This document is an Other Transaction Agreement (OTA) Request for Prototype Proposals (RPP) issued by Army Contracting Command – Detroit Arsenal for a Mobile Tactical Cannon (MTC) system. The government seeks fixed-price proposals for researching, developing, and experimenting with mature wheeled mobile tactical cannon systems, including an associated resupply vehicle. Key objectives include prototyping MTC systems to assess their suitability for replacing current artillery systems, allowing soldiers to conduct training and operations, test equipment capabilities, document feedback, and evaluate potential tactical and logistical improvements.

The solicitation requires offerors to submit multiple volumes including an Eligibility Volume, Technical Volume, Substantiating Documentation, Schedule, Cost Volume, Prototype Project Agreement, and Representations and Certifications. Critical technical requirements include a wheeled chassis, 49-56 caliber weapon capable of firing 155mm artillery ammunition, armored crew protection, and JP-8/F-24 fuel compatibility. The evaluation will focus on technical performance, maturity, cybersecurity, ammunition compatibility, production onshoring, and integration with U.S. military systems. Proposals will be rated on a Good/Acceptable/Moderate/Unacceptable scale, with the government anticipating awarding one prototype agreement but reserving the right to award multiple or no agreements.

View the file

Other files

File Type Posted
(DRAFT) MTC PPA SOW_22DEC25 (002).pdf PDF
(DRAFT) MTC PPA SOW_22DEC25.docx DOCX document
(DRAFT) Request for Prototype Proposal_181115DEC25.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Other Transaction Agreement (OTA)

Request for Prototype Proposals (RPP) For

Mobile Tactical Cannon (MTC)

Issued by:

Army Contracting Command – Detroit Arsenal (ACC-DTA)

RPP Issue Date: XX XXX XXXX

Due Date for Proposal Submission in PIEE:

XX XXX XXXX, 1600 ET

Controlled by: ACC-DTA Distribution Statement A POC: Mrs. Sarah Teschler, (571) 588-9264

DISTRIBUTION STATEMENT A. Approved for public release:

distribution unlimited.

PROTOTYPE PROJECT AGREEMENT, ATTACHMENTS and APPENDICES: The Offeror shall review the Prototype Project Agreement, all Attachments and Appendices in their entirety prior to its proposal preparation and submission.

Prototype Project Agreement – Mobile Tactical Cannon (MTC)

Attachment 001: Contract Data Requirements Lists (CDRLs) - Mobile Tactical Cannon (MTC)

Attachment 002: …

Appendix A – Project Articles

Appendix B – Project Other Terms and Conditions

Appendix C – Representations and Certifications

Appendix D – Solicitation Provisions

Appendix E – Milestone Pricing Template

PART I - INTRODUCTION

Army Contracting Command – Detroit Arsenal (ACC-DTA) issues this Request for Prototype Proposal (RPP) for the Army’s Mobile Tactical Cannon (MTC) requirement, in accordance with the authority at 10 United States Code (U.S.C) §4022.

1.1 Terms and Conditions

1.1.1 All attachments, as well as Appendix A – Project Articles, Appendix B – Project Other Terms and Conditions, and Appendix C – Representations and Certifications, will become part of the Prototype Project Agreement (PPA) award.

1.1.2 The Government reserves the right to select for funding any, all, part, or none of the proposals received.

1.1.3 The Government will not fund projects that do not meet one of the conditions of 10 U.S.C.

§4022(d)(1).

1.2 Project Cancellation

The Government may, at any time, within its own discretion, cancel the RPP. The Government will issue a notice of RPP cancellation.

PART II – PROJECT OVERVIEW

2.1 Project Objective

2.1.1 The purpose of this RPP is to solicit Fixed Price (FP) proposals for the research, development, and experimentation of mature and available wheeled Mobile Tactical Cannon (MTC) systems, which includes its associated resupply vehicle (RSV).

2.1.2 The overall objective of this project aims to prototype MTC systems and determine their overall suitability, through experimentation and other assessments, to replace artillery systems within the United States Army.

2.1.2.1 Allow US Soldiers opportunities to conduct training and operations utilizing mature and available artillery systems for the purpose of socializing equipment capabilities, documenting Soldier feedback, and determining potential revisions of US Army Tactics, Techniques, and Procedures (TTPs).

2.1.2.2 Provide US Soldiers opportunities to conduct operator maintenance and sustainment operations using provided equipment for the purpose of determining future logistics and maintenance requirements for the system.

