This Statement of Work is issued by the Oregon Department of Corrections for a fire alarm system upgrade and replacement project at Coffee Creek Correctional Facility in Wilsonville, Oregon. The project encompasses the complete demolition, replacement, installation, programming, testing, and commissioning of new addressable fire alarm systems throughout the Medium Security Facility, Minimum Security Facility, and all Support Facilities. The contractor shall furnish all labor, materials, equipment, tools, transportation, supervision, project management, and documentation necessary for system completion. The new systems will utilize Potter AFC-1000E-based addressable fire alarm systems with full fiber-optic interconnection and PotterNet supervising stations. All work must comply with 2025 OSSC, 2026 OESC, 2024/2025 NFPA 72, NFPA 70, NFPA 101, and applicable DOC security requirements. The project includes specific phasing for submittals, preparation, Minimum Facility installation, Medium Facility installation, Support Facilities installation, inspections, and closeout.
The contractor is responsible for all demolition and restoration work, new system installation including fiber optic cabling with SC connectors and mandrel testing, wiring and raceways per Division 26 & 28 specifications, comprehensive testing and commissioning per NFPA 72, and complete documentation including shop drawings, as-built drawings, and addressing schedules. All work must be performed by licensed electricians and limited energy technicians, with fire alarm programming conducted by certified technicians. The contractor must provide two staff training sessions covering system operation, troubleshooting, and maintenance, and shall provide a minimum 36-month warranty on all fire alarm components issued in the name of the Oregon DOC. Payment shall be based on an approved schedule of values with verified work progress and stored materials. The contractor is required to maintain a safe environment, provide background-checked staff, submit daily work logs, coordinate with DOC following escort protocols, and maintain facility security throughout the project duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Check Off sheet ITB~19.pdf | ||
| 18287_ITB_GTC_SGC.pdf | ||
| 18287 ATTACHMENT C PLANS.pdf | ||
| 18287 ATTACHMENT B SPECIFICATIONS .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Coffee Creek Correctional Facility
24499 SW Grahams Ferry Road, Wilsonville, OR 97070 Fire Alarm System Upgrade & Replacement Project
1. PROJECT OVERVIEW
The Oregon Department of Corrections (DOC) is replacing the existing fire alarm systems across the Coffee Creek Correctional Facility. The project includes the complete demolition, replacement, installation, programming, testing, and commissioning of new addressable fire alarm systems throughout the Medium Security Facility, Minimum Security Facility, and all Support Facilities. The new systems will be Potter AFC-1000E–based addressable fire alarm systems with full fiber-optic interconnection and PotterNet supervising stations. All work shall comply with 2025 OSSC, 2026 OESC, 2024/2025 NFPA 72, NFPA 70, NFPA 101, and applicable DOC security requirements.
2. SCOPE OF WORK
The Contractor shall furnish all labor, materials, equipment, tools, transportation, supervision, project management, and documentation necessary for a complete and operational fire alarm system replacement across all identified buildings, including Medium, Minimum, and Support Facilities.
2.1 Demolition
Remove all existing FACP equipment, NAC panels, notification appliances, initiating devices, wiring, modules, and hardware. Maintain existing systems until cutover. Restore all penetrations with approved firestopping. Maintain fire watch as required.
2.2 New System Installation
Install new Potter AFC-1000E FACPs, PotterNet Supervising Stations, smoke, heat, CO, combination detectors, pull stations, duct detectors, AV appliances, monitor modules, relay modules, isolation modules, NAC power supplies, conduit, wiring, fiber optic cabling, junction boxes, and mounting accessories. All installations must comply with Division 26 & 28.
2.3 Fiber Optic Network
Install new OS2 single-mode fiber between network nodes as shown on drawings. Provide SC connectors, new PVC-40 conduit routes, and complete mandrel testing before installation.
2.4 Wiring & Raceways
Provide EMT with compression fittings indoors and GRC below 8 feet or as required.
Conduit sizing shall comply with specifications. Provide pull boxes, junction boxes, and supports per Division 26/28 requirements.
2.5 Cutover & Phasing
Execute work according to project phasing including submittals, preparation, Minimum Facility, Medium Facility, Support Facilities, inspections, and closeout. Coordinate all outages with DOC, follow escort protocols, and maintain facility security.
2.6 Testing & Commissioning
Perform 100% testing per NFPA 72, including SLC testing, voltage drop testing, NAC synchronization, integration with mechanical systems, and AHJ-witnessed acceptance.
2.7 Documentation
Provide shop drawings, product data, O&M manuals, as-built drawings, addressing schedules, and testing reports. All submittals must meet Division 26 & 28 requirements.
3. CONTRACTOR RESPONSIBILITIES
Maintain safe environment, provide background-checked staff, submit daily work logs, coordinate with DOC, protect property, and maintain continuous as-built documentation.
4. SUBMITTAL REQUIREMENTS
Submit all product data, shop drawings, calculations, and system documentation in accordance with Division 26 & 28. Deferred submittals include seismic bracing and anchoring.
5. QUALITY CONTROL
All work must be completed by licensed electricians and limited energy technicians. Fire alarm programming shall be performed by certified technicians. Contractor must comply with NEC, NFPA 72, OESC, OSSC, and DOC regulations.
6. TRAINING REQUIREMENTS
Provide two staff training sessions, covering system operation, troubleshooting, and maintenance. Provide recorded training if required.
7. CLOSEOUT REQUIREMENTS
Provide final as-builts, test reports, device logs, AHJ approval, warranty documents, spare parts, and labeling per Division 26 05 53.
8. WARRANTY
Contractor shall provide a minimum 36-month warranty on all fire alarm components, including parts and labor. Warranty must be issued in the name of the Oregon DOC.
9. PERFORMANCE PERIOD
All project phases shall follow durations specified in Division 26 Section 1.5, including submittals, preparation, installation phases, inspections, and final closeout.
10. PAYMENT & PRICING
Payment shall be based on approved schedule of values, verified work progress, and stored materials. No additional compensation without written approval. Fire watch coordination shall be provided by the Owner.
| 1. PROJECT OVERVIEW |
| 2. SCOPE OF WORK |
| 2.1 Demolition |
| 2.2 New System Installation |
| 2.3 Fiber Optic Network |
| 2.4 Wiring & Raceways |
| 2.5 Cutover & Phasing |
| 2.6 Testing & Commissioning |
| 2.7 Documentation |
| 3. CONTRACTOR RESPONSIBILITIES |
| 4. SUBMITTAL REQUIREMENTS |
| 5. QUALITY CONTROL |
| 6. TRAINING REQUIREMENTS |
| 7. CLOSEOUT REQUIREMENTS |
| 8. WARRANTY |
| 9. PERFORMANCE PERIOD |
| 10. PAYMENT & PRICING |