Statement of Work (SOW).pdf

PDF 578 KB Posted

Attached to
Fort Bliss B2903 Kitchenette (Amendment 3)
Solicitation number
W911RX-26-B-A004
Issued by

About this file

This is a Statement of Work (SOW) for a kitchenette installation project at Building 2903, Fort Bliss, Texas, issued by the Directorate of Public Works Engineering Services Division under Work Order 11B 10112 6P as of May 7, 2006.

The project scope includes installation of new upper and lower cabinets, a kitchen island, countertops, backsplash, water fountain, sink and faucet, kitchen hoods, Ansul suppression system, and electrical outlets for appliances. The contractor must provide all labor, materials, and services to complete the work within 120 calendar days of the Notice to Proceed, with liquidated damages assessed at $1,717.24 per calendar day for overruns. Work will be performed in an occupied facility at the intersection of Cassidy Road and Carrington, requiring coordination with building occupants. The contractor must comply with current International Code Council (ICC) standards, Unified Facilities Criteria (UFC), NFPA 101 Life Safety Code, and the Architectural Barriers Act (ABA).

Key contractual requirements include designation of a Project Manager, Superintendent, Site Safety and Health Officer, and Quality Control Manager, all with specified experience thresholds of five years. The contractor must submit extensive pre-construction and construction submittals including an Accident Prevention Plan, Activity Hazard Analysis, construction schedule, quality control plan, environmental permits, and material submittals within prescribed timeframes. The work encompasses architectural finishes (oak cabinetry with specific stain, mineral fiber ceiling tiles, interior latex paint), mechanical/plumbing systems (stainless steel sink, faucet, kitchen hood with ductwork), electrical circuits for receptacles and ranges, and fire protection systems. Close-out deliverables include as-built drawings, warranty documentation, O&M manuals, and certifications of asbestos-free construction, with final payment pending approval of all documentation within 30 days of final inspection.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Directorate of Public Works Engineering Services Division

Fort Bliss, Texas

STATEMENT OF WORK

Install Kitchenette at B2903

WO# 11B 10112 6P 07 May 2006

Controlled Unclassified Information (CUI)

STATEMENT OF WORK WO# 11B 10112 6P

Table of Contents

PART 1 - DESCRIPTION OF WORK

1.1. Objectives

1.2. Period of Performance

1.3. Place of Performance

1.3.1. Occupancy:

1.4. Specific Work Requirements

1.4.1. General Requirements

1.4.2. Hazardous Materials Requirements

1.4.2. Civil

1.4.2. Architectural

1.4.3. Structural

1.4.4. Fire Protection

1.4.5. Electrical

1.4.6. Mechanical/Plumbing/HVAC

1.4.7. Telecommunications

1.5. Attachments

PART 2 - GENERAL REQUIREMENTS

2.1. Basic Guidelines

2.1.1. Preconstruction Conference

2.1.2. Construction Documents

2.1.4. Contractor Furnished Items

2.1.5. Installation Property

2.1.6. Contractor Vehicles

2.1.7. Buy American Act. Construction Materials

2.2. Key Personnel

2.2.1. PM

2.2.2. Superintendent

2.2.3. SSHO

2.2.4. QCM

2.3. Utilities

2.3.1. Utilities Cutovers and Interruptions

2.3.2. Portable Latrines

2.4. Hours of Operation

2.4.1. Normal Work Hours

2.4.1.1. Federal Government Holidays

2.4.2. Approval of Work Outside Normal Work Hours

2.6. Historical Properties

2.7. Environmental

2.7.1. Permits

2.7.5. Construction Waste Management and Disposal

2.7.5.1. Salvage, Waste, and Disposal

2.7.6. Natural Resources Program

2.7.7. Pollution Prevention Act (PPA)

2.7.8. Noise Control

2.8. Safety

2.8.1. Accident Prevention Plan (APP)/Safety Plan

2.8.2. Activity Hazard Analysis (AHA)

2.8.3. Army Radiation Permit

2.8.5. Hot Work Permit

2.9. Quality Control (QC)

2.9.1. QC Program Requirements

2.9.2. QCM

2.9.3. Contractor Quality Control (CQC) Plan

2.9.4. Contractor Quality Control Meetings

2.9.5. Contractor Quality Control Inspections

2.10. Security

2.10.1. Security Requirements

2.10.2. Physical Security

2.10.3. Key Control

2.10.4. Security of Classified Items, Systems and Information

2.10.5. Security of Staging Area

2.10.6. Antiterrorism / Operations Security (AT-OPSEC)

2.11. Submittals/ Deliverable Requirements

2.11.2. Pre-Construction Submittals / Deliverables Package

2.11.3. Construction Submittals/Deliverables Package

2.11.3.7. Close-out Submittals / Deliverables Package

PART 3 - APPLICABLE PUBLICATIONS AND FORMS

3.1. Applicable Publications

PART 1 - DESCRIPTION OF WORK

1.1. Objectives. Install kitchenette at B2903. Work includes the installation of new upper and lower cabinets, kitchen island, countertops, backsplash, water fountain and sink and faucet. Also, the installation of kitchen hoods, Ansul suppression system, electrical outlets for above the counter, refrigerator and ranges. The Contractor shall provide all work, labor, materials, related fees, and related services for construction requested herein until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract, by the Government in a professional and collaborative environment to sustain mission requirements. Construction services and finished products shall be delivered on schedule, safely, and compliant with regulatory codes and standards.

