About this file

This Project Manual details technical specifications for the Springs Hill Special Utility District's Seguin ISD Transmission Line project, prepared by Malone/Wheeler, Inc., a civil engineering firm located in Austin, Texas. The document provides comprehensive technical specifications for a water transmission line installation, covering multiple divisions including earthwork, concrete, utilities, and process interconnections. The specifications outline requirements for buried piping installation, valves and appurtenances, site clearing, excavation, trenching, backfilling, erosion control, and hydrostatic testing.

The technical specifications include detailed requirements for materials, installation methods, testing procedures, and quality assurance for various project components. Key specifications cover resilient wedge gate valves, fittings, corporation stops, ball valves, air valves, and other water infrastructure elements. The project involves installing water transmission infrastructure with specific technical standards for pipe materials, joint types, valve configurations, and installation techniques. The document emphasizes compliance with SHSUD (Springs Hill Special Utility District) and TCEQ (Texas Commission on Environmental Quality) standard specifications, and includes requirements for environmental protection, stormwater pollution prevention, and proper construction and restoration practices.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual for

Springs Hill Special Utility District

Seguin ISD Transmission Line

June 2025

Prepared for:

Springs Hill Special Utility District

5510 South Highway 123 Bypass

Seguin, TX 78155

Prepared by:

Malone/Wheeler, Inc.

TBPE No. F-786

5113 Southwest Parkway, Suite 260

Austin, Texas 78735

143607

JAMES INOCENCIO

L I C E N S E D

PROFESS I ONAL ENG I N

EE

R

ST

ATE OF TEXAS

03/27/206/12/25

Springs Hill Special Utility District Procurement and Contracting Requirements

Seguin ISD Transmission Line Section 00 01 10 – Table of Contents

00 01 10 – 1

Table of Contents

Division 00 – Procurement and Contracting Requirements

00 01 01 Cover Sheet

00 01 10 Table of Contents

Division 01 – General Requirements

01 22 10 Measurement and Payment

Division 02 – Existing Conditions

02080 Barricades, Signs, and Traffic Handling

02490 Loaming and Hydroseeding

02901 Miscellaneous Work and Cleanup

Division 03 – Concrete

03000 Concrete

03200 Asphalt Pavement Restoration

Division 31 – Earthwork

31 11 00 Site Clearing

31 23 00 Excavation and Fill

31 23 33 Trenching and Backfilling

31 25 00 Erosion and Sedimentation Control

Division 33 – Utilities

33 05 05 Buried Piping Installation

33 05 05.31 Hydrostatic Testing

Division 40 – Process Interconnections

40 05 61 Valves & Appurtenances

UNLESS OTHERWISE NOTED ON PLANS OR BID DOCUMENTS, CONTRACTOR MUST CONFORM TO SHSUD

SPECIFICATIONS AND DETAILS FOUND ONLINE HERE: HTTPS://SPRINGSHILL.ORG/ALL-FORMS-AND-REPORTS

Note: Procurement and Contracting Requirements are provided by the City of Seguin. This document contains technical specifications for the project.

DIVISION 01

GENERAL REQUIREMENTS

Springs Hill Special Utility District Technical Specifications

Seguin ISD Transmission Line Section 01 22 10 – Measurement and Payment

01 22 10 – 1

MEASURMENT AND PAYMENT

1.01 GENERAL

A. It is the intent of the Contract Documents that the aggregate amount of unit prices of

Work actually installed shall cover all Work required by the Contract Documents, in place, complete, and ready for use.

B. Prices in the Contract Documents include all compensation for full completion of all

Work items in place, and include providing all labor, materials, tools, equipment, services, supplies, incidentals, and all necessary operations.

C. Work to protect items to remain by installation of temporary construction, including posting of warning signs, placement of protective fencing, barriers, barricades and covers, and restoration of damaged items to remain, will be considered incidental to the various pay items and no separate payment for this work will be made.

D. Work necessary to haul materials from original positions to points of disposition, including excavation of earth materials and utilization in construction or other disposition, will be considered incidental to the various pay items and no separate payment for this Work will be made.

