Statement_of_Work_(SOW)_Crab_Orchard_NWR_Prairie_Creek.pdf

PDF 3 MB Posted

Attached to
IL-CRAB ORCHARD NWR-BOAT RAMP REHAB
Solicitation number
140F0822R0001
Issued by

About this file

This statement of work describes a construction project to rehabilitate two boat ramps at Crab Orchard National Wildlife Refuge in Illinois. The project involves replacing and widening an existing boat ramp at Prairie Creek Recreation Area, including installation of sheetpile along the ramp. It will require demolition of the current concrete ramp, excavation and site grading, construction of a reinforced concrete ramp, and site restoration. The statement of work provides specifications for concrete reinforcement, formwork, cast-in-place concrete, earthwork, excavation support and protection, and steel sheet pile. It also includes subsurface investigation reports, figures depicting the site layout and geological cross-sections, and boring logs from monitoring well installations. The construction is to be completed between November 2021 and March 2022 to take advantage of lower water levels.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES DEPARTMENT OF THE INTERIOR

U.S. FISH AND WILDLIFE SERVICE

CRAB ORCHARD NATIONAL WILDLIFE REFUGE

Statement of Work/Need Prairie Creek Boat Ramp Replacement

November 2021

Introduction

Crab Orchard National Wildlife Refuge (CONWR) is seeking replacement of an existing boat ramp located at the Prairie Creek Recreation Area on CONWR property. CONWR comprises approximately 44,000 acres of habitat in Southern Illinois, including hardwood forest, agricultural land, grazing units, brushland, wetlands, and lakes. Prairie Creek Recreation Area is a popular destination for boating, bank fishing, and picnicking in Southern Illinois.

Specifications

Specifications for the boat ramp work are included as Attachment A and Attachment B.

Attachment A is composed of architectural drawings and Attachment B is composed of written specifications for the project.

Performance Timeframes

Interested parties should be aware that this is a time-critical proposal. Optimal performance time exists between 1 November 2021 and 1 March 2022. During that timeframe, Crab Orchard Lake will be drawn down below normal pool. If site work extends beyond 1 March 2022, the Government cannot guarantee that the lake will continue to be below normal pool. Use of cofferdams and water control structures may be necessary, both prior to and after 1 March 2022, depending on the on-site situation. Interested parties should be prepared to de-water the worksite depending upon conditions.

Technical Point of Contact (POC)

The Technical Point of Contact (POC) for this contract is:

Mr. Kevin Reichert Maintenance Supervisor Crab Orchard National Wildlife Refuge 618-998-5980 Kevin_Reichert@fws.gov

Modifications to the Boat Ramp at Prairie Creek TOC October 2021

TECHNICAL SPECIFICATIONS

FOR

MODIFICATIONS TO THE BOAT RAMP AT PRAIRIE CREEK

BID SCHEDULE

TABLE OF CONTENTS

ARTICLE TITLE PAGE NOS.

01 11 00 Summary of Work 01 11 00-1 01 11 00-3 01 30 00 Administrative Requirements 01 30 00-1 01 30 00-4 01 31 00 Project Coordination 01 31 00-1 01 31 00-2 01 40 00 Quality Requirements 01 40 00-1 01 40 00-5 01 42 00 References 01 42 00-1 01 42 00-2 01 55 29 Staging and Stockpile Area 01 55 29-1 01 55 29-1 01 70 00 Contract Closeout 01 70 00-1 01 70 00-2 02 41 00 Demolition 02 41 00-1 02 41 00-2 03 20 00 Concrete Reinforcement 03 20 00-1 03 20 00-4 03 30 00 Cast-in Place Concrete 03 30 00-1 03 30 00-9 31 00 00 Earthwork 31 00 00-1 31 00 00-6 31 50 00 Excavation Support and Protection 31 50 00-1 31 50 00-3 31 62 16 Steel Sheet Pile 31 62 16-1 31 62 16-19

END OF CONTENTS

Modifications to the Boat Ramp at Prairie Creek

BID

SCHEDULE

1 Demolition Job Lump Sum -

2 Concrete Reinforcement Job Lump Sum -

3 Cast-in-Place Concrete Job Lump Sum -

4 Earthwork Job Lump Sum -

5 Dewatering Job Lump Sum -

6 Sheet Pile Job Lump Sum -

Total Cost

Total Cost Item No.

Item Description Quantity Unit Unit Price

United States Department of the Interior Fish and Wildlife Serfice

PROJECT TITLE: CRAB ORCHARD LAKE PRAIRIE CREEK BOAT

RAMP

Williamson County, Illinois Bid Schedule

Modifications to the Prairie Creek Boat Ramp 01 11 00-1 Summary of Work October 2021

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 SUMMARY

A. The work outlined in these Specifications includes replacement and widening of the Prairie Creek Boat Ramp and installation of sheetpile along the boat ramp.

1.02 SITE LOCATION

A. Project location is at the Prairie Creek Recreation Area on Crab Orchard Lake, located on Government land in the Crab Orchard National Wildlife Refuge, Williamson County, Illinois. Exact location of Project is indicated on the "Location Map" on the first sheet of the Drawings.

1.03 WORK COVERED BY CONTRACT DOCUMENTS

A. Without intending to limit or restrict extent of work required under this Contract, Work to be performed comprises the following:

1. Staging areas and erosion control measures.

2. Temporary control of the reservoir.

3. Diversion of water measures to protect the work area.

4. Demolition of the existing boat ramp.

5. Excavation and site grading for the widening and construction of the boat ramp and installation of the sheetpile.

6. Construction of the reinforced concrete boat ramp, which includes but is not limited to preparation of the subgrade and placement of the cast-in-place concrete.

