HQ AFSOC A5/8

Cubicle Modernization

Statement of Work

SCOPE

The contractor shall provide all labor, materials, personnel and equipment necessary to provide install, disassembly and removal of old and new furniture as requested below.

Work

1.1.1 Entire project must completed within four (4) months from the start date, to include planned delays from other required work. If additional work extends the timeline the expected completion date for cubicle work will be extended to match.

1.1.2 Prefer a contractor that is GSA approved, use products made in the USA to the maximum extent possible (>70% & able to prove), use sustainable, green/earth friendly materials that support future changes in workspace.

1.1.3 This project shall include: electrical utility work, cubicle modification, removal, and installation.

1.1.4 Contractor will work each office sequentially, completing the installation of one (1) office prior to beginning the next.

1.1.5 Contractor is responsible for disassembly and removal of old cubicle materials.

1.1.6 Contractor will be required to delay between removal and installation to allow for carpet install.

1.1.7 Both general constraints and room specific requirements are found in the attached document, “AFSOC/A5/8 Cubicle Modernization.” It is the primary document of the desired cubicle modernization plan.

DESCRIPTION OF SERVICES

General Services

Coordination and management of equipment and personnel to dismantle, remove, and dispose of all existing furniture and all new product, equipment and people required to create, deliver and install new systems and modular furniture within an Air Force location.

This includes ongoing servicing of any items defective due to manufacturing error as well as for replacement or repair of any damaged item after purchase.

2.1.1 The contractor shall be responsible for all personnel, equipment, tools, materials, supervision, storage, assembly, transportation, incidentals and all other items and services necessary to dismantle, remove, and dispose of all existing furniture and to provide and install systems and modular furniture.

2.1.2 The contractor shall be responsible for all personnel, equipment, tools, materials, supervision, storage, assembly, transportation, incidentals and all other items and services necessary to dismantle, remove, and dispose of all existing furniture and to provide and install systems and modular furniture.

2.1.3 The contractor shall be knowledgeable of and shall comply with all applicable federal, state, and local laws, codes, permits, DoD, AF, and base requirements and instructions required for the performance of the duties in this Performance Work Statement (PWS).

2.1.4 The contractor shall ensure policies and procedures are established that protect the safety and welfare of customers, employees, and the community to minimize or eliminate safety or environmental risks. These policies shall be in compliance with Federal and Installation policies and procedures.

2.1.5 The contractor shall provide a Project Manager, who is responsible for the perform-ance & executing of the work. The name of this person and an alternate(s) shall be designated in writing and provided to the Contracting Officer (CO) within 10 days after contract award. The POC or alternate(s) shall have full authority to act on behalf of the contractor and able to resolve all contract matters relating to the daily operations of this project.

2.1.5.1 The Project Manager shall have a minimum of five (5) years of relevant furniture installation experience, capable of managing the dismantling, removal, and disposal of all existing furniture, responsible for project site management, scheduling, coordination and technical assistance to the Air Force representative as required throughout the project.

2.1.6 All contractors shall submit a complete list of personnel in accordance with installation policy, including deliverymen, who will be expected to work on the installation. This list will contain Privacy Act information as required as well as the expectation that each individual will be able to present a current and valid state identification, to meet local Air Force security requirements. This information shall be sent to the CO at least 10 days in advance prior to the start of installation.

2.1.7 The contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees.

2.1.8 The contractor shall be an authorized dealer of the product they are quoting and allowed to accept a GSA Delivery Order through their manufacturer’s GSA Schedule contract.

2.1.9 The vendor shall manage ordering, shipment, delivery and installation of all new furniture from manufacturer to final acceptance by the designated Government Acceptor.

2.1.10 The contractor shall provide customer service during normal duty hours, 7:30AM

- 4:30PM CST hours, Monday through Friday; except for federal holidays.

2.1.10.1 Recognized US Federal Holidays are as follows: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving and Christmas. If the holiday falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.

2.1.11 When the contractor desires to work other than standard times, a written request shall be submitted to the CO for approval. This written request shall be reviewed & approved by the CO before proceeding with the work. The request shall be submitted at least five (5) work days prior to the proposed performance of work, and it shall indicate the day/days, time/amount of work, and reason why performance is necessary during nonstandard hours.