1.2. Period of Performance. The period of performance shall be One hundred and twenty (120) calendar days after issuance of Notice to Proceed (NTP). The POP includes time required to complete the submittals shown on section 2.10. Work beyond the established POP without proper justification will result in liquidated damages being applied to the project in the amount of $1,717.24 US dollars per calendar day.

1.2.1. The Contractor shall not commence work unless authorized by the Contracting Officer (KO).

All technical questions shall be addressed to the Contracting Officer’s Representative (COR) for resolution and clarification.

1.3. Place of Performance. The work to be performed under this contract will be performed in building 2903, in the vicinity of Cassidy Rd and Carrington intersection, located within the Fort Bliss TX Installation.

1.3.1. Occupancy: Facility will be occupied during construction. Do not enter the facility without prior approval of the KO.

1.3.2. All work shall adhere to and comply with the most current International Code Council (ICC), the Unified Facilities Criteria (UFC) https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc [military amended codes], NFPA 101 Life Safety Code, the Architectural Barriers Act (ABA) and all other Local, State and Federal Regulations, Codes, and Standards. All Unified Facilities Guide Specifications (UFGS) shall be used for this project (https://www.wbdg.org/guides-specifications).

1.4. Specific Work Requirements.

1.4.1. General Requirements.

1.4.1.1. The Contractor shall utilize all construction documents to ensure that all construction deliverables and resources are provided to the Government. Construction documents include, but not limited to, statement of work, construction drawings, specifications, amendments, requests for information (RFIs) modifications and change orders. Please refer to the drawings for location and room finishes.

1.4.1.2. Contractor shall ensure safe access to and egress from building and other adjacent occupied or used facilities during construction and shall provide all required barricades, fencing, covered walkways, planking, lighting, bracing, shoring, warning signs, etc. as required by OSHA and Fort Bliss Regulations for the protection of workmen, staff and Users.

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/guides-specifications https://www.wbdg.org/guides-specifications

1.4.1.3. Contractor shall field verify all existing conditions, dimensions, exact locations and quantities before commencing Work. Contractor shall examine existing structures, note all conditions as to character and extent of all work involved, validate and Bid accordingly.

1.4.1.4. Contractor shall protect the building, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from restoration operations. The contractor shall restore any items disturbed or damaged during construction to a condition equal or better than existing at no cost to the government.

1.4.1.5. Contractor shall comply with all local, state, and federal codes, ordinances, and regulations applicable for this project. Contractor shall file and secure all applicable permits and approvals.

1.4.1.6. Pollution Control: Comply with DPW Environmental regulations. Limit spread of dust and debris. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

1.4.1.7. All work is subject to inspection and testing by the Government at all places and at all reasonable times before acceptance, in accordance with FAR 52.246-12, Inspection of Construction. Government inspections and tests do not relieve the Contractor of the responsibility for providing adequate quality control measures, nor does it constitute or imply Government acceptance of the work. The presence or absence of a Government inspector does not relieve the contractor of complying with the specified requirements, nor is the Government inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

1.4.1.8. Daily Clean Up. The Contractor shall clean the work site daily. The Contractor shall maintain a clean work area, free of construction debris. The cleanup of the work site shall include, but not limited to, the removal of scrap (waste materials), spoils, debris, and salvage material that results from work on this project.

1.4.1.9. Final Clean up. The project area shall be cleaned and free of debris by the Contractor before

Final Inspection.

1.4.1.10. The Contractor shall obtain and submit the latest written Site Clearance and Line Markings Permit (SCLMR), if applicable, prior to any ground disturbance. This is an extended process and should be submitted soon after Contract is awarded. See section 2.11.2.10. for more information.

1.4.2. Hazardous Requirements.

1.4.2.1. Review the attached surveys for all asbestos and lead-containing materials to verify if they will be impacted by this project. If the project scope includes disturbing asbestos or lead-containing materials, work must be conducted by a Licensed Abatement Company. If additional materials, not tested in these surveys, need to be disturbed, they must first be tested for asbestos and lead.

Contact DPW-ED for additional testing. Failure to manage present hazardous materials may expose workers, building occupants, and their families to toxic substances, which include carcinogens.

1.4.3. Civil. Not Applicable

1.4.4. Architectural.

1.4.4.1. Remove existing mini blinds. Provide and install 2-inch vinyl slat cordless mini blinds, mounting hardware and all operating components. Color white. Contractor shall verify window dimensions prior to ordering.

1.4.4.2. Provide and install backsplash tiles, 4-1/4 inches x 12-3/4 inches, semi-gloss, Daltile Modern Dimension 0190 Artic White with running bond installation or approved equal. Provide laticrete spectrallock Pro Premiunm Grout in Bright White.

1.4.4.3. Provide continuous waterproof silicone sealant, mildew resistant, approved by the countertop manufacturer.

1.4.4.4. Remove existing countertop. Provide and install 1-inch thick solid surface countertop with 4-inch backsplash, quartz agglomerate material, homogenous filled solid polymer, not coated, laminated or of a composite construction. Color as available from manufacturer's standard color range, provide color chips and/or samples for review. Straight or quarter round edge profile.

Color to be determined during submittal review.