7. Site restoration including placement of topsoil and seeding.

B. Provide without additional compensation, any apparatus, material and labor not specifically mentioned in specifications or indicated on Drawings, that is necessary to complete or perfect any portion of work in a substantial manner and in compliance with requirements implied or intended in these Contract Documents. This includes materials, devices or methods peculiar to the apparatus or system provided.

1.04 DRAWINGS

A. Project Drawings: The Drawings accompanying these Specifications are hereby made a part of the Contract. The Work relative to the Contract is indicated in the set of Drawings.

Boat Ramp 01 11 00-2 Summary of Work

1.05 PROFILES AND TOPOGRAPHY

A. Profiles, topography, and details for the work are schematic in nature and, with the exception of dimensioned construction details, are presented only for the purpose of conveying the concept and the limit of specified work. The Contractor shall verify all details in the field. The misuse of noted information for other than that indicated and subsequent suffering of damages as a result of misuse shall not be cause for any claim by the Contractor. Information is believed to be reasonably correct, but is not guaranteed.

1.06 PHYSICAL DATA

A. Become fully informed concerning location of public or private facilities and structures on, under, or over Project, which may interfere with operations. It is assumed Contractor has prepared bid and entered into Contract with full understanding of conditions to be encountered, and responsibilities in connection with that.

B. From investigations and field surveys, location of facilities and structures are indicated on Drawings, but location of utilities (i.e. water, electric, gas, sewer, telephone lines, etc.), and nature of materials is not guaranteed. Indication on Drawings of such facilities will not be assumed to relieve Contractor of any responsibility with respect to it nor will CO/COR be held responsible for any omission or failure to give notice to Contractor of any other facility or structure on, under, or over Project, or presence of rock or unsuitable material.

1.07 ADJACENT PROPERTY AND RIGHT-OF-WAY

A. Do not trespass, store material or equipment or in any other manner occupy any property outside of the construction right-of-ways, easements or limits of disturbance shown on the Drawings without written permission of the owner of the property. Any damage done by the Contractor to property outside of said work areas shall be restored immediately to the property owner's satisfaction at the Contractor's expense.

1.08 UTILITY OWNERS

A. Do not operate, move, relocate, or in any way interfere with the operation of existing utilities at, near, or outside the work area without first contacting a qualified representative of the utility involved and obtaining a written approval from this representative.

PART 2 PRODUCTS

NOT USED

Boat Ramp 01 11 00-3 Summary of Work October 2021

PART 3 EXECUTION

NOT USED

PART 4 MEASUREMENT AND PAYMENT

END OF SECTION

Boat Ramp 01 30 00-1 Administrative Requirements

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 GENERAL

A. Refer the submittal register or technical specifications for all submittals required.

B. When specifically requested by the Contracting Officer (CO), Contractor’s Officer’s

Representative (COR) or the Government’s Construction Inspector, the Contractor shall provide copies of manufacturer's written installation instructions and/or recommendations for review and approval prior to accomplishing equipment installation.

1.02 SUBMITTALS

A. A submittal register, listing items requiring submittals, is provided as at attachment to this Specification. This listing is a minimum to be submitted by the Contractor, each specification section will have precedence over this listing.

B. The Contractor shall provide all required submittals to the COR within 30 days of award except for items noted otherwise on the submittal register.

C. Submittals shall be submitted electronically to the COR, unless otherwise requested.

D. The approval of submittals shall not relieve the Contractor to comply with the terms and conditions of the Contract Drawings and Specifications. The Contractor shall be responsible to determine correct dimension, design, connection, detail and satisfactory construction of all Work.

E. A submittal coversheet will be provided by the Government to be used for each and every submittal. Contractor is to provide submittals under each specification section complete with all requirements included. Partial submissions will be returned not reviewed.

F. After review by the COR shop drawings will be returned marked as follows:

Approved; Approved as Noted; Revise and Resubmit; Rejected; or Receipt Acknowledged.

1. Approved: When submittals are returned Approved, it is understood that the submittals have been found to be in conformance with the Contract Documents.

The COR's approval of the shop drawings does not relieve the Contractor from responsibility for errors or discrepancies in such shop drawings.

2. Approved as Noted: When submittals are returned Approved as Noted, it is understood that the submittals have been found to be in conformance with the

Boat Ramp 01 30 00-2 Administrative Requirements October 2021

Contract Documents, provided the changes noted by the COR are incorporated in the shop drawings. Shop drawings returned Approved as Noted will not require resubmission unless noted on the return transmittal.

3. Revise and Resubmit: When submittals are returned noted Revise and Resubmit, it is understood that the Contractor shall make the required corrections and resubmit corrected submittals to COR. No fabrication is allowed.

4. Rejected: When submittals are returned Rejected, it is understood that the Contractor shall make completely submittals and submit.

5. Receipt Acknowledged: Submittals returned Acknowledge Receipt means COR has acknowledged receipt of the submittals and provided applicable comments.

1.03 PROJECT SCHEDULE

A. Contractor shall provide as required by Federal Acquisition Regulation (FAR) clauses.

Applicable FAR clauses will be provided to the resultant Contractor at the pre-construction conference.

