This is a Scope of Work (SOW) document for Standing Stone State Park's hazardous tree removal project in Tennessee. The project encompasses the identification, assessment, and removal of hazardous trees throughout the park's 1,800-acre property. The primary objective is to eliminate trees that pose safety risks to park visitors and infrastructure while maintaining the park's natural aesthetics and ecological integrity. The scope includes tree evaluation using industry-standard hazard assessment protocols, selective removal of identified hazardous specimens, debris management and chipping, stump grinding or removal, and site restoration. The contractor must comply with all applicable safety regulations, environmental standards, and park operational requirements. The work is anticipated to be completed within a specified timeframe following contract award, with the successful contractor required to maintain current liability insurance and workers' compensation coverage throughout the project duration.
The contract is funded through Tennessee state park operational budgets and may be subject to Tennessee Procurement Division regulations and guidelines. The contractor must provide detailed pricing for all removal services, equipment rental, labor, and disposal costs on a per-tree or lump-sum basis as specified in the bidding documents. Preference may be given to contractors with demonstrated experience in hazardous tree removal within state park settings and those holding relevant certifications such as ISA (International Society of Arboriculture) credentials. The project prioritizes environmental stewardship alongside visitor safety, requiring contractors to implement erosion control measures and utilize sustainable disposal methods where feasible.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_32701-13970_Amd_1.pdf | ||
| List_of_Trees.pdf | ||
| 32701-13970_T_Cs.pdf | ||
| 32701-13970_Pre-Response_Conf_Memo.pdf | ||
| Standing_Stone_SP_Hazardous_Tree_Removal.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hazardous Tree Removal
Standing Stone State Park
1674 Standing Stone Park Highway
Hilham, Tennessee 38568
This request for bids is for a Contract to furnish all material, equipment, supplies, and labor necessary to remove hazardous trees.
General Conditions
1) On-Site work shall be performed between receipt of signed Contract or Purchase Order and
September 22, 2026, unless a written exception is granted by the Facilities Management
Regional Manager.
2) For this project, the Contractor and applicable subcontractors shall possess an active BC-b(sm), BC-B, BC-C, BC-29, S-Tree Trimming or higher Tennessee Building Contractor license prior to submitting a bid. Failure of the Contractor and applicable subcontractors to provide copies of their appropriate license shall result in the disqualification of the bid. All licenses shall be verified via Tennessee Commerce and Insurance database before project award.
3) The Contractor shall not assign this Contract or enter into a subcontract for this project without prior written approval of Facilities Management. The Contractor’s bid shall include a
Declaration of Intended Use of Subcontractor(s) form that clearly states the intent to use a subcontractor, along with their name and license number. Facilities Management reserves the right to reject a bid in whole or a subcontractor, based upon failure to possess an appropriate active TN builder’s license. After project award, any proposed substitution or addition of a subcontractor shall require written Facilities Management acceptance and approval before being allowed on-site or perform any work under this Contract. All subcontractors are required to have an active TN Building Contractor license for the applicable work to be performed before and throughout the project. Any proposed subcontractor failing to meet these requirements are not allowed to perform work on any portion of this project.
4) All work shall comply with State-approved versions of the IBC, standards, regulations, other applicable codes, and best practices. The Contractor is responsible for all permits and associated fees.
5) Only the Facilities Management Project Manager or Facilities Management Regional Manager can approve any modifications of the specifications or requirements of the project. No additional work shall be authorized unless pre-approved by either the Project Manager or
Regional Manager in writing. Park/Hospitality management and staff are not authorized to make any changes, deletions, or additions to the project or accept any portion of the work.
This Contract shall be modified only by a written agreement signed by all parties. Any work performed outside of the written scope with any written change orders will be the responsibility of the Contractor or others and not Facilities Management. All questions, directives, and acceptance shall come only from either the Facilities Management Regional
Manager and/or Project Manager.
6) The Contractor shall keep the jobsite clean and safe and leave in a neat and tidy manner.
7) All dimensions listed are approximate. The Contractor is solely responsible for verifying actual dimensions prior to bidding. No allowances shall be made due to a bidder neglecting to visit the site and verifying dimensions and conditions.
8) All work performance under this Contract shall be under the full-time direction of the
Contractor. The Contractor shall be responsible for work and performance, and damages of any subcontractors and/or independent contractors or laborers hired in connection with the work under this Contract.
General Scope of Work
Description of Demolition or Associated Work
All debris shall be removed from the park property and disposed of in accordance with all applicable regulations, unless specifically noted.
