File Type Posted
Additional Industry Qs CRM_2023_13JAN.pdf PDF
Additional Industry Qs CRM_2023_06JAN.pdf PDF
Additional Industry Qs CRM_2022-12-21.pdf PDF
FA8818-23-R-0002 Amendment 0001.pdf PDF
FA8818-23-R-0002 RFP FINAL.pdf PDF
SRP-4 Industry Day Questions and Responses.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORDER FOR SUPPLIES OR SERVICES

1. CONTRACT/PURCH ORDER/AGREEMENT NO.

FA881823D000X

2. DELIVERY ORDER/ CALL NO.

FA8818-23-F-000X

3. DATE OF ORDER/CALL

(YYYYMMMDD)

4. REQUISITION/PURCH REQUEST NO.

SEE SCHEDULE

5. PRIORITY

6. ISSUED BY SSC/AAK-KT CODE FA8818 7. ADMINISTERED BY (If Other than 6) CODE 8. DELIVERY FOB

SMC/PKT

3548 ABERDEEN AVE SE

KIRTLAND AFB, NM 87117

MARIACHESKA LEGENDRE (505)846-4597

MARIACHESKA.LEGENDRE@SPACEFORCE.MIL

DESTINATION

X OTHER

(See Schedule if other)

SCD: PAS: (NONE)

9. CONTRACTOR CODE FACILITY 10. DELIVER TO FOB POINT BY (Date) 11. X IFBUSINESS IS

(YYYYMMMDD) SEE SCHEDULE

SMALL

NAME

AND

12. DISCOUNT ITEMS

SMALL DISAD-

VANTAGED

ADDRESS N

WOMEN-

OWNED

13. MAIL INVOICES TO ADDRESS IN BLOCK

SEE BLOCK 15 (PAYMENT OFFICE)

14. SHIP TO CODE 15. PAYMENT WILL BE MADE BY CODE

SEE SCHEDULE MARK ALL

PACKAGES AND

PAPERS WITH

IDENTIFICATION

NUMBERS IN

BLOCKS 1 AND 2.

EFT:T

16. DELIVERY/

X This delivery order/call is issued on another Government agency or in accordance with and subject to terms and conditions of above numbered contract.

TYPE CALL

OF PURCHASE

Reference your furnish the following on items specified herein.

ORDER ACCEPTANCE. THE CONTRACTOR HEREBY ACCEPTS THE OFFER REPRESENTED BY THE NUMBERED PURCHASE ORDER AS IT MAY PREVIOUSLY HAVE

BEEN OR IS NOW MODIFIED, SUBJECT TO ALL OF THE TERMS AND CONDITIONS SET FORTH, AND AGREES TO PERFORM THE SAME.

NAME OF CONTRACTOR SIGNATURE

TYPED NAME AND TITLE DATE SIGNED(YYYYMMMDD)

If this box is marked, supplier must sign Acceptance and return the following number of copies:

17. ACCOUNTING AND APPROPRIATION DATA/LOCAL USE

18. ITEM NO. 19. SCHEDULE OF SUPPLIES/SERVICES 20. QUANTITY

ORDERED/

ACCEPTED*

21.

UNIT

22. UNIT PRICE 23. AMOUNT

*If quantity accepted by the Government is same as quantity ordered, indicate by X. If different, enter actual quantity accepted below quantity ordered and encircle.

24. UNITED STATES OF AMERICA

25. TOTAL

29.

DIFFERENCES

ALICIA L. CAWLEY

BY:

CONTRACTING/ORDERING OFFICER

26. QUANTITY IN COLUMN 20 HAS BEEN 27. SHIP NO. 28. D.O. VOUCHER NO. 30. INITIALS

INSPECTED RECEIVED ACCEPTED, AND CONFORMS TO THE

CONTRACT EXCEPT AS NOTED

PARTIAL 32. PAID BY 33. AMOUNT VERIFIED CORRECT FOR

_______ _________________________________________________ FINAL

DATE SIGNATURE AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32. PAYMENT 34. CHECK NUMBER

36. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT. COMPLETE

_______ _________________________________________________ PARTIAL 35. BILL OF LADING

DATE SIGNATURE AND TITLE OF CERTIFYING OFFICER FINAL

37. RECEIVED

AT

38. RECEIVED BY (Print) 39. DATE RECEIVED

(YYYYMMMDD)

40. TOTAL CON-

TAINERS

41. S/R ACCOUNT NO. 42. S/R VOUCHER NO.

DD FORM 1155, JAN 1998 (EG) ConWrite Version 7.6.1.0 PREVIOUS EDITION MAY BE USED Created 17 Nov 2022 7:18 AM

LIST OF ATTACHMENTS

FA8818-23-F-000X

A. PART I - SCHEDULE, This Task Order is hereby established for the Initial Minimum Award Special Study of the basic SRP-4, FA8818-23-D-XXXX. As a result, the task order established the following CLINs:

CLIN 0013; Initial Minimum Award Special Study CLIN 0014; Data and Reports

1. Work to be performed will be in accordance with the Performance Work Statement of the

Basic Contract and Statement of Work (SOW) for Initial Task Order Award Special Study, Attachment 1, dated 01 December 2017

2. The Task Order is established as follows:

B. PART I - THE SCHEDULE, SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS, is updated as follows:

As a result of this action, CLIN 0013 is established in the amount of $ TBD and obligated in the amount of

$ TBD.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

Minimum Award Special Study

0013 EST $_____________

Noun: INITIAL MINIMUM AWARD SPECIAL STUDY

PSC: AC25

Contract type: J - FIRM FIXED PRICE Completion Date: ASREQ Descriptive Data:

The Contractor shall furnish all supplies and services to accomplish work in accordance with the Basic Contract Attachment 1, Performance Work Statement (PWS) paragraph 1.8.7, and the attached Statement of Work dated 01 DEC 2017.