1.04 PRICE BREAKDOWN – LUMP SUM ITEMS

A. Contractor shall provide as required by Federal Acquisition Regulation (FAR) clauses.

Applicable FAR clauses will be provided to the resultant Contractor at the pre-construction conference.

1.05 SUBCONTRACTOR’S LIST

A. Submit a list of subcontractors who will be working on the project.

1.06 SUBMITTAL OF PROGRESS PAYMENT CERTIFICATE

A. Contractor shall provide as required by FAR clauses. Applicable FAR clauses will be provided to the resultant Contractor at the pre-construction conference.

1.07 DELIVERY TICKETS

A. The Contractor shall submit to the COR, one legible copy of each delivery ticket for all material delivered to the construction site.

B. The delivery ticket shall show brand name, catalog number, and number of items received.

Boat Ramp 01 30 00-3 Administrative Requirements October 2021

PART 3 EXECUTION

NOT USED

Boat Ramp 01 30 00-4 Administrative Requirements October 2021

SUBMITTAL REGISTRAR

Specification Reference

Section Description Project Coordination 01 31 00 Preconstruction Safety Checklist Quality Requirements 01 40 00 Testing Agency Qualifications Quality Requirements 01 40 00 Test Reports Contract Closeout 01 70 00 Record Drawings Contract Closeout 01 70 00 Test Reports Contract Closeout 01 70 00 Guarantees and Warranties Demolition 02 41 00 Demolition Plan Concrete Reinforcement 03 20 00 Shop Drawings Concrete Reinforcement 03 20 00 Certificates Concrete Reinforcement 03 20 00 Test Reports Cast-In-Place Concrete 03 30 00 Product Data Cast-In-Place Concrete 03 30 00 Mix Design Earthwork 31 00 00 Material Sources Earthwork 31 00 00 Compaction Density Test Reports Excavation Support and Protection 31 50 00 Engineering Qualification Data Excavation Support and Protection 31 50 00 Contractor Qualification Data Excavation Support and Protection 31 50 00 Cofferdam Plan Steel Sheet Pile 31 62 16 Installer Qualifications Steel Sheet Pile 31 62 16 Certifications Steel Sheet Pile 31 62 16 Installation Means, Methods, and Sequence

Modifications to the Prairie Creek 01 31 00-1 Project Coordination Boat Ramp

SECTION 01 31 00

PROJECT COORDINATION

1.01 JOBSITE COORDINATION

A. Superintendence, Subcontract administration and Quality Control, is the responsibility of the Contractor.

B. Final decisions relative to items in conflict shall be made by the Contracting Officer.

C. The Government shall have the authority to temporarily suspend the Work for such time as necessary because of the failure on the part of the Contractor to perform any of the provisions of the Contract. No extension of contract performance time will be permitted until the Government determines that the deficiencies in performance, which caused the temporary suspension, have been corrected.

D. The Contractor shall have responsible superintendence on site during all project operations. Contractor shall notify Government of any changes of superintendents.

E. The Contractor shall notify the COR at least ten (10) days prior to the anticipated date of completion of all Work specified herein. Upon completion of the Work, the COR shall proceed with the final inspection which shall be completed as promptly as practicable. The time required for such inspection and for performing any corrective Work shall be included in the contract performance time.

1.02 MODIFICATIONS/CHANGE ORDER PROCEDURES

A. In the event of the need for a Change Order, the Contractor will receive a letter requesting a price quote for proposed changes to the Contract.

B. For evaluation purposes, the Contractor's quote shall be broken down to show the costs of labor and materials for each proposed category of Work included with the change, along with the total cost for Contractor's overhead, profit, and bond for the proposed changes.

C. All Contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.

1.03 PRECONSTRUCTION CONFERENCE

A. Soon after award of the Contract and prior to commencing construction, the Contractor and any subcontractors shall attend a preconstruction conference with representatives of the Government. Timely notification of the meeting will be given

Modifications to the Prairie Creek 01 31 00-2 Project Coordination

October 2021 to the Contractor. Time, date, and place of the conference will be determined by the Contracting Officer. Requirements pertaining to Contract administration, construction operations and the project schedule will be discussed. The project schedule shall be in accordance with Section 01 30 00. The Preconstruction Safety Checklist shall be submitted for review during this conference.

1.04 PROJECT MEETINGS

A. Periodic general project meetings will be conducted with a representative of the

Contractor at the project site or by telephone by the Government's representative for the purpose of coordinating, expediting, and assessing the work progress.

B. The Contractor shall provide reports of progress on the project, discuss the work schedule for the coming period and present all conflicts, discrepancies or other difficulties for resolution. A record of discussions and decisions will be prepared by the Government and distributed to those attending and others affected.

NOTE USED

PART 3 EXECUTION

Modifications to the Prairie Creek 01 40 00-1 Quality Requirements

SECTION 01 40 00

QUALITY REQUIREMENTS

1.01 SECTION INCLUDES

A. Mock-ups.

B. Control of installation.

C. Testing and inspection services.

D. Manufacturer’s field services.

E. Contractor’s experience.

1.02 RELATED SECTIONS

A. Section 01 30 00 – Administrative Requirements.

1.03 REFERENCES

A. American Society for Testing and Materials:

1. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants.

2. ASTM C1077 - Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation.

3. ASTM C1093 - Standard Practice for Accreditation of Testing Agencies for Masonry.

4. ASTM D3740 - Standard Practice for Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Governmenting Design and Construction.

5. ASTM E329 - Standard Specification for Agencies Engaged in Construction Inspection Testing, or Special Inspection.

6. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing.

