This is a Statement of Work (SOW) for HVAC system cleaning services at Building 763 at Langley Air Force Base in Virginia, issued by the Department of the Air Force Air Combat Command. The work involves cleaning approximately 5 Air Handler Units, 102 supply vents, and 110 Plenum Return Grills, including all heating, air-conditioning and ventilation system components from air entry points to discharge points.
The contractor must be a certified member of the National Air Duct Cleaners Association (NADCA) with at least 3 years of experience and employ at least one Air System Cleaning Specialist (ASCS). Work must be performed between 1800-0400 hours outside normal operating hours. Key requirements include source removal mechanical cleaning methods, HEPA filtration for indoor exhaust, proper disposal of debris, protection of fibrous glass components, and cleaning verification through visual inspection and optional gravimetric analysis. The contractor must coordinate with building management for system shutdowns and provide a detailed work plan and employee information prior to beginning work. While the solicitation number is FA480025QA020, there appears to be a discrepancy as the description refers to a walk-in freezer repair rather than HVAC cleaning.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.docx | DOCX document | |
| STATEMENT OF WORK- BLDG. 763 Updated 01 21 2025.pdf | ||
| Questions and Answers.docx | DOCX document | |
| Base Form Template.pdf | ||
| Combined Synopsis Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR THE CLEANING OF COMMERCIAL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS
BUILDING, 763 LANGLEY AFB, VA
Table of Contents Contents Part 1 -- Special Provisions
1.01 Qualification of the HVAC System Cleaning Contractor
(A) Membership
(B) Certification
(C) Supervisor Qualifications
(D) Experience
(E) Equipment, Materials and Labor
(F) Licensing
1.02 Standards
(A) NADCA Standards
Part 2 -- HVAC System Cleaning Specifications and Requirements
2.01 Scope of Work
(A) Scope
2.02 HVAC System Inspections and Site Preparations
(A) HVAC System Evaluation
(B) Site Evaluation and Preparations
2.03 General HVAC System Cleaning Requirements
(A) Containment
(B) Particulate Collection
(C) Controlling Odors
(D) Component Cleaning
(E) Air-Volume Control Devices
(F) Service Openings
(G) Ceiling sections (tile)
(H) Air distribution devices (registers, grilles & diffusers)
(I) Air handling units, terminal units, blowers and exhaust fans
(J) Duct Systems
2.04 Health and Safety
(A) Safety Standards
(B) Occupant Safety
(C) Disposal of Debris
2.05 Mechanical Cleaning Methodology
(A) Source Removal Cleaning Methods
(B) Methods of Cleaning Fibrous Glass Insulated Components
(C) Damaged Fibrous Glass Material
(D) Cleaning of coils
(E) Biocidal Agents and Coatings
2.06 Cleanliness Verification
(A) General
(B) Visual Inspection
(C) Gravimetric Analysis
(D) Verification of Coil Cleaning
2.07 Pre-Existing System Damage
2.08 Post-Project Report
2.09 Applicable Standards and Publications
General Specifications
Part 1 -- Special Provisions
1.01 Qualification of the HVAC System Cleaning Contractor:
(A) Membership: The HVAC system cleaning contractor shall be a current certified member of the National Air Duct Cleaners Association (NADCA), or shall maintain a current membership and be certified in a nationally recognized non-profit industry organization dedicated to the professional cleaning of HVAC systems.
(B) Certification: The HVAC system cleaning contractor shall have had a minimum of one
(1) Air System Cleaning Specialist (ASCS) certified by NADCA on a full time basis for a period of no less than one year, or shall have had a member of their staff certified by a nationally recognized certification program and organization dedicated to the professional cleaning of HVAC systems on a full time basis for a period of no less than one year.
(C) Supervisor Qualifications: A person certified as an ASCS by NADCA, or maintaining an equivalent certification by a nationally recognized program and organization, shall be responsible for the total work herein specified.
(D) Experience: The HVAC system cleaning contractor shall submit records of a minimum of 3 years experience in the field of HVAC system cleaning in accordance with NADCA standards as requested by the government. Bids shall only be considered from firms which are primarily engaged in HVAC system cleaning and decontamination.
