A-603 FINISHING SCHEDULE-R2-A-603-A1.pdf

PDF 531 KB Posted

Attached to
KIZAD Warehouse Construction Services Federal contract opportunity
Solicitation number
STC10017R0004
Issued by
Department of State US Embassy Abu Dhabi

About this file

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to KIZAD Warehouse Construction Services, newest first.
File Type Posted
As_Built_-_Steel_1.zip ZIP file
A-108 —
A-401 —
A-601 —
A-407 —
A-108 —
A-403 SERVICE BUILDING-2-R2-A-403-A1.pdf PDF
A-201 —
A-401 STAIRCASE DETAILS-R2-A-401-A1.pdf PDF
A-404 —
A-301 —
A-104 —
A-105 —
A-107 —
A-406 —
A-107 —
A-105 —
A-103 —
A-405 —
A-103 —
A-602 —
A-108 —
A-104 —
A-102 —
A-101 —
A-301 —
A-106 —
A-201 ELEVATIONS-R2-A-201-A1.pdf PDF
A-403 SERVICE BUILDING-2-R2-A-403-A1.pdf PDF
A-105 —
A-107 —
A-003 —
A-105 —
A-103 —
A-407 —
A-105 —
A-201 —
A-104 —
A-106 —
A-403 —
A-001 —
A-301 SECTIONS-R2-A-301-A1.pdf PDF
A-101 —
A-105 —
As_Built_Drawing_-_MEP.zip ZIP file
As_Built_Drawing_-_Structural.zip ZIP file
Municipality_Approved_Drawings.pdf PDF
Municipality_Approved_Drawings.pdf PDF
Warranty_and_Forms.pdf PDF
Synopsis_FBO_Kizad_Fit-out.pdf PDF
Show all 50

KIZAD Warehouse Construction Services has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING TYPE -PHASE-1-TYPE-A1 (GROUND FLOOR)

WAREHOUSE-1A1-G-01 C2F2W2 --

ENTRANCEA1-G-01A --

LOBBYA1-G-01B --

ELECTRIC ROOMA1-G-01C --

KITCHENA1-G-01D

TOILET LOBBYA1-G-01E

TOILETA1-G-01F

TOILETA1-G-01G

WAREHOUSE-2A1-G-02

ENTRANCEA1-G-02A

LOBBYA1-G-02B

ELECTRIC ROOMA1-G-02C

KITCHENA1-G-02D

TOILET LOBBYA1-G-02E

TOILETA1-G-02F

TOILETA1-G-02G

WAREHOUSE-3A1-G-03

ENTRANCEA1-G-03A

LOBBYA1-G-03B

ELECTRIC ROOMA1-G-03C

KITCHENA1-G-03D

TOILET LOBBYA1-G-03E

TOILETA1-G-03F

TOILETA1-G-03G

WAREHOUSE-4A1-G-04

ENTRANCEA1-G-04A

LOBBYA1-G-04B

ELECTRIC ROOMA1-G-04C

KITCHENA1-G-04D

TOILET LOBBYA1-G-04E

TOILETA1-G-04F

TOILETA1-G-04G

WAREHOUSE-5A1-G-05

ENTRANCEA1-G-05A

LOBBYA1-G-05B

ELECTRIC ROOMA1-G-05C

KITCHENA1-G-05D

TOILET LOBBYA1-G-05E

TOILETA1-G-05F

TOILETA1-G-05G

S1

S1

S1

S1

S1

C5F3W3

C3F2W4

C3F2W4

C1F1W1

F1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C3F2W4

C3F2W4

C3F2W4

C3F2W4

C1F1

C1F1

C1F1

C1F1

A1-G-01H --C3F4IT ROOM W4

A1-G-02H --C3F4IT ROOM W4

A1-G-03H --C3F4IT ROOM W4

A1-G-04H --C3F4IT ROOM W4

A1-G-05H --C3F4IT ROOM W4

C1W4

W4

W4

W4

W1

ELECTRIC METER ROOMA1-G-12

L.V ROOMA1-G-13

TRANSFORMER ROOMA1-G-14

SWITCH ROOMA1-G-15

ELECTRICAL ROOMA1-G-16

W4 --C4F2

W4 --C4F2

W4 --C4F2

W4 --C4F2

W4 --C4F2

BUILDING TYPE -PHASE-1-TYPE-A1 (GROUND FLOOR)