2.1.12 All Air Force inquiries shall be responded to by a contractor representative within two (2) business days.

2.1.13 Meetings may periodically be held between top level base personnel and contractor management to discuss contract status. The CO will notify the contractor in writing in advance of the place and time of required meetings.

2.1.14 Vehicle registration, proof of insurance and a valid driver’s license shall be presented to gain base access.

2.1.15 The contractor shall be responsible for coordination of an escort through any controlled areas through the assigned Government POC.

2.1.16 Lost vehicle and entry passes shall be reported immediately to the Security Police as well as the Government POC in accordance with the local security forces policy.

2.1.17 The contractor shall be responsible for any storage of all new systems/modular/demountable wall furniture, components, parts and assemblies prior to and during installation in accordance with the agreed upon delivery schedule.

2.1.18 The contractor shall maintain the capability to surge in the event of unforeseen circumstances such as extended duty hours, travel, classes and education, and mission related surges.

2.1.19 The contractor shall maintain continuity between the support operations at Hurlburt Field, FL and all other assigned performance locations and the contractor’s corporate offices. The contractor shall provide the necessary resources to manage and administer the contract. The contractor shall, as a minimum, maintain a single point of contact for this effort to be available in person to the Government representative during the same business day.

2.1.20 The contractor shall provide for the management and support of personnel, to include: making necessary arrangements for employees required to travel;

supporting personnel co-located on Hurlburt Field, FL and other locations specified with additional resources, expertise, advice; necessary infrastructure to support work to be accomplished off-base; conducting personnel meetings; providing administrative support for employees in a timely fashion; and providing facility and staff security requirements.

2.1.21 All personnel attending meetings or working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

Design Services

Providing professionals versed in programming, space planning and product specification, able to communicate product capabilities to the customer, to ensure products purchased meets the requirements.

2.2.1 As a part of the request for quote process, the contractor will quote the set Typicals addressed under paragraph 1 of this Performance Work Statement. Following award, within parameters specified below, a complete design that takes into account site condition considerations, as well as information gathered during initial customer review, shall be provided to the CO in writing.

2.2.2 The contractor shall be able to provide design services, including space planning, site verification, material selection and programming for this project.

2.2.3 The contractor shall define and furnish the necessary hardware, software, and all other equipment necessary to accomplish design tasks. Standard equipment in addition to the hardware and software shall include but not necessarily be limited to: reproduction machines, plotters, paper, pencils, fax machines, and office furniture.

2.2.4 The contractor shall be responsible for collection of information relevant to the design of a space. Examples could include personnel interviews, questionnaires and walk-through inspections of the facility.

2.2.5 Services shall include site evaluation to ensure proper fit of the new furniture within the given space and that all structural and other anomalies are taken into account.

2.2.6 The contractor is responsible for notifying the Government POC of all power requirements regarding location of communication, LAN and power junction boxes. The user will be responsible for cabling as well as providing and locating those junction boxes within 4'-0" of the ceiling penetration of the power pole location provided by the contractor.

2.2.7 Design shall ensure that power poles do not protrude into main walkways or through the building exterior.

2.2.8 Design shall ensure that all outlets included in the design are accessible to the user, free and clear of obstacles.

2.2.9 Design shall not allow more than four cubicles to be served by a single circuit.

2.2.10 Design shall ensure that no more than two duplex outlets (four plug in points) are put onto the same circuit.

2.2.11 Design shall ensure that no existing wall outlets, thermostats, or internet ports are covered or concealed by panels or other systems furniture components.

2.2.12 Design shall consider utilize wall mounted applications where possible.

2.2.13 All designs of furniture layouts, including original designs and any subsequent redesigns, must be accomplished by, qualified professional Interior Designers with a four (4) year Interior Design degree and three years’ experience using design software necessary to meet the requirements of this Performance Work Statement.

2.2.14 The contractor shall meet with the Government POC and the CO to review the installation drawings prior to submission of order for materials.

2.2.15 The contractor shall provide additional drawings of furniture layouts, if requested by base organizations on a non-rewritable CD or DVD in both .dwg and .pdf formats unless otherwise specified in the contract.