(E) Equipment, Materials and Labor: The HVAC system cleaning contractor shall currently possess and furnish all necessary equipment, materials and labor to adequately perform the specified services.
1. The contractor shall submit to the contracting officer a current list of all specialized equipment necessary to perform cleaning in accordance with NADCA standards.
2. The contractor shall assure that its’ employees have received safety equipment training, medical surveillance programs, individual health protection measures, and manufacturer’s product and material safety data sheets (MSDS) as required for the work by the U.S. Occupational Safety and Health Administration, and as described by this specification.
3. The contractor shall maintain a copy of all current MSDS documentation and safety certifications at the site at all times, as well as comply with all other site documentation requirements of applicable OSHA programs and this specification
4. Contractor shall submit to the government Material Safety Data Sheets (MSDS) for all chemical products proposed for use in the cleaning process.
(F) Licensing: The HVAC system cleaning contractor shall provide proof of maintaining the proper license(s), if any, as required to do work in Virginia. Contractor shall comply with all Federal, state and local rules, regulations, and licensing requirements.
(G) Insurance: Reserved.
1.02 Standards.
(A) NADCA Standards: The HVAC system cleaning contractor shall perform the services specified herein accordance with current published standards of the National Air Duct Cleaners Association (NADCA).
1. All terms in this specification shall have their meaning defined as stated in the NADCA Standards.
2. NADCA Standards must be followed with no modifications or deviations being allowed.
1.03 Documents
(A) Mechanical Drawings: The government shall provide when applicable, the HVAC system cleaning contractor with one copy of the following documents:
1. Project drawings and specifications where applicable.
2. Approved construction revisions pertaining to the HVAC system
3. Any existing indoor air quality (IAQ) assessments or environmental reports prepared for the facility. In the event that drawing and specifications are not available, the HVAC system cleaning contractor shall be responsible to inspect the HVAC systems to familiarize himself with existing condition prior to start of work in accordance with the requirements of paragraph 2.02 HVAC System Inspections and Site Preparations
Part 2 -- HVAC System Cleaning Specifications and Requirements
2.01 Scope of Work
(A) Scope: The contractor shall provide all necessary labor, tools, equipment, supervision, materials, and transportation necessary to perform complete HVAC duct system cleaning in Building 763, Langley AFB, VA. ALL work must be done after normal hours of operation, between1800hrs-0400hrs *This Scope of Work covers a portion of air conveyance systems in the building. It is the responsibility of the contractor to determine the full scope of work associated with this solicitation during the site visit.
The contractor shall be responsible for the removal of visible surface contaminants and deposits from within the HVAC system in strict accordance with these specifications.
*Indicates a change.
Building 763 This system comprises approximately 5 Air Handler Units, 102 Supply vents, 110 Plenum Return Grills. The HVAC system includes any interior surface of the facility’s air distribution system for conditioned spaces and/or occupied zones. This includes the entire heating, air-conditioning and ventilation system from the points where the air enters the system to the points where the air is discharged from the system. The return air grilles, return air ducts (except ceiling plenums and mechanical room) to the fan coil units (FCU), the interior surfaces of the FCU’s, mixing box, coil compartment, condensate drain pans, supply air ducts, fans, fan housing, fan blades, turning vanes, filters, filter housings, heating coils, cooling coils and supply diffusers are all considered part of the HVAC system. The HVAC system may also include other components such as dedicated exhaust and ventilation components and make-up air systems.
2.02 HVAC System Inspections and Site Preparations
(A) HVAC System Evaluation: Prior to the commencement of any cleaning work, the HVAC system cleaning contractor shall perform a visual inspection of the HVAC system to determine appropriate methods, tools, and equipment required to satisfactorily complete this project.
1. Damaged system components found during the inspection shall be documented and brought to the attention of the contracting officer.
(B) Site Evaluation and Preparations: The contractor shall conduct a site evaluation, and establish a specific, coordinated plan which details how each area of the building(s) will be protected during the various phases of the project.
(1) Scheduling/Security Requirements: After a complete site evaluation, the contractor shall submit his plan to Maintenance Engineering, Service Contracts for approval. The plan shall include any systems shut-downs with approximate down-times discussed. Additionally, the contractor must ensure that his planned work is approved prior to any work being performed. This will be accomplished by close coordination with the contract inspector and the individual building managers. The contractor shall submit a written list of employees, prior to contract start, who will be performing work on this contract. The information required is Full Name, Social Security Number, and Date of Birth.