B. International Accreditation Service.

1. IAS AC89 - Accreditation Criteria for Testing Laboratories.

Modifications to the Prairie Creek 01 40 00-2 Quality Requirements

October 2021

1.04 SUBMITTALS

A. Testing Agency Qualifications:

1. Prior to start of Work, submit agency name, address, and telephone number, and names of full-time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by NIST Construction Materials Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

3. Qualification Statement: Provide documentation showing testing laboratory is accredited under IAS AC89.

B. Test Reports: After each test/inspection, promptly submit one copy of the report to the Government and Contractor:

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location of Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by COR, provide interpretation of results.

1.05 TESTING AND INSPECTION AGENCIES

A. Contractor shall employ and pay for services of an independent testing agency to perform specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

C. Contractor Employed Agency:

1. Testing agency: Comply with requirements of ASTM E329, ASTM E543, ASTM C1021, ASTM C1077, and ASTM C1093.

2. Inspection agency: Comply with requirements of ASTM D3740 and ASTM E329.

3. Laboratory Qualifications: Accredited by IAS according to IAS AC89.

4. Laboratory: Authorized to operate in the State in which the Project is located.

5. Laboratory Staff: Maintain a full-time registered Engineer on staff to review services.

6. Testing Equipment: Calibrated at reasonable intervals either by NIST or using an

NIST established Measurement Assurance Program, under a laboratory measurement quality assurance program.

Modifications to the Prairie Creek 01 40 00-3 Quality Requirements

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Government before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

3.02 MOCK-UPS

A. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Government and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock-up and clear area when directed to do so by Government.

3.03 TESTING AND INSPECTION

A. Testing Agency Duties:

1. 1. Provide qualified personnel at site. Cooperate with Government and Contractor in performance of services.

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

Modifications to the Prairie Creek 01 40 00-4 Quality Requirements

October 2021

4. Promptly notify Government and Contractor of observed irregularities or non-conformance of Work or products.

5. Perform additional tests and inspections required by Government.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Government and laboratory 48 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with Government's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency on instructions by Government.

E. Re-testing required because of non-conformance to specified requirements shall be paid for by Contractor.

3.04 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

Modifications to the Prairie Creek 01 40 00-5 Quality Requirements

October 2021

B. Submit qualifications of observer to Government 30 days in advance of required observations.

1. Observer subject to approval of Government.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.05 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of Government, it is not practical to remove and replace the Work, Government will direct an appropriate remedy or adjust payment.

3.06 CONTRACTOR'S EXPERIENCE

A. For work on this project the following Contractors must be able to provide evidence of Five (5) years of work experience of similar size and complexity of previous projects as noted below. If this section is in conflict with other sections the most stringent requirement will take precedence. Documentation to be submitted to Government.

1. Concrete Contractor.

Modifications to the Prairie Creek 01 42 00-1 References

SECTION 01 42 00

REFERENCES

1.01 ABBREVIATIONS

A. Abbreviations that may be used throughout the Specifications and the organization or document represented are:

AA Aluminum Association AAMA Architectural Aluminum Manufacturer's Association AASHTO American Association of State and Highway Transportation Officials ACI American Concrete Institute AIA American Institute of Architects AIEE American Institute of Electrical Engineers AISC American Institute of Steel Construction AISI American Iron and Steel Institute AMA American Materials Association ANSI American National Standards Institute ASA American Standards Association (now USAS) ASCE American Society for Civil Engineers ASME American Society of Mechanical Engineers ASTM American Society for Testing and Materials AWS American Welding Society AWWA American Water Works Association CFR Code of Federal Regulations CMP Corrugated Metal Pipe CO Contracting Officer COR Contracting Officer’s Representative CRSI Concrete Reinforcing Steel Institute CS Commercial Standards of U.S. Department of Standards CSI Construction Specifications Institute FAR Federal Acquisition Regulations FML Flexible Membrane Lining FS Federal Specifications GI Government Inspector HASP Health and Safety Plan IBC International Building Code NBC National Building Code NBS National Bureau of Standards NGVD National Geodetic Vertical Datum NPDES National Pollution Discharge Elimination System NRMCA National Ready Mix Concrete Association OSHA Occupational Safety and Health Administration, U.S. Department of

Labor PCA Portland Cement Association

Modifications to the Prairie Creek 01 42 00-2 References

October 2021

SPI Steel Products Institute SSPC Steel Structures Painting Council UBC Uniform Building Code UL Underwriters Laboratories USACE U.S. Army Corps of Engineers USBR U.S. Bureau of Reclamation USFWS U.S. Fish & Wildlife Service

B. Additional definitions, if any, will be defined as they appear in the Specifications.

1.02 DEFINITIONS

A. Definitions used in these Specifications include:

1. Government - the U.S. Fish & Wildlife Service (USFWS).

2. Contracting Officer (CO) - the person authorized by the USFWS to award and administer this Contract. The CO shall make all final decisions concerning contractual matters and has sole authority to direct changes to, or make any binding agreements concerning, this Contract.

3. Contracting Officer’s Representative (COR) - the person authorized by the USFWS and appointed by the CO, to represent the CO for all technical matters that arise under this Contract. The limited authorities and responsibilities of this person are specifically delegated in writing by the CO.