DATA AND REPORTS

NSP

Noun: DATA AND REPORTS

ACRN: U

PSC: AC25

DD1423 is Exhibit: G Contract type: J - FIRM FIXED PRICE Completion Date: ASREQ Descriptive Data:

The price of this CLIN is included in the price of CLIN 0013 in accordance with Contract Data Requirements List (CDRL), DD Form 1423-1, Exhibit G, attached to the Basic Contract. Data requirements are not separately priced (NSP).

C. PART I - THE SCHEDULE, SECTION C - CONTRACT SPECIFICATION, WORK STATEMENT

LIST OF ATTACHMENTS

Work shall be accomplished in accordance with the Performance Work Statement attached to the Basic Contract

D. PART I - THE SCHEDULE, SECTION D - PACKAGING AND MARKING

Packaging and marking shall be accomplished in accordance with Section D of the Basic Contract.

E. PART I - THE SCHEDULE, SECTION E - INSPECTION AND ACCEPTANCE

Inspection and Acceptance shall be accomplished in accordance with Section E of the Basic Contract.

F. PART I - THE SCHEDULE, SECTION F - DELIVERIES OR PERFORMANCE

Deliveries or Performance shall be accomplished in accordance with the CLIN Descriptive Data of this task order.

G. PART I - THE SCHEDULE, SECTION G - CONTRACT ADMINISTRATION DATA, is established as follows:

TO BE INSERTED PRIOR TO AWARD

H. PART I - THE SCHEDULE, SECTION H - SPECIAL CONTRACT CLAUSES

Section H shall be accomplished in accordance with the Basic Contract.

I. PART II - CONTRACT CLAUSES, SECTION I - CONTRACT CLAUSES

Section I shall be accomplished in accordance with the Basic Contract.

J. PART III - SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

J. PART III - SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS is established as follows:

a) Attachment 1, Statement of Work (SOW) for Sounding Rocket Program -4 Initial Minimum Award Special Study, dated 01 December 2017, attached hereto and hereby made a part of this task order.

SCHEDULE

DOCUMENT PGS DATE TITLE

ATTACHMENT 1 2 01 DEC 2017 STATEMENT OF WORK (SOW) FOR SOUNDING

ROCKET PROGRAM -4 INITIAL MINIMUM AWARD

SPECIAL STUDY

SRP-4 Initial Minimum Award Statement of Work

PAGE - 1 of 2

SRP-4, FA8818-23-R-0002

(Formerly FA8818-16-R-0022)

Task Order 0001

(FA8818-F-23-XXXX)

STATEMENT OF WORK (SOW)

For Sounding Rocket Program-4

Initial Minimum Award

Special Study

01 December 2017

SRP-4 Initial Minimum Award Statement of Work

PAGE - 2 of 2

1.0 OBJECTIVE

The objective of the Special Studies effort is for the Launch Service Contractor (LSC) to document and demonstrate the LSC ability to efficiently integrate systems engineering disciplines including configuration management, quality assurance, integrated test, and risk management.

2.0 PURPOSE

The purpose of the effort is to provide the Government a basis for review, evaluation and monitoring of the LSC systems engineering disciplines. The Government will place these plans on contract so the LSC is accountable for these critical systems engineering functions.

3.0 WORK DESCRIPTION

The LSC shall provide the following:

3.1 Configuration Management Plan (CMP). The CMP shall describe the LSC’s Configuration Management Program, including how organization and execution is accomplished. The CMP shall address the methods, procedures and controls, configuration identification, change control, status accounting, and audits of the total configuration for hardware, software and firmware (CDRL G029).

3.2 Quality Assurance Plan (QAP). The QAP shall describe the LSC’s Quality Assurance Program with all of the information, instructions and documentation necessary to produce a quality part, component, equipment, subsystem, or system in complete conformity with contractual requirements. The QAP will contain measurable quality objectives and the metrics by which they are to be measured (CDRL G030).

3.3 Risk Management Plan (RMP). The RMP shall describe the LSC’s Risk Management Process including risk mitigation strategies, definition of risk thresholds, and monitoring progress to ensure the effects of potential risks are minimized. The RMP shall describe LSC risk management planning, risk identification, risk assessment, risk handling, risk monitoring, risk control, and process metrics (CDRL G031).

3.4 Integrated Test Plan (ITP). The ITP shall describe the LSC’s Test Program plans and performance objectives at every level of hardware and software testing on systems or equipment, to include qualification and acceptance level testing. The ITP shall provide the test concept, objectives, requirements, methods, elements, responsible activities, measures, and recording procedures throughout all phases of LSC testing (CDRL G034).

4.0 DELIVERABLES

The LSC shall accomplish CDRL submittals per the referenced CDRLs for each of the special study plans, as required.

SRP-4 Model Task Order FINAL
ORDER FOR SUPPLIES OR SERVICES

STATEMENT OF WORK (SOW) FOR SRP-4 SPECIAL STUDY