Addl_Received_Questions_and_Responses.docx

DOCX document 21 KB Posted

Attached to
CC16HQR0012 SOLICITATION FOR A-123/ACCOUNTING SERVICES
Solicitation number
SYNOPSIS_A-123_ACCOUNTING_SERVICES
Issued by

About this file

The purpose of this notification is to provide responses to additional questions received relating to solicitation CC16HQR0012 for A-123/Accounting Services.

View the file

Other files

File Type Posted
Questions__ _Responses.docx DOCX document
Amendment_0002_CC16HQR0012.pdf PDF
Amendment__0001_CC16HQR0012.pdf PDF
Revised_Questions_ _Responses.docx DOCX document
Questions__ _Responses.docx DOCX document
Attachment_C_Performance_Requirement_Summary.docx DOCX document
Attachment_B_Non-Disclosure_Agreement.doc DOC document
Attachment_E_OCC_IT_Accessibility_Questionnaire.doc DOC document
Attachment_D_Contractor's_Off-Boarding_Tasks.docx DOCX document
Attachment_F_Q A_Template.docx DOCX document
Solicitation_A-123_AccountingServices.pdf PDF
Attachment_A_Past_Performance_Questionnaire.doc DOC document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A123/Accounting Services

CC-16-HQ-R-0012

Attachment F: Questions &Answers Q&A

#
RFQ Section
Question
Response
Change to RFP?
Description of Change
Technical/ Contractual
1
C.6 Key Personnel and C.4.1 Financial Systems Operations

Responses to Q. 21 & Q.39 The OCC’s Response to Q. 21 indicates that “PeopleSoft Financials is required for the Key Personnel: Principal 1/Program Manager.” The Response to Q. 39 Indicates that OCC will allow PeopleSoft Qualifications for a Senior Manager 1 (designated as Key Personnel) to meet this requirement in lieu of the Principal I/Program Manager.

Please confirm that in that instance, the offeror will be designating and submitting two Key Personnel resumes, a resume for the Principal I/Program Manager and a resume for the Senior Manager I with the requisite PeopleSoft Qualifications.

No, if additional key personnel are proposed, only one (1) proposed key personnel needs to have the PeopleSoft requirement. As indicated in response to question 39, “if the Offeror designates one (1) of the Senior Manager I positions as Key Personnel within its proposal, OCC will allow the PeopleSoft qualifications for that individual to meet this requirement in lieu of the Principal I/Program Manager.” In addition, please review amendment #0001: specifically, C.6 and C.6.1.
No

Technical

2
L.5 Submission of Offers and L.7.3 Past Performance
Given that the NAICs code designation has just been changed to allow broader participation and that the adjustments to the RFQ resulting from Q’s and A’s have not yet been formalized by Amendment, would OCC please extend the proposal submission and past performance questionnaires submission dates to May 17 or one week from the issuance of the conforming Amendment?
The proposal due date remains unchanged. All proposals are due on Thursday, May 12, 2016 at 2:00 PM ET.
No

Contractual

3
B.2
Could the Government please clarify the distinction between Senior III and Senior II LCATs, each for 155 hours? Are these SME LCATS (e.g. FISCAM, Statisticians, Data Analysis)?
A Senior labor category generally has over ten years of experience and a MA/MS degree. A Senior labor category is able to perform duties independently and is able to oversee the work of less senior staff. A Senior III is more experienced and skilled than a Senior II. Subject matter expertise in areas relevant to the PWS is a plus for the Senior III and Senior II labor categories.
No

Technical

Would the government accept CPARS as proof of project performance, in lieu of questionnaire responses?

CPARS may be submitted along with the completed past performance questionnaire. Please note that the past performance questionnaire requests additional information not in CPARS; therefore, the CPARS is not sufficient on its own.
No

Contractual

*Note: Contractor only needs to fill out the highlighted columns: Company, RFP Section (please include the section, paragraph, and page number that your question refers to), and Question. Contractor s may add additional rows, if necessary. Please do not add/remove columns or change column width. Please keep this in MS Word.