2.2.16 The hardware/software shall perform computerized inventory, computer aided design, automated take-off function, and report generation for all product purchased. The software for this contract shall be compatible software for AutoCAD and Microstation. The software shall be fully compatible with Microsoft Windows, the most current version.

2.2.17 Design service shall include an initial complete design with up to two (2) additional revisions prior to final approval. The design and planning will accommodate the government’s proposed installation sequence of “installation areas” and the required personnel movement.

2.2.18 Design shall include a Basic component floor plan sheet in which all systems furniture and workstation is tagged: to include graphic symbols for all major hanging components (flipper cabinets, shelves, task lights, tack boards, work surfaces, drawers, etc.) as determined by the government. This design sheet shall include station numbers and movable wall and associated product locations, in 1/4" = 1'-0" scale.

2.2.19 Designs of each location shall include a Panel and Hardware Layout sheet: to include all finish colors and fabrics, panel widths (30", 36", 42", etc.), in 1/4" = 1'0" scale, in addition to display hardware, keys and locksets shall be included.

2.2.20 Design sheet layouts of each location shall include a Furniture Power Distribution sheet in 1/4" = 1'0" scale to include: the location of all new powered panels, powered components, receptacles, communication ports, power poles, powered raceways, base electrical feeds and building connection points.

2.2.21 Design/redesign timelines shall be expected:

2.2.21.1 Design sheet layouts for all phases of design (initial, revisions and final) shall be received within 15 business days.

2.2.22 Within ten (10) workdays after the final design has been accepted by the base requesting organization, a bill of materials detailing all new inventory, and (3) copies of all plans including basic floor plan, movable wall, panel and electrical layouts will be provided to the Government POC and CO.

2.2.23 The contractor shall maintain an updated, automated master copy of all furniture layouts, (designs/redesigns) accomplished under this contract for the duration of the warranty, after government acceptance of the project.

2.2.24 Drawing changes required to a layout due to contractor errors or omissions shall be the responsibility of the contractor and the corrected drawing and bill of materials shall be delivered to the government within three calendar days of the request.

2.2.25 Contractor shall provide the base or requiring location a copy the installation drawings and bill of materials via mutually agreed upon electronic media.

2.2.26 Contractor shall make the government aware of any discrepancies to existing conditions not previously identified.

2.2.27 Design shall conform to the parameters established in the Architectural Barriers Act regarding accessibility of persons with disabilities.

2.3 Product Markings/Documentation/Tools

Items used after product acceptance used to identify or modify a particular product.

2.3.1 All documentation (Owner’s manuals, warranty information, assembly instructions, maintenance and care instructions, operating instructions, etc.) shall be provided to and reviewed with the Government Acceptor and/or Government Project Manager upon completion of the installation.

2.3.2 Special assembly tools (security hardware wrench, spare parts provided with the furnishings, etc.) shall be provided to the Government Acceptor and/or Government Project Manager prior to final Government acceptance of products and services.

2.4 Delivery Services

Transportation of all new products, loading, unloading, storage and all necessary movement from factory to final onsite set up.

2.4.1 The contractor Project Manager shall be responsible for on-site coordination of all staging and deliveries of their product, to include access to and operation of any equipment needed for unloading and movement of materials or product.

2.4.2 Contractor shall be responsible for determination of the appropriate delivery method and handling, based on site conditions to include the non- existence of loading docks and equipment at any given location. Special circumstances may be identified by and negotiated with the Contracting Officer.

2.4.3 A maximum of 30 days storage for new products shall be included in the contractor's agreement.

2.4.4 Work shall comply with applicable building standards and codes, specifically:

National Electrical Code (National Fire Protection Association (NFPA 70) and National Life Safety Code (NFPA 101).

2.4.5 The contractor shall be responsible for following all safety and security guidelines within the area in which work is being performed, to include securing any contractor owned tools or equipment, and any on site storage being utilized.

2.4.6 The contractor shall prevent its personnel from entering any area other than the designated work area.

2.4.7 The contractor shall maintain a means of egress within all designated work areas to comply with fire codes.

2.4.8 The contractor shall ensure its personnel eat, drink, or smoke only in designated areas.

2.5 Installation and Removal Services

Manufacturer certified professionals to install systems and modular furniture per the approved design drawings.