WAREHOUSE-11A1-G-11

ENTRANCEA1-G-11A

LOBBYA1-G-11B

ELECTRIC ROOMA1-G-11C

KITCHENA1-G-11D

TOILET LOBBYA1-G-11E

A1-G-11F

A1-G-11G

S1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C3F2W4

F1W4

FEMALE TOILET

MALE TOILET

A1-G-11H

WAREHOUSE-9A1-G-09

ENTRANCEA1-G-09A

LOBBYA1-G-09B

ELECTRIC ROOMA1-G-09C

KITCHENA1-G-09D

TOILET LOBBYA1-G-09E

A1-G-09F A1-G-09G

S1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C3F2W4

C1F1W4

FEMALE TOILET

MALE TOILET

A1-G-09H --C3F4IT ROOM W4

WAREHOUSE-6A1-G-06

ENTRANCEA1-G-06A

LOBBYA1-G-06B

ELECTRIC ROOMA1-G-06C

KITCHENA1-G-06D

TOILET LOBBYA1-G-06E

TOILETA1-G-06F

TOILETA1-G-06G

WAREHOUSE-7A1-G-07

ENTRANCEA1-G-07A

LOBBYA1-G-07B

ELECTRIC ROOMA1-G-07C

KITCHENA1-G-07D

TOILET LOBBYA1-G-07E

TOILETA1-G-07F

TOILETA1-G-07G

WAREHOUSE-8A1-G-08

ENTRANCEA1-G-08A

LOBBYA1-G-08B

ELECTRIC ROOMA1-G-08C

KITCHENA1-G-08D

TOILET LOBBYA1-G-08E

TOILETA1-G-08F

TOILETA1-G-08G

S1

S1

S1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C3F2W4

C3F2W4

C3F2W4

C1F1

C1F1

C1F1

A1-G-06H --C3F4IT ROOM W4

A1-G-07H --C3F4IT ROOM W4

A1-G-08H --C3F4IT ROOM W4

W1

W4

W4

WAREHOUSE-10A1-G-10

ENTRANCEA1-G-10A

LOBBYA1-G-10B

ELECTRIC ROOMA1-G-10C

KITCHENA1-G-10D

TOILET LOBBYA1-G-10E

A1-G-10F

A1-G-10G

S1

C2F2W2

C5F3W3

C3F2W4

C1F1W1

C1F1W1

C1F1W1

C3F2W4

C1F1W4

FEMALE TOILET

MALE TOILET

A1-G-10H --C3F4IT ROOM W4

C1

--C3F4IT ROOM W4

BUILDING TYPE -PHASE-1-TYPE-A1 (MEZZANINE FLOOR)

OFFICE-1A1-M-01 C2F2W5 --

OFFICE-2A1-M-02 --

C2F2W5

OFFICE-3A1-M-03 C2F2W5

OFFICE-4A1-M-04

OFFICE-5A1-M-05

OFFICE-6A1-M-06

OFFICE-7A1-M-07

OFFICE-8A1-M-08

W5

W5

W5

W5

W5

F2

F2

F2

F2

F2

C2

C2

C2

C2

C2

--OFFICE-9A1-M-09 W5 F2 C2

--OFFICE-10A1-M-10 W5 F2 C2

--OFFICE-11A1-M-11 W5 F2 C2

W1

FINISHES LEGEND

F1

C1

SANDWICH PANEL AS PER SPECS.C2

EXPOSED BLOCK WALLW2

SMOOTH POWER FLOATEDF2

F3

300 X 300MM DARK GREY FLOOR TILE

600X600MM PERFORATED METAL CEILING TILE.

