Statement of Work_FFT Test Stand.pdf

PDF 1 MB Posted

Attached to
Fuel Flow Transmitter Test Stand Federal contract opportunity
Solicitation number
FA8126
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This Statement of Work (SOW) details the requirements for designing, manufacturing, and installing a new Fuel Flow Transmitter (FFT) Test Stand at Tinker Air Force Base, Oklahoma City Air Logistics Center. The test stand will be used to test fuel flow transmitters for multiple aircraft platforms including A-10, B-1, B-52, C-130, KC-135, F-15, F-16, and F-22 aircraft. Key technical specifications include a semi-automated system with a Human Machine Interface (HMI) touchscreen, high flow and high-pressure testing capabilities, a 63"Wx50"Dx82"H test chamber with clear Plexiglas doors, and comprehensive software requirements utilizing LabVIEW and a Siemens S7 Programmable Logic Controller.

The project requires a comprehensive delivery including design reviews, calibration procedures, factory acceptance testing, correlation testing, training for operators and maintenance personnel, and extensive documentation. The contractor must provide Level 3 drawings, commercial and operation manuals, and meet strict technical standards including NFPA and ASME compliance. The test stand must be designed for a Class I, Division II environment, with specific requirements for electrical components, software security, and data acquisition. The total contract is structured with multiple payment CLINs totaling 100% of costs, with deliverables and milestones spanning approximately 18 months from contract award, with a target delivery date of no later than eighteen months after contract issuance.

View the file

Other files for this federal contract opportunity

Other files attached to Fuel Flow Transmitter Test Stand, newest first.
File Type Posted
Sources Sought_FFT Test Stand.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

FUEL FLOW TRANSMITTER TEST STAND

BUILDING 3907

Oklahoma City Air Logistics Center Tinker Air Force Base

Prepared by

Thomas Pham

76 CMXG/MXDEC

17 July 2025

DRAFT

Fuel Flow Transmitter Test Stand Statement of Work

SOW-Fuel Flow Transmitter Test Stand Page 2

Table of Contents

1. SCOPE OF WORK:

1.1 SCOPE:

1.2 BACKGROUND:

2. APPLICABLE GOVERNMENT AND INDUSTRY STANDARDS:

2.1 GOVERNMENT STANDARDS:

2.2 NON-GOVERNMENT STANDARDS:

2.3 ORDER OF PRECEDENCE:

2.4 APPLICABLE STANDARDS

2.5 PROHIBITED MATERIALS:

2.6 ENVIRONMENTAL PROTECTION:

3. TEST STAND REQUIREMENTS:

3.1 GENERAL:

3.2 CONSTRUCTION:

3.3 INTERCHANGEABILITY:

3.4 MAINTAINABILITY:

3.5 LUBRICATION:

3.6 UTILITIES AND MAINTENANCE ACCESS:

3.7 INSTALLATION PLAN:

3.8 TEST STAND AREA CLASSIFICATION:

3.9 PC AND PLC CONTROL SYSTEM:

3.10 CALIBRATION EQUIPMENT:

3.11 TEST STAND PRELIMINARY/FINAL CALIBRATION:

3.12 TEST STAND IVV AND AS-BUILT DRAWING REVIEW:

3.13 UUT FIXTURES AND TOOLING:

3.14 SOFTWARE:

3.15 PC AND SOFTWARE SECURITY:

3.16 EXTENDED SPARES KIT:

4. ACCEPTANCE TESTS

4.1 ACCEPTANCE TESTING WITH BASELINE DATA:

4.2 VIBRATION BASELINE TESTING:

4.3 AUDIBLE NOISE TEST:

4.4 FACTORY ACCEPTANCE TEST REPORT:

4.5 SOFTWARE TEST REPORT:

4.6 CORRELATION TEST REPORT:

4.7 MONTHLY STATUS REPORT:

4.8 TEST PLAN:

4.9 TRAINING PLAN:

4.10 WARRANTY:

5. QUALITY ASSURANCE PROVISIONS

5.1 RESPONSIBILITY FOR INSPECTIONS:

5.2 RESPONSIBILITY FOR COMPLIANCE:

5.3 ENVIRONMENTAL CONDITIONS:

5.4 VISUAL EXAMINATION:

6. DESIGN REVIEWS

6.1 PRELIMINARY DESIGN REVIEW:

SOW-Fuel Flow Transmitter Test Stand Page 3

6.2 INTERMEDIATE DESIGN REVIEW:

6.3 CRITICAL DESIGN REVIEW:

6.4 FACTORY ACCEPTANCE TEST:

6.5 TEST STAND CORRELATION:

6.6 FINAL ACCEPTANCE:

6.7 EMERGENCY POC:

7. TECHNICAL DATA REQUIREMENTS

7.1 MANUALS/DRAWINGS:

7.2 WORK PLAN DRAWINGS

7.3 AS-BUILT DRAWINGS

7.4 SOFTWARE DOCUMENTATION:

7.5 COMMERCIAL MANUALS:

7.6 LEVEL 3 DRAWINGS:

7.7 DOCUMENTATION:

8. TRAINING REQUIREMENTS

8.1 GENERAL:

8.2 OPERATOR TRAINING:

8.3 ELECTRICAL/MECHANICAL TRAINING:

8.4 CALIBRATION TRAINING:

8.5 SOFTWARE/PROCESS ENGINEER TRAINING:

9. SPECIAL PROVISIONS

9.1 GOVERNMENT OCCUPANCY OF FACILITIES & RESPONSIBILITIES:

9.2 GOVERNMENT INSTALLATION ACCESS:

9.3 WORKING HOURS:

9.4 SAFETY, FOREIGN OBJECT DEBRIS (FOD), DROPPED OBJECT PREVENTION (DOP) & QUALITY CONTROL

9.5 HOUSEKEEPING

9.6 TOOL CONTROL AND ACCOUNTABILITY:

9.7 FIELD VERIFY:

10. PROPOSAL BY CONTRACTOR:

10.1 DESCRIPTION:

10.2 REQUIREMENTS:

10.3 NOTICE:

11. OTHER WRITTEN SUBMITTALS:

11.1 REQUIRED SUBMITTALS

12. GOVERNMENT FURNISHED PROPERTY AND SERVICES

12.1 GOVERNMENT FURNISHED PROPERTY (GFP)

12.2 SHARED PROPERTY OF THE GOVERNMENT

12.3 SHARED STORAGE AREAS

12.4 CEASE TO USE AND RETURN TO GOVERNMENT

12.5 GOVERNMENT FURNISHED SERVICES

12.6 INTANGIBLE GOVERNMENT PROPERTY

12.7 GOVERNMENT FURNISHED DRAWINGS

SOW-Fuel Flow Transmitter Test Stand Page 4

Table of Tables Table 1- Summary of Required Submittals

APPENDICES

Appendix A: Reliability Centered Maintenance and Vibration Severity Chart Appendix B: Safety Specifications Appendix C: Glossary and Definitions Appendix D: Environmental Appendix E: Certification Test Plan Appendix F: Current Test Stand Technical Manuals Appendix G: Current Test Stand Drawings Appendix H: UUT Test Specifications Appendix I: 76 CMXG Design Guidelines Appendix J: Contract Data Requirements List (CDRL)

