PRE-FABRICATED FIRE TRAINING TOWER
Solicitation number
W50S9H26QA011
Issued by

About this file

This Statement of Work (SOW) details the requirements for a new prefabricated fire training tower for Volk Field Combat Readiness Training Center in Camp Douglas, Wisconsin. The project involves replacing an existing fire training tower from the early 1990s with a new NFPA 1402 compliant structure that includes three stories with four working deck levels, multiple specialized training areas (burn room, residential section, training tower section), and numerous specific features like vertical ventilation trainer, chop trainer, rappelling anchor points, and a burn room with insulation system. The tower must be delivered by May 15, 2026, with estimated tower assembly completion by August 7, 2026, and will be installed using troop labor following the manufacturer's specifications. The contractor is required to provide site adaptation plans, comprehensive assembly instructions, technical support during assembly, and conduct commissioning services to verify proper installation and functionality.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

for

New Prefabricated Fire Training Tower

December 19, 2025

REQUIREMENT LOCATION:

The Fire Trainer Tower is located in the Fire Training Area on Volk Field Combat Readiness Training Center (CRTC), Camp Douglas, Wisconsin.

BACKGROUND:

The Volk Field Combat Readiness Training Center, located at the Volk Field Air National Guard Base, currently utilizes a fire training tower that was manufactured and installed in the early 1990s. After decades of service, the structure has reached the end of its operational life cycle and is no longer suitable for continued use. To maintain effective fire training capabilities, the Government has identified the need to replace the existing tower with a new prefabricated fire training tower that meets current safety and performance standards. The replacement project will be executed using troop labor, with installation conducted in accordance with the manufacturer’s specifications. The Government’s objective is to have the new tower manufactured and delivered to Volk Field by Spring 2026. Following installation, the manufacturer will be required to certify that the tower has been properly installed and is fully operational.

PROJECT OBJECTIVES:

The objective of the project is to provide the materials, designs, plans, and assembly instructions required to replace the existing Volk Field Fire Trainer Tower with a new, site adapted, NFPA 1402 compliant prefabricated Fire Trainer Tower.

The new Prefabricated Fire Trainer Tower MUST include the following features:

OVERALL STRUCTURE

Three (3) story with four (4) working deck levels Minimum one (1) burn room – See Burn Room Annex below Minimum one (1) room with reconfigurable/movable walls Vertical Ventilation Trainer Chop trainer Rappelling/Fall protection anchor points on all roof working surfaces Balcony appropriate for ladder training operations Manufacturer’s structural documentation, plans, designs (to include as-builts) 3 Separate Sections (Burn Annex, Residential Section, Training Tower Section)

TRAINING TOWER SECTION

12’-0” x 22’-0” x 40’-0” Flat roof Wind Load 100 MPH, Exposure C, Risk Category I Roof live load - 100 PSF Floor live load - 100 PSF 2’-6” x 3’ roof hatch (1 ea.)

3’ x 4’ window openings with steel shutters (one per floor) 3’ x 7’ metal exterior door (1 ea.)

2’-8” x 7’ metal exterior door (Second and third floor) Interior “U” shaped stairs to the third deck level Interior fixed ladder, third deck to lower roof Parapet roof guard with exclusive roof drainage to the exterior of the building with chained openings

RESIDENTIAL SECTION

22’-8” x 22’-0” x 27’-3” ridge

16-degree double pitched, gabled roof Wind Load 100 MPH, Exposure C, Risk Category I Roof live load 100 PSF Deck live loads 100 PSF (including attic area) 11’-8” x 22’-0” Burn Room with Insulation System suitable for a live-burn environment Attic drywall frame (2 ea.)

Roof ladder fender brackets (8 ea.)

3’ x 4’ window openings with steel shutters (7 ea.)

6’ x 4’ window opening with steel shutters (1 ea.)

3’ x 7’ exterior steel door (1 ea.)

6’ x 7’ exterior double leaf steel door (1 ea.)

3’ x 7’ interior steel door (1 ea.)

3’ x 3’ hinged gable louvered shutters (2 ea.)

4’ x 4’ roof chop-out curbs, 12 ga. galvanized (2 ea.)

