This statement of work outlines requirements for rehabilitating the Flamingo Wastewater Treatment Plant at Everglades National Park. Key work includes structural steel repairs, painting inside and outside two tanks, repairing steel piping, installing a sluice gate and process valves, adding mixers, repairing an existing jet air system, replacing membrane filters, replacing conduits and wiring, replacing air conditioning systems, installing new flow meters integrated into the existing control panel. Optional work that can be bid separately includes adding an aluminum staircase and replacing grating. The National Park Service is the contracting agency. The contractor must furnish all labor, materials, and equipment to complete the work by the specified completion date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EVERGLADES NATIONAL PARK FLAMINGO DISTRICT
FLAMING0 WASTEWATER TREATMENT PLANT
REHABILITATE THE WASTEWATER TREATMENT PLANT PMIS 285791
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE DECEMBER
000001-1
PMIS 285791 TABLE OF CONTENTS
EVER-160-143392 00 00 01
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 00 01 – TABLE OF CONTENTS
SECTION 00 01 15 – LIST OF DRAWING SHEETS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00 – SUMMARY OF WORK
SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
SECTION 01 32 33 – PHOTOGRAPHIC DOCUMENTATION
SECTION 01 33 23 - SUBMITTAL PROCEDURES
SECTION 01 35 23 – SAFETY REQUIREMENTS
SECTION 01 40 00 – QUALITY REQUIREMENTS
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
SECTION 01 67 00 – PRODUCT REQUIREMENTS
SECTION 01 73 29 – CUTTING AND PATCHING
SECTION 01 73 40 – EXECUTION
SECTION 01 77 00 - CLOSEOUT PROCEDURES
SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA
SECTION 01 78 39 – PROJECT RECORD DOCUMENTS
SECTION 01 79 00 – DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
NOT APPLICABLE
DIVISION 03 - CONCRETE
NOT APPLICABLE
DIVISION 04 - MASONRY
NOT APPLICABLE
DIVISION 05 - METALS
SECTION 05 10 00 – STRUCTURAL STEEL
SECTION 05 12 00 – STRUCTURAL STEEL FRAMING
SECTION 05 50 00 – METAL FABRICATIONS
SECTION 05 51 20 – ALUMINUM STAIRS
SECTION 05 52 13 – PIPE AND TUBE RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
NOT APPLICABLE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
DIVISION 08 - OPENINGS
NOT APPLICABLE
DIVISION 09 - FINISHES
SECTION 09 97 00 – STEEL COATINGS (PAINTING)
DIVISION 10 - SPECIALTIES
NOT APPLICABLE
DIVISION 11 - EQUIPMENT
NOT APPLICABLE DIVISION
12 - FURNISHINGS
NOT APPLICABLE
DIVISION 13 - SPECIAL CONSTRUCTION
NOT APPLICABLE
DIVISION 14 - CONVEYING EQUIPMENT
NOT APPLICABLE
DIVISION 21 - FIRE SUPPRESSION
NOT APPLICABLE
DIVISION 22 - PLUMBING
NOT APPLICABLE
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC) NOT
APPLICABLE
DIVISION 25 - INTEGRATED AUTOMATION
DIVISION 26 - ELECTRICAL
SECTION 26 05 00 – BASIC ELECTRICAL MATERIALS AND METHODS
SECTION 26 05 19 – LOW-VOLTAGE WIRES AND CABLES
SECTION 26 05 26 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 26 05 29 – SUPPORTING DEVICES
SECTION 26 05 51 – CONDUIT SYSTEMS
SECTION 26 08 00 – ACCEPTANCE TESTING & PERFORMANCE VERIFICATION
SECTION 26 29 13 – MOTOR STARTERS
SECTION 26 36 13 – SAFETY SWITCHES AND DISCONNECTS
SECTION 26 85 00 – INSTRUMENTATION AND CONTROL SYSTEM
DIVISION 27 - COMMUNICATIONS
NOT APPLICABLE
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY NOT
APPLICABLE
DIVISION 31 - EARTHWORK
NOT APPLICABLE
DIVISION 32 - EXTERIOR IMPROVEMENTS
NOT APPLICABLE
DIVISION 33 - UTILITIES
NOT APPLICABLE
DIVISION 34 - TRANSPORTATION
NOT APPLICABLE
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 16 – SLUICE GATES
DIVISION 40 - PROCESS INTEGRATION
SECTION 40 92 14 – VALVES AND APPURTENANCES
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT NOT
APPLICABLE
DIVISION 42 - PROCESS HEATING, COOLING, AND DRYING EQUIPMENT NOT
APPLICABLE
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT
SECTION 43 22 53 – MAGNETIC FLOW METER & APPURTENANCES
DIVISION 44 - POLLUTION CONTROL EQUIPMENT
SECTION 44 42 13 – JET AERATION SYSTEM
SECTION 44 45 13 – MBR – MEMBRANE MODULES
DIVISION 45 - INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT NOT