SOW-Fuel Flow Transmitter Test Stand Page 5

1. SCOPE OF WORK:

1.1 Scope: The following establishes the minimum requirement for the purchase, delivery and installation of one (1) Fuel Flow Transmitter (FFT) Test Stand with equipment and accessories specified herein; and training on the maintenance, calibration, programming, and use of said test stand. The test stand will be used to test A-10, B-1, B-52, C-130, KC-135, F-15, F-16 Fuel Flow Transmitters and F-22 Flow Valve as required and as per their relevant Technical Orders (T.O.’s). The Contractor shall supply all engineering, labor, materials, parts, tools, equipment, supplies, transportation, software, and incidentals necessary to operate the test stand. The overall project shall be considered a whole and complete procurement with final acceptance requirements met and approved by the appropriate Government POCs and operational training having been completed. Acceptance testing must be performed onsite at B3907 and the government shall supply the end-items for the acceptance testing.

1.2 Background: The test stands described in this document are intended for use in the Aerospace Repair Industry. The equipment shall be installed in Building 3907, Room 112, at Tinker AFB, OK. This shop runs on 24 hours basis Monday through Friday with possible overtime hours on the weekend. Test stands will be installed in a National Electric Code, Class I, Division II, Group D environment, as per NFPA 70, Article 500. All installation work associated with this contract shall have no impact on production.

2. APPLICABLE GOVERNMENT AND INDUSTRY STANDARDS:

Contractor, at a minimum, is required to comply with the current editions of the following requirements for design, construction, installation, and safety as applicable. The term “most recent edition” shall be understood to mean “most recently released edition as of date of issuance of contract.”

2.1 Government Standards: The following documents form a part of this purchase description to the extent stipulated herein.

2.1.1 U. S. DEPARTMENT OF LABOR

2.1.1.1 29 CFR 1910 – General Industry, OSHA Safety and Health Standards (29 CFR

1910), 2010 or most recent edition (available at http://www.osha.gov/)

2.1.1.2 (Application for copies should be addressed to the U.S. Department of Labor, 200

Constitution Ave, Washington, D.C. 20210)

2.1.2 ENVIRONMENTAL PROTECTION AGENCY

2.1.2.1 40 CFR 82 – Protection of Stratospheric Ozone, 2010 or most recent edition

2.1.2.2 (Application for copies should be addressed to the U.S. Department of Labor, 200

Constitution Ave, Washington, D.C. 20210)

2.1.3 FEDERAL STANDARDS

2.1.3.1 FED-STD-H28A – Screw Thread Standards for Federal Services, 1994 (R2001) or most recent edition http://www.osha.gov/

SOW-Fuel Flow Transmitter Test Stand Page 6

2.1.3.2 FED-STD-H28/21B – Screw Thread Standard for Federal Service, Metric Screw Threads, 1984 (R2006) or most recent edition

2.1.3.3 UFC 3-600-01 – Fire Protection Engineering for Facilities

2.1.3.4 UFGS 07 84 00 – Firestopping

2.1.3.5 UFGS 21 13 13 – Wet Pipe Sprinkler Systems

2.1.3.6 UFGS 21 13 22 – Foam Fire Extinguisher for Haz/Flam Material Facility

2.1.3.7 UFGS 21 21 01 – Carbon Dioxide Fire Extinguishing (High Pressure)

2.1.3.8 UFGS 21 21 02 – Carbon Dioxide Fire Extinguishing (Low Pressure)

2.1.3.9 UFGS 28 31 64 – Fire Detection and Alarm System

2.1.3.10 (Application for copies should be addressed to Superintendent of Documents, Government Printing Office, Washington, D.C. 20402-001).

2.2 Non-Government Standards: The following documents form a part of this document to the extent stipulated herein.

2.2.1 NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

2.2.1.1 NFPA 1 – Fire Code, 2010 edition or most recent edition

2.2.1.2 NFPA 11 – Standard for Low-, Medium-, and High-Expansion Foam, 2016 edition or most current

2.2.1.3 NFPA 12 – Standard on Carbon Dioxide Extinguishing Systems, 2024 edition or most current

2.2.1.4 NFPA 16 – Standard for the Installation of Foam-Water Sprinkler and Foam-Water

Spray Systems, 2019 edition or most current

2.2.1.5 NFPA 70 – National Electrical Code, 2014 edition

2.2.1.6 NFPA 70E – Standard for Electrical Safety in the Workplace, 2011 edition or most recent edition

2.2.1.7 NFPA 79 – Electrical Standards for Industrial Machinery, 2007 or most recent edition

2.2.1.8 (Application for copies should be addressed to National Fire Protection

Association, Battermarch Park, Quincy, MA 02269)

2.2.2 TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA) STANDARD

2.2.2.1 EIA/TIA-232-F – Interface Between Data Terminal Equipment and Data Circuit- Terminating Equipment Employing Serial Binary Data Interchange, 1997 (R 2002) or most recent edition

2.2.2.2 (Application for copies should be addressed to IHS International Inc., http://www.ihs.com, or call 1-800-854-7179 for U.S. and Canada)

2.2.3 NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

2.2.3.1 NEMA MG 1 – Motors and Generators, 2009 (R2010) or most recent edition http://www.ihs.com/

SOW-Fuel Flow Transmitter Test Stand Page 7

2.2.3.2 NEMA ICS 6 – Industrial Control and Systems: Enclosures, 1993 (R2006) or most recent edition

2.2.3.3 (Application for copies should be addressed to National Electrical Manufacturers Association, 1300 N 17th Street, Suite 1752, Rosslyn, VA 22209)

