Summary of Work.pdf

PDF 90 KB Posted

Attached to
Carpet Removal and Installation of Vinyl Planks
Solicitation number
FA282325Q0011
Issued by

About this file

This Statement of Work outlines requirements for carpet removal and vinyl plank installation at Eglin Air Force Base Building 351, rooms 111 and 112. The contractor must remove approximately 1500 SY of existing roll/sheet carpet damaged by water and mold, without disturbing the substrate, and install new Symbiotic 5.0 vinyl planks (6" x 48") with dark grey cove base. The work includes disposal of old materials.

The contractor is responsible for all materials, equipment, labor and personnel needed for the project. Key requirements include meeting NFPA and NEC standards, UFC 3-600-01 specifications, and NFPA 101 Chapter 10 for interior finishes. Special instructions mandate coordination of base passes/security access, provision of escorts if needed, ensuring proper ventilation during work, and providing warranty documentation and maintenance instructions to the COR before invoice payment. No civil, mechanical, HVAC, electrical or communications work is included in the scope. The point of contact is Troy A. Nappier of Torch Technologies at 850-882-1308.

View the file

Other files

File Type Posted
Room 111 112 scaled drawing (004).pdf PDF
Solicitation Amendment FA282325Q00110001 SF 30.pdf PDF
Summary of Work Amendment.pdf PDF
Site Visit (FA282325Q0011).pdf PDF
FA282325Q0011 Questions and Anwser.pdf PDF
Wage Determination 2015-4531.txt TXT text file
Drawings.pdf PDF
Contracting Pricing Form.xlsx XLSX spreadsheet
Solicitation - FA282325Q0011.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CE Work Tasks: #15111334 and #15186130 Project Title: Carpet Removal and Installation of Vinyl Planks; Bldg. 351 rooms 111 and 112 Date: 5 December 2024

SUMMARY OF WORK

1. PURPOSE OF SECTION: The purpose of this section is to provide the Contractor with a Statement of Work for the above mentioned project. The Contractor shall follow the guidelines and Service Summary provided in the PWS of said contract. The Contractor shall seek clarification from the Contracting Officer (CO) if there is any question on the applicability of a provision. These provisions are for the purpose of general information only and are not intended to completely describe the regulations and restrictions that apply on Eglin AFB.

2. PROJECT SCOPE: The project is located on Eglin AFB, Florida. The Contractor shall be required to furnish all materials, equipment, plant, labor and personnel necessary to design, manage, and accomplish this work in accordance with the contract requirements. The Contractor is expected to maintain safety requirements and demonstrate standard construction methods, at all times.

A. The old carpet must be removed due to water and mold damage, and new luxury vinyl planks and cove bases will be installed

B. Contractors shall be responsible for the disposal of the old carpet, vinyl cove base, transition strips and any waste generated by the installation of flooring products.

3. PRINCIPAL FEATURES: Principal features of work are as follows:

A. Civil:

a. None.

B. Architectural:

a. Remove existing roll/sheet carpet. Do not disturb substrate to ensure a smooth and secure bonding surface. (~ 1500 SY)

b. Install new Symbiotic 5.0 vinyl planks, 6” x48” or approved otherwise.

c. Install cove base, dark grey (color will coordinate with vinyl planks)

d. All work shall be in accordance with the latest NFPA and NEC requirements to ensure maximum protection against loss of life and property by fire.

e. Design and installation must meet all UFC 3-600-01 and applicable NFPA

Standards.

f. All interior finishes, contents and furnishings must meet NFPA 101 Chapter 10.

C. Mechanical (HVAC):

a. None

D. Electrical

E. COMMUNICATIONS: (Customer and 96 CS will verify)

F. SPECIAL INSTRUCTIONS:

a. Customer will coordinate base passes and security access

b. Customer will provide escorts if needed.

c. Ensure adequate ventilation and coordination prior to work generating fumes, dust, debris and vibration, prior to the activity.

d. Provide warranty, certificates of compliance plus maintenance/cleaning instructions, as applicable the COR prior to the invoice being paid.

Point of Contact will be: Troy A. Nappier / 36 EWS Facilities Project Manager Torch Technologies 850-882-1308