2.5.1 Each dealership shall be able to provide, or capable of obtaining support services to include removal of the proposed systems furniture and demountable walls.

2.5.2 The contractor shall appoint an authorized representative who will be the company's senior representation on site for all customer communication and enforce compliance of all requirements for the project. This representative shall have a physical presence during any delivery and throughout installation unless agreed to by the Government Acceptor and/or Government Project Manager.

Resumes and letters of intent shall be provided for these employees.

2.5.3 The contractor representative shall meet with Government POC and CO to review the installation drawings prior to installation.

2.5.4 The contractor shall install new systems and modular furniture in accordance with this requirements document and basic component floorplan, panel plan and electrical plan, designed and provided by the contractor.

2.5.5 Contractor shall be liable for any damage to government property caused by the contractor or their representatives.

2.5.6 During installation the contractor shall protect all furniture and building materials, to include carpet, existing within the space with industry approved protective coverings inclusive of craft paper, moving blankets and such type material. The contractor shall not use protective materials that will leave any type of residual print, outline or imaging on any furniture or building materials. Contractor shall not repair damage to finishes but will be responsible to pay for damages. The government will make repairs and back charge the installation contractor.

2.5.7 The contractor shall uncrate/unpack all new items and perform required assembly in accordance with the manufacturer instructions.

2.5.8 Services shall include inspection of product for shipping damage. If damage is found it shall be the responsibility of the contractor to notify the authorized government representative and make all arrangements for replacement or repair of the item(s) damaged. Damaged items are not to be installed unless otherwise directed by the Government Acceptor.

2.5.9 Services shall include assembly of new product to conform to final Air Force approved design drawings.

2.5.10 Any furnishings attached to the building shall be securely attached.

2.5.11 Installation of new systems and modular furniture must be under the oversight of an onsite manufacturer certified installer.

2.5.12 The contractor shall ensure that all communication outlet faceplates are provided with the new furniture and accommodate a standard RJ45 quad port or fiber-inserts that will be provided by the local communications group or general contractor.

2.5.13 Services shall include removal of packing materials from the installation.

2.5.14 All trash removed from the worksite shall be disposed of in accordance with state laws, and packaging and other recyclable materials shall be recycled where ever possible.

2.5.15 The contractor shall maintain environmental controls when working in any Air Force facility, to include but not limited to keeping doors shut and lights off when not in use and turning off vehicle engines when parked.

2.5.16 Light fixtures shall have appropriate lamps and be fully operational.

2.5.17 Prior to acceptance, the contractor shall clean all new furniture, equipment and materials only with the manufacturer's recommended cleaning agents/products.

2.5.18 The contractor shall provide all new components, completely assembled, installed, and operational, including keys in each lock set.

2.5.19 New furniture, equipment, and accessories shall be level, square, and in proper alignment with adjoining furniture. All drawers should operate smoothly and stay closed when not in use.

2.5.20 The contractor shall inspect to ensure the new furniture, equipment and materials are free of surface dirt and defects, the installation is complete, and the new furniture and equipment is ready for use.

2.6 Inspection/Acceptance Checklist

Validation between the contractor and the Government Acceptor that all product has been installed according to manufacturer guidelines and customer specifications.

2.6.1 A post-installation walkthrough for this project shall be coordinated with the contractor’s authorized representative and Government POC and CO.

2.6.2 All areas requiring correction shall be documented in a punch list by the contractor and provided to the authorized government representative upon completion of a joint walk through by the contractor and authorized government representative.

2.6.3 A final walk through for each “installation area” will be performed with the contractor and the Government POC and CO to ensure all punch list items have been addressed to the satisfaction of the Government POC.

2.6.4 Upon completion of all contract requirements for all installation areas, the contractor will submit to the Government Acceptor documentation of completed punch list items. The Contractor may then submit a final invoice in the Wide Area Workflow system (WAWF) (https://wawf.eb.mil/).

GOVERNMENT FURNISHED PROPERTY/SUPPORT

Base support includes Government-controlled working space and utilities.