1.4.4.5. Remove existing cabinets. Provide and install new 12-inches deep wood wall cabinets and 24-inches deep wood base cabinet. Oak wood, with medium stain, color to be determined during submittal review. All plywood carb compliant box construction. Solid 1/2-inch thick engineered wood for back and sides. Solid Oak door frame with sturdy 1/2-inch thick oak center panel.

Shaker doors with 3-inches wide frames and flat recessed center panels. 3/4-inch thick plywood adjustable shelves with clear high strength locking shelf supports for added strength. Concealed high quality steel door hinges. Two (2) door bumpers per door/drawer. Provide 3-inches satin nickel bar in all wall cabinets, base cabinets and drawers. Two (2) full depth adjustable shelves for wall cabinets and one (1) half depth adjustable shelf for base cabinet. All base cabinets will have a drawer with full access hidden glides system. Provide two (2), four (4) drawer base cabinets. Toe kick to match finish. Contractor to ensure that existing walls can support new cabinets. Wood Stain Color: Minwax ‘Heirloom Oak’ MW 441 or approved equal.

1.4.4.6. Provide and install kitchen island, 10-FT x 4-FT, with a 24-inches wood base. Oak wood, with medium stain, color to be determined during submittal review. Match cabinets stain.

1.4.4.7. Provide cabinet shop drawings for review, including plan views, elevations, sections and attachment details. Show large-scale details. Show dimensions and locations and sizes of furring, blocking, and hanging strips.

1.4.4.8. Remove existing ceiling tiles. Provide and install 2-FT x 2-FT, 5/8-inches thick, fire rated mineral fiber acoustic ceiling panels. Armstrong “Kitchen Zone” 672 or approved equal. Include wire hangers, fasteners, main runners, cross tees, wall angle moldings. 30-year performance guarantee & warranty. Ceiling grid to remain. Modify grid as needed to accommodate new kitchen cabinets, range hood and any other equipment.

1.4.4.9. Paint walls, ceiling, moldings, windows, etc. One coat of primer and two coats of interior latex paint. Semi-gloss finish for kitchen area and eggshell finish for the rest of the rom. Prior to painting, ensure surfaces are free from dirt and dust and dry, repair joints, cracks, holes, surface irregularities, and other minor defects with patching plaster or spackling compound and sand smooth. Following completion of painting, reinstall removed items. Match existing color.

1.4.4.10. Electrical ranges and refrigerator will be provided by the government.

1.4.5. Structural. Not Applicable

1.4.6. Fire Protection.

1.4.6.1. Provide and install fire extinguisher and cabinet, Fire extinguisher and cabinet shall be installed

IAW the most current editions of UFC 3-600-01, NFPA 10 Standard for Portable Fire Extinguishers, NFPA 1 and NFPA 101 Life Safety Code. Fire extinguisher cabinet shall be of all metal construction and the unlocked type to accommodate 10lb ABC extinguisher as per NFPA 10, 2022 edition or most current edition available. FBFES request fire extinguishers with a rating of 4-A: 60 B: C (10#) for all installations. Extinguisher cabinets shall not have glass or be lockable.

1.4.6.2. Contractors shall review the Fire Prevention Construction Guide 2025 prior to construction work.

1.4.7. Electrical.

1.4.7.1. All electrical work must be completed by a licensed technician. Technicians must be licensed/certified in the state of Texas. Contractor to verify breaker capabilities before adding new load.

1.4.7.2. All new circuits to be derived from panel in hallway, label panel schedule.

1.4.7.3. Provide and install new 20A feeder for new above the counter receptacles w/GFCI at sink counter.

New 20A single pole breaker. New 120V 20A duplex receptacles, 6” above counter sink. One receptacle w/GFCI and feed downstream.

1.4.7.4. Provide and install new 20A feeder for new above the counter receptacles w/GFCI at ranges counter. New 20A single pole breaker. New 120V 20A duplex receptacles, 6” above counter. One receptacle w/GFCI and feed downstream.

1.4.7.5. Provide and install new 20A feeder for refrigerator receptacle w/GFCI. New 20A single pole breaker. New 120V 20A duplex receptacles, 18” A.F.F. at refrigerator location.

1.4.7.6. Provide and install new NEMA-14 125/250V 50A receptacle, 18 AFF, at range locations. Two

(2) new 50A 2-pole breakers. 50A feeders.

1.4.7.7. Provide new range control contactors above ceiling, as accessible. Feed range receptacles.

1.4.7.8. Provide new 120V 20A duplex receptacle inside cabinet space above each range hood. New 20A single pole breaker, 20A feeder for both hoods.

1.4.7.9. Interconnect range hood fire suppression system with building fire alarm system zone for the respective floor. Verify interconnection point/method with fire alarm maintenance contractor.

1.4.7.10. Derive the 120V control circuit for the range control contactors and fire suppression system from the range hood feeder. Install metal junction boxes, as required. Control circuit for range control contactors fed from relay/switch of fire suppression system control. Operation: Range hood fire suppression system activated, range control contactor opens and power cut off to range.

1.4.7.11. Feeders:

20A - 3 - #12 1/2” C (or as required) 50A - 3 - #6 3/4” C

1.4.7.12. Provide and install range control contactor. Full voltage contactor, 2-pole (min), 240 V (min), 50A

(min) continuous current rating. 120V coil, NEMA-1 Enclosure.

