK JOINT. ALL SAW CUTTING SHALL BE FULL DEPTH,
UNLESS OTHERWISE NOTED ON THE PLANS OR DIRECTED BY THE ENGINEER AND SHALL
BE PAID FOR UNDER ITEM 762001 – SAW CUTTING, CONCRETE, FULL DEPTH.
10. PORTLAND CEMENT CONCRETE CHANNELIZING ISLANDS THAT ARE LESS THAN 75 SQ.
FT. MAY BE POURED MONOLITHICALLY, OR AS DIRECTED BY THE ENGINEER.
11. FOR FULL DEPTH PAVEMENT CONSTRUCTION, PEDESTRIAN CONNECTION
CONSTRUCTION, SIDEWALK CONSTRUCTION, AND/OR UTILITY RELOCATIONS, BARE
SOILS SHALL BE COVERED WITHIN THREE (3) CALENDAR DAYS TO PREVENT EROSION.
THIS CAN BE ACCOMPLISHED BY PLACING PROPOSED SUBBASE MATERIAL SUCH AS
GRADED AGGREGATE BASE COURSE (GABC) OR GEOTEXTILE / PLASTIC SHEETING THAT
IS SECURED SO AS TO NOT BLOW AWAY OR BE UNDERMINED BY RUNOFF, OR AS
OTHERWISE DIRECTED BY THE ENGINEER.
12. IF WETLANDS ARE LOCATED IN THE VICINITY OF A WORK ORDER, THE ENGINEER MAY
REQUEST THAT THE CONTRACTOR FLAG THE WETLAND AREA. THE WORK REQUIRED
FOR WETLAND FLAGGING SHALL BE MEASURED AND PAID IN ACCORDANCE WITH 763622
– CONSTRUCTION ENGINEERING, PAR REHABILITATION. THE MATERIAL TO BE USED FOR
FLAGGING THE LIMITS OF CONSTRUCTION SHALL BE ORANGE VINYL MATERIAL WITH
THE WORDING "WETLAND BOUNDARY" PRINTED THEREON. IN WOODED AREAS, THE
FLAGGING SHALL BE TIED ON THE TREES, AT APPROXIMATE 20-FOOT INTERVALS
THROUGH WETLAND AREAS. IN OPEN FIELD AND YARD AREAS THAT HAVE BEEN
IDENTIFIED AS WETLANDS, 6-FOOT POSTS SHALL BE DRIVEN INTO THE GROUND AT
APPROXIMATE 20-FOOT INTERVALS AND TIED WITH THE FLAGGING. IF THE FLAGGING
HAS BEEN DESTROYED AS A RESULT OF THE CONTRACTOR’S MEANS AND METHODS AND
THE ENGINEER DETERMINES THAT ITS USE IS STILL REQUIRED, THE CONTRACTOR SHALL
REFLAG THE AREA AT NO COST TO THE DEPARTMENT. IF THE CONTRACTOR, AFTER
NOTIFICATION BY THE ENGINEER THAT REPLACEMENT FLAGGING IS NEEDED, DOES NOT
REPLACE THE DESTROYED FLAGGING WITHIN 48 HOURS, THE ENGINEER MAY PROCEED
TO HAVE THE AREA REFLAGGED. THE COST OF THE REFLAGGING BY THE ENGINEER WILL
BE CHARGED TO THE CONTRACTOR AND DEDUCTED FROM ANY MONIES DUE UNDER THE
CONTRACT. AT THE COMPLETION OF CONSTRUCTION, THE CONTRACTOR SHALL
REMOVE ALL POSTS AND FLAGGING.
MAINTENANCE OF TRAFFIC
1. ALL WORK SHALL BE PERFORMED IN A MANNER THAT SHALL ENSURE THE LEAST
PRACTICAL OBSTRUCTION TO ALL ROAD USERS, INCLUDING VEHICULAR, PEDESTRIAN,
AND BICYCLE TRAFFIC, AND SHALL COMPLY WITH THE REQUIREMENTS SPECIFIED IN
THE LATEST VERSION OF THE “DELAWARE MANUAL ON UNIFORM TRAFFIC CONTROL
DEVICES" (DEMUTCD) PART 6, INCLUDING REVISIONS IN EFFECT AT THE TIME OF
ADVERTISEMENT FOR BIDS.