2.2.4 AMERICAN NATIONAL STANDARD INSTITUTE

2.2.4.1 ASTM SI 10 – American National Standard for use of the International System of

Units (SI): The Modern Metric System, 2010 or most recent edition

2.2.4.2 (Application for copies should be addressed to American National Standards

Institute, Attn: Sales Department, 1430 Broadway, New York, NY 10018-3363)

2.2.5 AMERICAN WELDING SOCIETY INC (AWS)

2.2.5.1 AWS D14.4 – Specification for Welded Joints in Machinery and Equipment, 1997 or most recent edition

2.2.5.2 (Applications for copies should be addressed to the American Welding Society Inc., 550 North LeJeune Road, Miami, FL 33126)

2.2.6 INTERNATIONAL ORGANIZATION FOR STANDARDIZATION

2.2.6.1 ISO 4413 – Hydraulic Fluid Power – General Rules and Safety Requirements for

Systems and Their Components, 2010 or most recent edition

2.2.6.2 (Application for copies should be addressed to International Organization for

Standardization, 1, Ch. de la Voie-Creuse, Case postale 56, CH-1211 Geneva 20, Switzerland, e-mail central@iso.ch or IHS International Inc., http://www.ihs.com, or call 1-800-854-7179 for U.S. and Canada)

2.3 Order of Precedence: In the event of a conflict between the test of this specification and the references cited herein, the test of this specification takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exception has been obtained.

2.4 Applicable Standards

2.4.1 Dimensional Systems: U.S. Customary System of Units (US) shall be used in the design and construction. In this specification, all measurements, dimensions, sizes, and capacities are given in the U.S. Customary System of Units (US).

2.4.2 Measuring/Indicating Devices: All measuring and indicating devices, such as dial indicators, pressure gauges, temperature indicators, depth stops, and other similar devices used on the machine, shall be graduated in inch-pound units. Marking on all measuring and indicating devices shall be permanently and legibly engraved or etched on a non-glare background. All dials and other type indicating devices shall be securely mounted in place. Such devices shall be located to allow reading from the operator’s normal workstation.

2.4.3 Safety and Health: Covers, guards, and other safety devices shall be provided for all parts of the machine that present safety hazards. The safety devices shall not interfere with the operation of the machine. The safety devices shall prevent unintentional contact

DRAFT

mailto:central@iso.ch http://www.ihs.com/

SOW-Fuel Flow Transmitter Test Stand Page 8 with the guarded part and shall be removable to facilitate inspection, maintenance and repair of the parts. All machine parts, components, mechanisms and assemblies furnished on the machine shall comply with all of the requirements of 29 CFR 1910.

2.4.4 Cautions–Warning Plates: Corrosion resistant “Caution” or “Warning” Plates shall be securely attached to the equipment in visible locations with any safety precautions to be observed by the operator or maintenance personnel permanently marked on the plates.

2.4.5 Noise Levels: The noise level emitted by the equipment under load shall not exceed 80 dBA when measured at the operator’s workstation or at any other point at a distance of three (3) feet from any of the equipment associated with the test stand unit as measured on the “A” weighted scale of a standard Type II sound level meter.

2.4.6 Chemicals: The Contractor shall not transport, ship or use any chemical, material or substance used in the performance of this SOW unless prior written approval is provided, Natural Infrastructure Management (Environmental Compliance). The Contractor shall furnish to the Government POC a list of all chemicals used in conjunction with the Installation of the equipment, container sizes and quantities, and their Safety Data Sheets (SDS) sixty (60) working days prior to shipment. The government reserves the right to reject use of any chemicals and request alternative(s) be proposed for completion of the installation. Proper use, storage and removal of any chemical required during installation of test stand shall be coordinated with the Tinker Unit Environmental Coordinator (UEC). UEC info will be made available to Contractor by Government POC, as needed. Contractor shall remove all unused chemicals from Tinker AFB. Contractor shall comply with all chemical and environmental requirements as stipulated in Appendix D.

2.4.7 Instruction Plates: All words on instruction plates shall be in the English language.

Words shall be engraved, etched, embossed, or stamped in boldfaced letters on a contrasting background. Lettering shall be a minimum of 18-point font and the plates shall be sized accordingly to accommodate all standard text in this point size. Plates and lettering shall be fully compatible with MIL-PRF-7808L Grade 3 synthetic turbine engine oil and suffer no degradation when subjected to it.

2.4.8 Nameplate: A corrosion resistant metal nameplate permanently and legibly marked with the following information shall be securely attached to the machine in a readily visible location. Nameplate and lettering shall be fully compatible with MIL-PRF-7024 Type II Calibrating Fluid and shall suffer no degradation when subjected to it. Lettering shall be a minimum of 18-point font.

2.4.8.1 Nomenclature of the Machine

2.4.8.2 Manufacturer’s Name and Address

2.4.8.3 Manufacturer’s Model Number

2.4.8.4 Manufacturer’s Serial Number

2.4.8.5 Date of Manufacture

2.4.8.6 Contract Number

2.4.8.7 Services Requirements – All service requirements to be included.

SOW-Fuel Flow Transmitter Test Stand Page 9

2.4.9 Castings and Forgings: All castings and forging shall be free from defects, scale, or mismatching. Processes such as welding, peening, plugging, or filling with solder or paste shall not be used on casting and forgings for reclaiming any parts of the machine.

Such processes may only be used for enhancing surface finish and appearance.

2.4.10 Welding, Brazing, and Soldering: Welding, brazing, or soldering shall be employed only where those operations are included in fabrication of the original design. These operations shall not be employed as repair or reclamation measures for defective parts.

Any excess material used for such operations shall be thoroughly removed from the part(s) upon completion of the operations. Weldments shall comply with AWS D14.4.

2.4.11 Surface Finish: All surfaces of castings, forgings, molded parts, stampings, and welded parts shall be clean and free from sand, dirt film, sprues, flash, scale flux, and other harmful or extraneous materials. External surface edges shall be either rounded or beveled unless sharpness is required to perform a necessary function. Except as otherwise specified herein, the condition and finish of all surfaces shall be commensurate with the manufacturer’s standard commercial practice.