1.4.7.13. Conductors to be CU. THHN-THWN. Conduit to be EMT w/compression fittings only, flexible metal conduit where required. Metal outlet/junction boxes only. Feeders to be run above existing suspended ceiling.

1.4.7.14. All new receptacles flush mounted. Anchor boxes to studs/framing. Cut out drywall where required. Patch and paint drywall to match existing.

1.4.7.15. Firestop at all; wall penetrations, where required.

1.4.7.16. All new receptacle plates to be labeled with panel name and circuit breaker number for corresponding circuit.

1.4.8. Mechanical/Plumbing/HVAC.

1.4.8.1. Remove existing kitchen sink. Provide and install new kitchen sink. Top mounted, single compartment, 20 gage stainless steel with integral mounting rim for flush installation, minimum dimensions of 30-inches wide by 21-inches, with undersides fully sound deadened, with supply openings for use with top mounted washerless sink faucet with hose spray and 3.5 -inch drain outlet. Provide stainless steel drain outlets and stainless-steel cup strainers. Provide separate 1.5 -inch p-trap and drain piping to vertical vent piping from each compartment.

1.4.8.2. Remove existing sink faucet. Provide and install top mounted washerless sink faucet with hose spray. Water flow rate must not exceed 2.2 gpm when measured at a flowing water pressure of 60 psi. Provide aerator with faucet. Faucet color brushed nickel.

1.4.8.3. Provide new kitchen hood as specified in the drawings and schedules. Kitchen hood exhaust shall be ducted from the exhaust of the hood through cabinets to the vent on the exterior wall as shown in the drawings. Ductwork shall be of industrial grade. Ensure range hood functions properly. Patch and paint wall as needed.

1.4.8.4. Provide new eight (8) inch round duct connected to range hood through wall to the new wall vent for exterior exhaust as specified in the drawings. Wall vent shall meet size and airflow requirements of the kitchen hood and accompanying ductwork. Finish the wll vent to match the exterior wall of the building or as specified by the government representative.

1.4.8.5. Provide new Ansul fire suppression system with kitchen hood. Ansul system shall meet all applicable codes and regulations. System shall be connected to the building fire alarm system.

All Fire alarm, fire suppression, and mass notification modifications and additions must be approved by Fort Bliss Fire Department (FBFD) prior to starting installation. FBFD must also test and certify all affected systems prior to project completion.

1.4.8.6. Remove existing water fountain. Provide and install drinking fountain with bottle filling station.

Elkay ezH20 Bottle Filling Station and Single ADA Cooler Non-Filtered Refrigerated Light Gray Model # EZS8WSLK or approved equal.

1.4.9. Telecommunications. (if/as applicable)

1.4.9.1. Furnish incidental work and materials to disconnect, remove, store, secure, protect, and reinstall applicable roof telecommunication equipment, connections, and features. Protect temporary terminations. Any communication cable either Fiber or Copper coming in aerially into the building will need to be decommissioned, prevented from being damaged, and re-installed per the current Installation Information Infrastructure Architecture (I3A) and UFC Army regulations and standards. Any damage or cut cables will be reported to The Project Manager Network Enterprise Center (NEC). Operations & Plans Branch via the COR.

1.4.9.2. If any communication lines need to be moved, please do so IAW I3A and UFC standards. If any communication lines, equipment, or hardware is disturbed, it will need to be reinstalled IAW the most current 3 UFC 580-01 Information Technology Infrastructure Planning and Design.

1.4.9.3. Current I3A Army Communication Standards 2010. All installed communication wires, cables, equipment, racks, and cabinets shall be properly grounded and labeled. Data jacks to be tested and results sent to the NEC Plans office for review and approval the same is for all fiber termination.

Fiber test results to be reviewed and approved prior to communication installation is approved and accepted for turnover. Fiber Fusion Splicer Technician certifications shall be provided to the NEC Plans office for review prior to any fiber termination or work to be started.

1.4.9.4. If any communication lines need to be moved, please do so IAW I3A and UFC standards. If trenching or marking is required, please submit requests to usarmy.bliss.106-sig-bde.mbx.nec-dig-permits@mail.mil as NEC is not tied in with 811. Please contact the Network Enterprise Center (NEC) before disturbing any communications equipment the contractor may come across (network switches, fiber lines, etc.). Please do not dispose of any communications equipment the contractor may come across. Please request a site visit by the NEC NLT 7 days prior to work start date and NLT 7 days prior to project completion to ensure surveys and inspections ensuring communication lines are operational. If fiber needs to be pulled through duct banks, please ensure pathways have been checked and cleared. Please ensure the Contractor(s) hold all required industry recognized certifications (Fiber Splicing, Confined Spaces, BICSI, etc.). Please report any damage to any communication equipment, cables, infrastructure, data drops, data jacks, etc., to the Fort Bliss NEC at (915) 568-7526

1.5. Attachments.

A. Environmental Review Form B. ESD-RFI Template C. Drawing sets D. Eng_Form_4288-R, Submittal Register Form E. Fort Bliss Fire Prevention Construction Guide 2025 F. iWatch Training for Contractors G. TRADOC Form 928-R-E, Material Approval Submittal Form mailto:usarmy.bliss.106-sig-bde.mbx.nec-dig-permits@mail.mil mailto:usarmy.bliss.106-sig-bde.mbx.nec-dig-permits@mail.mil

