Statement.of.Work-SOW.pier.pdf
PDF 1 MB Posted
- Attached to
- Water and Sewage Connection Pier
- Solicitation number
- 19308Q260000007
About this file
This is a Statement of Work (SOW) for pier shore services at the United States Coast Guard Cutter PATOKA in Greenville, Mississippi. The contractor must provide all labor and materials to repair the cutter's pier sewage and potable water piping systems. Key scope items include replacing approximately 150 feet of sewage piping and fittings, replacing approximately 150 feet of potable water piping and fittings, and replacing insulation and heater strips on the piping system at the pier. The contractor must ensure both the potable water and sewage systems are fully operational, with the Coast Guard Contracting Officer's Representative (COR) present during testing of both systems and heating strips. Additionally, the contractor must verify that new heating strips are operational and remove all trash and debris upon project completion. The work must be approved by the Contracting Officer's Representative.
The contractor shall provide qualified personnel and maintain required staffing levels at all times, with advance notification to the COR if employees will be absent. Work is generally performed between 0730 and 1600 CST, Monday through Friday, excluding federal holidays, though weekend and holiday work may be required. The primary place of performance is the contractor's facilities with frequent visits to USCGC Patoka, 1797 Harborfront Road, Greenville, Mississippi 38701. The period of performance is to be determined (TBD). The contractor must furnish all facilities, materials, equipment, and services necessary to complete the project, as the government will not provide resources. The COR will review deliverables and may reject work with documented reasons, allowing the contractor 30 business days to make corrections and redeliver.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Here are the answers to the questions.docx | DOCX document | |
| Constructions.Solicitation.docx | DOCX document | |
| SF1442-14b.solicitation.offer.and.award.docx | DOCX document | |
| SF1442-14b.solicitation.offer.and.award.docx | DOCX document | |
| Constructions.Solicitation.docx | DOCX document | |
| Constructions.Solicitation.docx | DOCX document | |
| Construction Clauses.docx | DOCX document | |
| SF1442-14b.solicitation.offer.and.award.docx | DOCX document | |
| ms1.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #:
STATEMENT OF WORK
PAGE 1/8
STATEMENT OF WORK (SOW)
FOR
Pier Shore Services For CGC Patoka, Greenville, MS
1.0 GENERAL
1.1 BACKGROUND
United States Coast Guard Cutter PATOKA is accepting proposals for qualified individuals or firms to repair the cutters pier sewage and potable water piping system. Prior to submitting a quote, it is mandatory to examine the scope of work and it’s highly encouraged to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at CGC PATOKAs shore facility.
1.2 SCOPE
Below work will be completed onboard CGC PATOKAs shore facility.
1. Contractor shall provide ALL labor and materials necessary to complete the project.
2. Contractor shall comply with submittal requirements if applicable.
3. Contractor shall protect all equipment and merchandise in work locations.
4. Contractor shall replace approximately 150 ft of sewage piping and fitting at the pier.
(see figure 3)
5. Contractor shall replace approximately 150 ft of potable water piping and fitting at the pier. (see figure 3)
6. Contractor shall replace insulation and heater strips on the piping system at the pier.
7. Contractor shall ensure the new potable water system and sewage system at the pier is fully operations. Coast Guard COR must be present during the testing of both systems.
8. Contractor shall ensure the new heating strips are operational. Coast Guard COR must be present during the testing of the heating strips.
9. Contractor shall be responsible for the removal of all trash and debris from project area upon completion.
10. All work must be approved by the Contracting Officer’s Representative
1.3 OBJECTIVE
The awarded contractor will return full functionality of CGC Patoka’s pier, to include sewage offload system, and potable water system. Sewage offload and potable water systems should be operable from all stations.
The vendor will also furnish any additional items that maybe needed to complete this project.
file://hqnas/SHARED/G-A/G-ACS/CAAT%20Team/TOOLBOX/SCOPE%20PARAGRAPHS.doc
PAGE 2/8
1.4 APPLICABLE DOCUMENTS
See the pictures in solicitation package.
2.0 SPECIFIC REQUIREMENTS/TASKS
Please see 1.3 Objective
3.0 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this
SOW.
3.1 CONTINUITY OF SUPPORT
The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor shall ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor shall provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor shall provide a fully qualified replacement.
3.2 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Homeland Security. The Project Manager shall ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.3 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer*), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.
Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.0 PERIOD OF PERFORMANCE
The period of performance TBD.
4.1 PLACE OF PERFORMANCE
The primary place of performance will be the Contractor’s facilities with frequent visits to the United States Coast Guard at USCGC Patoka
1797 Harbor front Rd Greenville, MS 38701
PAGE 3/8
662-394-9746 POC: MKC Jacob Newland
4.2 HOURS OF OPERATION
Contractor employees shall generally perform all work between the hours of 0730 and 1600 CST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
4.3 TRAVEL
Contractor travel shall not be required for this requirement.
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 5.0.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
7.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
7.2 The Contractor shall have 30 business days to make corrections and redeliver.
PAGE 4/8
Figure 1:
Main sewage connection
Figure 2:
Pier sewage connection that was cut and capped on the main connection side
PAGE 5/8
Figure 3:
Red = Sewage
Blue = Potable water Figure 4:
Station 1: potable watervalve needs replacement, sewage valve under walkway needs replacement
PAGE 6/8
Figure 5:
Station 2: Potable water valve needs replacement, no sewage connection.
Figure 6:
Station 3: Potable water valve needs replacement, needs sewage valve and camlock connection installed.
PAGE 7/8
Figure 7:
Station 4: Potable water valve needs replacement, needs sewage valve and camlock connection replaced.
Figure 8:
Station 5: Potable water valve needs replacement, no sewage connection.
PAGE 8/8
Figure 9:
Sewage end connection: needs new valve and camlock connection.
| STATEMENT OF WORK (SOW) |
| FOR |
| 1.4 APPLICABLE DOCUMENTS |
| 2.0 SPECIFIC REQUIREMENTS/TASKS |
| 5.0 GOVERNMENT FURNISHED RESOURCES |
| 6.0 CONTRACTOR FURNISHED PROPERTY |
File details come from the government source that posted it. Updated .