E. Work necessary to provide proper drainage during construction, including temporary construction and maintenance of ditches, culverts, and drainage ways, will be considered incidental to the various pay items and no separate payment for this Work will be made.

F. No costs in connection with Work required by the Contract Documents for proper and successful completion of the Contract will be paid outside of or in addition to prices named in the Contract Documents.

G. Work not specifically set forth in the Contract Documents as pay items shall be considered subsidiary obligations of Contractor and costs shall be included in prices named in the Contract Documents.

1.02 UNIT PRICE DESCRIPTIONS

A. Mobilization will be paid for at the unit contract price, per lump sum, which shall be considered full compensation for establishment of the requisite bonds, insurance, documentation, etc. necessary for the project to proceed in accordance with the

Contract Documents as well as the readying and/or movement of equipment, personnel, material, supplies, etc. to the project site and the establishment of office and other facilities necessary prior to beginning the work.

B. Environmental Protection / Stormwater Pollution Prevention Plan (SWPPP) will be paid for at the unit contract price, per lump sum, placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be

01 22 10 – 2 considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete installation to provide effective erosion control.

This item includes maintenance of the erosion controls for the duration of the contract as well as removal and disposal upon project completion.

C. Miscellaneous Work and Cleanup will be paid for at the unit contract price, per lump sum, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary for a complete restoration of the site to pre-project or finished grades conditions to comply with engineering regulations. Unit price shall include, but is not limited to, crossing and relocating existing utilities, restoration of driveways, fences and curbing, easement and right-of-way restoration, and other necessary work to place the site in acceptable condition following the conclusion of the work.

D. Loaming and Hydroseeding will be paid for at the unit contract price, per square yard, placed at locations shown on the construction plans and/or as approved by

Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary for a complete installation to provide effective loaming and hydroseeding including but not limited to erosion control and topsoil, grading, application of fertilizer, hydraulically applying seed and mulch or sod, and maintaining all areas. Work may also include items such as grading to transition the ground surface to tie into new construction, topsoil placing, seeding, and sodding. Excavation, storage, protection, soil preparation, placement, seeding, and fabric shall be included.

E. Right-of-Way Clearing & Grading will be paid for at the unit contract price, per lump sum, as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for right-of-way clearing and grading.

F. Trench Excavation Safety Protection will be paid for at the unit contract price, per linear foot, which price shall be considered full compensation for furnishing all required personnel, equipment, tools, materials, supplies, and incidentals necessary to provide the trench safety protection, trenching and backfilling. Unit price shall include locating and marking existing on-site utilities for identification of crossings, placing and removing all shoring, sheeting or bracing, dewatering or temporary diversion and proper recapture and transportation of water, and jacking and jack removal.

G. Remove and Replace Concrete Sidewalks and Driveways will be paid for at the unit contract price, per square yard, which price shall be considered full compensation for furnishing and installing materials, equipment, stockpile, blading, removal and disposal of existing surface, backfilling with flowable fill, placing, compaction, testing, finishing, striping, marking, painting, and any other incidentals necessary to complete the work.

01 22 10 – 3

H. Remove and Replace Asphalt Driveways will be paid for at the unit contract price, per square yard, which price shall be considered full compensation for furnishing and installing materials, equipment, stockpile, blading, removal and disposal of existing surface, backfilling with flowable fill, placing, compaction, testing, finishing, striping, marking, painting, and any other incidentals necessary to complete the work.

I. Remove and Replace Curb & Gutter will be paid for at the unit contract price, per linear foot, which price shall be considered full compensation for temporary removal of existing curb & gutter; restoring any curb & gutter disturbed to the original condition or better; furnishing, preparing, hauling, and installing curb & gutter;

excavation, backfilling, and disposal of surplus material; and equipment, labor, tools, and incidentals.

J. Traffic Control will be paid at the unit contract price, per lump sum, as approved by

Owner/Engineer, which shall be considered full compensation for maintenance of traffic, all materials, labor, tools, equipment, and incidentals necessary, in conformance with the current edition of the Texas Manual of Uniform Traffic Control

Devices for Streets and highways and as indicated by the Engineer, including any traffic control plans required beyond what is provided.