H. Specifications: All Unified Facilities Guide Specification (UFGS) shall be used for this project including but not limited to those listed below. All specifications can be found at https://www.wbdg.org/guides-specifications)

UFC 3-110-03 ROOFING, WITH CHANGE 5

UFGS 01 45 00.00 20 QUALITY CONTROL (HVAC)

UFGS 01 45 00.00 40 QUALITY CONTROL (PROCESS)

UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

UFGS 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

UFGS 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

UFGS 01 75 00.00 40 STARTING AND ADJUSTING

UFGS 01 78 00 CLOSEOUT SUBMITTALS

UFGS 02 41 00 DEMOLITION AND DECONSTRUCTION

UFGS 02 82 00 ASBESTOS

UFGS 02 83 00 LEAD REMEDIATION

UFGS 06 10 00 ROUGH CARPENTRY

UFGS 06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINET

UFGS 06 61 16 SOLID SURFAVE FABRICATIONS

UFGS 07 92 00 JOINT SEALANTS

UFGS 09 29 00 GYPSUM BOARD

UFGS 09 51 00 ACOUSTICAL CEILINGS

UFGS 09 90 00 PAINTS AND COATINGS

UFGS 22 00 00 PLUMBING GENERAL PURPOSE

UFGS 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

UFGS 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

UFGS 26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

https://www.wbdg.org/guides-specifications)

PART 2 - GENERAL REQUIREMENTS.

2.1. Basic Guidelines.

2.1.1. Preconstruction Conference. Prior to the start of any construction work an authorized representative of the KO will schedule and conduct a preconstruction conference. The notification will include specific details regarding the date, time, and location of the conference, any need for attendance by sub-Contractors, and information regarding the items to be discussed.

2.1.1.1. The Contractor's Project Manager (PM), Superintendent, and Quality Control Manager (QCM) shall attend this meeting. Minutes of the meeting will be prepared and signed by the Contractor.

The minutes shall be sent to the COR for review and approval no later than 24 hours after the meeting.

2.1.2. Construction Documents. Contractor shall have a copy of the [Paving IDIQ Contract,] Scope of Work (SOW), Drawings, and specifications at the construction site at all times.

2.1.3. Licenses and Permits. The Contractor shall verify all dimensions and investigate existing site conditions prior to submitting proposal. The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits. The Contractor shall comply with all applicable laws and regulations, including but not limited to Building Codes, Federal Law, Texas State Law, Occupational Safety and Health Administration (OSHA) regulations, Army and installation regulations.

2.1.4. Contractor Furnished Items. Everything included in this paragraph and its subparagraphs is basic to the contract and should be included in the contract price.

2.1.4.1. The Contractor shall provide all labor, supervision, transportation, vehicles, supplies, equipment, materials and services required to perform work under this contract. The Contractor shall, as necessary, provide all equipment needed to perform the work safely and to meet the requirements herein.

2.1.5. Installation Property. Contractor shall exercise extreme caution to protect building finishes, private property, military property, historic material, cultural resources, etc., from damage during the performance of these contract requirements. Contractor shall be responsible for all loss or damage to Government and private property while executing contract requirements as a result of negligence on behalf of the Contractor, subcontractors, or any representatives of the Contractor or subcontractors.”

2.1.6. Contractor Vehicles. Contractor’s personnel, whose tasks involve operation of any vehicles, shall possess a valid U.S. state driver’s license, certificates and permits, applicable for the type and class of vehicle being operated.

2.1.6.1. Limited Access. The Contractor shall only use existing roadways when transporting personnel and/or material during the execution of the contract. The Contractor shall strictly adhere to the foregoing and shall not develop new ingress or egress roads.

2.1.6.2. Parking. The Contractor shall ensure that its personnel use designated parking areas only. Personal and non-construction related vehicles shall not be parked on grassy, gravel, or landscaped areas (unless identified as acceptable in drawings).

2.1.7. Buy American Act. Construction Materials. Applying to contracts for the construction, alteration, or repair of any public building or public work in the United States, the Contractor shall utilize commercially available off-the-shelf (COTS) construction materials in accordance with Executive Order 10582 and 41 U.S.C. chapter 83, Buy American.

2.2. Key Personnel. The personnel listed below are considered essential to the work being performed under this contract. Prior to substituting, removing, replacing, or diverting any of the specified individuals, the Contractor shall notify the KO fifteen (15) working days in advance and shall submit a written request and justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this Contract. The proposed substitution of personnel must meet or exceed the experience and other technical requirements of the personnel being replaced.

No change in personnel shall be made by the Contractor without the prior written consent of the KO. However, in urgent situations, as determined or agreed to by the KO, an oral request to substitute key personnel may be approved and subsequently ratified by the KO in writing. Such ratification shall constitute the consent of the KO required by this paragraph. The KO will notify the Contractor within ten (10) working days after receipt of all required information of the decision on the substitution(s). In the event the proposed substitution of key personnel does not meet or exceed the experience and other technical requirements of the personnel being replaced, substitution of acceptable replacements for the individuals as specified below. The key personnel listed below may, with the consent of the contracting parties, be amended during the course of the Contract to either add or remove personnel as necessary.