300 X 300MM DARK GREY WALL TILE

TEXTURED MATT FINISH OVER PLASTERW3

EMULSION PAINT WITH TOP COAT OVER PLASTERW4

C4

MEZZANINE DECKING PANELC3

PAINT APPLIED ON CONCRETE SURFACE

EMULSION PAINT OVER GYPSUM BOARD / DRYWALLW5

C5 ALUMINUM COMPOSITE PANEL

S1

ANTISTATIC FLOOR FINISHF4

300 X 100MM DARK GREY FLOOR TILE

NON SLIP BLACK GRANITI TEXTURED TILE

(FOR ENTRANCE, RISER & TREAD)

Project Name And

Location

Main Contractor

Design Consultant

Owner Name

DESCRIPTION DATENO.

INDUTRIAL ZONE AREA A-

KIZAD PRE BUILT WAREHOUSES

KHALIFA PORT & INDUSTRIAL ZONE (KPIZ)

PLOT No. 8 - SECTOR No. KH1A9 - ABU DHABI

PROJECT ID No. 46300

WSP MIDDLE EAST, P.O.BOX 112046

ABU DHABI, UAE

TEL: +971 2 667 3875 FAX: +971 2 667 3876

CHECKED BY

PREPARED BY

WSP

Reviewed / Approved

MIDDLE EAST,

ABU DHBAI,

A1

DETAIL DESIGN DRAWING

Drawing No.

Drawing Status

Revision

Sheet Number Paper SizeScale

Drawing Title

G + M WAREHOUSE

Project Description

WE, SYSTEM CONSTRUCT, VERIFY THAT THIS CONTRACTOR'S

DOCUMENT

HAS BEEN PRODUCED AND CHECKED IN ACCORDANCE

WITH CONTRACTOR'S QUALITY ASSURANCE PLAN

IS OF A STANDARD THAT WILL ENABLE THE EMPLOYER

TO ACCEPT IT IN ACCORDANCE WITH THE CONTRACT.

COMPLIES WITH ALL REQUIREMENTS OF THE CONTRACT.

FOLLOWING DEVIATIONS TO CONTRACT ARE REFERENCED FOR

WHICH A DISPENSATION HAS BEEN ACCEPTED BY THE EMPLOYER:

NIL

OTHER RELATED LETTERS/CTIs WHICH DOCUMENT

CLARIFICATIONS ASSOCIATED WITH THIS DOCUMENT ARE LISTED

BELOW:

NIL

CONTRACTOR'S PROJECT MANAGER:

PM NAME SIGNATURE DATE

NOTES:

DOCUMENT STATUS STAMP

THE STATEMENT "WORK MAY PROCEED" APPLIES TO THE

FOLLOWING WORK ACTIVITIES ASSOCIATED WITH THE MATTERS

CONTAINED WITHIN THE CONTRACTOR'S DOCUMENT:

CONSTRUCTION

WORK MAY PROCEED

REVISE & RESUBMIT. WORK MAY PROCEED

SUBJECT TO INCORPORATION OF

COMMENTS INDICATED

REVISE & RESUBMIT. WORK MAY NOT

PROCEED

REVIEW NOT REQUIRED. WORK MAY

PROCEED

CODE 1

CODE 2

CODE 3

CODE 4

ANY REVIEW, COMMENT OR ACCEPTANCE BY EMPLOYER UNDER

THIS CONTRACT WITH RESPECT TO ANY OF CONTRACTOR'S

DOCUMENTS SHALL NOT IN ANY WAY BE, OR DEEMED TO BE, AN

APPROVAL OF ANY WORKS OR AN ACCEPTANCE THAT THE

CONTRACTOR'S DOCUMENTS MEET THE REQUIREMENTS OF THE

CONTRACT, AS CONTRACTOR HAS THE SOLE RESPONSIBILITY FOR

PERFORMING THE WORKS IN ACCORDANCE WITH THE

REQUIREMENTS OF THIS CONTRACT.

ABU DHABI PORTS COMPANY DATE

ARCHITECTURAL

FINISHING SCHEDULE (TYPE - A1)

A-603