4. Work - The entire construction of the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

5. Neat Lines - the dimension as shown on the Drawings of a line from a specified or labeled reference point.

B. Additional definitions, if any, will be defined as they appear in the Specifications.

Modifications to the Prairie Creek 01 55 29-1 Staging and Stockpile Area

SECTION 01 55 29

STAGING AND STOCKPILE AREA

1.01 WORK SCOPE

A. This Section includes the requirements for Contractor operations in:

1. Staging and Stockpile Areas, located in the gravel parking area, as shown on the

Drawings.

1.02 STAGING AND STOCKPILE AREAS

A. Clean up and reclaim the Staging and Stockpile Area at the end of construction.

4.01 MEASUREMENT

A. All work required in this Section will not be measured for payment.

4.02 PAYMENT

A. Compensation to the Contractor for all work required in this Section shall be included in the prices bid in the Bid Schedule for other items of Work. No separate payment will be made to the Contractor for Work required in this Section.

Boat Ramp 01 70 00-1 Contract Closeout

SECTION 01 70 00

CONTRACT CLOSEOUT

1.01 MANUFACTURERS SPECIFICATIONS

A. The installation of manufactured products and equipment, together with all associated parts, shall be in conformance with the manufacturer's recommendations, and code requirements. All installations shall be complete and ready for immediate use, and every part required for proper operation of the manufacturer's equipment shall be provided. Following the completion of the Work under this Contract, all installed equipment shall be tested for proper operation and compliance with the Contract.

1.02 FINAL INSPECTION

A. The Contractor shall request a final inspection in writing at least ten (10) days prior to the anticipated date of completion.

B. Work will not be considered ready for final inspection until all the Work has been completed and the Contractor has certified that all items are properly operating and in strict compliance with all Contract terms and conditions.

C. The Contractor or the project supervisor shall be at the job site during the final inspection.

1.03 TESTS

A. Complete all tests required to prove actual operating performance of equipment and systems incorporated into the project.

B. Submit reports of all tests to the Contracting Officer prior to final payment.

C. Provide any regulatory acceptance documents in cases of cleanup.

1.04 RECORD DRAWINGS

A. The Contractor shall provide and maintain in proper order and in good, clean condition, at the project site, one (1) complete set of full-size prints of all Drawings.

On this set, with red pencil or ink, the Contractor will neatly inscribe all changes in Work. At time of final acceptance, and prior to final payment, these corrected prints will be presented to the COR. The Contractor will note all data and changes on these

Boat Ramp 01 70 00-2 Contract Closeout record drawings in sufficient detail and clarity to provide information necessary for preparation of "as built" drawings by the Government.

1.05 GUARANTEES, WARRANTIES, AND CERTIFICATES

A. The Contractor will submit all guarantees, warranties, and certificates to the

Government prior to final payment.

B. The Government requires a 100% warranty for a period of one full year after final acceptance. Items of Work found defective during the warranty period will be replaced at no cost to the Government and the warranty for that particular part of the Work shall automatically extend for one full year beyond the completion date of repairs.

C. If a manufacturer or supplier offers a guarantee in excess of the one year requirement outlined herein, then the longer guarantee period will apply for those particular items.

PART 3 EXECUTION

NOT USED

Modifications to the Prairie Creek 02 41 00-1 Demolition

SECTION 02 41 00

DEMOLITION

1.01 WORK INCLUDES

A. Selective demolition of built site elements as noted on the Drawings.

1.02 REFERENCES

A. 29 CFR 1926 - U.S. Occupational Safety and Health Standards; current edition.

B. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition

Operations; 2013.

1.03 SUBMITTALS

A. Demolition Plan – The Contractor shall submit their means and methods of demolition of the concrete boat ramp.

3.01 SCOPE

A. Remove concrete boat ramp as required to accomplish new work and as shown on the

Drawings.

B. Remove granular material below boat ramp to a minimum depth of 8 inches to new finished surface.

3.02 GENERAL PRCEDURES AND PROJECT CONDITIONS

A. Comply with applicable codes and regulations for demolition operations and safety of adjacent structures and the public.

1. Obtain required permits.

2. Provide, erect, and maintain temporary barriers and security devices to close ramp/parking area during construction. Provide signage two weeks prior to start of project work noting to public dates that ramp area is to be closed and then reopened.

Modifications to the Prairie Creek 02 41 00-2 Demolition

October 2021

3. Conduct operations to minimize effects on and interference with adjacent structures and installations.

B. Do not begin demolition until receipt of notification to proceed from Government.

C. Protect existing structures and other elements that are not to be removed.

1. Prevent movement or settlement of adjacent structures.

2. Stop work immediately if adjacent structures appear to be in danger.

D. If hazardous materials are discovered during removal operations, stop work and notify Government; hazardous materials include regulated asbestos containing materials, lead, PCB's, and mercury.

E. Hazardous Materials: Comply with 29 CFR 1926 and state and local regulations.

3.03 EXISTING UTILITIES

A. Protect existing utilities to remain from damage.

3.04 DEBRIS AND WASTE REMOVAL

A. Remove debris, junk, and trash from site.

B. Leave site in clean condition, ready for subsequent work.

C. Clean up spillage and wind-blown debris from public and private lands.

A. Compensation to the Contractor for all costs associated with demolition of the existing boat ramp as shown on the Drawings shall be made at the lump sum price in the Bid Schedule for Demolition. Includes all labor, material, and equipment required to perform the demolition of the concrete and asphalt pavement as shown on the Drawings.