2.1.2.3 Conduct integration training using as many available enablers and unit capabilities as possible to document all incremental upgrades each platform would require integrating with US Army Doctrine, Organization, Training, Material, Leadership and Education, Personnel, Facilities, and Policy

(DOTMLPF-P).

2.1.2.4 Obtain vendor input on required modification(s) to vendor systems to integrate MTC systems into existing and/or future US Army fires network.

2.1.2.5 Obtain vendor input on available resupply capabilities native to, or compatible with, the proposed MTC. This is a non-evaluated objective.

2.1.3 The Government anticipates awarding one (1) Prototype Project Agreement (PPA) as a result of proposal evaluation. However, the Government may award more than one (1) PPA or make no awards within its sole discretion.

2.2 Follow-on Production

The Government anticipates follow-on production. Section XX of the PPA contains follow-on production details.

3 PART III – PROPOSAL CONTENT, PREPARATION, AND SUBMISSION hidden

3.1 Administrative Information

3.1.1 The Offeror may submit any clarification questions and/or concerns directly to (XXX) with the subject “RPP XX-XXX Questions/Comments”. All questions/comments must be submitted by 1600 ET, on XX XXX XX. The Government will review and consider all timely submitted questions/comments but is not obligated to respond.

3.1.2 The Offeror’s proposal must be submitted through the Procurement Integrated Enterprise Environment (PIEE) at https://piee.eb.mil/ by the due date and time specified in the below Submission Requirements Table.

3.1.3 Only one (1) proposal shall be submitted per Offeror. Proposal submissions must include the required files identified within and below the Submission Requirements Table. Emailed submissions will not be accepted, unless identified in the Submission Requirements Table.

3.1.4 LATE PROPOSALS WILL NOT BE ACCEPTED.

3.1.5 Proposal Content, Preparation, and Submission Requirements

RPP XX-XXX SUBMISSION REQUIREMENTS TABLE

Proposal Document File Type Size/Limit Due Date

Eligibility Volume

Reference Section 3.2 below for all required submissions

One (1) file in MS Word or

PDF

10 pages

Limited to 6 MB

XX XXX

XX

NLT1600 ET

Technical Volume

Reference Section 3.3

30 pages

Limited to 6 MB

XX XXX

https://piee.eb.mil/

Technical Volume – Substantiating Documentation

Reference Section 3.4 or

Multiple files in ZIP format

Limited to 6 MB

No page limit

XX XXX

Schedule

Reference Section 3.5

One (1) file in MS Excel, MS Word, or PDF

Limited to 6 MB

5 pages

XX XXX

Cost Volume

Reference Section 3.6

One (1) file in ZIP format:

Completed Appendix E – Milestone Pricing Template and Cost Narrative with supporting documentation

Limited to 6 MB

No page limit

XX XXX

Prototype Project Agreement

Reference Section 3.7

One (1) file in MS Word or Multiple MS Word files in ZIP format:

Completed Prototype Project Agreement via tracked changes.

Limited to 6 MB

No page limit

XX XXX

Appendix C Representations and Certifications Form

Reference Section 3.8 submissions

One (1) file in MS Word or Multiple MS Word files in ZIP format:

Completed Appendix C:

Representations and Certifications

Limited to 6 MB

No page limit

XX XXX

3.2 Eligibility Volume: GO / NO GO

The Eligibility Volume shall address the following criteria. It shall contain all substantiating data and shall not exceed 10 pages.

3.2.1 The Offeror shall affirm that the proposed system for this effort is based on a wheeled chassis. The Offeror shall briefly describe the system sufficient for the Government to confirm this eligibility requirement is met.

3.2.2 The Offeror shall identify and substantiate that the proposed system has a caliber between 49 and 56 calibers. Caliber is defined as the ratio of the projectile travel length divided by the projectile diameter.

The Offeror shall identify and substantiate that their MTC weapon system can fire 155mm class artillery ammunition.

3.2.3 The Offeror shall identify and substantiate that the proposed system can achieve a maximum range as described in performance characteristics attachment XX.

3.2.4 The Offeror shall identify and substantiate that the proposed system shall provide, at a minimum, armored protection from counter-battery artillery and kinetic energy threats for the crew members while conducting mobility operations. NOTE: Substantiating data that contains Classified information or armor makeup is not required; only an architectural overview of how the crew is protected is requested.

