This Scope of Work document details a road modification project for the Tennessee Department of Transportation involving the widening and improvement of State Route 29 at Lane Mile 10.87 in Hamilton County, Tennessee. The project involves widening the exit ramp from State Route 29 NB to State Route 153 from one 16-foot lane with a 10-foot left shoulder to two 12-foot lanes with a 10-foot left shoulder. Key work components include submission and implementation of traffic control plans to TDOT standards with barrier rail installation, excavation and pavement removal with assumed layers of 8 inches concrete, 4 inches TPB, and 4 inches base stone, excavation to solid engineered fill, base stone compaction at proper moisture content, and widening of 8 feet of concrete Type A mix with anti-skid aggregate on the left side. The contractor must maintain one lane of traffic on the exit ramp at all times during construction. Bids are due June 18, 2026, at 10:00 a.m. CDT, and written questions are due June 10, 2026. On-site inspection is mandatory prior to bid submission as no allowances will be made for errors resulting from failure to examine the premises.

The median improvements on SR153 include replacement of pavement markings, installation of 85 feet of Tuff Curb with 10 feet of spacing at the median nose, and thermoplastic striping. Exit ramp improvements include full-depth left shoulder replacement, directional arrows, sign replacement including upsize yield signs to 60 inches by 60 inches by 60 inches with reflective red strips, replacement of stop signs and one-way arrow signs, installation of new wrong way and movement restriction symbol signs, and advance intersection lane control signs. All work must comply with TDOT's Standard Specifications for Road and Bridge Construction (January 1, 2021). The contractor must provide all labor, equipment, traffic control devices, materials, and services necessary to complete the work. Bids are submitted as lump sum pricing through the State's Supplier Portal (Edison system), and pricing must remain firm for 90 days. Award will be made to the single responsive and responsible respondent offering the lowest cost. The contractor must be registered with the Tennessee Department of Revenue and must comply with prevailing wage laws. Required insurance includes a payment bond equal to 25 percent of Maximum Liability, workers' compensation insurance of not less than $1 million, commercial general liability insurance with combined single-limit coverage of $1 million per occurrence and $2 million aggregate, and automobile liability insurance of $1 million per occurrence. The contract is subject to appropriation and availability of State or federal funds.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hamilton County Interchange Improvements SR29 (US 27) L.M. 10.87 and SR153 Hamilton County, TN

Specifications

The Tennessee Department of Transportation (TDOT) would like to widen the exit ramp from

State Route 29 NB to State Route 153 from one 16’ lane and a 10’ left shoulder to two 12’ lanes and a 10’ left shoulder in Hamilton County on SR 29, at Lane Mile 10.87. One contractor will be selected to perform the full scope of services described in this document. Please note the attached drawings.

1. Scope of Work

Contractor will submit traffic control plans to be approved by TDOT. Contractor will provide all traffic control to TDOT standards. Barrier Rails will need to be utilized. The contractor shall provide all labor, equipment, traffic control, and material and perform all services necessary to complete the following tasks, using the attached drawings and images for guidance.

A. Traffic Control

• Provide all necessary traffic control devices, signage, and personnel required to safely perform work on an active state route.

• One lane of traffic will need to be open at all times on the exit ramp.

B. Excavation

• One lane of traffic will need to be open at all times on the exit ramp.

• Sawcut a clean joint of full depth of pavement along the entire length of the exit ramp, to include the rectangular section where the turn lane meets SR153.

• Remove and dispose of pavement that is beyond the sawcut

• Remove and dispose of all rock and organic matter such that the constructed exit ramp is built on solid engineered fill (pug road base)

• Contractor will assume the following layers for the travel lane:

- 8" Concrete

- 4” TPB

- 4” Base Stone

• Ensure that the base stone is properly compacted with a vibratory roller (at proper moisture content).

• The total width of the graded area shall be 18 feet (as shown in the attached drawings)

• Ensure the road base matches the cross-slope that the asphalt above it will have (please note the attached images)

• Demobilize and remove all trash and debris from the work site

• Seed and straw any disturbed areas

• Add Snow plowable Raised Pavement Markers according to standard drawing T-M-1

By submitting bids for this work, the bidder represents that it has:

• Carefully examined the site of the work described herein

• Has become familiar with local conditions and the character and extent of the work.

• Has carefully examined the Plan images and the Standard Specifications for Road and

Bridge Construction (January 1, 2021) adopted by the State of Tennessee, Department of Transportation and recognizes and attests that all work will be conducted in accordance with these plans and standards.

C. Median Improvements (S.R. 153)

• Replace pavement markings for the left turn lane, acceleration lane, white island, and yellow median channelization.

• Add 85' of Tuff Curb to the median with 10' of space between the end of the curb and the median nose.

• All striping shall be thermoplastic.

D. Exit Ramp Improvements (S.R. 29) NB

• Widen the exit ramp from SR29 NB to SR 153 from one 16' lane to two 12' lanes.

• Widen 8' of concrete type A mix with anti-skid aggregate on the left side to widen to the left.

• Use Standard Drawing RD18-TS-8 for the typical section (attached).

• Do a full depth replacement on the left shoulder pavement as it will become travel lane pavement.

• Add Type B Wrong Way arrows and left and right turn arrows.

• Adjust the left turn lane to turn less sharply than the existing condition. It should be at a 60-degree angle to SR153.

• Channelize the left shoulder and replace island channelization as shown.

• Remove existing signs on the ramp except for guide signs.

• Replace and upsize yield sign to 60"x60"x60" with reflective red strips on the posts.

• Replace the two 36"x36" stop signs and four 54"x18" one-way arrows

• Replace three 36"x36" "DO NOT ENTER" signs. Two will now be on separate posts.

• Place two new 36"x36" movement restriction symbol signs.

• Place four new 42"x30" "WRONG WAY" signs.

• Place four new 36" tall Advance Intersection Lane Control signs.

• Replace the striping as shown on these drawings.

• All striping shall be thermoplastic.

https://www.tn.gov/tdot/tdot-construction-division/transportation-construction-division-resources/2021-standard-specifications.html https://www.tn.gov/tdot/tdot-construction-division/transportation-construction-division-resources/2021-standard-specifications.html

1. Scope of Work
C. Median Improvements (S.R. 153)
D. Exit Ramp Improvements (S.R. 29) NB

File details come from the government source that posted it. Updated .