This is a Statement of Work for exterior painting services at the USDA Eastern Regional Research Center (ERRC) facility in Wyndmoor, Pennsylvania. The contractor must paint a 40 x 55 x 14 foot concrete masonry unit (CMU) building with approximately 45 linear feet of small cracks. The scope includes complete surface preparation, repairs, priming, and application of a full coating system in accordance with industry standards and manufacturer specifications.

Technical requirements include power washing the building, removing peeling paint to well-adhered edges, sealing exposed block surfaces, applying one coat of masonry primer to all exterior walls, and applying two coats of approved exterior high-build CMU coating. The contractor must protect adjacent surfaces, windows, doors, landscaping, and utilities while maintaining a clean work area throughout the project. All work must comply with UFGS 09 90 00 standards. Deliverables include product data sheets for sealer, primer, block filler (if required), and finish coats; color samples (current building is white); and a detailed work schedule and sequencing plan. No materials may be purchased or applied until submittals receive government approval. The contractor must provide a one-year warranty on installation and workmanship, notify the Contracting Officer's Representative upon completion, and schedule a final walkthrough for acceptance before invoicing. Security requirements mandate that contractors and subcontractors present picture identification at the main lobby before receiving visitor badges and maintain access only to COR-authorized areas.

View the file

Other files

File Type Posted
SF30 - Amend 01.pdf PDF
RFIs.pdf PDF
Site Visit Sign-In Sheets.pdf PDF
Wage Determination.pdf PDF
SF-1442.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

USDA, ERRC Facility Vehicle Service Building Exterior Painting

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Deliverables / Schedule

5.0 Security

Project USDA, Eastern Regional Research Center, Wyndmoor, PA Facility Vehicle Services Building Exterior Painting

General Information

1.0 Scope of Work

USDA, ERRC Facility Vehicle Service Building (VSB) requires Exterior Surface Maintenance and Painting.

2.0 Background

The Eastern Regional Research Center (ERRC) is one of four Regional Research Centers of the Agricultural Research Service, U.S. Department of Agriculture. The ERRC is home to the nation’s leading scientists and engineers who solve problems facing the U.S. today and tomorrow with fundamental, applied, and developmental research on agricultural commodities.

Most of this research is conducted in the main building within two laboratory wings. The original building was constructed in 1940. Due to continuous upgrades and renovations, ERRC is very modern with respect to laboratory design and system condition.

Contractor Requirements

3.0 Technical Requirements / Tasks

1. This Scope of Work requires painting a 40 x 55 x 14 concrete block building with approx. 45 linear feet of small cracks. Contractor shall verify all dimensions and conditions and report any discrepancies to the Government prior to start of work.

2. The Contractor shall provide all labor, materials, equipment, supervision, and incidentals necessary to prepare and paint the exterior surfaces of a concrete masonry unit (CMU) building. Work includes surface preparation, repairs, priming, and application of a complete coating system in accordance with industry standards and manufacturer requirements.

3. Existing paint.

a. Building shall be power washed,

b. Peeling paint shall be removed to the edges where well adhered paint meets removed peeling paint

4. New paint.

a. Exposed block surface shall be sealed before masonry primer is applied,

b. All exterior walls shall be primed before painting with one (1) coat of masonry primer,

c. All exterior walls shall apply two (2) coats of an approved exterior high-build CMU coating,

d. Surfaces shall be prepared, primed, and painted in accordance with manufacture’s recommendations and in accordance with UFGS 09 90 00.

5. Protection and Clean Up.

a. Protect adjacent surfaces, windows, doors, landscaping, and utilities,

b. Maintain a clean work area throughout the project,

c. Remove all debris, paint chips, masking, and equipment upon completion,

d. Restore any damaged property to original condition

4.0 Deliverables / Schedule

1. The Contractor shall provide:

a. Product data sheets for sealer, primer, block filler (if required), and finish coats

b. Color samples (current building is white)

c. Work schedule and sequencing plan

2. No materials shall be purchased and/or applied until submittals are approved.

3. Installation and workmanship shall have a warranty for a one (1) year period,

4. The Contractor shall notify the Contracting Officer’s Representative (COR) when work is complete,

5. Invoicing only after walk through with COR for acceptance.

5.0 Security

1. Contractors and their Subcontractors shall provide a picture ID to Security at the main lobby before visitor badges are issued, unless a site badge or linkpass has been approved

2. Contractors and their subcontractors shall be allowed access to only those areas authorized by the COR or

Facility Operations and Maintenance Contractor

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverables / Schedule
5.0 Security