2. THE CONTRACTOR SHALL SUBMIT TEMPORARY TRAFFIC CONTROL DEVICE SOURCE OF
SUPPLY DOCUMENTATION FOR THE DEPARTMENT’S APPROVAL AS REQUIRED PER
STANDARD SPECIFICATION SECTION 106.1.
3. THE DELDOT PROJECT MANAGER SHALL BE NOTIFIED OF ANY ANTICIPATED
TEMPORARY/PERMANENT IMPACT TO TRAFFIC SIGNALS AND/OR TRAFFIC EQUIPMENT.
THESE IMPACTS TO TRAFFIC SIGNALS AND/OR TRAFFIC EQUIPMENT MUST BE REVIEWED
BY THE DELDOT TRAFFIC SIGNAL CONSTRUCTION SECTION PRIOR TO CONSTRUCTION.
THEY CAN BE CONTACTED AT 302-659-4060.
4. THE CONTRACTOR SHALL HAVE AN AMERICAN TRAFFIC SAFETY SERVICES
ASSOCIATION (ATSSA) SUPERVISOR ASSIGNED TO EACH WORK ORDER LOCATION AS
DIRECTED BY THE ENGINEER AND THAT PERSON’S SOLE RESPONSBILITY SHALL BE THE
MANAGEMENT AND SUPERVISION OF THE WORK ORDER’S TEMPORARY TRAFFIC
CONTROL ACTIVITIES. THIS PERSON SHALL NOT HAVE ANY OTHER ROLE ON THE WORK
ORDER LOCATION. RESPONSIBILITIES AND REQUIREMENTS OF THE ATSSASUPERVISOR
ARE DEFINED IN SECTION 812 OF THE STANDARD SPECIFICATIONS, PAYMENT FOR ATSSA
SUPERVISOR IS INCIDENTAL TO ITEM 801000 – MAINTENANCE OF TRAFFIC.
5. MAINTAIN SIGNS THAT MUST REMAIN IN PLACE DURING THE PROJECT AS NOTED IN
THE CONTRACT DOCUMENTS AND/OR AS DIRECTED BY THE ENGINEER. REMOVE OR
COVER ANY EXISTING SIGNS THAT CONFLICT WITH ANY CONSTRUCTION SIGNS, AND AS
DIRECTED BY THE ENGINEER. PROPERLY STORE REMOVED SIGNS TO PREVENT LOSS OR
DAMAGE. REPAIR OR REPLACE ANY LOST OR DAMAGED EXISTING SIGNS AT THE
CONTRACTOR EXPENSE.
6. THE CONTRACTOR WILL BE RESPONSIBLE TO CORRECT ANY ERRONEOUS PAVEMENT
MARKINGS IMMEDIATELY AND AT THE CONTRACTOR’S EXPENSE. ERRONEOUS
MARKINGS OR SHADOWS THAT EXCEED ONE (1) INCH IN WIDTH SHALL BE REMOVED BY
EITHER SAND OR WATER BLASTING OR BLACK OUT PAINT IN ACCORDANCE WITH
SECTION 817. ANY DAMAGE TO THE PAVEMENT CAUSED BY THE REMOVAL OF
ERRONEOUS MARKINGS SHALL BE REPAIRED OR REPLACED TO THE SATISFACTION OF
THE ENGINEER AT THE CONTRACTOR’S EXPENSE.
7. BEFORE TRAFFIC IS RETURNED TO UNRESTRICTED ROADWAY USE, TEMPORARY
STRIPING SHALL BE UTILIZED AT LOCATIONS THAT REQUIRE PERMANENT STRIPING.