PM

Superintendent Site Safety and Health Officer (SSHO)/ QCM

2.2.1. PM. The Contractor shall provide a PM.

2.2.1.1. The role of the Construction PM is to be the Government’s Point of Contact (POC) for projects and administration of construction. Per project, the PM is accountable for:

2.2.1.1.1. Management of performance of all trade Contractors, review and analysis of SOW, architectural and engineering drawings and specifications; ensuring contract documents and regulations are comprehended and followed; supervision of Construction Superintendent(s), reviewing and approving their reports, submittals, monitor reported difficulties, and correcting safety violations/ deficiencies; developing, tracking, updating and controlling construction schedule; project management plan, and associated costs to achieve completion of project; coordinating the closure of a project.

2.2.1.2. The PM shall possess the following:

2.2.1.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in English.

2.2.1.2.2. Experience. Five (5) years of experience (within the last ten (10) years) working as a Construction PM (or in a position with equivalent responsibilities) managing multiple construction projects simultaneously related to the project.

2.2.2. Superintendent. The Contractor shall assign one competent superintendent for each project. The superintendent shall be accountable for overall supervision and management of job site coordination, day-to-day operations, schedule adherence, enforcement of safety and quality, managing subcontractors, has authority to act for the Contractor, and shall be on site at all times during Construction. The superintendent is required to attend facility turnover meetings (Red Zone meetings), partnering meetings, and quality control meetings. The qualification requirements for the alternate superintendent are the same as for the superintendent.

2.2.2.1. The Superintendent shall possess the following:

2.2.2.1.1. Language. Full Professional working proficiency at speaking, listening, reading, and writing in

2.2.2.1.2. Experience. Five (5) years’ experience (within the last ten (10) years) working as a Construction Superintendent (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project. The superintendent must be familiar with the requirements of Engineering Manual (EM) 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The KO may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

2.2.3. SSHO. The SSHO shall be accountable for overall supervision and management of the

Contractor’s safety program(s) and plan(s). Contractor shall assign one SSHO for each project, who will work simultaneously as the SSHO and QCM. The SSHO shall be on site at all times during construction to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. An alternate shall be identified in the Construction Safety Plan to serve in the event of the SSHO’s absence. The requirements for the alternate are the same as the SSHO. The SSHO shall meet the requirements of EM 385-1-1 Chapter 2 Safety and Occupational Health Program management for Contractors. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. It is responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.

2.2.3.1. The SSHO shall be the Government’s POC for all aspects relating to safety. The SSHO responsibilities include, but are not limited to facilitating and ensuring the completion of facility safety assessments/investigations of reportable and non-reportable mishaps involving personal injury accidents, property damage, and cases of occupational illnesses; recording accident reports in an accurate, complete, and timely manner; assuring that claims for injuries and illnesses are posted in the Occupational Safety and Health Administration log; promoting and furnishing applicable safety and health, accident prevention, and investigation training for Contractor’s employees; assessing and evaluating work environment, identifying potential hazards, and aiding Contractor, Construction PM, and Construction Superintendent during work place inspections;

supporting Contractor, Construction PM(s), and Construction Superintendents in investigating accidents and developing measures to prevent recurrences.

2.2.3.2. The Safety Manager shall possess the following:

2.2.3.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in

2.2.3.2.2. Experience. Five (5) years’ experience (within the last ten (10) years) working as a SSHO (or in a position with equivalent responsibilities), identifying potential risks and hazards, investigating accidents, and promote occupational safety on multiple construction projects, simultaneously, related to the project.

2.2.3.2.3. Certification. SSHO shall possess active credentials as a Certified Safety and Health Official

(CSHO) in construction or Master Certification (MC) from an OSHA Training Institute Education Centers.

2.2.4. QCM. The QCM shall be accountable for overall supervision and management of the construction’s quality control and management program(s) and plan(s). Contractor shall assign one QCM for each project, who will work simultaneously as SSHO and QCM. The QCM shall be on site at all times during construction and alternate shall be identified in the Construction Quality Control Plan to serve in the event of the QCM’s absence. The requirements for the alternate are the same as the QCM. It is the responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.

2.2.4.1. The QCM is to be the Government’s POC for all aspects relating to quality control. the QCM responsibilities include but are not limited to the supervision and management of the Contractor’s quality control and management program(s) and plan(s) in accordance with specifications;

inspecting work for conformance to project plans and specifications identifying issues arising during construction and verifying that deficiencies have been corrected; recording and notifying the PM and/or Superintendent of problems on a timely basis so that corrections can be made without impact to the project schedule; creating, updating and maintaining the project submittal log and all other project specific quality control reports; reviewing shop drawings and submittals for conformance with project specifications by direct review and by leveraging the knowledge and experience of others in the project team when necessary; scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, manufacturers, offsite fabricators, suppliers, and purchasing agents; tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation; continuing development of the project Quality Control Plan to address the specific needs of task orders, as required; examining the work area to assure that all required preliminary work has been completed and is in compliance with the contract; reviewing drawings and each paragraph of applicable specifications, reference codes, and standards applicable to work being performed in the field.

2.2.4.2. The QCM shall possess the following:

2.2.4.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in

2.2.4.2.2. Experience. Five (5) years’ experience (within the last ten (10) years) working as a QCM (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project.