3.2.5 The Offeror shall identify and substantiate that the proposed system is compatible with JP-8 or F-24 fuels.

3.3 Technical Volume

The Technical Volume shall not exceed 30 pages. The Offeror shall submit the Technical Volume and Technical Volume Substantiating Documentation as separate document submissions. The Technical Volume submission should demonstrate the Offeror’s understanding of the project requirements and shall provide sufficient technical detail and analysis to support how the proposed approach will be conducted to meet the prototype project requirements. The Offeror shall submit a clear, concise proposal showing how project objectives will be met. At the minimum, the Technical Volume shall contain the following:

3.3.1 Factor 1: Technical Performance and Maturity

3.3.1.1 Sub-Factor 1.1: Maturity

Offerors shall provide a comprehensive system overview and supporting documentation to demonstrate the maturity of their proposed self-propelled howitzer system. This documentation should include, but is not limited to, evidence of design stability, completed developmental and operational testing results (including reliability), and details of any previous operational use. To substantiate claims, Offerors may submit Systems Engineering artifacts, test reports, public press statements, or assessments from foreign military partners. Additionally, a Safety Assessment Report (SAR) or industry equivalent for the proposed system must be included in the submission.

3.3.1.2 Sub-Factor 1.2: Technical Performance

The Offeror shall provide a comprehensive technical volume that directly addresses the Key Characteristics Definition outlined in Attachment XXX. This volume must contain technical evidence and quantitative substantiating data to validate all performance claims against the key characteristics, which include threshold performance, desired performance levels, and future improvement capabilities. The submission should be clear and concise, providing sufficient analysis to demonstrate a thorough understanding of the key characteristics and how the proposed system will meet thresholds.

3.3.1.3 Sub-Factor 1.3 Cyber Risk

The Offeror shall provide a comprehensive submission detailing its approach to system cybersecurity.

This submission shall include a narrative description of all system functions. It should include detailed hardware and software architecture diagrams, and a complete Software Bill of Materials (SBOM). The purpose of this volume is to demonstrate the Offeror’s understanding of the proposed system’s cybersecurity posture and to provide sufficient technical detail for the Government to assess how the proposed approach will meet the Army’s cybersecurity strategy.

3.3.1.4 Sub-Factor 1.4: United States Artillery Ammunition Compatibility Offerors shall submit a technical volume detailing the compatibility of their proposed self-propelled howitzer system with current United States-inventory ammunition. The volume shall include technical assessments and any existing test data related to ammunition interoperability, with emphasis on the tiered ammunition list below. A detailed description of the system’s fuze setter capability is also required, addressing its functionality with the specified munitions.

Tier 1: M795, M232A2 (1-5 increments), M782 (MOFA Fuze) Tier 2: M232A2 (6 increments), M1128, M739A1, M982 (Excalibur), M1156 (PGK Fuze), M1155 Enhanced Portable Inductive Artillery Fuze Setter (EPIAFS) Tier 3: High performance propelling charges (Supercharge), developmental projectiles (NGRAP, ERAP, etc.), future precision guided fuzes

3.3.2 Factor 2: United States Integration

3.3.2.1 Sub-Factor 2.1: Commerciality/Supportability

The Offeror shall submit a completed Supply Chain Market Checklist (Attachment XXXX) and a narrative describing their approach to obsolescence management for the proposed system. This submission should demonstrate the Offeror’s ability to support the system by providing a clear and concise overview of their supply chain’s health and readiness. To reduce assessed risk, the Offeror should highlight the percentage of parts with National Stock Number (NSN)/NATO Stock Number assignments, any parts commonality with existing U.S. platforms, demonstrated performance of delivering critical parts, and the responsible use of established commercial supply chains.

3.3.2.2 Sub-Factor 2.2: Production Onshoring and Organic Industrial Base Utilization The Offeror shall provide a detailed plan for transitioning to the domestic production of the proposed self-propelled howitzer system. The plan must detail a timeline to establish U.S.-based production no later than two years after contract award, identifying probable production locations within the contiguous United States and considering the potential use of the Organic Industrial Base (OIB). The submission shall outline key risks and mitigations, and major milestones associated with this transition. Furthermore, the plan must demonstrate the capability to achieve a production rate of 24 systems per year for the first two years of production, with a subsequent ramp up to 48 systems per year. The Offeror should include information regarding any existing industry partnerships or agreements that would facilitate a rapid transition.

3.3.2.3 Sub-Factor 2.3: Technical Data/Software, Intellectual Property, and Digital Acquisition The Government desires Specially Negotiated Rights equivalent to Government Purpose Rights for the specified deliverables within the PPA. The Offeror shall complete and submit Attachment XXX (Data Rights Assertions List) and provide any proposed edits or red-lines to Attachment XXX (Specially

Negotiated Rights License Template). Proposals that offer Specially Negotiated Rights Licenses equivalent to Government Purpose Rights to more of these areas will be evaluated more favorably than those that offer limited and/or restricted rights.

