Questions_ _Answeres_No3.pdf

PDF 93 KB Posted

Attached to
Furnish and Install new Telecom Structure
Solicitation number
SSU40014R0012
Issued by

View the file

Other files

File Type Posted
Presiential_villas-_Telecomm__tower_drawings_.pdf PDF
Questions_ _Answers.pdf PDF
Q A.pdf PDF
RFP_for_communication_Tower.doc DOC document
SF1442-14a 1 .pdf PDF
drawings.pdf PDF
PV-_supply_and_installation_of_telecom_Structure_SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1- According to previous experience in such type of work, the license approved for telecommunications towers not more than 30 meters by the (national telecommunication company) NTC and the Civil Aviation reminding you that the location of the compound at the flying line of the airport .so, confirm about the license approval for 60 meters as required is a possibility .

We have technical requirements for 60 meters. Getting permission or licenses from the Sudanese NTC will be considered the responsibility of the contractor if awarded this project.

2- Mentioned that the construction completion time is 180 days, commencing after receiving notice to proceed from contracting officer and another completion date 90 days was mentioned as well, so please confirm wish one is the completions date?

3 months should be more than enough and we need this, ASAP. 90 days.