Statement of Work RLB21403 Latrine.docx

DOCX document 26 KB Posted

Attached to
Sanitary Capacity
Solicitation number
W9124926RA015
Issued by

About this file

This is a Statement of Work (SOW) for a plumbing system replacement and main line upgrade at Building RLB21403. The contractor shall remove approximately 630-650 linear feet of existing 3-inch sanitary main piping and install new 4-inch and 6-inch sanitary sewer mains, including demolition, installation of branch and main lines, reconnection of all plumbing fixtures, excavation to tie into the Augusta Utilities Department (AUD) main, and restoration of disturbed areas. All work must comply with applicable plumbing codes, safety standards, and local utility requirements.

The project requires reconnection of 23 toilets, 27 sinks, 6 urinals, 5 floor drains, 8 drinking fountains, 2 floor sinks, and 1 mop sink. The contractor shall install four 4-inch branch lines (two serving each latrine) and a new 6-inch main line running approximately 230-250 feet from beneath the building to the AUD sanitary main. Prior to shutting down the latrines, the contractor must provide and maintain temporary restroom facilities comprising 29 portable toilets and 27 handwashing stations, with pricing required for both once-per-week and twice-per-week servicing. The solicitation (W9124926RA015) is issued by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis, with contract questions due April 1, 2026 at 10:00 AM EST and proposals due April 7, 2026 at 10:00 AM EST.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Project: Plumbing System Replacement and Main Line Upgrade Location: Building RLB21403

1.0 Scope

The Contractor shall provide all labor, materials, equipment, supervision, and necessary to remove existing sanitary piping and install new 4‑inch and 6‑inch sanitary sewer mains in Building RLB21403. Work includes demolition of existing 3‑inch mains, installation of new branch and main lines, reconnection of all plumbing fixtures, excavation to tie into the Augusta Utilities Department (AUD) main, and restoration of disturbed areas. Contractor shall perform all work in accordance with applicable plumbing codes, safety standards, and local utility requirements.

2.0 Project Requirements

2.1 Demolition and Removal

· Contractor shall remove approximately 630 – 650 linear feet of existing 3‑inch sanitary main piping located beneath the building.

· Contractor shall disconnect all existing piping at or above floor penetrations to avoid damage to finished surfaces.

· All removed materials shall be disposed of in accordance with federal, state, and local regulations.

2.2 Installation of New Piping

2.2.1 Fixture Reconnection

Contractor shall reconnect the following plumbing fixtures to the new sanitary system:

Fixture Type
Quantity
Location
Toilets
23 total (10 women’s, 13 men’s)
Latrines
Sinks
27 total (9 women’s, 18 men’s)
Latrines
Urinals
6
Men’s latrine
Floor Drains
5 total (2 women’s, 3 men’s)
Latrines
Drinking Fountains
8
Throughout building
Floor Sinks
2
Utility areas
Mop Sink
1
Utility area

· Contractor shall install P‑traps on all floor drains, sinks, floor sinks, and the mop sink.

2.2.2 Branch Line Installation

· Contractor shall install new 4‑inch branch lines serving the men’s and women’s latrines.

· Each latrine contains two primary branch lines, for a total of four (4) branch lines.

· All branch lines shall be installed with proper slope per code and supported per manufacturer and code requirements.

2.2.3 Main Line Installation

· Contractor shall install a new 6‑inch sanitary main running between the men’s and women’s latrines.

· The four (4) branch lines (two from each latrine) shall tie into the new 6‑inch main.

· The 6‑inch main shall run approximately 230 – 250 feet from beneath the building to the AUD sanitary main located outside the structure (identified by green paint).

· Contractor shall route the new main to exit the building adjacent to the left‑side porch to avoid structural removal.

· All piping shall be fully supported and installed with correct pitch to ensure proper flow.

2.3 Excavation and Utility Tie‑In

· Contractor shall excavate to the required depth to expose the AUD main line.

· Contractor shall tie the new 6‑inch building main into the AUD main in accordance with AUD standards and inspection requirements.

· After tie‑in, Contractor shall backfill to rough grade and install erosion control matting to prevent soil washout.

3.0 Temporary Facilities

· Prior to shutting down the latrines, Contractor shall provide and maintain temporary restroom and handwashing facilities.

· Required minimum quantities:

· 29 portable toilets

· 27 handwashing stations

· Contractor shall provide pricing for once‑per‑week and twice‑per‑week servicing/cleaning.

· Temporary facilities shall remain in place and fully operational until the permanent plumbing system is restored and accepted.

4.0 General Requirements

· Contractor shall comply with all OSHA, federal, state, and local safety regulations.

· Contractor shall coordinate all inspections with the Government and AUD.

· Contractor shall maintain a clean and safe worksite at all times.

· All work shall be performed during approved working hours unless otherwise authorized.