2.4.12 Gears: All gears and pinions, if applicable, shall be designed and manufactured of a suitable ferrous material with proper width and size to transmit full-rated torque and horsepower throughout the speed ranges without failure for the expected service life of the machine.

2.4.13 Painting: Yellow or orange safety color-coding shall be used for designated physical hazards.

2.4.14 Screw Threads: All threaded parts used on the machine and its related attachments and accessories shall conform to FED-STD-H28 or FED-STD-H28/21B.

2.4.15 Electrical Items: All electrical/electronic components located within the interior and footprint of test stand shall meet or exceed the minimum requirements defined by NFPA 70 Article 500 Class I, Division 1, Group D environment. Areas exterior to this region shall be Class I, Division 2 rated per NFPA 70, Article 500.

2.4.15.1 If purge air cabinets are utilized, purge air requirements shall be limited to 200 scfm. Contractor shall be responsible for tapping into existing supply duct in the Test Bay as necessary for any required feed to system and shall include a manual volume damper for flow control.

2.4.15.2 Purge air system and enclosures shall be protected from over pressurization. The system shall conform to NFPA 496 and International Society of Automation (ISA)

12.4 standards and be Underwriters Laboratory (UL) classified.

2.4.16 Electrical System: The machine shall be capable of running using the existing power supply source 480 VAC, 60 Hz, 3 Phase, Y Configuration.

2.5 Prohibited Materials:

2.5.1 Mercury restriction: The machine shall contain neither mercury nor mercury compounds or be exposed to free mercury during manufacture.

2.5.2 Asbestos restriction: Asbestos and materials containing asbestos shall not be used on or in the machine.

SOW-Fuel Flow Transmitter Test Stand Page 10

2.5.3 Polychlorinated Biphenyl (PCB) restriction: The use of polychlorinated biphenyl on or in the machine is prohibited.

2.5.4 Lithium restriction: Lithium batteries used in the computer system are exempt from this requirement.

2.5.5 Ozone Depleting Chemicals (ODC) Restrictions: Class I ozone depleting substances in accordance with (IAW) section 602(a) of the Clean Air Act Amendments 1990, 42 USC 7671a(a) as implemented by 40 CFR 82 Protection of Stratospheric Ozone, shall not be contained within or used on this equipment.

2.6 Environmental Protection: Under the operating, service, transportation and storage conditions described herein the machine shall not emit materials hazardous to the ecological system as prohibited by federal, state or local statutes in effect at the point of installation.

2.6.1 Other Environmental Compliance: Contractor shall comply with all environmental requirements as stipulated in Appendix D.

3. TEST STAND REQUIREMENTS:

3.1 General: The Fuel Flow Transmitter (FFT) Test Stand shall be new and unused (not a prototype) and constructed using cutting-edge technology. FFT Test Stand design specifications shall be based on Unit Under Test (UUT) requirements as noted in associated UUT Technical Orders (T.O.’s). Any provided documents/manuals associated with existing test equipment are for reference only. FFT Test Stand particulars are noted below:

3.1.1 FFT Test Stand construction and layout shall be of new design.

3.1.2 FFT Test Stand construction and layout shall be no more than 100 ft2.

3.1.3 Original test stand technical documentation are the property of the USAF and relevant sheets are attached in Appendices F, G, and J. These technical documents are for reference only and shall not be used for derivation of FFT Test Stand specification requirements.

3.1.4 Design shall include provisions for connecting test stand calibration fluid tank to existing Tinker central calibration fluid piping system, nominally 1” stainless steel piping. Test stand calibration fluid tank shall be stainless steel and also include a sight glass.

3.1.5 Design shall include provisions for a vent for connecting test stand calibration fluid tank to existing 1-1/2” calibration fluid tank vent piping system.

3.1.6 FFT Test stand shall be outfitted with a calibration fluid dump system for the event of excessive heat or fire within the test stand. Dump system shall be capable of pumping the calibration fluid from the test stands to, and into, the industrial floor system.

3.1.6.1 Dump system shall be capable of a minimum flow of 50gpm.

3.1.6.2 Contractor shall be responsible for installation of all piping from test stand to floor drain.

SOW-Fuel Flow Transmitter Test Stand Page 11

3.1.6.3 Test stand shall come with an option to allow manual operation of the pumping system to pump out calibration fluid tank when needed.

3.1.7 FFT Test Stand shall be a semi-automation, Human Machine Interface (HMI) touch screen. Test operator can select each test program and screen shall display all test parameters.

3.1.8 FFT Test Stand shall include:

3.1.8.1 High Flow System

3.1.8.1.1 Shall provide continuously laminar flow 0-120,000pph, MIL-PRF-7024 calibrating fluid, ±0.5% of reading, 100psig, 60-90F.

3.1.8.1.2 Shall be controlled to avoid overshoot setpoint.

3.1.8.1.3 Shall have flow straighteners and shut off valves mounted upstream and downstream of the flowmeter.

3.1.8.1.4 Shall have accumulator with pressure sensor.

3.1.8.1.5 Nominal 4” diameter stainless steel piping and Victaulic fittings.

3.1.8.2 High Pressure System

3.1.8.2.1 Supply 0-500psig MIL-PRF-7024 calibrating fluid, 60-90F, to UUT for leak and proof test.

3.1.8.2.2 SAE 37o -04 stainless steel fittings.

3.1.8.3 Filtration System

3.1.8.3.1 Test stand shall be equipped with a 10-micron filtration system designed to be usable with MIL-PRF-7024 calibrating fluid.

3.1.8.3.2 Filtration system shall have Differential Pressure monitoring sensor.

3.1.8.4 Test Chamber and Sink

3.1.8.4.1 Test Chamber and Sink overall dimension 63”Wx50”Dx82”H. Test Chamber dimension 48”Wx50”Dx40”H with 3/8” Clear Plexiglas doors for all sides to allow full access to UUT.

3.1.8.4.2 One (1) each explosion proof LED light Class 1, Division 1 mounted inside the test chamber. Heat does not exceed 100F and shall illuminate 50 ft2.

3.1.8.4.3 One (1) each air exhaust fan with explosion proof motor and shall exhaust 40 SCFM minimum at 0.5 in. water vacuum. Contractor shall be responsible for tying into nearest existing exhaust duct.

