Statement of Work.pdf

PDF 921 KB Posted

Attached to
Greenhouse Ridge Vent Replacements Federal contract opportunity
Solicitation number
1232SA26Q0946
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Statement of Work for the USDA Agricultural Research Service Western Regional Research Center to replace greenhouse ridge vents at their Albany, California facility.

The project requires the contractor to provide all management, supervision, labor, equipment, and tools to remove and replace rack and pinion ridge vents (both roof and wall mounted) in eight PGEC greenhouse rooms: six rooms in Greenhouse 1 and two rooms in Greenhouse 2. The scope includes removing existing systems and disposing of materials, disconnecting and reconnecting electrical wiring, collecting mercury switches for USDA disposal, installing new steel rack and pinions (or functionally equivalent alternative systems), replacing all drive shafts, and replacing screens, screen frames, and brushes with stainless steel or equivalent more durable materials. The contractor must provide a cost proposal and coordinate greenhouse availability with USDA personnel to minimize disruption to ongoing research operations. A detailed table specifies the number of roof and wall vent motors and rack & pinion units per room, ranging from 40 to 20 feet in length. The project contract time is 90 calendar days from Notice to Proceed. The project is subject to the Davis Bacon Wage Act. Key contacts include Ron Haff (Research Program Representative and Location Monitor) and Chris Carter (Administrative Officer). Deliverables required prior to final payment include a one-year warranty on work, operation and maintenance data, release of liens, and a final invoice. The contractor must also submit a Site Specific Safety Plan or Accident Prevention Plan within 10 days of contract award and provide documentation of waste diverted to recycling or a letter explaining why diversion was not practical.

View the file

Other files for this federal contract opportunity

Other files attached to Greenhouse Ridge Vent Replacements, newest first.
File Type Posted
SF30 - Amend 01.pdf PDF
RFIs.pdf PDF
Site Visit Sign-In Sheet.pdf PDF
SF1442.pdf PDF
Wage Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Title USDA-WRRC Greenhouse Ridge Vents

USDA-ARS

Western Regional Research Center 800 Buchanan Street.

Albany, CA 94710 May 19, 2026

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Number: TBD

b. Project Title: USDA WRRC Greenhouse Ridge Vent Replacement

c. Project Location:

Western Regional Research Service 800 Buchanan Street Albany, CA 94710

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

TBD

b. RESEARCH PROGRAM REPRESENTATIVES (RPR):

Ron Haff

USDA-WRRC

Western Regional Research Service 800 Buchanan Street Albany, CA 94710

Phone: (510)-559-5868 Email: ron.haff@usda.gov

c. ADMINISTRATIVE OFFICER (AO acting):

Chris Carter

USDA-ARS

Western Regional Research Service 800 Buchanan Street Albany, CA 94710

Phone: (510)-559-6300 Email: Christopher.carter3@usda.gov

d. LOCATION MONITOR:

USDA-ARS

Western Regional Research Service 800 Buchanan Street Albany, CA 94710

Phone: (510) 559-5868

e. AREA SAFETY AND HEALTH MANAGER (ASHM) Ken Cushman

Email: ken.cushman@usda.gov

f. REAL PROPERTY MANAGEMENT:

N/A

g. ENGINEERING PROJECT MANAGER (EPM)

USDA-ARS

Western Regional Research Service 800 Buchanan Street Albany, CA 94710

Phone: (510) 559-5868

3.0 SCOPE OF SERVICES:

The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.

a. The Contractor shall provide services for the following tasks marked by an

“X”:

[X] Provide a cost proposal to complete the project as per project requirements.

[X] Provide and install all material to complete the project as per project requirements.

4.0 PROJECT REQUIREMENTS:

The contractor shall provide all management, supervision, labor, equipment, and tools to replace roof and wall ridge vents in eight PGEC greenhouse rooms.

a. The Contractor will work with Location Monitor and other site personnel to ensure minimum downtime as heating the and cooling of the building will likely be affected.

b. The Contractor’s work shall adhere to the criteria stated within these project requirements. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

c. All work must meet all pertinent Unified Facilities Guide Specifications

(UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.

d. This project falls under the DAVIS BACON Wage Act.

e. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for people experienced in performing this type of work.

4.1 Background & Site Description:

The project site is the main building of the Western Regional Research Service located at 800 Buchanan Street, Albany, CA, 94710. The contractor is responsible for determining the scope of the inspections and tests to meet the code requirements in 4.0 above.

4.2 Bid Schedule:

A quotation for the following items: Repair or replace as necessary for full functionality ridge vents in eight PGEC greenhouse rooms.

4.3 Description of Work:

Provide all management, supervision, labor, equipment, and tools to replace rack and pinion ridge vents (both roof and wall) in PGEC Greenhouse 1, rooms 1 to 6, and in PGEC Greenhouse 2, rooms 1 and 2. All roof vent systems are dual (with vents opening on each side of the top ridge).

The chart below details the number and length of units in each room. Pictures are attached. Site visits are strongly encouraged and welcome to understand the full scope of the required work.

• The contractor shall remove and dispose of existing systems.

• The contractor shall be responsible for the disconnection and reconnection of electrical wiring for the demolished & newly installed system.

• There are existing mercury switches on many of the motors. The contractor shall gather these mercury switches and provide them to the USDA, the USDA will be responsible for the disposal of these mercury switches. The contractor is responsible for the disposal of everything else.

• The contractor should use new steel rack and pinions (or an alternative similar functioning system).

• The contractor shall replace all drive shafts.

• The contractor shall replace all screens, screen frames and brushes. Replacement screen and frame shall be stainless steel or equivalent (more durable than the existing nylon, aluminum, and steel screens).

https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/

• Contractor shall provide schedule for work completion. Greenhouse availability must be carefully coordinated with USDA personnel to minimize disruption to ongoing research.

4.4 Government Furnished Equipment\Services

a. none

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research.

Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose of all any materials removed that will not be retained. The contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycling, the contractor shall submit a letter stating so and why diversion was not practical.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with

Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the

COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government.

Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) 10 days after contract award. SSSP / APP shall be approved by the Government before construction work commences.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged conditions to the satisfaction of the COR.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utility and is responsible for any damage caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be provided to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the

Contractor shall obtain approval for such shutdown from the COR 21 working days prior to the need.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment.

All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The construction site shall be always kept clean and free of debris. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.10 Warranty:

a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO

FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum one (1) year warranty on work.

b. Operation and Maintenance Data

c. Release of liens.

d. Final Invoice

6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to

Proceed.

7.0 Photos, attachments, etc N/A

United States Department of Agriculture
Agricultural Research Service
Title
USDA-WRRC Greenhouse Ridge Vents
USDA-ARS
Western Regional Research Center
800 Buchanan Street.
Albany, CA 94710
May 19, 2026