Statement of Work.pdf

PDF 113 KB Posted

Attached to
Y1DA--Project # 596-19-104, Construction to Correct FCA Deficiencies - FSC
Solicitation number
36C24923R0147
Issued by

About this file

This statement of work outlines requirements for a construction project to correct deficiencies at a Federal Supply Center. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9 seeks bids for a project to demolish existing structures and perform general construction, alterations, electrical work, and installation of architectural elements, doors, door hardware, and physical access controls at multiple buildings. Work will be completed in phases, with the statement of work dividing the project into five bid items corresponding to different periods of performance for work at specific buildings. Bidders must make arrangements to visit the site and all contractor employees will require VA security approval and access restrictions. The solicitation number provided is 36C24923R0147 for project 596-19-104.

View the file

Other files

File Type Posted
Site Visit Sign-in Sheet.pdf PDF
36C24923R0147 0001.docx DOCX document
Solicitation Questions - Answers.pdf PDF
Project Drawings_Part1.pdf PDF
Pricing Schedule.xlsx XLSX spreadsheet
Project Drawings_Part2.pdf PDF
Past Performance Questionnaire.pdf PDF
Project Specifications.pdf PDF
36C24923R0147_1.docx DOCX document
Wage Determination KY20230090 9-8-2023.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project: 596-19-104 Correct FCA Deficiencies - FSC

GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project 596-19-104 Correct FCA Deficiencies - FSC as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Contracting Officer.

C. Offices of Apogee, Inc. as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

STATEMENT OF BID ITEM(S)

A. BID ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, walks, electrical, architectural, doors, door hardware, physical access controls and necessary removal of existing structures and construction and certain other items. Reference contract drawings and specifications.

Period of performance shall be 240 calendar days.

B. BID ITEM II, all work in Bid Item I except work in Building 1.

Period of performance shall be 220 calendar days.

C. BID ITEM III, all work in Bid Item II except work in Building 27.

Period of performance shall be 200 calendar days.

D. BID ITEM IV, all work in Bid Item III except work in Building 12.

Period of performance shall be 180 calendar days.

E. BID ITEM V, all work in Bid Item IV except work in Building 29.

Period of performance shall be 180 calendar days.

END STATEMENT OF WORK