1) The Contractor shall remove all identified hazardous trees in the Park.
2) The Contractor shall grind the stumps on the identified trees and level the ground, seed and straw in all disturbed areas.
New Work
1) The Contractor shall remove all identified hazardous trees in the Park.
2) The Contractor shall grind the stumps of the identified trees.
3) The Contractor shall smooth all disturbed areas.
4) The Contractor shall seed and straw all disturbed areas.
Specific Instructions
1) The Contractor shall cut and remove one hundred and twenty-one (121)- identified hazardous trees in the Park and dispose of in a designated area on Park property that the
Park staff has chosen.
2) The Contractor shall grind the stumps of twenty-four (24)- identified trees and dispose of shavings at designated area on Park property that the Park staff has chosen.
3) The Contractor shall level, smooth out the ground and spread seed and straw in all disturbed areas.
4) The Contractor shall trim the limbs on five (5) - trees so that they don’t rub the roofs and sides of the buildings and structures that they are close to.
5) The Contractor shall chip up all brush and limbs up to eight (8)-inches in diameter and shall dispose of chips in designated areas on Park property chosen by Park staff.
6) The Contractor shall dispose of all logs in designated areas on Park property chosen by Park staff.
7) The Contractor shall dispose of all other wood from trees in a designated site on Park property chosen by Park staff.
Additional Terms and Conditions
1) All aspects of this job shall be left in a finished condition.
2) The Contractor shall be responsible for determining where all utilities are on the job site and care should be taken to protect the utilities from any damage caused by the tree removal.
This shall include any underground utilities around the job site area. If damage occurs, it shall be repaired within a twenty-four (24)-hour period from the time damage occurs.
3) The Contractor shall perform work on regular time and shall invoice work time and material not to exceed the quoted price. Any variance in quote shall be addressed only with a representative of the Facilities Management Regional Office before any additional work is undertaken or materials ordered.
4) Work shall be scheduled to avoid any interference with normal operation of the Park as much as possible. During the construction period, coordinate construction schedules and operations with the Park Manager. Work shall be conducted during the normal business hours of Monday through Friday, 8:00 a.m. to 4:30 p.m., unless an alternate schedule is approved by Facilities Management.
5) The successful Contractor shall schedule and attend a pre-construction conference where a pre-construction form shall be signed by Facilities Management, Contractor and Park
Manager or Park representative before work can begin. The Contractor shall also schedule and attend a final inspection where a final inspection form shall be signed by Facilities
Management, Contractor and Park Manager or Park representative before final invoice shall be paid.
6) The Contractor shall protect areas adjacent to his work and shall be required to repair any damage they may cause. The Contractor shall protect work of other trades. The Contractor shall correct any painting related damage by cleaning, repairing, or replacing, and refinishing as directed by Facilities Management. The Contractor shall leave residences and other buildings in a habitable manner after hours by securing unfinished openings.
7) Workmanship shall be warrantied for not less than one year from date of final inspection.
8) Clean up of the project site shall be the responsibility of the Contractor. The Contractor shall assure that job site is clean of nails, debris, etc., at end of each day to ensure safety. The
Contractor shall clean up and haul away all scrap when work is completed to an approved location off state property.
9) At all times, the Contractor shall have a copy of project specifications, permits, and Certificate of Insurance on-site.
10) The Contractors and all subcontractors are not authorized to day laborers or temporary labor on this project without the express written permission of Facilities Management.
11) Note: Before the Contract resulting from this Invitation to Bid is signed, the apparent successful proposer shall be registered with the Department of Revenue for the collection of
Tennessee sales and use tax. The State shall not approve a Contract unless the proposer provides proof of such registration. The foregoing is a mandatory requirement of an award of a Contract pursuant to this solicitation.
12) Invoice shall be submitted for payment not before project completion and final project acceptance but also no later than ten (10) days after project completion and acceptance. A copy of the invoice shall be submitted to: Deborah Quist, 160 State Circle, Rocky Top, TN
37769, 865-606-0785, deborah.g.smith@tn.gov.
13) Facilities Management Regional Contacts for this project are:
Regional Manager: Chad Young, 865-606-1551, chad.young@tn.gov
Project Manager: Gary Greenwood, (865) 806-8300, gary.greenwood@tn.gov
Nothing Follows mailto:deborah.g.smith@tn.gov mailto:chad.young@tn.gov mailto:gary.greenwood@tn.gov