Statement of Work.docx
DOCX document 1 MB Posted
- Attached to
- Manhole Concrete Repair
- Solicitation number
- N6893620Q0211
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment.docx | DOCX document | |
| Q and A.docx | DOCX document | |
| Manhole-Vault Pictures.zip | ZIP file | |
| 20Q0211 Commercial Solicitation Amendment.docx | DOCX document | |
| Statement of Work Rev 2.docx | DOCX document | |
| 20Q0211 Commercial Solicitation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Repair Manhole Covers Going Up Laguna Peak
1 General Intention and Scope of Work
The project will address the inadequate conditions of existing manhole concrete enclosures and steel plate covers. These manholes support various communication cables, connecting NAS Point Mugu infrastructures and Laguna Peak communication equipment assets. All six manhole concrete enclosures have different degree of deterioration, showing settlements, cracks and chips, which will be repaired through this project. The existing steel plate covers will require newly fabricated aluminum steel plate assembly, allowing one person to open and close.
1.1 Statement of Work
The contractor shall furnish all labor, management, supervision, tools, materials, equipment, incidental engineering, and transportation necessary to perform all ordered work. All work shall be performed on Regular Working Hours.
1.1.1 Demolition Work
a. Remove and dispose of all existing steel plate manhole cover plates and associated hardware.
b. Selective demolition of manhole concrete enclosures as a part of repair process.
1.1.2 New Construction
a. Field measurement shall be performed to verify the exact dimensions.
b. Make necessary repairs to each concrete manhole enclosures, addressing the settlement, cracks and chips to meet the Non-traffic rated manhole standard per UFC3-550-01 and associated UFGS sections.
c. Provide and install new 48” x 96” two door aluminum vault lids on each manhole. The lids shall be equipped with torsion assisted hinges, bolted down frames, recessed lock box, self-locking safety arms, and 6” x 6” x 3/8” reverse angle frame w/ anchor straps. The lids shall be coated w/ zinc rich epoxy powder.
1.2 SPECIAL REQUIREMENTS
· Coordinate disposal of all recyclable metal and other construction debris with the NBVC Recycling Center for proper disposal. The point of contact at the Recycling Center is Mr. Lloyd Nash at (805) 989-9899.
· All construction waste must be disposed properly in accordance with all federal, state, and local regulations and NBVC instructions.
· Please contact (805) 982-1970 or DSN: 551-1970 for hazardous waste disposal guidance and support.
· Maintain a clean job site and ensure that all required personal protective equipment is utilized throughout the execution of this project.
· Test and verify all new installations for proper operations.
· Site cleanup must be completed and inspected by KO or COR before move out.