TEMPORARY PAVEMENT MARKINGS SHALL BE MEASURED AND PAID IN ACCORDANCE
WITH ITEM 817003 – TEMPORARY MARKINGS, PAINT, 4” AND ITEM 817004 – TEMPORARY
MARKINGS, PAINT, SYMBOL/LEGEND. THE CONTRACTOR IS RESPONSIBLE FOR
MAINTAINING THE TEMPORARY MARKINGS PER STANDARD SPECIFICATION SECTION
801.3.4 SUCH THAT THE PAVEMENT IS PROPERLY DELINEATED AT ALL TIMES. ANY
REFRESHING OF THE TEMPORARY MARKINGS WILL BE AT THE CONTRACTOR'S EXPENSE.
8. PLACEMENT OF TEMPORARY MARKINGS SHALL RECEIVE PRIOR APPROVAL FROM THE
ENGINEER. TEMPORARY PAVEMENT MARKING MATERIAL SHALL FOLLOWING STRIPING
ITEMS GUIDELINES – 2020 STANDARD SPECIFICATIONS ON DELDOT’S DESIGN RESOURCE
CENTER (DRC).
9. PEDESTRIAN MAINTENANCE OF TRAFFIC:
THIS WORK SHALL CONSIST OF PROVIDING AND MAINTAINING AN ACCESSIBLE
PEDESTRIAN ROUTE WHEN EXISTING PEDESTRIAN FACILITIES ARE DISRUPTED,
CLOSED, OR RELOCATED IN A TEMPORARY TRAFFIC CONTROL ZONE IN
ACCORDANCE WITH THE AMERICANS WITH DISABILITIES ACT OF 1990 (ADA) TITLE
II, PARAGRAPH 35.130.
THE CONTRACTOR SHALL BE REQUIRED TO REVIEW EACH PEDESTRIAN
CONNECTION LOCATION AND SUBMIT THE APPROPRIATE MAINTENANCE OF
TRAFFIC DETAIL AND DEVICES TO THE ENGINEER FOR EACH LOCATION FOURTEEN
(14) DAYS BEFORE CONSTRUCTION FOR REVIEW, COMMENT, AND APPROVAL BY
THE DISTRICT TRAFFIC SAFETY OFFICER
THE FOLLOWING CONSIDERATIONS SHALL BE TAKEN INTO ACCOUNT WHEN
ADDRESSING ACCESSIBLE PEDESTRIAN MAINTENANCE OF TRAFFIC:
o ALL PEDESTRIANS, INCLUDING PERSONS WITH DISABILITIES, SHALL BE
PROVIDED WITH A REASONABLY SAFE, CONVENIENT AND ACCESSIBLE
PATH THAT REPLICATES AS MUCH AS PRACTICABLE THE EXISTING
PEDESTRIAN FACILITIES.
o PROVIDE PEDESTRIAN ACCESS THROUGH OR AROUND THE WORK ZONE.
THE CONTRACTOR MAY ELECT TO MAINTAIN ACCESS EITHER WITH A
PEDESTRIAN DETOUR OR A PEDESTRIAN FLAGGER. THIS INFORMATION
MUST BE DOCUMENTED IN THE CONTRACTOR’S SUBMISSION TO THE
DEPARTMENT FOR MOT APPROVAL. IF A DETOUR IS CHOSEN, THE DETOUR
ROUTE MUST MEET OR EXCEED THE CURRENT ACCESS CONDITIONS.
o WORK SHOULD BE PHASED SO THAT ALL AREAS OF AN
INTERSECTION/SIDEWALK PATH ARE NOT UNDER CONSTRUCTION AT THE
SAME TIME UNLESS A CLEAR PATH IS PROVIDED AND IDENTIFIED.