2.03 General HVAC System Cleaning Requirements
(A) Containment: Debris removed during cleaning shall be collected and precautions must be taken to ensure that Debris is not otherwise dispersed outside the HVAC system during the cleaning process.
(B) Particulate Collection: Where the Particulate Collection Equipment is exhausting inside the building, HEPA filtration with 99.97% collection efficiency for 0.3-micron size (or greater) particles shall be used. When the Particulate Collection Equipment is exhausting outside the building, Mechanical Cleaning operations shall be undertaken only with Particulate Collection Equipment in place, including adequate filtration to contain debris removed from the HVAC system. When the Particulate Collection Equipment is exhausting outside the building, precautions shall be taken to locate the equipment down wind and away from all air intakes and other points of entry into the building. Care should be taken to ensure that temperature and humidity controls are not compromised by high pressure collection equipment. Externally located collection equipment that places the building under a strong negative air pressure and causes the facility to lose its’ temperature and humidity control should not be used. In special cases, such as computer rooms and libraries, care should be taken to maintain a constant temperature and humidity within the facility. If a system shutdown is required for extended periods of time during cleaning, it must be coordinated with the Building Manager prior to any shutdown.
(C) Controlling Odors: All reasonable measures shall be taken to control offensive odors and/or mist vapors during the cleaning process.
(D) Component Cleaning: Cleaning methods shall be employed such that all HVAC system components must be Visibly Clean as defined in applicable standards (see NADCA Standards). Upon completion, all components must be returned to those settings recorded just prior to cleaning operations.
(E) Air-Volume Control Devices: Dampers and any air-directional mechanical devices inside the HVAC system must have their position marked prior to cleaning and, upon completion, must be restored to their marked position.
(F) Service Openings: The contractor shall utilize service openings, as required for proper cleaning, at various points of the HVAC system for physical and mechanical entry, and inspection.
1. Contractor shall utilize the existing service openings already installed in the HVAC system where possible.
2. Other openings shall be created where needed and they must be created so they can be sealed in accordance with industry codes and standards.
3. Closures must not significantly hinder, restrict, or alter the airflow within the system.
4. Closures must be properly insulated to prevent heat loss/gain or condensation on surfaces within the system.
5. Openings must not compromise the structural integrity of the system.
6. Construction techniques used in the creation of openings should conform to requirements of applicable building and fire codes, and applicable NFPA, SMACNA and NADCA Standards.
7. Cutting service openings into flexible duct is not permitted. Flexible duct shall be disconnected at the ends as needed for proper cleaning and inspection.
8. Rigid fiberglass duct board duct systems shall be resealed in accordance with current NAIMA recommended practices. Only closure techniques which comply with UL Standard 181 or UL Standard 181a are suitable for fiber glass duct system closures.
9. All service openings capable of being re-opened for future inspection or remediation shall be clearly marked and shall have their location reported to the contracting officer in project report documents.
(G) Ceiling sections (tile): The contractor may remove and reinstall ceiling sections to gain access to HVAC systems during the cleaning process.
(H) Air distribution devices (registers, grilles & diffusers): The contractor shall remove and clean all air distribution devices.
(I) Air handling units, terminal units (VAV, Dual duct boxes, etc.), blowers and exhaust fans: The contractor shall insure that supply, return, and exhaust fans and blowers are thoroughly cleaned. Areas to be cleaned include blowers, fan housings, plenums (except ceiling supply and return plenums), scrolls, blades, or vanes, shafts, baffles, dampers and drive assemblies. All visible surface contamination deposits shall be removed in accordance with NADCA Standards. Contractor shall:
1. Clean all air handling unit (AHU) internal surfaces, components and condensate collectors and drains.
2. Assure that a suitable operative drainage system is in place prior to beginning wash down procedures.
3. Clean all coils and related components, including evaporator fins.
(J) Duct Systems: Contractor shall:
1. Create permanent SMACNA approved service openings in the system as necessary in order to accommodate cleaning and inspection of otherwise inaccessible areas.