K. Pipe Water Main (16”)(PVC)(C-909)(Open Trench Installation) will be paid for at the unit contract price, per linear foot, of the pipe size indicated placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary to provide a complete and functioning pipeline in conformance with the plans and specifications. This item shall include excavation, embedment, restraint, backfill, testing and cleanup, complete in place. Unit price shall include locating existing on-site utilities for tie-ins, coordinating with the water treatment plant operator to minimize the duration for any system outages, excavation, dewatering, bedding and backfill, pipe wrap, testing, and cleanup, complete and in place.

L. Steel Casing (Open Cut)(30”) will be paid for at the unit contract price, per linear foot, of the size indicated, placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete and functioning pipeline installation in conformance with the plans and specifications. Steel must conform to ASTM A53 Grade B or ASTM A252 or approved equal and must be approved by the city or engineer. Unit price shall include open trench installation.

M. 16” Gate Valve will be paid for at the unit contract price, per each, placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete installation. This item shall

01 22 10 – 4 include valve, any and all boxes and covers, excavation, embedment, backfill, testing and cleanup, complete in place.

N. 16” D.I. Fittings will be paid for at the unit contract price, per ton, placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete installation. This item shall include excavation, embedment, restraint, backfill, testing and cleanup, complete in place Unit price shall include all PVC fittings associated with pipe connections, pipe bends and deflections, reducers, and ball valves, where shown on the plans, directed by Engineer, or required in accordance with the pipe manufactures installation guidelines.

O. 2” Air Release Valve (Complete) will be paid for at the unit contract price, per each, Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete installation. This item shall include valve, any and all boxes and covers, excavation, embedment, backfill, testing and cleanup, complete in place.

P. Hydrostatic Testing will be paid for at the unit contract price, per lump sum, which shall be considered full compensation for hydrostatic testing of the completed pipeline after final grading and services are connected in accordance with the Contract

Documents and technical specifications.

Q. 2” Temporary Blow-Off will be paid for at the unit contract price, per each, placed at locations shown on the construction plans and/or as approved by Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary for a complete installation. This item shall include valve, any and all boxes and covers, excavation, embedment, backfill, testing and cleanup, complete in place.

R. Detection Wire and Tape will be paid for at the unit contract price, per linear foot, Owner/Engineer, which price shall be considered full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary for a complete and functional installation.

DIVISION 02

EXISTING CONDITIONS

Barricades, Signs, and Traffic Handling 02080-1

SECTION 02080

BARRICADES, SIGNS, AND TRAFFIC HANDLING

PART 1 GENERAL

1.01 SCOPE OF WORK

Furnish all labor, materials, equipment required to provide traffic control in conformance with the current edition of the Texas Manual of Uniform Traffic Control Devices for Streets and Highways and as indicated by the Engineer.

PART 2 PRODUCTS

2.01 SIGNS

A. Sign Plates – 0.080-in thickness Alodine finished Federal Specification 6061-T6 aluminum.

B. Sign Posts – 1.25 ounces per square foot hot dipped galvanized welded steel tubing ASTM A513, outer diameter 2.375-in, wall thickness 0.065-in, 1.60 pounds per foot, or 4-in X 4-in treated lumber.

C. Hardware – Aluminum alloy ASTM A 444 sign hardware for clamp casting or stainless steel with galvanized or electroplated cold rolled steel U bolts, bolts, washers and nuts.

2.02 SIGN PLATE MESSAGE AND SIZE

Sign Designation Size

CW20-1D 48-in X 48-in CW20-4D 48-in X 48-in CW20-7aD 48-in X 48-in G20-2 60-in X 24-in

2.03 LUMBER

A. Rails shall be new, unweathered S4S grade #2 fir or yellow pine of the size indicated.

B. Posts, of the size indicated, shall be pressure treated with pentachlorophenol.

PART 3 EXECUTION

3.01 CONSTRUCTION METHODS

A. Prior to commencing construction, suitable barricades, signs, and traffic handling devices shall be installed to protect workers and the public.

B. The Contractor shall be responsible for installing all markers, signs and barricades conforming to the Texas Manual on Uniform Traffic Control Devices and/or as indicated.