BURN ANNEX

14’-0” x 22’-0” x 9’-10” High ½” in 12” single pitch roof Wind Load 100 MPH, Exposure C, Risk Category I Roof live load - 100 PSF 3’ x 4’ window openings with steel shutters (3 ea.)

3’ x 7’ exterior metal door (1 ea.)

3’ x 7’ interior metal doors (1 ea.)

Stainless Steel insulation system & temperature monitoring system suitable for a live-burn environment

ADDITIONAL REQUIREMENTS

Fire Escape Ships Ladder Roof hatch Forged Swivel Rappelling Anchor Riser System Sprinkler system (for training) Exhaust Fan Smoke Distribution System Reconfigurable Maze Using Movable Wall System Ladder Hook Bar Rappel Railing System Foundation Design Cantilevered Rappelling Platform (minimum of 4’x4’) Corner/inset Balcony Forcible Entry Training System/door Heavy-duty Spring Closer for Burn Room Doors Helicopter Skid Simulator Stainless Steel burn room insulation system Integrated Temperature Monitoring System As-builts Concrete footing/pad design Assembly Instructions including recommended tools/equipment 1-year Product Warranty

SITE ADAPTATION - Contractor shall provide site adaptation plans. The plans must provide detailed concrete footing and pad design, including necessary rebar size and layout, minimum concrete strength specifications, and subbase requirements. Project area is highlighted on the attached map. The contractor is responsible for verifying the site condition. A site visit is highly encouraged.

ASSEMBLY INSTRUCTIONS – The contractor shall furnish comprehensive written and graphical assembly instructions to support the installation of the Fire Training Tower by competent tradesmen who may have no prior experience with fire training tower assembly. These instructions must clearly detail each step of the assembly process and include a complete list of required equipment and tools.

The contractor shall provide the instructions in electronic format via CD or DVD, along with three (3) printed hard copies delivered to the Government.

TECHNICAL SUPPORT AND COMMISSIONING SERVICES – During assembly, the Contractor shall be available to review and respond to technical questions regarding proper assembly. The Government will make all attempts to utilize the provided assembly instructions prior to contacting the Contractor with questions. Following the completion of tower construction, the contractor shall conduct a site visit to Volk Field Air National Guard Base to perform commissioning services. This includes verifying the proper assembly and operational functionality of all components of the Fire Training Tower. Should any deficiencies be identified, the contractor shall return to the site to ensure all necessary corrections are made and full functionality is achieved. The one-year warranty period will commence upon successful commissioning of the tower.

WORK SCHEDULING:

1. Normal base work hours for the Contractor are defined as 6:00 am – 4:30 pm Monday - Friday, excluding Federal Holidays.

2. If the Contractor desires to deliver the prefabricated fire training tower materials during periods other than above, they must coordinate with and gain approval from the Contracting Officer in advance of their intention to deliver during other periods.

3. The required delivery date of the concrete pad design is March 2nd, 2026

4. The required delivery date of the tower and the assembly instructions is May 15, 2026

a. The estimated completion of the tower assembly by troop labor is August 7th, 2026.

Prior to completion, the Government will schedule a date for commissioning services.

5. Additional coordination will be required after the completion to facilitate project closeout requirements.

GENERAL CONDITIONS:

The contractor shall comply with all applicable local, State and Federal laws and regulations. The contractor shall field verify all site conditions, quantities, measurements, and requirements.

MATERIAL DELIVERIES:

The contractor shall notify the Government prior to delivery of any material to the site. The contractor shall ensure someone is available to receive delivered materials. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and will be turned away.

ANTITERRORISM / OPERATIONS SECURITY / INFORMATION PROTECTION

1. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

2. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC- III) and Terrorist Screening Database (TSDB) (DODIO 2000.16V1_DAFI 31-145, DAFI 31-101 and DODM 5200.08v3_DAFMAN 31-101v3), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor, completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online (JKO) at https://jko.jten.mil/courses/AT-level1/launch.html . For those without a CAC, select "Non-CAC" user on the JKO site. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.

Questions concerning this SOW can be directed to Volk Field Contracting at 608-427-1235 or by email at