3.4 Substantiating Technical Volume

For all performance claims, the Offeror shall provide substantiating data that is complete, specific, and relevant to the specific requirement of the project. This information may include, but is not limited to, test data, historical information, commercial literature, manufacturer’s specification sheets, materiel release information, analytical support, design documentation, resupply capability (non-evaluated), or other substantiating data supporting conformance with the proposed performance levels. The Offeror shall submit Government test data, Offeror test data, Finite Element Analysis (FEA) or other dynamic modeling, simple analysis including hand calculations and photos/videos, or existing Offeror literature (not created for the purpose of responding to this RPP) containing information about the vehicle as substantiating data.

3.5 Prototype Delivery Schedule

Offerors shall provide a comprehensive delivery schedule detailing the timeline for the delivery of all prototype vehicles. This schedule should be presented in comparison to the Government’s desired delivery schedule as outlined in the Prototype Project Agreement, section XXX. The submission must include a supporting narrative that describes the Offeror’s production plan, manufacturing capacity, and supply chain strategy that enables them to meet their proposed timeline. The narrative should provide sufficient detail to demonstrate a clear and realistic path to achieving the proposed delivery dates.

3.6 Cost Volume

The Offeror shall complete and submit (Attachment XXXX) – Cost Volume. Instructions for completing (Attachment XXXX) are within the attachment.

3.7 Prototype Project Agreement (PPA)

The Offeror shall fill in the PPA cover page and the following PPA sections via tracked changes. The PPA sections referenced below are in red font within the PPA.

3.7.1 Milestone Payment Schedule

The Offeror’s PPA submission shall contain either a completed Table X OR Table X, Milestone Payment Schedule, along with a completed Table X: Cumulative Resource Sharing Table (if applicable). The Offeror shall reference Appendix X – Solicitation Provisions, Section X, Milestone Payment Schedule Instructions, for instructions on proper completion of all Milestone Payment tables contained within the

PPA .

3.7.2 Intellectual Property/Data Rights Assertions

The Offeror shall reference Appendix X– Solicitation Provisions, Section X, Data Rights and Copyrights, for instructions on proper completion of Table X within the PPA.

3.7.3 PPA Rejection

If the Offeror fails to fill in the above sections via tracked changes, the Government will reject the PPA submission. If the due date for proposal submission has not passed, the Offeror may resubmit a new PPA that contains revisions via tracked changes. Otherwise, the Offeror’s proposal may not be considered eligible for award. Additionally, if the Offeror revises any language outside of the sections mentioned above, the Government will not review those changes.

3.8 Representations and Certifications Form – Appendix C

The Offeror shall complete and submit Appendix C – Representation and Certifications Form. Instructions for completing Appendix C are contained within the Appendix.

PART IV: PROPOSAL EVALUATION

4.1 Eligibility for Award

To be eligible for an award, the Offeror shall be compliant with 10 U.S.C. § 4022(d). If the Offeror’s completed Section A, Appropriate Use of Other Transaction Authority within Appendix C – Certifications and Representations does not sufficiently describe how the Offeror will satisfy at least one of the conditions of the statute, then the Offeror may not be eligible for an award.

4.1.1 The Offeror shall not be a firm, nor have a subcontractor at any level, that is owned, operated, or controlled by the Government of a country that is a state sponsor of terrorism.

4.2 Evaluation Factors and Relative Order of Importance

The Government will evaluate each Offeror’s proposal on two (2) Technical Factors and two (2) Non- Technical Factors. For all Technical sub-factors, the Government reserves the right to validate the Offeror's submission by conducting an independent assessment using publicly available information and internal Government sources. The Government may assign strengths or weaknesses based on the proposal's alignment with these objectives. The Relative Order of Importance of the Evaluation factors are as follows:

4.2.1 (Non-Technical) Delivery Schedule The Government will evaluate the Offeror’s proposed delivery schedule to assess the risk associated with their ability to deliver vehicles in accordance with PPA requirements. This evaluation will be a narrative risk assessment based on the feasibility and aggressiveness of the proposed timeline when compared against the Government’s baseline delivery schedule outlined in the PPA. Proposals that demonstrate an ability to meet or exceed the schedule will be viewed most favorably.