Modifications to the Prairie Creek 03 20 00-1 Concrete Reinforcement

SECTION 03 20 00

CONCRETE REINFORCEMENT

A. Reinforcing steel for cast-in-place concrete.

B. Supports and accessories for steel reinforcement

A. Section 03 30 00 – Cast-in-Place Concrete.

A. American Concrete Institute:

1. ACI 301; Specifications for Structural Concrete.

2. ACI 315; Details and Detailing of Concrete Reinforcement.

3. ACI 318; Building Code Requirements for Reinforced Concrete.

4. ACI SP-66 - ACI Detailing Manual; American Concrete Institute International.

B. American Society for Testing and Materials:

1. ASTM A615; Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement.

2. ASTM A663; Specification for Steel Bars, Carbon, Merchant Quality, Mechanical Properties.

3. ASTM A775/A775M - Standard Specification for Epoxy-Coated Steel Reinforcing Bars.

4. ASTM A884/A884M - Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement

5. ASTM A1064; Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete.

6. ASTM D3963/D3963M - Standard Specification for Fabrication and Jobsite Handling of Epoxy Coated Reinforcing Steel Bars.

C. Concrete Reinforcing Steel Institute:

1. CRSI, Manual of Standard Practice for Reinforcing Concrete Construction.

2. CRSI (DA4) - Manual of Standard Practice; Concrete Reinforcing Steel Institute.

3. CRSI (P1) - Placing Reinforcing Bars; Concrete Reinforcing Steel Institute.

Modifications to the Prairie Creek 03 20 00-2 Concrete Reinforcement

October 2021

1.04 SUBMITTALS

A. Shop Drawings: Comply with requirements of ACI SP-66. Include bar schedules, shapes of bent bars, spacing of bars, and location of splices.

B. Manufacturer's Certificate: Certify that reinforcing steel and accessories supplied for this project meet or exceed specified requirements.

C. Reports: Submit certified copies of mill test report of reinforcement materials analysis.

1.05 QUALITY ASSURANCE

A. Perform work of this section in accordance with ACI 301.

1.06 DELIVERY, STORAGE AND HANDLING

A. Storage of Materials:

1. Store reinforcing materials in a manner to prevent excessive rusting and fouling with dirt, grease and other bond-breaking coatings.

2. Identify bundles of reinforcing steel with tags wired to steel.

2.01 MATERIALS

A. Reinforcing Steel: ASTM A615/A615M, Grade 60 (60,000 psi).

1. Epoxy coated in accordance with ASTM A775/A775M.

B. Reinforcement Accessories

1. Tie Wire: Annealed, minimum 16 gage, 0.0508 inch.

2. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for adequate support of reinforcement during concrete placement. If blocks are used they must be of same.

2.02 FABRICATION

A. General: Fabricate reinforcement to the dimensions indicated on the Drawings and within the tolerances given in ACI 315. Perform bending of steel reinforcement by the cold bending method.

1. Do not use bars with kinks or bends not indicated on Drawings.

2. Perform bar shape fabrication in a manner that will not injure the material or lessen the member strength.

3. Use a designed bending machine, either hand- or power-operated.

4. Do not field bend bars partially embedded in concrete unless approved by the

Contracting Officer’s Representative.

Modifications to the Prairie Creek 03 20 00-3 Concrete Reinforcement

3.01 INSPECTION

A. Notify Contracting Officer’s Representative 48 hours before placing concrete so they can inspect placement of metal reinforcement if desired.

3.02 INSTALLATION

A. Placing:

1. Place metal reinforcement accurately and securely brace against displacement within permitted tolerances and in accordance with ACI 318 through the use of reinforcing accessories.

2. Terminate reinforcement two inches from face of expansion joints.

3. Continue reinforcement across or through construction joints.

4. When obstructions interfere with the placement of reinforcement, pass such obstructions by placing reinforcing around it. Do not bend the reinforcing to clear the obstructions.

5. Install welded wire fabric as indicated, lapping joints eight inches and wiring securely. Extend welded wire fabric to within two inches of sides and ends of slabs.

6. Do not lay metal reinforcement on formwork.

7. Place slab reinforcement supported from the ground on concrete blocks of the correct height and having a compressive strength equal to or greater than the specified compressive strength of concrete being placed. Use concrete blocks not larger than 3 inches by 3 inches with a height equal to required bottom steel cover.

8. Reinforcement supported from formwork for slabs and beams not exposed to weather or to a continuous wet environment may use bar chairs made of plastic or metal. Use stainless steel boosters in areas exposed to a wet environment.

B. Splicing:

1. Splice metal reinforcement as indicated on the Drawings and in accordance with

ACI 318.

2. Welding of crossing bars (tack welding) is not permitted.

3. Secure metal reinforcement at intersections with not less than No. 16-gauge annealed wire or appropriate size clips. When bar spacing is less than 12 inches, tie alternate intersections.

4. Make mechanical butt splices in accordance with rebar splicing coupler manufacturer's installation instructions.

C. Cleaning: Clean or otherwise protect metal reinforcement so that at the time concrete is placed, reinforcement is free from rust, scale or other coatings that will destroy or reduce bond.

Modifications to the Prairie Creek 03 20 00-4 Concrete Reinforcement

October 2021

D. Concrete Reinforcement Protection:

1. Provide protection for reinforcement during concrete pours in accordance with

ACI 318, unless indicated otherwise on the Drawings.

A. Compensation to the Contractor for all costs associated with placement of concrete reinforcement as shown on the Drawings shall be made at the lump sum price in the Bid Schedule for Concrete Reinforcement. Includes all labor, material, and equipment required for procurement and placement of the concrete reinforcement, as shown on the Drawings.