MINIMIZE THE NUMBER OF DISTURBED AREAS AT ANY GIVEN TIME, AS
DIRECTED BY THE ENGINEER.
o TRAFFIC CONTROL DEVICES AND OTHER CONSTRUCTION MATERIALS AND
FEATURES SHALL NOT INTRUDE INTO THE USABLE WIDTH OF THE
SIDEWALK, TEMPORARY PATHWAY OR OTHER PEDESTRIAN FACILITY.
o SIGNS AND OTHER DEVICES MOUNTED LOWER THAN 7 FT ABOVE THE
TEMPORARY PEDESTRIAN PATHWAY SHALL NOT PROJECT MORE THAN
4 IN. INTO ACCESSIBLE PEDESTRIAN ROUTE.
o A UNIFORM MATERIAL THAT IS FIRM, STABLE, AND SLIP RESISTANT
MEETING ALL REQUIREMENTS IN THE STANDARD SPECIFICATIONS FOR
TEMPORARY PEDESTRIAN PATHWAYS SHALL BE PROVIDED THROUGHOUT
THE ENTIRE LENGTH AND WIDTH OF THE PEDESTRIAN ROUTE
THROUGHOUT CONSTRUCTION. THERE SHALL BE NO CURBS OR VERTICAL
ELEVATION CHANGES GREATER THAN ¼ IN. IN GRADE OR TERRAIN THAT
COULD CAUSE TRIPPING OR BE A BARRIER TO WHEELCHAIR USE.
10. THE CONTRACTOR SHALL MAINTAIN ACCESS TO AND ALONG PEDESTRIAN FACILITIES
AT ALL TIMES DURING CONSTRUCTION. FOR ANY PEDESTRIAN CONNECTION AND/OR
SIDEWALK AREAS UNDER CONSTRUCTION THAT CLOSE OR BLOCK A PEDESTRIAN ROUTE
FOR AN EXTENDED PERIOD, ALTERNATE PEDESTRIAN ACCESS SHALL BE PROVIDED,
APPROVED AND MAINTAINED AS DIRECTED BY THE ENGINEER. ALL COSTS SHALL BE
INCIDENTAL TO ITEM 801000 – MAINTENANCE OF TRAFFIC.
11. PEDESTRIAN FLAGGER: ADDITIONAL QUANTITY HAS BEEN ESTIMATED FOR ITEMS
811001 - FLAGGER, NEW CASTLE COUNTY AND 811013 - FLAGGER, NEW CASTLE COUNTY,
OVERTIME TO PROVIDE A FLAGGER PRESENCE DURING PEDESTRIAN CONNECTION
CONSTRUCTION AS DIRECTED BY THE ENGINEER. AS NECESSARY, THE FLAGGER WILL
BE PRESENT TO PROVIDE SAFE PEDESTRIAN MOVEMENTS AT LOCATIONS WHERE
NORMAL PEDESTRIAN MOVEMENTS HAVE BEEN INTERRUPTED.
12. THE USE OF MILLINGS AND GRADED AGGREGATE BASE COURSE (GABC) IN THE
TRAVEL WAY, TEMPORARY TRAVEL WAY, HIGH VOLUME ENTRANCES AND ACCESS
RAMP FOR THE PURPOSE OF PROVIDING A TEMPORARY ROADWAY SURFACE, POTHOLE
REPAIR, TAPERED EDGE FOR UTILITIES, BUTT JOINTS, AND LONGITUDINAL DROP-OFFS
(MILLING AND PAVING OPERATIONS) IS PROHIBITED UNLESS IT IS OTHERWISE
DESIGNATED TO BE USED IN THE CONTRACT PLANS. USE COLD PATCH, BITUMINOUS
CONCRETE, BITUMINOUS CONCRETE WEDGE, OR TAPER MILL, AS NOTED IN THE
CONTRACT DOCUMENTS OR APPROVED BY THE ENGINEER. PAYMENT FOR COLD PATCH,
BITUMINOUS CONCRETE OR BITUMINOUS CONCRETE WEDGE SHALL BE PAID AS NOTED
IN THE CONTRACT DOCUMENTS. TAPER MILL BITUMINOUS CONCRETE SHALL BE PAID
UNDER THE BITUMINOUS CONCRETE MILLING ITEM.