2.3. Utilities. The Government will provide electricity and water for Contractor use in conjunction with this contract where available, and commodities will be at no cost to the Contractor. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities. Contractor shall meter all utilities used and report them to Sustainability & Energy and Engineering Services Division. To coordinate the use of utilities please contact the COR. The Contractor shall provide its own sources of utilities (water, electricity, etc.) needed to complete the work in the SOW at locations where Government utilities are not available.

2.3.1. Utilities Cutovers and Interruptions. All anticipated utility outages shall be coordinated with DPW through the COR. A minimum advance notice of fourteen (14) calendar days shall be provided by the Contractor. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise. Conform to procedures required in paragraph Work Outside Regular Hours.

2.3.2. Portable Latrines. The Contractor shall be responsible for furnishing portable latrines as required by OSHA and American National Standards Institute (ANSI), for the use of employees at such locations as designated by the KO or COR.

2.4. Hours of Operation.

2.4.1. Normal Work Hours. The Contractor shall perform all work during normal work hours. Normal work hours are defined as the time period from 0730 hours (7:30 AM) to 1630 hours (4:30 PM) MDT/MST, Mondays through Fridays except on Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall not be reimbursed when the Government facility is closed for the above reasons.

2.4.1.1. Federal Government Holidays. For Government holidays visit https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview .

2.4.1.2. This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.

2.4.1.3. It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel will not be a reason for an additional period of performance, or entitlement of compensation except as set forth within the contract. In the event the Contractor’s personnel work during the holiday, the Contractor may reimburse them; however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked, unless stipulated otherwise. This provision does not preclude reimbursement for authorized overtime work if applicable.

2.4.1.3.1. When the Department of Defense grants excused absence to its employees, the Contractor agrees to continue to provide sufficient personnel to perform critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the KO or the COR.

2.4.1.4. If Government personnel are furloughed, the Contractor shall contact the KO or the COR to receive direction. It is the Government’s decision as to whether the contract price/cost will be affected as a result of Government shutdown and/or furloughed Government employees. In the https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview event that Government shutdown and/or furloughed Government employee does impact contract price/cost, a negotiated settlement will be reached as deemed appropriate by the KO.

2.4.2. Approval of Work Outside Normal Work Hours. Work outside regular working hours requires KO approval. Make application fifteen (15) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title.

Based on the justification provided, the KO may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the

KO.

2.5. Approval of work other than normal work-hours of the military reservation will be based upon the requirements of the task, technical or safety factors and not for the convenience of the Contractor.

This is not intended to restrict the Contractor to an 8-hour day if the segment of project requires continuous work until completed because of mission requirements, the technical nature thereof, in the interest of safety, or to prevent damage to the project or other property. The Contractor shall give prior notice of such requirements to the KO. The KO may authorize the Contractor to perform work outside of normal working hours and/or working days. When the Government requires the Contractor to work outside normal hours, the Contractor shall be notified at the onset of the project, but not less than 24 hours in advance.

2.6. Historical Properties. All work performed on historic properties, or within historic districts and view sheds, shall meet the Secretary of Interior’s Standards for the Treatment of Historic Properties; AR 200-1: Environmental Protection and Enhancement; the Fort Bliss Integrated Cultural Resource Management Plan (ICRMP); the Fort Bliss Programmatic Agreement for the Management, Operation, and Development of Historic Properties; and all associated regulations. The code of Federal Regulations can be found at eCFR :: 36 CFR Part 68 -- The Secretary of the Interior's Standards for the Treatment of Historic Properties.

2.6.1. The Historic Architecture Program within the Fort Bliss Directorate of Public Works – Environmental Division (DPW-ED) or DPW-ED Cultural Resource Manager (CRM) shall review and approve the project before any work begins. All coordination with DPW-ED shall be made through the COR.

2.6.2. The Contractor shall comply with all of the laws, regulations, orders, and procedures governing historic preservation, including the following documents: National Historic Preservation Act of 1966 (NHPA) as amended, and the Integrated Cultural Resource Management Plan (ICRMP) for Fort Bliss. All work done on historic properties, or properties within the view shed of a historic district must be reviewed and approved by Cultural Resource Manager (CRM) Staff prior to start of work. Contact Fort Bliss Historic Architect, for details and requirements. Coordinate with Fort Bliss Historic Architect POC via COR.

2.6.3. The Contractor shall provide maximum protection, take every reasonable means, and exercise care to prevent unnecessary damage to exiting historic structures, contemporary structures, landscape plantings, natural features, roads, utilities, and other public or private facilities. Special attention shall be given to historic structures, natural and landscape features of the areas to protect these elements and their surroundings. In addition, Contractor shall remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain and repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the KO. At the completion of https://www.ecfr.gov/current/title-36/chapter-I/part-68 https://www.ecfr.gov/current/title-36/chapter-I/part-68 operations, existing work shall be in a condition equal to or better than that which existed before new work started.

2.7. Environmental. The Contractor shall perform all work in such a manner as to minimize the polluting of air, water, or land and shall, within reasonable limits, control noise and the disposal of solid waste material, as well as other pollutants. The Contractor shall comply with AR-420-47 Solid & Hazardous Waste Management, Title 40 CFR Part 260 through 273 and with all Federal, State, and local laws and regulations concerning environmental pollution control.

Compliance by Subcontractors shall be the responsibility of the Contractor.

