About this file
This document is an Experience Questionnaire template designed to collect past performance information from offerors responding to a federal construction solicitation. The form is organized to capture details about three distinct construction projects (CON #1, CON #2, CON #3) and requires offerors to provide comprehensive project history including the performing entity's name, address, SAM UEI, and point of contact information. The questionnaire accommodates situations where the original entity has been acquired, requiring documentation of the acquiring firm's current possession of relevant assets and personnel to demonstrate predictive value for future performance.
The form requests specific construction project details including the contract and delivery/task order numbers, award and completion dates, contract type (Firm-Fixed Price, Cost/Time and Material, or other arrangements), and total award and final construction prices. For construction projects specifically related to pressurized aircraft hydrant fueling systems, offerors must provide detailed information on piping system length, hydrant outlet pit quantities, emergency fuel shutoff or power down stations, cathodic protection systems for underground fuel piping, and testing, pigging, and commissioning activities. The questionnaire distinguishes between contract delivery methods (Design-Build, Design-Bid-Build, IDIQ, or other) and requires offerors to document their role as prime contractor, subcontractor, joint venture member, or other arrangement, including the percentage of work performed. Block 9 requires a detailed narrative description of each project's relevance to the RFP requirements, including unique features, construction methods, and any problems encountered and resolutions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SSAttch1-Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2
EXPERIENCE QUESTIONNAIRE
Project No. (check one): CON #1 CON #2 CON #3
1. Name of Entity that Performed Project: _________________________________________________________ Address: ____________________________________________________________________________________ Phone Number: __________________________________ SAM UEI: ________________________________ Point of Contact: _________________________________ Contact Phone Number: _____________________
a. If the Entity (named above) that performed the project has been acquired and is no longer a separate legal entity, provide the name of the Acquiring Firm and an explanation of the acquisition sufficient to demonstrate 1) that the Entity is now part of the Acquiring Firm, and 2) that the Acquiring Firm currently possesses assets and personnel from the Entity sufficient for the Entity’s experience and past performance to be reasonably predictive of the Acquiring Firm’s performance on this contract.
Name of Acquiring Firm: ____________________________________ UEI of Acquiring Firm: ______________
Acquisition Terms:
b. Name of Entity that Performed Work that Experience is Claimed for (i.e.; if the project was performed by a Joint Venture (JV) and Offeror is claiming experience of one of the J/V members that performed work on the project, state the exact legal name of the JV member the Offeror claims experience for):
Address: ____________________________________________________________________________________ Phone Number: ___________________________________ SAM UEI: ________________________________ Point of Contact: __________________________________ Contact Phone Number: _____________________
2. Work Performed as*: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was prime (Name/Phone #):
3. Contract Number: Delivery/Task Order Number:
Title:
Location:
4. Award Date (mm/dd/yy): Completion Date (mm/dd/yy):
If not complete, % physically complete as of the date of issuance of this RFP:
5. Type of work: New Construction Renovation Repair Alteration Other (explain):
6. Type of Contract/Task Order: (Check ALL that apply)
Firm-Fixed Price Cost/Time and Material Other (explain):
7. Construction Project:
Total Construction Award Amount: $__________________ Final Construction Price: $_________________
Type of Contract/Task Order: (Check ALL that apply)
Design-Build Design-Bid-Build Delivery/Task Order (IDIQ) Other (explain):
8. Construction Project Details: Offerors shall complete the following information for each relevant individual feature: (For each item checked, provide a detailed description of the work in Block 9).
• New construction of pressurized aircraft hydrant fueling system: Yes No
• Length of piping system constructed:
_________ linear feet with #_____ hydrant outlet pits.
• Emergency fuel shutoff stations or emergency power down stations at hydrant: Yes No
• Cathodic protection system for underground fuel piping: Yes No
• Testing, pigging, and commissioning of hydrant fueling systems: Yes No
9. Provide a detailed description of the project and the relevancy to the project requirements of this RFP. (e.g.:
unique features, quantity of piping and hydrant outlet pits, size of piping, square footage, construction methods, any problems encountered and how it was resolved).