4.2.2 (Technical) Technical Performance & Maturity

4.2.2.1 Sub-Factor: Maturity

The Government will evaluate the Offeror's submission to assess the developmental maturity and associated risks of the proposed system. This evaluation will consist of a review of the provided documentation to form a narrative risk assessment. Systems with a well-documented history of successful testing and operational deployment will be considered to pose a lower risk. The submitted Safety Assessment Report (SAR) will be evaluated for its completeness and determine whether the system’s safety risk is acceptable to the Government. Safety reports that are written in accordance with MIL-STD- 882E, CH1 will be viewed more favorably.

4.2.2.2 Sub-Factor: Technical Performance

The Government will evaluate the Offeror’s submitted Technical Volume to assess the proposed system's compliance with the Key Characteristics Definition in Attachment XXX. The evaluation will focus on the competency of the Offeror's approach and the quality of substantiating data provided to support performance claims. Systems demonstrating the highest levels of validated compliance, supported by robust data such as extensive test rounds fired or operational miles driven, will be assessed as having a lower risk. Additionally, systems showing the possibility of addressing objectives will be viewed more favorably. A weakness may be assigned for unsubstantiated claims, while a failure to meet any threshold characteristic(s) will be viewed as an extremely high risk.

4.2.2.3 Sub-Factor: Cyber Risk

The Government will evaluate the Offeror’s approach to cybersecurity to understand the proposed system's posture and identify any existing gaps in relation to Army policy. The evaluation will favorably assess proposals that demonstrate a thorough understanding of relevant cyber threats, clear familiarity with the Risk Management Framework (RMF), and provide detailed descriptions of security features that align with the Cybersecurity Implementation Guide.

4.2.2.4 Sub-Factor: United States Artillery Ammunition Compatibility The Government will evaluate the Offeror’s technical volume to assess the extent to which the proposed system is compatible with the designated tiers of US-inventory ammunition, including projectiles, fuzes, and propelling charges. This evaluation will assess the risk associated with firing this ammunition from the proposed system, based on the information provided. Proposals that demonstrate a higher degree of compatibility across all tiers, substantiated by robust and extensive test data and independent assessments, will be viewed more favorably and considered to be lower risk. Proposals that include information on cannon interior ballistics and the complete ammunition handling path (internal to the system, inclusive of maximum allowable ammunition envelope and acceleration forces) will be viewed more favorably.

4.2.3 (Technical) U.S. Integration

4.2.3.1 Sub-Factor: Commerciality/Supportability

The Government will evaluate the Offeror’s ability to support the proposed system by assessing the information provided in the Supply Chain Questionnaire (Attachment XXXX) and the Offeror’s obsolescence management approach. The evaluation will assess the Offeror's approach to meeting the project's supportability requirements, and the Government may assign strengths for approaches that decrease risk.

4.2.3.2 Sub-Factor: Production Onshoring and Organic Industrial Base Utilization The Government will evaluate the Offeror’s domestic production transition plan to assess the feasibility of the approach and determine the risk associated with establishing a U.S.-based production line and supply chain. The Government’s evaluation will consider the comprehensiveness and achievability of the proposed plan, including the timeline, identification of production facilities, and strategy for utilizing a U.S. supply chain. Offerors that demonstrate an existing U.S. presence and provide a clear, detailed strategy for achieving the required production rates will be considered more favorably.

4.2.3.3 Sub-factor: Technical Data/Software, Intellectual Property, and Digital Acquisition The Government will evaluate the Offeror’s proposed approach to assess the risk in the Government’s ability to achieve its objectives. The evaluation will consider the completeness of the Offeror's breakdown of all offered data, the associated data rights, any restrictions, and the cost to acquire these rights as detailed in the Offeror's completed Attachment XXX and proposed edits to Attachment XXX. A proposal that offers Specially Negotiated Rights equivalent to Government Purpose Rights for the specified deliverables within the PPA will be assessed as lower risk. Additionally, proposals that enable collaboration on technical data between the Government and the vendor in a common digital environment or Authoritative Source of Truth will be viewed favorably as further reducing risk and may be assessed as a strength.

4.2.4 (Non-Technical) Prototype Unit Cost The Government will evaluate the Offeror’s proposed system cost. A unit cost that is equal to or lower than the Government affordability target will be rated more favorably.

4.2.5 Rating Definitions

4.2.5.1 The Government will assign one of the following ratings to Technical Factor 1 and 2:

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Acceptable Proposal indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Moderate Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high

Unacceptable Proposal does not meet requirements of the solicitation and, thus, contains one or more deficiencies and is not awardable, and/or risk of performance is unacceptably high. The proposal demonstrates a thorough approach that is expected to exceed project objectives.