2.7.1. Permits.

2.7.1.1. Hazardous Material Abatement. The Contractor shall coordinate all hazardous material removal with the DPW-ED through the COR and execute all projects in strict adherence to the latest installation, Federal, state, and local regulations. Copies of the ten (10) day notification shall be required prior to any abatement. Copies of all clearance reports, air monitoring, and waste manifests shall be required at the completion of the project. All notifications and records pertaining to hazardous materials shall be submitted to the Fort Bliss Safety Office, Industrial Hygiene Services, COR, and DPW-ED Asbestos and Lead Program Manager.

2.7.1.2. Air Emissions. Construction Operating Permits may be required prior to the installation of a significant, stationary, and/or air emissions source. Possible sources include but are not limited to:

boilers, generators, paint booths, baghouses, cyclones, painting operations, wood working operations, welding operations, de-painting or blasting operations, engine test cells, solvent baths/degreasers, fuel storage tanks, or fueling operations. The air emission units listed above may also require a modification to the installation’s Title V Permit and cannot be installed nor operated until a permit is issued is issued by the state permitting authority as applicable. Coordinate with the Air Program Manager via the COR for further guidance.

2.7.2. Storm Water Pollution Prevention Plan (SWPPP). If more than an acre is to be disturbed during construction, the Contractor shall submit a SWPPP for approval. Contractor’s final SWPPP shall be submitted no later than (NTL) fifteen (15) calendar days after contract award.

2.7.3. Not Applicable

2.7.4. Hazardous Materials Requirements

2.7.4.1. Certification of Asbestos Free Construction. Texas House Bill 1927, effective September 2001, requires a Safety Data Sheet and a signed statement by an architect, engineer or Texas Department of Health Inspector identifying presence of asbestos containing material in all construction building materials (reference Texas Asbestos Health Protection Rules, Section 295.34, Part J). The Contractor shall provide a signed statement a CERTIFICATION form and attached with Safety Data Sheet (SDS) on each construction material (i.e. interior & exterior material of construction including mastic, sealant, roofing felt, roofing coating, non-roofing coating, floor tile and mastic, pipeline wrap, any type of friction material, etc.) and equipment.

Any excavation could encounter asbestos-containing concrete pipe, a.k.a. transite. If, during excavation, transite pipe is found the material shall not be disturbed by grinding, breaking, scraping or crushing, but shall be abated or removed by a licensed company with properly trained personnel using best management practices to prevent worker exposure, and proper handling and disposal of Asbestos Containing Materials (ACM) pipe; or excavation deviated to leave transite pipe undisturbed and left abandoned in place. If ACM pipe is encountered contact the Lead/Asbestos Program via the COR for further guidance.

2.7.4.2. Hazardous/ Regulated Materials. Hazardous materials (new) that are required for the project need to get approval from AFSB-FB through the Haz-Mart. The SDS is submitted to the Haz-Mart for review and approval. Once approved it can be brought and used on the installation, and must be stored according to the manufacturer’s recommendation.

2.7.4.3. No material other than construction materials, e.g. PVC, CPVC, or other suitable materials, will be brought into the installation.

2.7.5. Construction Waste Management and Disposal

2.7.5.1. Salvage, Waste, and Disposal. The Contractor shall dispose of excess scrap, materials, debris or waste at an approved off-post location IAW applicable Local, State and Federal laws and regulations and pay any related fees. Burning or burial of materials is not permitted. The Contractor shall maintain a clean work area free of construction debris.

2.7.5.2. Daily Clean Up. The cleanup of the work site shall include, but not limited to, the removal of scrap (waste materials), spoils, debris, and salvage material that results from work on this project as well as general upkeep of the site to include mowing, trimming and weed control. The Contractor shall maintain a clean work area, free of construction debris. The Contractor shall clean the work site daily as well as after completion of the project in the project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter and foreign substances.

2.7.5.3. Texas Commission of Environmental Quality (TCEQ). Contractor shall comply with Texas

Commission on Environmental Quality, Chapter 290 – Public Drinking Water, 290.101 – 290.119, 290.121, 290.122, Effective March 30, 2017, or most current approved version. The purpose of these standards is to assure the safety of public water supplies with respect to microbiological, chemical, and radiological quality and to further efficient processing through control tests, laboratory checks, operating records, and reports of public water supply systems.

2.7.5.3.1. For new construction it is required to follow the plumbing code for the state of Texas before they can connect to secondary water system. A customer service inspection (CSI) certificate shall be completed prior to providing continuous water service to new construction, on any existing service either when the water purveyor has reason to believe that cross-connections or other potential contaminant hazards exist, or after any material improvement, correction, or addition to the private water distribution facilities.

2.7.5.4. Deconstructed and Salvageable Materials. All items and materials to be salvaged shall be carefully removed, cleaned, prepared for storage, delivered and stored where indicated and-or specified.

Salvageable material is an object or material that can be reused again, either for its original purpose or for a similar purpose, without significantly altering the physical form of the object or material.

2.7.5.5. Haul Routes. The Contractor shall submit haul routes, spill prevention and contingency plans to the COR and DPW-ED for review and approval prior to start of work. Any costs associated with spill cleanup, decontamination, abatement, disposal, mitigation, etc., shall be borne by the Contractor.

2.7.5.6. Solid Waste & Recycling Programs. Proposed project shall generate waste streams from the demolition of building construction; however, it is not anticipated that the project…