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT NOT
APPLICABLE
DIVISION 48 - ELECTRICAL POWER GENERATION NOT
EVER-160-143392 01 10 00 - 1
SUMMARY OF WORK
SECTION 01 10 00
PART 1 - GENERAL
1.1 SUMMARY
A. This project includes providing all labor, materials, and equipment to rehabilitate the Flamingo Wastewater
Treatment Plant at Everglades National Park in Flamingo, Florida.
The work includes structural steel repairs to the MBR tank (membrane bioreactor) and the membrane treatment tank, painting (inside and outside) the MBR tank (membrane bioreactor) and the membrane treatment tank, repair of steel piping, installing a sluice gate, replacing process valves, adding two (2) mixers in the aerobic zone repairs to existing jet air system, and purchasing spare membrane filters.
Work also includes replacing conduits and electrical wiring, replacing panel air conditioning systems, installing new flow meters and integration with existing control panel.
The following optional work shall be bid separately: Add aluminum staircase for aeration tank.
Replace grating on walkway.
B. The work site is Everglades National Park, 38 miles southwest from Main Park entrance in the Flamingo Area”.
C. The work shall be constructed under a single contract.
1.2 DEFINITION OF BID ITEMS
A. Line Item 010, Base Bid: This item consists of all work at the Flamingo Wastewater Treatment Plant as shown on the drawings and all work not specifically included in a bid option.
B. Line Item 020 Bid Option 1: This item includes adding an aluminum staircase.
C. Line Item 030 Bid Option 2: This item includes replacing grating over MBR.
1.3 USE OF PREMISES AND WORK RESTRICTIONS
D. Use of the lagoon area: The Government will pump plant water into the lagoon before the construction starts. The
Contractor shall remove any remaining sludge in the plant.
E. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb portions of the site beyond the work area.
1. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
EVER-160-143392 01 10 00 - 2
2. Preservation of Cultural Resources: No known archeological resources are in the area of this construction.
If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work in the area of discovery and notify the Contracting Officer. An equitable adjustment will be made under the contract’s changes clause.
3. Runoff: Install silt fence downhill from all earth disturbing activities.
F. Protection Of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
G. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to
5:00 p.m., Monday through Friday, except when otherwise indicated. Requests for any work outside those hours, including weekends and holidays, must be submitted for approval at least 48 hours in advance.
H. Existing Utilities
1. Existing Utilities: Notify Contracting Officer (CO) and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made under the contract’s changes clause.
I. Hurricanes: The Government requires closing of operations between 72 and 48 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials will be adequately secured or removed from the site within that time frame.
1.4 PRECONSTRUCTION CONFERENCE:
A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, submittals, and project closeout requirements.
1.5 CONSTRUCTION MATERIALS:
A. All materials, including borrow and aggregates, shall be Contractor furnished from outside the park, except the static screen system to be provided by the Government.
1.6 DISPOSAL
A. All removed material including, soil and rock, becomes the property of the Contractor and shall be disposed of outside the park.
1.7 FIELD VERIFICATION:
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer will be done at the Contractor’s own expense.
PART 2 - PRODUCTS
2.1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
EVER-160-143392 01 10 00 - 3
2.2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.3 SANITARY FACILITIES
A. Sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, sturdy enclosures. The Contractor shall not use the restroom facilities provided for the public. Place in approved locations secluded from public observation and convenient to work stations.