4.2.5.2 The Government will assign one of the following ratings to Non-Technical Factors 3 and 4.

Good The proposed schedule is very clear, and lays out the tasks, subtasks, and durations in a very logical sequence. The proposed unit cost is advantageous to the Government. The schedule and risk mitigation are very achievable and will meet or exceed the project schedule, including critical project milestones.

Acceptable The proposed schedule is generally clear and lays out the tasks, subtasks, and durations in a logical sequence. The proposed unit cost is reasonable and acceptable to the Government. The schedule and risk mitigation are likely achievable and will meet the project schedule, including critical project milestones.

Unacceptable The proposed schedule and risk mitigation lacks clarity and fails to lay out tasks and durations in a logical sequence, and/or may not be achievable and will most likely not meet the project schedule, including critical project milestones. The proposed unit cost is unreasonable and/or unacceptable to the Government.

4.3 Use of Artificial Intelligence (AI) tools in Proposal Evaluation

4.3.1 Use of AI tools in Support of Evaluations: The Government will employ AI as a tool to assist in the analysis and review of Offeror proposals. AI tools may be used to support tasks such as summarizing proposal content, identifying compliance with request for task order proposal / solicitation requirements, and highlighting areas of potential strength, weakness, or risk.

4.3.2 Maintaining Inherently Governmental Functions: Notwithstanding the use of AI tools to support the evaluation process, all final evaluation judgements, including the assignment or assessment of adjectival ratings, and source selection decisions, will be made exclusively by duly appointed Government personnel. The Government retains sole responsibility for all inherently governmental functions and will not delegate decision making authority to any AI tool.

4.3.3 Offeror Confidentiality and Data Protection: The AI tools utilized by the Government will be employed in a manner consistent with applicable regulations that govern the protection of proprietary and source selection sensitive information. The AI tool will be an output-only system. Any generated report data is not saved. No proposal data will be transmitted to or processed by external, non-Government systems without appropriate safeguards and authorizations in place.

4.4 Support Contractor Usage in Proposal Evaluation:

The Government intends to use non-Government advisor(s) as an addition to the evaluation team. The non-Government advisor(s) will serve as a subject matter expert to review each proposal and assist with proposal evaluation. Though the non-Government advisor(s) will have access to proposal information, they will not have the ability to rate the proposals or select a proposal for award. The Government will require the non-Government advisor(s) to sign a Source Selection Participation Agreement, which includes non-disclosure provisions, before reviewing proposal information.

Submission of an offer under this RPP will constitute a grant of authority by the submitting company to the Government to allow the use of non-Government advisor(s) to participate in evaluations of its proposal.

PART V: BASIS OF AWARD AND PRICE ASSESSMENT

5.1 Basis of Award

The selection decision for award of this prototype project will be determined using the evaluation criteria and relative order of importance as stated in this RPP. The Government will award the most highly rated Offeror(s) based on the Technical Factors and the Non-Technical Factors. When the most highly rated Offerors are rated equally, the Offeror(s) with the lowest price will be selected for award.

5.2 Discussions and Clarifications

The Government intends to evaluate proposals and make an award without discussions with Offerors.

Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a cost/price and technical standpoint. However, the Government does reserve the right to open and conduct discussions with one or more Offerors at its sole discretion if the Agreements Officer determines them to be necessary. The Government may also contact Offerors for clarifications of their submittals or to explain perceived typographical errors or inaccuracies.

5.3 Price Assessment

At the conclusion of Government evaluation, the Government will assess the proposal(s) selected for award as follows:

5.3.1 The Price assessment will consider whether the Total Proposed Price is fair and reasonable.

5.4 Cost Sharing

If the Offeror is proposing a cost share to meet 10 U.S.C. §4022(d)(1), the Government will assess the Offeror’s proposed cost share to ensure that it is 1/3 of the total evaluated price and to ensure the cost share is allowable, allocable and reasonable.

Other Transaction Agreement (OTA)
PART I - INTRODUCTION Army Contracting Command – Detroit Arsenal (ACC-DTA) issues this Request for Prototype Proposal (RPP) for the Army’s Mobile Tactical Cannon (MTC) requirement, in accordance with the authority at 10 United States Code (U.S.C) §402...
PART II – PROJECT OVERVIEW
PART IV: PROPOSAL EVALUATION
PART V: BASIS OF AWARD AND PRICE ASSESSMENT