This Supplementary Conditions document outlines additional requirements for the Wastewater Treatment Plant No. 1A – Clarifier No. 1 Rehabilitation project in Rosenberg, Texas. The project, managed by the City of Rosenberg in Fort Bend County with engineering support from Garver, LLC, carries an estimated budget of $1,000,000 and a completion timeline of 365 calendar days. Key project specifications include traffic management requirements prohibiting full lane closures during peak hours while maintaining uninterrupted thru traffic, site restoration using hydromulch from right-of-way to right-of-way lines with one row of full 18-inch-wide sodding placed behind curbs or sidewalks for the project length, and water service line connections utilizing copper for the short side and EndoPure PE-4710 in sleeve (or approved equal) for the long side.

The contractor shall compensate the City Inspector at an hourly rate of $150.00 for any Saturday work performed on the project. These supplementary conditions establish specific material standards, traffic control protocols, landscaping requirements, and labor cost expectations that bidders must incorporate into their project proposals and cost estimates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPC1

SUPPLEMENTARY CONDITIONS

A. Full lane closures shall not be during peak hours. Contractor to manage traffic control to ensure thru traffic without disruption or delay during peak traffic hours.

B. Hydromulch will be used for site restoration from ROW to ROW line within the project limits and beyond ROW as indicated on plans. One (1) row of full sodding 18-inches wide will be placed behind the curb or sidewalk for the length of the project.

C. The hourly rate to be paid by the Contractor to the City Inspector for Saturday work is $150.00/hour.

D. For water service line connections, the material shall be as follows:

a. Short side shall be copper.

b. Long side shall be EndoPure PE-4710 in sleeve or approved equal.