3.1.8.4.4 Shall have pressure, flow supply/return ports, and power connector.

3.1.8.4.5 UUT Test Fixture shall be rotated 0 – 90 degree and shall have quick disconnect fittings.

3.1.8.4.6 Stainless steel sink, drip pan with drain and 50 gal holding tank shall be pumped fluid back to FFT Test Stand reservoir when full.

3.1.8.4.7 Drip pan shall be easily to take out to clear the drain hole of debris.

SOW-Fuel Flow Transmitter Test Stand Page 12

3.1.8.5 Forklift pockets

3.1.8.6 Door switches with lighting

3.1.8.7 Shop air gun on retractable reel with sufficient length to comfortably reach any point on UUT.

3.1.9 FFT Test Stand shall replace the obsolete the Fuel Flow Transmitter Cart 1TL32-

4715.30-OC001 and the obsolete Harmonic Transducer 44SM1.

3.1.10 FFT Test Stand shall replace the obsolete the Test Set A2511ZG701.

3.1.11 All pressure sensing devices must be located within the shortest distance possible from the UUT.

3.1.12 All FFT Test Stand components shall be available as commercial off the shelf (COTS) items.

3.1.13 New equipment shall be enclosed, and enclosure shall include access to all repairable components and doors large enough to repair & replace without major disassemble.

3.1.14 Any connection adaptors and power cables shall be provided by Contractor.

3.1.15 Electrical, hydraulic, and mechanical level 3 drawings as per MIL-STD3100B of the

FFT test stand shall be provided to the government in .dwg format (AutoCAD 2024 or newer).

3.1.16 The FFT test stand shall be a completely standalone unit, fully capable of successfully testing every UUT and subcomponents IAW their respective T.O.’s.

3.1.16.1 Requirements are listed in Appendix H, the UUTs T.O.’s Test Section, and are also available to the Contractor upon request.

3.1.16.2 Contractor shall verify latest Technical Order in use prior to software development.

3.1.16.3 No modification/tweaking, by operator, of any testing control loop shall be required regardless of UUT being tested.

3.1.16.4 Test Parameters: The Contractor shall consult with Government engineering and production POCs throughout design process and at design reviews to ensure test procedures as implemented in Test Stand adequately reflect UUT T.O.

requirements and sufficiently test each UUT. The Contractor will provide the following deliverables at the indicated design reviews, which will be returned with comments for correction at the end of the Government review period as noted for each review.

3.1.16.4.1 PDR: A document cataloguing all relevant test parameters for each UUT and UUT test with clear reference to the UUT T.O. requirements.

3.1.16.4.2 CDR: A general test flowchart indicating how the Test Stand’s planned components will meet UUT test requirements.

3.1.16.5 Test Procedure: The Contractor shall provide, for each UUT, a completed draft of the test procedure as will be displayed on the test stand at least four (4) weeks prior to factory acceptance testing. Government engineering and production POCs shall

SOW-Fuel Flow Transmitter Test Stand Page 13 return any comments or corrections to the contractor for implementation at least two (2) weeks prior to factory acceptance testing.

3.1.16.6 Time to test requirement for each known good UUT, as tested by a certified Tinker mechanic, shall not exceed the following:

UUT Part Number Technical Order Minute A-10 Fuel Flow Transmitter 8TJ64GDM2 5L13-3-19-3 35 B-1B Fuel Flow Transmitter 8TJ100GAR1 5L20-12-3 120 B-52 Fuel Flow Transmitter 8TJ50GBM5 5L13-2-12-3 30 C-130 Fuel Flow Transmitter 8TJ50GAS 5L13-2-12-3 32 C-130 Fuel Flow Transmitter 8TJ50GAS4 5L13-2-12-3 45 C-130 Fuel Flow Transmitter 8TJ50GAS5 5L13-2-12-3 45

KC-135 Fuel Flow Transmitter 8TJ85GHY3 5L13-2-20-3 108 F-15 Fuel Flow Transmitter 150-005-003 5L13-2-21-3 80 F-15 Fuel Flow Transmitter 150-005-004 5L13-2-21-3 80 F-15 Fuel Flow Transmitter 8TJ62GCA3 5L13-2-19-3 120 F-16 Fuel Flow Transmitter 8TJ62GBZ3 5L13-2-19-3 40 F-16 Fuel Flow Transmitter 150-022-002 5L13-2-27-3 65

F-22 Engine Feed Fuel Flow Valve 5VJ40132-101 F-22-D-OC-046 120

3.1.17 No proprietary software or technical data (manuals, drawings) shall be used. The USAF shall have unlimited rights for all technical data and non-COTS software developed for this effort. All non-COTS source code and technical data developed shall be delivered to the government along with the COTS licenses at the end of the contract.

3.1.18 The Data Acquisition (DAQ) system shall utilize LabVIEW (2024 or newer) to develop a test program to communicate with Siemens S7 Programmable Logic Controller (PLC).

3.1.19 Test variables shall be indicated one of three ways: red if out-of-limits (OOL)-high, green if in limits, and yellow if OOL-low. Substitutions to colors may be used if approved by government POC.

3.1.20 The screen display readings shall be defined by the testing requirements for all UUTs.

The display screen shall be able to display all the monitored parameters, organized in logical groups. The display default parameter display sizes shall be large enough to be seen by the operator and inspector during testing.

3.1.21 Delivery date for the FFT Test Stand shall be no later than eighteen (18) months after date of contract.

3.1.22 The Contractor shall attend monthly collaboration meetings (conference calls acceptable) with Government POC for the purpose of specifying progress to date, any changes to estimated completion date and sharing information to ensure accurate

SOW-Fuel Flow Transmitter Test Stand Page 14 completion of all major milestones to meet performance requirements. Government POC includes but is not limited to 76 CMXG Engineering and 76 CMXG Production.

3.1.22.1 If the contractor has more than 5% delays by no fault of the government, the contractor shall submit a catch up plan and hold weekly meeting at no cost to the government.

3.1.23 Prior to acceptance, test stand and subcomponents shall be cleaned to adhere to cleaning guidelines as defined in existing test stand manuals. Cleanliness of the test stand is important to satisfactory operation and to promoting a longer life for test stand equipment and components.