Modifications to the Prairie Creek 03 30 00-1 Cast-In-Place Concrete

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

A. Concrete formwork.

B. Concrete for boat ramp.

C. Joint devices associated with concrete work.

D. Concrete curing.

A. Section 03 20 00 – Concrete Reinforcement.

A. American Concrete Institute:

1. ACI 117; Specifications for Tolerances for Concrete Construction and Materials and Commentary.

2. ACI 211.1; Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete.

3. ACI 221; Guide for Use of Normal Weight and Heavy Weight Aggregates in Concrete.

4. ACI 301; Specifications for Structural Concrete.

5. ACI 304R; Guide for Measuring; Mixing, Transporting and Placing Concrete.

6. ACI 305R; Hot Weather Concreting.

7. ACI 306R; Cold Weather Concreting.

8. ACI 308R; Guide to Curing Concrete.

9. ACI 311.5; Guide for Concrete Plant Inspection and Testing of Ready-Mixed

Concrete.

10. ACI 318; Building Code Requirements for Structural Concrete and Commentary.

11. ACI 347; Guide to Formwork for Concrete.

12. ACI 350; Code Requirements for Environmental Engineering Concrete Structures and Commentary.

B. American Society for Testing and Materials:

1. ASTM C 31; Methods of Making and Curing Concrete Test Specimens in the

Field.

2. ASTM C 33; Specification for Concrete Aggregates.

Modifications to the Prairie Creek 03 30 00-2 Cast-In-Place Concrete

October 2021

3. ASTM C 39; Test Method for Compressive Strength of Cylindrical Concrete Specimens.

4. ASTM C 78; Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading).

5. ASTM C 94; Specification for Ready-Mixed Concrete.

6. ASTM C 143; Test Method for Slump of Portland Cement Concrete.

7. ASTM C 150; Specification for Portland Cement.

8. ASTM C 171; Specification for Sheet Materials for Curing Concrete.

9. ASTM C 172; Methods of Sampling Freshly Mixed Concrete.

10. ASTM C 173; Test Method for Air Content of Freshly Mixed Concrete by the

Volumetric Method.

11. ASTM C 192; Practice for Making and Curing Concrete Test Specimens in the

Laboratory.

12. ASTM C 231; Test Method for Air Content of Freshly Mixed Concrete by the

Pressure Method.

13. ASTM C 260; Specification for Air-Entraining Admixtures for Concrete.

14. ASTM C 295, Guide for Petrographic Examination of Aggregates for Concrete.

15. ASTM C 330; Specification for Lightweight Aggregate for Structural Concrete.

16. ASTM C 494; Specification for Chemical Admixtures for Concrete.

17. ASTM C 618; Standard Specification for Coal Fly Ash and Raw or Calcined

Natural Pozzolan for Use in Concrete.

18. ASTM C

19. ASTM C 989; Standard Specification for Slag Cement for Use in Concrete and

Mortars.

20. ASTM C 1260; Standard Test Method for Potential Alkali Reactivity of

Aggregates (Mortar-Bar Method).

21. ASTM C 1567; Standard Test Method for Determining the Potential Alkali-Silica

Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method).

22. ASTM C1602; Standard Specification for Mixing Water Used in the Production of Hydraulic Cement Concrete.

23. ASTM D 1751; Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types).

24. ASTM D 1752; Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction.

25. ASTM E 329; Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection.

26. ASTM D3963/D3963M - Standard Specification for Fabrication and Jobsite Handling of Epoxy Coated Reinforcing Steel Bars.

Modifications to the Prairie Creek 03 30 00-3 Cast-In-Place Concrete

October 2021

1.04 SUBMITTALS

A. Product Data: Submit manufacturer's descriptive product data and current specifications for the concrete accessories specified herein (admixtures, joint fillers, joint sealants, curing materials, waterstops, etc.). Include installation instructions.

B. Mix Design: Submit proposed concrete mix design.

1.05 QUALITY ASSURANCE

A. Perform work of this section in accordance with ACI 301 and ACI 318.

B. Follow recommendations of ACI 306R when concreting during cold weather.

1.06 MOCK-UP

A. Construct mock-up groove pattern panel for concrete surface.

1. Panel Size: 6 feet by 6 feet.

2. Panel to be located in adjacent parking area during construction.

B. Accepted mock-up panel is considered basis of quality for the finished work. Keep mock-up exposed to view for duration of concrete work.

C. Mock-up may not remain as part of the Work, remove as directed by Government at completion of the Work.

2.01 FORMWORK

A. Formwork Design and Construction: Comply with guidelines of ACI 347 to provide formwork that will produce concrete complying with tolerances of ACI 117.

B. Form Materials: Contractor's choice of standard products with sufficient strength to withstand hydrostatic head without distortion in excess of permitted tolerances.

1. Form Materials: Contractor's choice of standard products with sufficient strength to withstand hydrostatic head without distortion in excess of permitted tolerances.

2.02 REINFORCEMENT

A. Comply with requirements of Section 03 20 00.

Modifications to the Prairie Creek 03 30 00-4 Cast-In-Place Concrete

October 2021

2.03 CONCRETE MATERIALS

A. Cement: ASTM C150, Type II - Moderate Portland type.

1. Acquire all cement for entire project from same source.

2. Meet equivalent alkalies requirements of ASTM C150 – Table 2.

3. Meet false-set requirements of ASTM C150 – Table 4.

B. Fine and Coarse Aggregates: ASTM C 33.

1. Acquire all aggregates for entire project from same source.

2. Coarse aggregate shall have a maximum 3/4-inch particle size.

3. Fine and coarse aggregate shall not be of a carbonate-based rock.

C. Water.

1. Clean and free from injurious amounts of oils, acids, alkalis, salts, organic materials, or other substances that may be deleterious to concrete or reinforcement.