END OF SECTION
EVER – 160 – 143392 013100 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION PART
1 - GENERAL
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating the Contract closeout.
1.2 DEFINITIONS
A. Authority Having Jurisdiction (AHJ): An AHJ is an agency that has been granted legal authority over a location, action or resource. This authority includes the ability to issue a permit or other legal permission document.
B. Construction Permits: Are those permits obtained by the contractor based on means and methods used to perform the work. Construction Permits are issued to the Contractor and not to the National Park Service
(NPS).
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
EVER – 160 – 143392 013100 - 2
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor’s Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
1.4 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week before the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre- Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Historic Preservation Treatment Plan.
11. Required Construction Permits List. Include the following information for each permit:
a. Name of Permit.
b. The AHJ issuing the permit.
c. Information required from the Government to complete the permit application.
EVER – 160 – 143392 013100 - 3
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held.
If all of these documents have not been received one week before the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor’s suggested resolution. If Contractor’s suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor’s signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
EVER – 160 – 143392 013100 - 4
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor’s means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect’s actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO’s action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO’s action on RFIs may result in the need for a change to the Contract Time or the Contract Sum.
All contract changes will be processed following the terms and conditions of the contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, CO will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. Acceptance/rejection of work.
17. Progress meetings.
18. Submittal procedures.
19. NPS Final Accessibility Inspection.
20. Environmental requirements.
21. Permit requirements.
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials.
25. Value engineering.
B. Progress Meetings: The CO will schedule weekly meetings with the Contractor.
1. Attendees: Besides Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All
EVER – 160 – 143392 013100 - 5
participants at the meeting shall be familiar with the Project and authorized to conclude matters regarding the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business regarding work.
k. Permit requirements.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Possible conflicts.
i. Compatibility requirements.
j. Time schedules.
k. Weather limitations.
l. Manufacturer’s written instructions.
m. Warranty requirements.
n. Compatibility of materials.
o. Acceptability of substrates.
p. Temporary facilities and controls.
q. Space and access limitations.
r. Regulations of authorities having jurisdiction.
s. Testing and inspecting requirements.
t. Installation procedures.
u. Coordination with other work.
v. Required performance results.
EVER – 160 – 143392 013100 - 6
w. Protection of adjacent work.
x. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope;
with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan (WMP).
c. Present an overview of environmental issues and summarize site specific procedures regarding management plans at the Preconstruction conference.
d. Training for Contractor personnel under their position requirements.
e. Monitoring and documentation of environmental procedures.
B. Perform project quality control under requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management.
D. Provide documentation for environmental procedures as specified herein and under approved Waste
Management Plan.
EVER – 160 – 143392 013100 - 7
1.8 PERMITS
A. General:
1. Permits and Responsibilities: The Contractor will, without additional expense to the Government, obtain any necessary licenses and permits, and comply with any federal, state and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until the work’s completion and acceptance.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government.
Therefore, the Contractor will comply with the appropriate federal, state and local laws.
B. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits will be required for the contract’s chosen means and methods. The list shall not be considered complete, as it is the Contractor’s responsibility to determine means and methods, and obtain the required permits. It is the Contractor’s responsibility to obtain all permits required to legally conduct the work.
1. Electrical Utility Hookup
2. Sewer Hookup
C. Coordination with AHJ Issuing Permits
1. Coordination: Contact the AHJs as needed and sufficiently in advance to avoid delaying the work:
Coordinate meetings, reporting requirements, inspections, or any other requirements.
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with AHJs, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.
2. Supply all needed information to AHJs issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
EVER – 160 – 143392 013216 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and CO in monitoring the work progress, evaluating proposed changes, and processing the Contractor’s monthly progress payment.
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless the CO otherwise approved.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
EVER – 160 – 143392 013216 - 2
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted by email to the NPS COR, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.
D. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.
Provide two paper copies.
E. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.
1.4 QUALITY ASSURANCE
A. The Contractor shall meet with the CO on the day of the preconstruction conference to go over the following:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including phasing, work stages, interim milestones and partial Government occupancy.
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.