3.2 Construction: The FFT Test Stand shall be constructed of parts that are new, without defects, COTS, and free of repairs. Quality of materials used in construction shall be equivalent to or superior to those used in construction of existing FFT Test Stand located in B3902. Metals shall be of corrosion-resistant materials unless suitably protected to resist corrosion. The machine construction shall include all components, parts, and features necessary to meet the performance requirements specified herein. All parts subject to damage from environmental hazards shall be sealed or otherwise protected. The machine shall be capable of withstanding all forces encountered during operation of the machine at its maximum rating and capacity without distortion or failure. Welding, plugging, or filling with solder or paste shall not be employed as repair or reclamation measures for defective parts. All screws, pins, bolts and similar parts shall be installed with means of preventing loss of tightness. All parts subject to removal or adjustment, shall not be swaged, peened, staked, or otherwise permanently deformed. Test stand shall be built in compliance with Design Guideline 450 as shown in Appendix I. The final design of the FFT test stand shall be neat, tidy, and match existing B3902 test stand colors.

3.2.1 Component Labeling: All test stand components shall be labeled with an embossed metal tag denoting part number as per the Illustrated Parts Breakdown (IPB). All hoses shall also be labeled with an embossed metal tag and hose schedule included in the IPB that details required pressure rating of hose, hose size, length, fluid compatibility requirements, maximum temperature, and nominal location. All electrical wiring shall have heat shrink labels (or equivalent) placed on either end of wire and labels and lettering shall suffer no degradation when subjected to any fluids associated with the FFT Test Stand.

3.2.2 Test Stand Anchoring: If FFT Test Stand is required to be anchored to the slab, anchors shall be no longer than three and three-quarter inches (3.75”) in length. All holes required to be drilled into the slab shall be no more than four inches (4”) deep. Any damage to the existing vapor barrier due to holes deeper than those allowed shall be fully repaired by the Contractor. Repair method and final repair shall be reviewed and approved by Tinker AFB Civil Engineering.

3.3 Interchangeability: To provide for replacement of worn parts, all parts bearing the same part number shall be functionally interchangeable and dimensionally identical within the manufacturer’s tolerance limits. Parts shall be the latest version available by the equipment supplier so that any replacement parts are available to the customer throughout the life of the equipment.

SOW-Fuel Flow Transmitter Test Stand Page 15

3.4 Maintainability: The machines shall be designed and constructed to permit effective maintenance. The machines shall be equipped with access covers (if applicable) to facilitate inspection, cleaning, repair, and replacement of parts.

3.5 Lubrication: Means shall be provided to ensure adequate automatic lubrication for all moving parts. Recirculating systems shall include filters which are cleanable or replaceable.

Each lubricant reservoir shall have visible or mechanical means for determining fluid level.

All oil holes, grease fittings and filler caps shall be accessible. Parts consuming fluids shall be clearly identified as such along with the recommended periods of additions and the type of fluid that should be used. Contractor shall recommend a remedial maintenance schedule for servicing the lubrication system of the test stand.

3.6 Utilities and Maintenance Access: The Contractor shall provide maintenance access to the control panel, filters, pumps, and other parts requiring periodic maintenance or repair. All equipment access doors, control panels, and process sensitive areas shall be lockable. Keying configurations and methods of locking shall be discussed in the design reviews. The Contractor shall label each breaker pulled from the main electrical panel. Electrical schematic(s) shall be attached inside of the control panel with all components labeled and identified. A listing of all components and their ratings shall be provided. Unions and isolation valves shall be placed inline before and after each pump to allow for better maintenance access to the equipment. Catwalks, ladders, platforms, and other access considerations shall be the responsibility of the Contractor. Ladders exceeding twelve (12) feet in height shall contain fall protection. Contractor shall denote on the test stand main electrical device(s) the source panel name, location, and circuit breaker number(s) used to feed the electrical device even if using existing connections.

3.6.1 Utilities Interconnection: The Government will provide the required utilities, except for the electrical, to within twenty-five (25) feet of test stand location.

3.6.1.1 A single connection point will be supplied.

3.6.1.2 Contractor shall set the test stand in Room 112, Building 3907, Tinker AFB and make final terminations of utilities to the test stand. Contractor shall provide and run all conduit, conductors, and all other required electrical components from Room 111 (50 feet) to the stand to make the stand fully operational electrically.

3.6.1.3 All interconnections shall maintain the hazardous classifications for both inside and outside the test stand.

3.6.2 Electrical System: The machine shall be designed to operate from a single 460 volt (± 3%). 3 phase, 60-hertz (HZ) (± 1 hertz) power source. All electrical equipment shall comply with NFPA 79, NFPA 70 and NFPA 70E standards.

3.6.3 Surge Protection: All equipment shall utilize surge protection provided by Contractor with Government approval.

3.6.4 Emergency Stop Buttons: The test stand shall include a minimum of one (1) emergency stop button to cut off all electrical power and utilities to the test stand in case of emergency. These emergency stop buttons shall of a sufficient amount and shall be located such that an operator will have direct access to a button at all times during operation and maintenance.

SOW-Fuel Flow Transmitter Test Stand Page 16

3.6.5 Ventilation: Minimum of one (1) interior exhaust properly separated for exhausting floor-level fumes, each sized for 100 SCFM at 0.5 in. water vacuum. Each exhaust shall be outfitted with volume damper; damper shall close automatically in the event of fire suppression gas discharge but also maintain a manual ability to open/close. Contractor shall be responsible for tying into nearest existing exhaust duct.

3.7 Installation Plan: Contractor shall submit an Installation Plan (CDRL001, Appendix J) to the Government POC for review and approval. Installation Plan shall include:

3.7.1 Drawing denoting test stand location on existing floor plan.

3.7.2 Design drawing denoting general locations of major components including, but not limited to pumps, motors, pressure transducers, tanks, conduit sizes, conductor types and sizes, seal off locations, test stand electrical interconnect drawing, and over-current protection devices and sizes.

3.7.3 All subcontractor and partnership information.

3.7.4 Installation Plan shall be submitted to the Government POC a minimum of sixty (60) workdays prior to initial work on test stand. Stand shall not be delivered until written approval of plan has been received by Contractor from the Government POC. The government shall have 10 working days to review the Installation Plan and initiate contact with Contractor to discuss/review/resolve any issues. Following resolution, Contractor shall have 5 working days to resubmit revised Installation Plan to Government POC for review and approval.

3.8 Test Stand Area Classification: The FFT test stand shall meet the following hazardous area classification requirements:

3.8.1 Interior Electrical Items: All electrical/electronic components and connections located within the FFT test stand footprint - floor to ceiling - shall be Class I Division I Group D rated as defined in NFPA 70 Article 500.