SITE CONDITIONS

4.1 Standard site conditions shall be considered those that include:

4.1.1 Free and clear hard surface access to the receiving and installation location during regular working hours

4.1.2 Parking and off-loading area suitable for access by a semi-trailer combination or truck within 100 feet of the building entrance closest to product installation area

4.1.3 Threat condition level of the base is Alpha. This requires dealer personnel to get base access in order to complete the product installation.

4.1.4 A staging area adequate to sort, stage and uncrate products along with a waste receptacle suitable for disposal of materials

4.1.5 Includes electric power, working lights, heating and air conditioning, and access to a working freight elevator if location is on a floor other than the first floor.

4.2 Contractor shall notify the CO of any deviations from the above standards.

ADDITIONAL SERVICES INFORMATION

The following services are required:

5.1 The contractor shall provide professional electrical services to disconnect the existing furniture and connect the new furniture to the building’s electrical system. The electrician provided by the contractor shall be a licensed electrical contractor.

5.2 The contractor shall be responsible for collection of information relevant to the redesign of a space. Examples could include personnel interviews, questionnaires and walk-through inspections of the facility as well as the existing furniture database (if available).

VOLUNTARY PROTECTION PROGRAM (VPP)/SAFETY

Voluntary Protection Program: The Air Force is part of the AOSHA VPP. All contractors are required to familiarize themselves with the requirements of the VPP. Information on VPP can be accessed at http://www.osha.gov/desp/vpp/index.html.

BASE/INSTALLATION SPECIFICS

7.1 All commercial trucks must enter through the Commercial Gate on Cody Ave off of Independence Road, Fort Walton Beach, FL for inspection. Prior to going through the Commercial Gate, contractor will have to obtain a visitors pass from the Visitors Center located off of HWY 98. In accordance with the Installation 1st SOSFS Visitor Control Center; base entry procedures must adhere to delivery vehicle process requirements mandated by the 1st SOSFS. Vehicles are subject to inspection. To obtain a base pass from the Visitors Center, the driver will require:

A current Vehicle Registration A current Proof of Insurance A valid and current Driver's License for the driver A valid and current Driver's License or other State Identification for any passenger(s) in the vehicle.

A Base Pass Letter from the CO with the contract number, and individuals requiring base access. The base pass request must be submitted to the CO at least 10 days prior to scheduled delivery and include the names and driver’s license number of each individual requiring base access. The request shall also include the anticipated installation timeframe for this project.

7.2 Gate Procedures:

Once at Cody Ave. Gate, be prepared to exit the vehicle and allow for vehicle inspection. At this time you may ask for directions to your final destination.

If the final destination requires the driver to leave Cody Ave. Gate, and re-enter the base through an alternate gate, the pass received will be sufficient documentation for entry into both gates, within a pre-established time directed by the Security Forces representative.

Arrival at the appropriate gate after the designated allotted time will result in non-admittance to the installation.

This procedure will occur each time a commercial truck requests access to the base.

7.3 Current Bill of Lading (BOL) to get delivery driver and the vehicle on base. BOL must include the AF installation name, date of anticipated delivery, and specific destination (including building number, street address, and point of contact information).

7.4 Personnel should the following items when entering an installation:

Current Registration for all vehicles Current Proof of Insurance for all vehicles Valid driver’s license for each driver Valid driver’s license or other state identification for each passenger Depending on the current Force Protection Condition, a government representative may be required to sponsor those people in person at Pass & ID/Visitors Center.

7.5 Prohibitions: Firearms & Illicit drugs may not be brought on base under any circumstances. Individuals with criminal records are not allowed on base. Contractor personnel are prohibited from sponsoring guests onto the installation.

8 WARRANTY

The contractor shall provide a one (1) year warranty on all the equipment required under this Statement of Work. Defective components and parts shall be repaired or replaced as soon as possible but within a reasonable amount of time, no more than seven days. This includes any damage done during shipment, delivery, and installation. Repair and replacement shall be provided at no additional cost, including freight and labor. Normal wear and tear is exempt. The contractor shall repair or replace any damage done to existing property, equipment or facilities during deliver and installation.

9 MEASURING, CONVERSION AND GUARANTEE

It shall be the complete responsibility of the contractor to obtain accurate dimensions at the job site and to examine all conditions as they relate to this installation. Skilled technicians shall perform the installation. All work shall be accomplished in a neat and professional manner.