Statement of Work.pdf

PDF 597 KB Posted

Attached to
Decommission and Remove Lift Federal contract opportunity
Solicitation number
1232SA26Q0693
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Statement of Work (SOW) for the decommissioning and remediation of a Weaver EC105B/106B Twin Post Heavy Duty Lift at the USDA Dairy Forage Research Center in Prairie du Sac, Wisconsin. The project involves complete removal of the non-functioning lift, soil contamination testing, backfill and compaction, and installation of new heavy-duty rated concrete flooring that ties into and matches the existing shop floor.

Key technical requirements include conducting a site assessment; submitting a detailed demolition plan with safety protocols, equipment specifications, and disposal methods prior to work commencement; acquiring Wisconsin Department of Safety & Professional Services (DSPS) permits and approvals; performing removal by credentialed personnel per SPS 305.991; properly disposing of used oil in accordance with federal, state, and local regulations; executing straight saw cuts with right angles to maintain parallel and square lines; removing all lift components and sub-assemblies for disposal or recycling; conducting soil testing before backfill begins; backfilling to sub-slab level with appropriate compaction; tying new concrete with rebar/mesh to existing flooring; and matching the finish texture of new concrete to the existing floor. Work must be performed during normal business hours (7:00 am–5:00 pm, Monday–Friday, excluding federal holidays). The contractor's site superintendent must demonstrate prior experience removing underground lifts with proof of past performance. Key deliverables include the demolition plan and permit copies, soil test results, backfill material and concrete strength specifications, and a final recycling content report documenting pounds of material recycled, all to be submitted via email to the Contracting Officer's Representative (COR) at specified intervals before and after work phases.

View the file

Other files for this federal contract opportunity

Other files attached to Decommission and Remove Lift, newest first.
File Type Posted
SF30 - Amend 01.pdf PDF
RFIs.pdf PDF
Photo 06.jpg JPG image
SF-1442.pdf PDF
Photo 08.jpg JPG image
Photo 09.jpg JPG image
Photo 02.jpg JPG image
Photo 04.jpg JPG image
Photo 05.jpg JPG image
Wage Determination.pdf PDF
Photo 01.jpg JPG image
Photo 03.jpg JPG image
Photo 07.jpg JPG image
Photo 10.jpg JPG image
Photo 11.jpg JPG image
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project Title General Information

1.0 Background and Purpose

2.0 Definitions

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Deliverable / Schedule

5.0 Government Furnished

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 - Electronic and Information Technology Standards

11.0 Performance Requirement Measures

Attachment

Project Title Decommissioning Floor Lift

General Information

1.0 Background and Purpose

The Dairy Forage Research Center, located at S8822 Sunset Drive, Prairie du Sac, WI, has an existing Weaver EC- 105B/106B Twin Post Heavy Duty Lift that is no longer functioning and needs to be decommissioned. The lift is in a maintenance building for tractors and farm vehicles. The goal is to have the contactor remove the lift, test the soil for contamination, restore/prep the area with fill and compaction, tie in/reinforce the new concrete to the slab with same thickness and texture of the existing shop floor. Saw cuts/demo should be done with the goal to keep lines parallel and square as possible. The lift is comprised of the main portion which is L-shaped of about 4’X18’X18”wide ~ 7 ½ deep. A smaller ~18”x3’ section. See attached Parts Manual for exploded diagram. New concrete shall be rated for heavy duty shop floor traffic. Wisconsin DSPS approval and permitting will need to be completed by contractor.

2.0 Definitions

DSPS – Department of Safety & Professional Services

Contractor Requirements

3.0 Technical Requirements / Tasks

Conduct site visit to assess the equipment and surrounding area as needed Submit a detailed demolition plan including safety protocols, equipment to be used, disposal methods, and schedule Acquire appropriate permits/inspections Coordinate with location employees when time for demolition begins Removal must be performed by credentialed personnel per SPS 305.991 Used oil is to be removed and properly disposed/transported/recycled in accordance with federal, state and local regulations Lift demo shall be made with straight saw cuts with right angles Lift and sub-assemblies to be removed and disposed of/recycled by the contractor Backfill to sub-slab level with appropriate compaction Tie in new concrete with rebar/mesh to existing floor using heavy duty rated concrete Match finish of new floor to that of existing floor Inspect and clean the work area Confirm the area is returned to a safe and usable condition Contractor to provide contacts/evidence of previous work

4.0 Deliverable / Schedule

Key Deliverables

Item No.

Deliverable / Item Title

Description Frequency Delivery Format

Due By

1 Demo plan and permit copies

Demo plan and permits 1 Via email to

COR

Before demo work begins

2 Soil Test Results Soil test results 1 Via email to

COR

Before back fill begins

3 Back fill material & concrete strength

Report of type of back fill material and concrete strength used

1 Via email to

COR

Before back fill begins

4 Recycling content

Report on pounds of material recycled

1 Via email to

COR

Before contract close

5.0 Government Furnished

No Government property or equipment will be provided. Work to be performed during normal business hours of 7:00 am – 5:00 pm. Monday – Friday, excluding any Federal holidays.

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

Site Superintendent should have experience in removing underground lifts. Provide proof of past performance.

8.0 Security Requirements

No special security requirements will be needed.

9.0 Data Rights

N/A

10.0 Section 508 - Electronic and Information Technology Standards N/A

11.0 Performance Requirement Measures

Performance Objective

Performance Standard Acceptable Quality Level

Contractor shall submit a detailed demolition plan and proof of permits

Submitted prior to demolition/work to begin

Submitted before work begins

Removal and disposal of lift components

Removal of all lift components 100% compliance

Soil Testing Provide soil test results 100% compliance Backfill/remediation Backfill/remediate as necessary 100% compliance Prep/pour new floor

Tie in new work to existing flooring with rebar/mesh as needed for heavy duty work area

100% compliance

Clean work area Produce clean finished work area 100% compliance

Attachment

Cylinder

Project Title
General Information
1.0 Background and Purpose
2.0 Definitions
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverable / Schedule
5.0 Government Furnished
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 - Electronic and Information Technology Standards
11.0 Performance Requirement Measures
Attachment