Subcontractor_Summary_-_Sheltered_.xlsx

XLSX spreadsheet 33 KB Posted

Attached to
Oversized Vehicle Towing
Solicitation number
IFB- 26 - 330
Issued by
Pinellas County, Florida

About this file

This is a Subcontractor Summary Worksheet instruction document from the City of St. Petersburg, Florida, establishing guidelines for subcontractor participation in municipal projects. The worksheet serves as a mandatory submission component with all bids and requires prime contractors to disclose all intended subcontractors, including their names, addresses, contact information, and trade classifications. The document specifies that 80% of the Shelter contract work may be subcontracted, with only first and second-tier subcontractors permitted unless otherwise noted in contract documents. Prime contractors must provide the name and date of the employee completing the form and identify whether subcontractors are Small Business Enterprises (SBEs) or Minority/Women Business Enterprises (MWBEs).

The worksheet establishes strict restrictions on subcontractor changes post-award, permitting substitutions only under specific circumstances including contractor failure to execute agreements, lack of proper licensing, bankruptcy, insolvency, ineligibility, performance failure, unsatisfactory work quality, or substantial project delays. SBE subcontractors used to meet percentage requirements must be replaced with other SBEs unless the prime contractor demonstrates alternative compliance methods. Any requested changes to the subcontractor list must be submitted in writing to the City's Procurement & Supply Management office, specifically to the Contracts Compliance Manager at Stephanie.Swinson@stpete.org. The instructions note that subcontracting restrictions and multiple-tier limitations do not apply to FDOT LAP or federally funded projects.

View the file

Other files

File Type Posted
Oversized_Vehicle_Towing_(Addendum_#2_Revision).pdf PDF
Agreement.pdf PDF
Subcontractor_Summary_Spreadsheet.xlsx XLSX spreadsheet
Light_Construction_Agreement.docx DOCX document
Performance_&_Payment_Bond_.DOCX DOCX document
Public_Construction_Bond.docx DOCX document
Subcontractor_Utilization_Plan.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

City of St. Petersburg
Subcontractor Summary Instructions

WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID

1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.

2. Enter the name of your company in the Prime Contractor field.

3. Enter the name and date of Prime Contractor employee completing this form.

4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.

5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:

A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;

B. Subcontractor is not appropriately licensed to perform the scope of work;

C. Subcontractor becomes bankrupt or insolvent;

D. Subcontractor is ineligible to perform the work on the project;

E. Subcontractor fails or refuses to perform its subcontract;

F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;

G. Subcontractor is substantially delaying or disrupting the progress of the work.

Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.

6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.

7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.

Subcontractor Worksheet

City of St. Petersburg
Subcontractor Summary
Project Name:
Project Number:
Percentage of Contract Which May be Subcontracted: 80% for Shelter Bid
Name of Prime Contractor:Cells below will be "hidden" on the worksheet since they are only for Procurement's use.
Name/Date of Individual Completing this Form:
City of St. Petersburg SBE or MWBE Contractor Yes or NoSubcontractor's Name (Provide complete Legal Name)Subcontractor's Primary Business AddressName/Phone Number and Email Address of Subcontractor's Employee Responsible for Project SupervisionFirst or Second Tier Subcontractor*Trade Classification(s) Being Subcontracted (List One Trade per Line)Subcontract Amount ($)Added (A) Deleted (D)Reason CodeCity Approver/DateAdd (A) and Delete (D) Legend
Example: YesXYZ Contractors, Inc.123 N. Burlington Ave., St. Petersburg, FL 33701Joe Jones - 727-555-555 Email - XYXCon@yahoo.comFirstElectrical13,234.00DBEmployee XYZ/03-01-19A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications;

G. Subcontractor is substantially delaying or disrupting the progress of the work.

Total: 0.00

*Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents.Contract Amount
0.00Amount Allowed to be Subcontracted

&8Rev. January 2020 &10Page 1 of &P

File details come from the government source that posted it. Updated .