EVER – 160 – 143392 013216 - 3
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals
Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of the Work from parties involved.
3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The CO may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump- sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and CO before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than
30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.
EVER – 160 – 143392 013216 - 4
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work.
Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates.
Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work. Baseline schedule must be saved and not modified. Actuals will then be recorded and compared to saved baseline.
5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.
6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.
7. Time Frame: Proposed duration assigned to each activity shall be the Contractor’s best estimate of time required to complete the activity considering the scope and resources planned for the activity.
a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:
1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.
2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.
3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. The Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include a calendar that is based on a 7 day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-
EVER – 160 – 143392 013216 - 5
work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.
3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.
e. Activity Duration: Define activities so no activity is longer than 15 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Submittal Review Time: Include review and re-submittal times indicated. Coordinate submittal review times in Construction Baseline Schedule.
g. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Division 01 Specification 01 77 00 Closeout Procedures.)
8. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show the effect of the following items on the schedule:
1) Coordination with existing construction.
2) Limitations of continued occupancies.
3) Uninterruptible services.
4) Partial occupancy before Substantial Completion.
5) Use of premises restrictions.
6) Provisions for future construction.
7) Seasonal variations.
8) Environmental control.
9) Permit provisions.
d. Work Stages: Indicate important stages of construction for each major portion of the Work.
1) Subcontract awards.
2) Submittals.
3) Purchases.
4) Fabrication.
5) Sample testing.
6) Deliveries.
7) Installation.
8) Tests and inspections.
9) Adjusting.
10) Curing.
11) Building flush-out.
EVER – 160 – 143392 013216 - 6
9. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion.
C. Joint Review, Revision, and Acceptance:
1. Within 7 calendar days of receipt of the Contractor’s proposed Construction Baseline Schedule, the
Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Baseline Schedule. Any areas which, in the CO’s opinion, conflict with timely completion of the project shall be subject to revision by the Contractor.
2. Within 7 calendar days after the joint review between the Contractor and Contracting Officer, the Contractor shall revise and resubmit the Construction Baseline Schedule under agreements reached during the joint review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the CO review does not detect this omission or error, such omission or error, when discovered by the Contractor or CO, shall be corrected by the Contractor within 7 calendar days and shall not affect the contract period.
4. Upon acceptance of the Construction Baseline Schedule by the CO, save the schedule as a baseline and update on a monthly basis. The construction schedule update will be used to evaluate the Contractor’s monthly applications for payment based upon information developed at the monthly Construction Schedule update meeting.
D. Recovery Schedule: When periodic schedule update indicates the Work is 14 or more calendar days behind the current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule must also be submitted. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery will be accomplished.
E. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.
1. Use Microsoft Project, Primavera, or Meridian Prolog for current Windows operating system.
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a 2 week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize the look-ahead schedule to facilitate and take notes on discussions held during the progress meeting.
B. Monthly Schedule Updates:
1. General: Update the Construction Schedule monthly to reflect actual construction progress and activities throughout the entire contract period and until project substantial ccompletion. The status date of each schedule update shall be the 7th day preceding the progress payment request date.
Procedure: The Contractor shall meet with the CO each month at a Construction Schedule update meeting to review actual progress made through the status date of the Construction Schedule update, including dates activities were started and completed and the percentage of work completed on each activity started and/or completed.
2. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing the
a. Identification of activities that have changed.
b. Changes in early and late start dates.
c. Changes in early and late finish dates.
EVER – 160 – 143392 013216 - 7
d. Changes in activity durations in workdays.
e. Changes in the critical path.
f. Changes in total float or slack time.
g. Changes in the Contract Time.
3. Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.
4. As the Work progresses, indicate Actual Completion percentage for each activity.
5. If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:
a. Any known delays.
b. Actions that will be taken to get back on schedule.
c. Pending modifications.
d. Impediments or constraints affecting progress.
6. Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.