2. Mechanically clean all duct systems to remove all visible contaminants, such that the systems are capable of passing Cleaning Verification Testing (see NADCA Standards).
2.04 Health and Safety
(A) Safety Standards: Cleaning contractors shall comply with all applicable federal, state, and local requirements for protecting the safety of the contractors' employees, building occupants, and the environment. In particular, all applicable standards of the Occupational Safety and Health Administration (OSHA) shall be followed when working in accordance with this specification.
(B) Occupant Safety: No processes or materials shall be employed in such a manner that they will introduce additional hazards into occupied spaces.
(C) Disposal of Debris. All Debris removed from the HVAC System shall be disposed of in accordance with applicable federal, state and local requirements.
2.05 Mechanical Cleaning Methodology
(A) Source Removal Cleaning Methods: The HVAC system shall be cleaned using Source Removal mechanical cleaning methods designed to extract contaminants from within the HVAC system and safely remove contaminants from the facility. It is the contractor’s responsibility to select Source Removal methods which will render the HVAC system Visibly Clean and capable of passing cleaning verification methods (See applicable NADCA Standards) and other specified tests, in accordance with all general requirements. No cleaning method, or combination of methods, shall be used which could potentially damage components of the HVAC system or negatively alter the integrity of the system.
1. All methods used shall incorporate the use of vacuum collection devices that are operated continuously during cleaning. A vacuum device shall be connected to the downstream end of the section being cleaned through a predetermined opening. The vacuum collection device must be of sufficient power to render all areas being cleaned under negative pressure, such that containment of debris and the protection of the indoor environment is assured.
2. All vacuum devices exhausting air inside the building shall be equipped with HEPA filters (minimum efficiency), including hand-held vacuums and wet-vacuums.
3. All vacuum devices exhausting air outside the facility shall be equipped with Particulate Collection including adequate filtration to contain Debris removed from the HVAC system. Such devices shall exhaust in a manner that will not allow contaminants to re-enter the facility. Release of debris outdoors must not violate any outdoor environmental standards, codes or regulations.
4. All methods require mechanical agitation devices to dislodge debris adhered to interior HVAC system surfaces, such that debris may be safely conveyed to vacuum collection devices. Acceptable methods will include those which will not potentially damage the integrity of the ductwork, nor damage porous surface materials such as liners inside the ductwork or system components.
(B) Methods of Cleaning Fibrous Glass Insulated Components:
1. Fibrous glass thermal or acoustical insulation elements present in any equipment or ductwork shall be thoroughly cleaned with HEPA vacuuming equipment, while the HVAC system is under constant negative pressure, and not permitted to get wet in accordance with applicable NADCA and NAIMA standards and recommendations.
2. Cleaning methods used shall not cause damage to fibrous glass components and will render the system capable of passing Cleaning Verification Tests (see NADCA Standards).
(C) Damaged Fibrous Glass Material
1. If there is any evidence of damage, deterioration, de-lamination, friable material, mold or fungus growth, or moisture such that fibrous glass materials cannot be restored by cleaning or resurfacing with an acceptable insulation repair coating specifically designed for breathing air systems with a class A fire rating, they shall be identified for replacement.
2. When requested or specified, Contractor must be capable of remediating exposed damaged insulation in air handlers and/or ductwork requiring replacement.
3. Replacement material: In the event fiber glass materials must be replaced, all materials shall conform to applicable industry codes and standards, including those of UL and SMACNA.
(D) Cleaning of coils
1. Any cleaning method may be used which will render the Coil Visibly Clean and capable of passing Coil Cleaning Verification (see applicable NADCA Standards). Coil drain pans shall be subject to Non-Porous Surfaces Cleaning Verification. The drain for the condensate drain pan shall be operational. Cleaning methods shall not cause any appreciable damage to, displacement of, inhibit heat transfer, or erosion of the coil surface or fins, and shall conform to coil manufacturer recommendations when available. Coils shall be thoroughly rinsed with clean water to remove any latent residues.
(E) Biocidal Agents and Coatings
1. Biocidal agents shall only be applied if active fungal growth is reasonably suspected, or where unacceptable levels of fungal contamination have been verified through laboratory testing.
2. Application of any biocidal agents used to control the growth of fungal or bacteriological contaminants shall be performed after the removal of surface deposits and debris.