2. Meeting all requirements of ASTM C 94.

2.04 ADMIXTURES

A. Air Entrainment: ASTM C 260.

B. Chemical Admixture:

1. Do not use chemical admixtures which contain more than 0.1 percent chloride, by weight.

2. Admixtures shall be compatible with each other.

3. Allowable chemical admixtures:

a. ASTM C 494, Type A, D, F, G, or S.

b. ASTM C1017, Type I or II.

c. ASTM C494, Type C and E, provided they do not contain chloride.

C. Hydration Control: MasterSet, as manufactured by Master Builders Solutions, or approved equal.

D. Specialized chemical admixtures

1. If the Contractor has not previously used a specialized chemical admixture, admixture manufacturer shall provide on-site representative to assist with mix design and to trial batch plant personnel in dispensing and mixing operations.

2. Chemical and Drying Shrinkage Reducing Admixture

a. PREVent-C manufactured by Premier Magnesia, Construction Products

Group. www.premiercpg.com, or approved equal with the following essential characteristics:

i. Designed to facilitate expansion of concrete at essentially the same rate as shrinkage during curing period.

ii. Designed to reduce capillary surface tension of pore water.

Modifications to the Prairie Creek 03 30 00-5 Cast-In-Place Concrete

October 2021

iii. Provides at least 60% shrinkage reduction.

iv. Formulated for use in freezing weather.

v. Mortar and concrete under restrained shrinkage test, ASTM C1581: No cracking for a minimum 90 days.

b. Coordinate with manufacturer regarding dosage.

2.05 CONCRETE MIX DESIGN

A. Mix concrete in accordance with ASTM C 94.

B. Provide cast-in-place concrete with the following characteristics:

1. Compressive Strength, when tested in accordance with ASTM C39/C39M at 28 days: 4,500 psi.

2. Total Air Content: 5 percent, +/- 1%, determined in accordance with ASTM C173/C173M.

3. Maximum Slump: 4 inches, ± 1 inch.

4. Maximum Aggregate Size: 3/4 inch.

2.06 CURING MATERIALS

A. Polyethylene Film: ASTM D2103, 6 mil thick, clear.

B. Water: Potable, not detrimental to concrete.

C. Liquid curing materials are not acceptable unless approved by the COR.

3.01 GENERAL

A. Place concrete in general conformance with ACI 301, ACI 304.2R, and ACI 314.2R.

3.02 EXAMINATION

A. Verify lines, levels, and dimensions before proceeding with work of this section.

3.03 PREPARATION

A. Formwork: Comply with requirements of ACI 301. Design and fabricate forms to support all applied loads until concrete is cured, and for easy removal without damage to concrete.

B. Pre-position reinforcement in advance of concrete pours.

Modifications to the Prairie Creek 03 30 00-6 Cast-In-Place Concrete

October 2021

3.04 CONCRETE DELIVERY TIME LIMIT

A. The Contractor shall have the capability to deliver the structural concrete to the site within 90 minutes from the time water is added into the concrete mix at the batching plant.

3.05 PLACING CONCRETE

A. Place concrete in accordance with ACI 304R.

B. Notify Government not less than 7 days prior to commencement of placement operations.

C. Ensure reinforcement will not be disturbed during concrete placement.

D. Concrete shall not be placed when the ambient temperature drops below 40°F until provisions and procedures for cold weather concreting are implemented. During periods of cold weather, as defined by ACI 306.1, the Contractor will only be allowed to place concrete in accordance with the approved cold-weather placement plan.

Concrete may not be placed during heavy rain (more than 0.3 inch per hour or 0.03 inch in 6 minutes as defined by the Weather Bureau Glossary of Meteorology). If unusual adverse weather such as heavy rain, severe cold, heavy snow, etc. occurs, or is forecast to occur during placement, an interruption in placing operations may be approved or directed. All placed concrete materials shall be fully consolidated prior to stopping work. The Contractor should allow for any construction schedule risk and added expense that could occur as a result of adverse weather, and shall receive no additional compensation because of weather delays.

E. Concrete temperature at the time of placement shall be between 50°F and 90°F.

Concrete which does not meet this temperature requirement shall be rejected.

Rejected concrete shall not be paid for.

F. Conveying

1. Handle concrete from mixer to final deposit rapidly by methods which will prevent segregation or loss of ingredients to maintain required quality of concrete.

2. Do not convey concrete through aluminum or aluminum alloy.

3. Do not place concrete by pumps or other similar devices without prior written approval of Contracting Officer’s Representative.

4. Placing concrete by pumping methods shall conform to the applicable requirements of ACI 304R, Chapter 9, and ACI 304.2R.

5. Concrete shall be placed within 1-1/2 hours of introduction of water to the cement and aggregates at the batching plant. Do not add water to the concrete mix at the site.

Modifications to the Prairie Creek 03 30 00-7 Cast-In-Place Concrete

October 2021

G. Depositing

1. Do not drop concrete freely where reinforcing will cause segregation, nor more than four (4) feet.

2. Do not allow concrete to flow laterally more…