MILLINGS OR GABC SHALL BE USED AT THE FOLLOWING LOCATIONS WHERE ACCESS TO
A BUSINESS, RESIDENCE, OR EDGE DROP OFF NEEDS TO BE MAINTAINED UNLESS
OTHERWISE NOTED IN THE PLANS OR DIRECTED BY THE ENGINEER TO USE BITUMINOUS
CONCRETE OR COLD PATCH. ALL MILLINGS AND GABC WILL BE ROLLED AND
COMPACTED TO HELP PREVENT THE MATERIAL FROM UNRAVELLING:
a. DRIVEWAYS
b. ENTRANCES
c. LOW VOLUME ACCESS RAMPS (IDENTIFIED IN THE CONTRACT DOCUMENTS)
d. EDGE DROP-OFFS ADJACENT TO LIVE ROADWAY (LANES AND SHOULDER) AND
THE PROPOSED ROAD CONSTRUCTION
e. EDGE OF ROADWAY DROP-OFF
GRADING AND MAINTAINING BASE COURSE THAT IS BEING USED FOR ROADWAY
WEDGE/FILLET BETWEEN TRAVEL LANES AND PAVEMENT BOX, EDGE OF TRAVEL WAY,
DRIVEWAY OR ENTRANCE ACCESS SHALL BE INCIDENTAL TO ITEM NO. 801000 -
MAINTENANCE OF TRAFFIC. THE BASE COURSE MATERIAL SHALL BE PLACED AT NO
GREATER THAN THE SLOPE SPECIFIED IN TABLE 6G-1 AND SHALL BE COMPACTED.
EXCESS BASE COURSE MATERIAL SHALL BE PUSHED AHEAD AND USED IN THE NEXT
SEGMENT AND SHALL BE INCIDENTAL TO THE PARTICULAR BASE COURSE PAY ITEM. NO
SEPARATE PAYMENT SHALL BE MADE FOR MILLINGS OR GABC TEMPORARY ROADWAY
MATERIAL (TRM) USED TO PROTECT EDGE DROP-OFFS, UNLESS THE MATERIAL IS
EVENTUALLY UTILIZED AS PART OF A PERMANENT ROADWAY AT WHICH TIME THE
MATERIAL WOULD BE PAID FOR UNDER THE RESPECTIVE CONTRACT MATERIAL ITEM.
VERTICAL DIFFERENCES SHALL BE CORRECTED IN ACCORDANCE WITH TABLE 6G-1 OF
THE DELAWARE MUTCD.
13. THE SAFETY MEASURES OUTLINED WITHIN THIS CONTRACT AND THE DELAWARE
MUTCD ARE NOT SUFFICIENT IN EVERY INSTANCE TO GUARANTEE THE PROTECTION OF
THE TRAVELING PUBLIC OR THE PERSONS WORKING ON THE PROJECT. THEREFORE, THE
PROVISIONS OF THIS CONTRACT DO NOT RELIEVE THE CONTRACTOR OF THE SOLE
RESPONSIBILITY FOR THE SAFETY OF ALL PERSONS WORKING WITHIN OR TRAVELING
THROUGH THE WORK ZONE DURING THE DURATION OF THE PROJECT. THE CONTRACTOR
SHALL IMPLEMENT ANY ADDITIONAL SAFETY MEASURES THAT ARE NOT EXPRESSLY
REQUIRED BY THE CONTRACT AND ARE NECESSARY TO ENSURE THE SAFETY OF ALL
PERSONS. THE CONTRACTOR SHALL SUBMIT TO THE ENGINEER JUSTIFICATION FOR
DEVIATIONS FROM THE TRAFFIC CONTROL PLAN OR TRAFFIC MANAGEMENT PLAN.
FINAL APPROVAL OF THE DEVIATIONS OR ADDITIONS SHALL REST WITH THE ENGINEER
WITH GUIDANCE FROM THE TRAFFIC SAFETY SECTION. ALL COSTS FOR DEVELOPING
AND SUBMITTING THIS JUSTIFICATION DOCUMENTATION IS INCIDENTAL TO 801000 –
MAINTENANCE OF TRAFFIC.