3. Only biocidal agents registered by the U.S. Environmental Protection Agency (EPA) specifically for use within HVAC system shall be used.
4. Biocidal agents shall be applied in strict accordance with manufacturer’s instructions.
5. Biocidal coating products for both porous and non-porous surfaces shall be EPA registered, water soluble solutions with supporting efficacy data and MSDS records.
6. Biocidal coatings shall be applied according to manufacturer’s instructions. Coatings shall be sprayed directly onto interior ductwork surfaces, rather than “fogged” downstream onto surfaces. A continuous film must be achieved on the surface to be treated by the coating application. Application of any biocidal coatings shall be in strict accordance with manufacturer’s minimum millage surface application rate standards for effectiveness.
2.06 Cleanliness Verification
(A) General: Verification of HVAC System cleanliness will be determined after mechanical cleaning and before the application of any treatment or introduction of any treatment-related substance to the HVAC system, including biocidal agents and coatings.
(B) Visual Inspection: the HVAC system shall be inspected visually to ensure that no visible contaminants are present.
1. If no contaminants are evident through visual inspection, the HVAC system shall be considered clean; however, the government reserves the right to further verify system cleanliness through gravimetric or wipe testing analysis testing as specified herein.
2. If visible contaminants are evident through visual inspection, those portions of the system where contaminants are visible shall be re-cleaned and subjected to re-inspection for cleanliness.
(C) Gravimetric Analysis: At the discretion and expense of the government, sections of the HVAC system may be tested for cleanliness using the NADCA Vacuum Test (gravimetric analysis) as specified in applicable NADCA Standards. Levels of debris collected shall be equal to or less than acceptable levels defined in applicable NADCA Standards.
1. If gravimetric analysis determines that levels of debris are equal to or lower than those levels specified in applicable NADCA standards, the system shall be considered clean and shall have passed cleanliness verification.
2. If gravimetric analysis determines that levels of debris exceed those specified in applicable NADCA standards, the system shall not be considered clean and those sections of the system which failed cleanliness verification shall be re-cleaned at the expense of the HVAC system cleaning contractor.
3. Gravimetric analysis shall be performed by a qualified third party experienced in testing of this nature.
4. Cleanliness verification shall be performed immediately after mechanical cleaning and before the HVAC system is restored to normal operation.
(D) Verification of Coil Cleaning
1. Cleaning must restore the coil pressure drop to within 10 percent of the pressure drop measured when the coil was first installed. If the original pressure drop is not known, the coil will be considered clean only if the coil is free of foreign matter and chemical residue, based on a thorough visual inspection (see NADCA Standards).
2.07 Pre-Existing System Damage
(A) Contractor is not responsible for problems resulting from prior inappropriate or careless cleaning techniques of others.
2.08 Post-Project Report
(A) At the conclusion of the project, the Contractor shall provide a report to the owner indicating the following:
1. Success of the cleaning project, as verified through visual inspection and/or gravimetric analysis.
2. Areas of the system found to be damaged and/or in need of repair.
2.09 Applicable Standards and Publications -- The following current standards and publications of the issues currently in effect form a part of this specification to the extent indicated by any reference thereto:
(A) National Air Duct Cleaners Association (NADCA): NADCA 1992-01, “Mechanical Cleaning of Non-Porous Air Conveyance System Components,” 1992
(B) National Air Duct Cleaners Association (NADCA): “Understanding Microbial Contamination in HVAC Systems,” 1996.
(C) National Air Duct Cleaners Association (NADCA): “Introduction to HVAC System Cleaning Services,” 1995.
(D) National Air Duct Cleaners Association (NADCA) NADCA Standard 05 “Requirements for the Installation of Service Openings in HVAC Systems,” 1997.
(E) Underwriters’ Laboratories (UL): UL Standard 181
(F) American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE): Standard 62-89, "Ventilation for Acceptable Indoor Air Quality"
(G) Environmental Protection Agency (EPA): "Building Air Quality" December, 1991
(H) Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): “HVAC Duct Construction Standards - Metal and Flexible,” 1985
(I) North American Insulation Manufacturers Association (NAIMA): "Cleaning Fibrous Glass Insulated Air Duct Systems." 1993