3.8.1.1 All components located inside the stand envelope and not Class I, Division I Group D rated shall be placed in purge air enclosures.

3.8.1.1.1 Purge air enclosures may be accessible from test stand interior provided point of access is reasonable from a maintenance perspective. All purge air enclosures shall be configured in accordance with all specifications listed and referenced in this SOW.

3.8.2 Exterior Electrical Items: All electrical/electronic components outside the test stand footprint shall be a minimum of Class I Division II Group D rated as defined by NFPA 70 Article 500 and shall be mounted in an enclosure(s). Enclosure(s) interior shall only be accessible from outside the test stand envelope.

3.8.2.1 While the intent is to maintain the integrity of a Class I Division II environment for all exterior electrical items, the very nature of electrical connections resident on the UUT’s prevents strict adherence with this rating.

3.9 PC and PLC Control System: FFT Test Stand shall be controlled using a Professional Computer (PC) / Programmable Logic Controller (PLC) configuration as noted below:

SOW-Fuel Flow Transmitter Test Stand Page 17

3.9.1 PLC shall be Siemens S7 or Government approved equivalent and controlled using LabVIEW, no earlier than 2024, no substitutes accepted.

3.9.2 New Computer System with the following requirements:

3.9.2.1 Latest Air Force approved Windows Enterprise version

3.9.2.2 CPU: Quad Core i7 (minimum)

3.9.2.3 Redundant Array of Independent Disks (RAID) array based with a minimum of

1TB SSDs

3.9.2.4 8GB Synchronous Dynamic Random - Access Memory (SDRAM) minimum.

3.9.2.5 Detachable, standard 101 key computer keyboard and mouse, Class I, Division II, Group D rated.

3.9.2.6 USB mass storage device ports.

3.9.2.7 Data Access. The Controller shall be equipped with Ethernet Interface (RJ45 port accessing on enclosure).

3.9.2.8 Account Privileges. At a minimum, privileges shall be configured for user and administrative accounts. User accounts shall be able to perform all machine functions without use of Windows administrative privileges.

3.9.2.9 Universal Serial Bus (USB) Communications. Use of any internal and external USB communications on the equipment shall be clearly documented and described within the contractor provided technical data. All external USB ports accessible to the user shall be able to be physically disconnected or rendered inoperable by non-permanent means.

3.9.2.10 Data Access Protocols. Equipment shall be able to communicate externally for machine monitoring and data collection purposes via Ethernet (RJ45 port) Interface using industry standard communication protocols. The controller shall be licensed and able to communicate, at a minimum, via Fanuc Focas 2 and MTConnect for data access/collection. The installed MTConnect adapter shall be version 1.3 or later. Specific data collection tags of interest acquired through Fanuc Focas 2 and MTConnect shall be discussed and determined at post award meeting. Contractor shall provide complete list of all TCP-IP ports and protocols utilized by the equipment.

3.9.2.11 Discrete Input/Discrete Output (Di/Do) Information. Contractor shall provide a complete Di/Do address (and/or tag) table with the machine technical data. The Di/Do table shall provide at a minimum the Di/Do signal address or tag name, signal or tag description, and any applied conditioning value or functions.

3.9.2.12 Minimum Sensing Requirements. All sensors and sensor components shall be integrated into the machine control system and readable through MTConnect. All discrete outputs for data collection purposes shall be conditioned to display meaningful values. All sensor data shall be available as a discrete output for data collection purposes.

3.9.3 Minimum 17” color flat screen (touch screen) HMI with adjustable StrongArm (or equivalent) mount to test stand.

SOW-Fuel Flow Transmitter Test Stand Page 18

3.9.4 No proprietary software shall be used.

3.9.5 Local Area Network (LAN) connection capability to existing LAN system allowing full interface with and backup capability of test stand PC and PLC.

3.9.6 System shall be configured to allow flowmeter calibration data to be uploaded to test stand thru USB port or alternate means approved by Tinker. Manual loading (keying in) of flowmeter calibration data shall not be required.

3.9.7 System addressing of LAN hardware will be set with guidance from system administrators to comply with existing network standards.

3.9.8 Hardware shall be chosen, where feasible, that has error handling capabilities and be tied back through LabVIEW for pre-test verification of operation.

3.9.9 PLC software shall be password protected at three separate levels as noted below:

3.9.9.1 Operator level: allows access for testing of UUTs alone. Software changes and access to calibration data are NOT allowed at this level.

3.9.9.2 PMEL Tech level: allows access to Operator level as well as Calibration level to permit test stand calibration including entry of calibration data. Software changes are NOT allowed at this level.

3.9.9.3 Administrative level: allows access to all previous levels as well as capability to modify any test stand software as necessary. Any changes to software shall cause the associated Rev level of the software to change to the next logical level, i.e. Rev.

levels shall not be check sum based.

3.10 Calibration Equipment: Required calibration features for test stands are detailed below:

3.10.1 Design shall include provisions for connecting test stand calibration equipment currently located in Tinker AFB B3902/B3907.

3.10.1.1 Appendix F contains a list of items requiring calibration based on the FFT Test

Stand designs. This list is for reference only; new FFT Test Stand design may have more or fewer items requiring calibration.

3.10.1.2 All items requiring calibration shall be currently listed in Air Force Metrology and Calibration Program (AFMETCAL) (Air Force TO 33K-1-100-2) as approved devices.

3.10.1.3 HMI shall display real-time feedback of item being calibrated.

3.10.1.3.1 Raw signal and final units shall both be shown on HMI.

3.10.1.4 As Found and As Left data shall be available on HMI during calibration with an option to save data to hard drive during calibration.

3.10.1.5 A minimum of 20 data points must be available for each item requiring calibration.

3.10.1.5.1 Five (5) alignment points minimum.

3.11 Test Stand Preliminary/Final Calibration: The first draft of the calibration process shall be delivered by Contractor for review at Intermediate Design Review. Calibration process shall

SOW-Fuel Flow Transmitter Test Stand Page 19 include distinct procedures for both alignment (full adjustment of calibrated instruments when out of spec) and verification (regular checks to determine whether instruments are in spec). Review comments will be delivered via the Government POC back to Contractor within 10 working days. Contractor shall fully incorporate comments as necessary and resubmit revised procedure prior to Critical Design Review.

