This is a Unit Developed Statement of Work (SOW) for the Delta Fence Project by the 55th AMXS at the Bennie Davis Maintenance Facility. The project requires installing a 6 foot 8 inch wide by 10 foot high walkway gate with a cipher lock (KABA Simplex 1021B or similar) between Deltas 1 and 2 to block unauthorized personnel from accessing restricted areas. The gate will have secured fence posts, a chain-fence, and potentially be topped with barbed wire to reach the full 10-foot height requirement.
Key project requirements include obtaining necessary security and safety clearances, performing a mandatory pre-bid site visit, breaking down the bid into materials and labor line items, meeting federal safety standards, and completing the installation within specified parameters. The contractor must obtain all required permits, clean up the work site, repair any government property damage, and dispose of excess materials properly. The project aims to enhance security by creating a controlled access point in a currently unrestricted area of the facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Unit Developed Statement of Work
FOR
Delta Fence Project 55th AMXS
Objectives: The 55th AMXS is requesting a gate with a cipher lock be put up in the hallway between Deltas 1&2. The gate will be next to the opening closest to Delta 1.
Justification: The gate would block unauthorized personnel from reaching restricted areas of the Bennie Davis Maintenance Facility. Delta 1 is a “free zone” used for various functions around the base, and currently, personnel can get into restricted areas with minimal restriction; this would add a barrier for them to get into restricted areas
Description of services: Project includes, but not limited to the following work elements. Use system components below to define scope of requirements.
1. Interior Construction Requirement
a. This requirement needs a 6 foot 8 inch wide by 10 foot high walkway with open ceiling blocked by a fence with a gate that may be topped with barbed wire to reach the 10 foot height requirement.
b. Fence posts secured to the ground and/or walls in a fashion that they could not be manipulated to move, Chain-fence and gate to fit in between fence posts/walls.
c. Install gate with cipher lock KABA Simplex 1021B or similar equipment approved by the government that code can be changed.
Acceptance Criteria: Work will be considered acceptable after all the following conditions are met
1. When a gate is installed with a cipher lock that can be changed.
2. All loose and unnecessary supplies and items associated with the work contained in this SOW have been removed from the work site and properly disposed of.
Other Requirements
1. Ensure all construction meets federal regulations for safety standards.
2. Bonding is required (if applicable).
3. The contractor is required to perform a site visit prior to and must coordinate with the facility manager to schedule work to be performed.
4. All security requirements must be met to include times of demolition and construction.
5. The contractor is required to perform a site visit prior to bid. Contractor who are not present will not be in consideration.
6. Bid shall be broken down to materials and labor as individual line items.
7. The Contractor shall furnish all required services, labor, tools, material, and equipment necessary to complete the installation and integration of the prime mission equipment in accordance with the approved site design and installation plan. In addition, the Contractor shall be responsible for the following actions:
a. Obtaining all necessary security and safety clearances for facilities and personnel. This includes obtaining escort badges necessary for unaccompanied work within the area.
b. Obtaining necessary certifications for installation equipment and technologies to be installed.
c. Obtaining environmental and life safety approvals.
d. Acquiring all necessary federal, state, local and base environmental and civil engineering permits and approvals.
e. Cleaning-up and restoring the site to its original or better condition within 10 workdays after project completion.
f. Repairing damage to Government property resulting from contractor activities, assuring the property is returned to its original or better condition.
g. Removing all debris at the end of each shift or more frequently if required to keep the work area safe and useable.
h. Disposing of excess equipment and materials in accordance with General Requirements.