C. Distribution: Distribute copies of accepted schedule to CO, Contracting Officers Representative, Construction Management Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
D. Construction Schedule Revisions:
1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted
Construction Schedule no longer represents the actual prosecution and progress of the work, the CO will request, and the Contractor shall submit, a revision to the Construction Schedule. The Contractor may also request reasonable revisions to the currently accepted Construction Schedule in the event the Contractor’s planning for the work is revised. If the Contractor desires to make changes, the Contractor shall notify the CO in writing, stating the reason for the
EVER – 160 – 143392 013216 - 8
proposed revision. Accepted revisions will be incorporated into the currently accepted Construction Schedule for the next monthly schedule update.
2. Procedure: If revision to the currently accepted Construction Schedule is contemplated, the Contractor or CO shall so advise the other in writing at least 7 calendar days before the next monthly schedule update meeting, describing the revision and reasons for the revision. Government-requested revisions will be presented in writing to the Contractor, who shall respond in writing within 7 calendar days.
3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing the
a. Identification of activities that have changed.
b. Changes in early and late start dates.
c. Changes in early and late finish dates.
d. Changes in activity durations in workdays.
e. Changes in the critical path.
f. Changes in total float or slack time.
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS AND
CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays are experienced, or the
Contractor desires to revise the currently accepted Construction Schedule, the Contractor shall submit to the CO a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.
2. Time Extensions: Activity delays, which result in projecting a late completion date, shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the Schedule, thereby not causing any effect on the contract time. Time extensions will be granted under the terms of the contract.
3. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.
4. Procedure: Each time impact analysis shall be submitted within the time period stated in a request for proposal, or the time period designated under the clauses entitled Changes or Default. In cases where the Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, the time impact analysis shall be incorporated into the currently accepted Construction Schedule at the next monthly schedule update.
5. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall Construction Schedule.
END OF SECTION 01 32 16
EVER – 160 - 143392 013233 - 1
Photographic Documentation
SECTION 01 32 33 - PHOTOGRAPHIC DOCUMENTATION
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Periodic construction photographs.
3. Final completion construction photographs.
B. Related Requirements:
1. Section 01 77 00 “Closeout Procedures” for submitting photographic documentation as Project
Record Documents at Project closeout.
1.3 INFORMATIONAL SUBMITTALS
A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.
B. Digital Photographs: Submit image files within three days of taking photographs.
1. Submit photos on thumb-drive. Include copy of key plan indicating each photograph’s location and direction.
2. Identification: Provide the following information with each image description in file metadata tag:
a. Name of Project.
b. Name and contact information for photographer.
c. Name of Owner.
d. Name of Contractor.
e. Date photograph was taken.
f. Description of location, vantage point, and direction.
g. Unique sequential identifier keyed to accompanying key plan.
C. Printed Photographs: Submit two sets of prints of each photographic view within seven calendar days of taking photographs.
EVER – 160 - 143392 013233 - 2
1. Format: 8-by-10-inch smooth-surface matte prints on single-weight, paper; enclosed back to back in clear plastic sleeves punched for three-ring binder. Include copy of key plan indicating each photograph’s location and direction. Provide one binder for each set of prints.
2. Identification: On back of each print, label with the following information:
a. Name of Project.
b. Name and contact information for photographer.
c. Name of Owner.
d. Name of Contractor.
e. Date photograph was taken if not date stamped by camera.
f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
g. Unique sequential identifier keyed to accompanying key plan.
1.4 FORMATS AND MEDIA
A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of 12 megapixels, and at an image resolution of not less than 3200 by 2400 pixels, and with vibration-reduction technology. Use flash in low light levels or backlit conditions.
B. Digital Images: Submit digital media as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
C. Metadata: Record accurate date and time from camera.
D. File Names: Name media files with date and Project area and sequential numbering suffix.
1.5 CONSTRUCTION PHOTOGRAPHS
A. Photographer: Engage a qualified photographer to take construction photographs.
B. General: Take photographs with maximum depth of field and in focus.
1. Maintain key plan with each set of construction photographs that identifies each photographic location.
C. Preconstruction Photographs: Before commencement of demolition, take photographs of Project site and surrounding properties, including existing items to remain during construction.
1. Flag construction limits before taking construction photographs.
2. Take 20 photographs to show existing conditions adjacent to property before starting the Work.
3. Take 75 photographs of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
4. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements.
EVER – 160 - 143392…