3.11.1 Preliminary Calibration process shall be carried out as follows:

3.11.1.1 Contractor shall be present for initial calibration of the test stand and shall remain present until calibration of the stand is complete.

3.11.1.2 Calibration support shall be provided and be responsible for resolving any calibration issues that may arise from the modifications above within 10 days of identification.

3.11.1.3 Following installation of FFT Test Stand at Tinker AFB, Contractor shall complete and prove out the entire approved calibration process prior to contacting PMEL personnel.

3.11.1.4 Preliminary calibration process shall include a Calibration Summation spreadsheet (CDRL003, Appendix J) completed by Contractor detailing the following:

3.11.1.4.1 Each item calibrated and calibration results (Pass or Fail).

3.11.1.4.2 Initials of technician who performed item calibrated and date the calibration was completed.

3.11.1.4.3 As Left values for each item calibrated.

3.11.1.4.4 Any alignments or adjustments performed during calibration.

3.11.1.4.5 Technical documentation revision history (if applicable).

3.11.2 Final Calibration process shall be carried out as follows:

3.11.2.1 Contractor shall have appropriate personnel present during the entire Final

Calibration process.

3.11.2.2 Final calibration process instructions (CDRL003, Appendix J) shall be written to accurately reflect new test stand port and connection labels as applicable.

3.11.2.3 Review and perform entire calibration process, step-by-step, with PMEL personnel present.

3.11.2.4 Modify calibration procedure and software as recommended and agreed to by

PMEL personnel, as necessary.

3.11.2.5 Once the calibration procedure is finalized, revised, and resubmitted by Contractor, PMEL will formally calibrate the test stand.

3.11.2.6 Limitations on the calibration are not acceptable and any limitations noted by

PMEL shall be fully resolved by Contractor within 14 calendar days.

3.12 Code Compliance: The Test Stand shall be compliant with the latest American Society of Mechanical Engineers (ASME) and the National Fire Protection Association (NFPA) 70 Article 500, Hazardous Locations. The Contractor shall provide Code Compliance Reports

SOW-Fuel Flow Transmitter Test Stand Page 20 signed by a licensed engineer. The Code Compliance Reports shall be provided to the COR as part of the Critical Design Review. (CDRL004, Appendix J)

3.13 Safety Analysis: The Contractor shall provide a Cause and Effect Matrix (Alarms and Shutdowns) and a Test Stand Safety Analysis which has been verified by a disinterested third party. The Contractor shall provide one (1) each hard copy and one (1) each electronic copy of the Cause and Effect Matrix and Test Stand Safety Analysis. The electronic copy shall in PDF format and compatible with the latest version of Adobe Acrobat. The Cause and Effect Matrix and the Test Stand Safety Analysis shall be provided to the COR as part of the Critical Design Review. (CDRL004, Appendix J)

3.14 Test Stand IVV and As-Built Drawing Review: Prior to government calibration, contractor shall provide the latest data package to the government. The government will verify the accuracy of all As-Built drawings, to include but not limited to IPB and all drawings associated with the project. Following review, the Government shall list all deficiencies noted and submit list to Contractor for correction. All deficiencies shall be corrected by Contractor prior to final As-Built drawing submittals. Once finalized, the Government shall submit a signed and dated document noting that As-Built drawings are 100 percent accurate.

Please note that Level 3 drawings as per MIL-STD-31000B are required. Document shall include a detailed list of As-Built drawings including each drawings name, date, and revision level. (CDRL005, Appendix J)

3.15 UUT Fixtures, Tooling, and Power Cables: Contractor shall provide all fixtures and tooling necessary for mounting and testing each UUT on the FFT Test Stand. Tools and fixtures may be reverse engineered and fabricated, or authentic from Original Equipment Manufacturer (OEM).

3.15.1 Legacy fixtures do not need to be reproduced.

3.15.2 If tools and fixtures are reverse engineered, manufacture drawings shall be included for all tools and fixtures that are reverse engineered and fabricated. Manufacture drawings shall be such that local manufacture of any item can be achieved without further engineering. Requirements for tooling and fixtures can be found in UUT T.O.s (Appendix H).

3.15.3 Fixtures may be incorporated into new test stand design.

3.16 Software: The Contractor shall develop a Test Executive as well as individual UUT Computer Software Configuration Items (CSCIs) so that they can have separate configuration management at the completion of the contract. The software shall be developed utilizing an object-oriented design such that there is an Executive piece that calls independent pieces for each UUT.

3.16.1 Software assurance shall be designed into the software.

3.16.2 Stands shall have a software Administrative Level ON/OFF option to allow UUT test results/reports to be automatically uploaded to the existing LAN system only when turned ON.

3.16.3 Self-Test: The Contractor shall develop self-test software to identify faulty equipment in the test stand and be used for troubleshooting of the stand.

SOW-Fuel Flow Transmitter Test Stand Page 21

3.16.4 Executive Software: Contractor shall develop executive software that is common to all UUT types tested.

3.16.4.1 The Executive Software shall run on the latest Air Force approved Windows OS platform.

3.16.4.2 Occasionally, a Windows OS may freeze or lock up when a software program performs an illegal operation, or it may include an Interrupt Request line (IRQ) conflict, incompatible device driver, virus, etc. To prevent such problems, all software updates to OS, device drivers, or anti-virus software and the addition of hardware shall be performed by an authorized software maintainer.

3.16.4.3 A password protected Administrative level shall be used to limit user access to executive software including drives, read/write access, and OS privileges.

3.16.4.4 In the event of Windows OS lock ups, a manual E-stop switch shall allow the operator to bring the UUT to a safe condition.

3.16.5 UUT Software: Contractor shall develop menu screens that shall be used for UUT test screens.

3.16.5.1 Before executing selected UUT test the software shall capture and archive the UUT specifications including, but not limited to: weapon system, Individual Tracking Number (ITN), UUT serial number, test stand’s On-Condition (OC) number, date, and time.

3.16.5.2 Test results in PDF format shall also be capable of being printed out in hard copy for every UUT and every required test point (see Appendix G for minimum content required).

3.16.5.3 The Test Points (TPs) shall be formatted in accordance with (IAW) the target test equipment style requirements. The main test menu shall display a list each individual TP, matching the most current version of T.O. requirements.

3.16.5.4 Operator shall be prompted to…