If in the opinion of the Engineer, additional markers, signs, or barricades are needed in the interest of safety, the Contractor will install as required.

Barricades, Signs, and Traffic Handling 02080-2

3.02 MAINTENANCE

It shall be the Contractor’s responsibility to maintain, clean, move, and replace if necessary, barricades, signs, and traffic handling devices during the time required for construction of the Project. When no longer needed, all temporary barricades, signs, and traffic handling devices shall be removed, and the area restored to its original condition unless specified by the Engineer.

END OF SECTION 02080

Loaming and Hydroseeding 02490-1

SECTION 02490

LOAMING AND HYDROSEEDING

PART 1 GENERAL

1.01 SCOPE OF WORK

Furnish all labor, materials, equipment and incidentals required for loaming and hydroseeding including; provide erosion control and place topsoil, finish grading, application of fertilizer, hydraulically applying seed and mulch or sod, and maintaining all seeded areas as specified herein.

1.02 SUBMITTALS

Samples of all materials shall be submitted for inspection and acceptance upon Engineer’s and/or Owner’s request.

PART 2 PRODUCTS

2.01 MATERIALS

A. Topsoil shall be fertile, friable, natural topsoil typical of the locality and shall be obtained from a well-drained site free of flooding. It shall be without admixture of subsoil or slag and free of stones, lumps, plants or their roots, sticks, clay, peat, and other extraneous matter and shall not be delivered to the site or used while in a frozen or muddy condition.

Topsoil as delivered to the site or stockpiled shall have pH between 6.0 and 7.0 and shall contain not less than 3 percent organic matter, as determined by loss of ignition of moisture-free samples dried at 100 degrees Celsius. The topsoil shall meet the following mechanical analysis:

Percentage Finer

1-in screed opening 100 No. 10 mesh 95-100 No. 270 mesh 35-75

0.002 mm* 5-25

*Clay size fraction determined by pipette or hydrometer analysis.

A minimum ten days prior to topsoil placement, a one-pint sample of topsoil material shall be delivered to the Owner for testing and approval. Based on tests performed by the Engineer and/or Owner, the topsoil shall be identified as acceptable, acceptable with certain fertilizer and limestone applications, or unacceptable. If the topsoil is found acceptable the fertilizer and lime requirements will be as specified or as recommended by the Engineer and/or Owner. If the topsoil is found unacceptable, the Contractor shall be responsible for identifying an acceptable source of topsoil and shall incur all expenses associated with testing of additional samples. All topsoil incorporated into the site work shall match the sample provided to the Engineer for testing. Topsoil stockpiled under other sections of the Contract Documents may be used subject to the testing and approval outlined above. The Contractor will be responsible for screening stockpiled topsoil and providing additional topsoil as required at his/her own expense.

02490-2

B. Fertilizer shall be commercial mixed free granules or pelleted fertilizer, 10-20-10 (N-P205-K20) grade for lawn and naturalized areas. Fertilizer shall be delivered to the site in original unopened containers, each showing the manufacturer’s guaranteed analysis confirming to applicable state fertilizer laws. At least 40 percent of the nitrogen in the fertilizer used shall be in slowly available (organic) form.

C. Lime shall be ground limestone containing not less than 85 percent calcium and magnesium carbonates and be ground to such fineness that at least 50 percent shall pass a 100-mesh sieve, and at least 90 percent shall pass a 20-mesh sieve.

D. Seed shall be labeled in accordance with USDA Rules and Regulations under the Federal Seed Act and applicable State seed laws. Seed shall be furnished in sealed bags or containers bearing the date of the last germination, which date shall be within a period of 6 months prior to commencement of planting operations. Seed shall be from same as previous year’s crop; each variety of seed shall have a purity of not less than 85 percent, a percentage of germination not less than 90 percent, shall have a weed content of not more than 1 percent, and contain no noxious weeds. The seeding shall be applied over areas disturbed by construction as follows:

1. Broad Cast Seeding

a. From September 15 to March 1, seeding shall be with a combination of two pounds per 1,000 square feet of unhulled Bermuda and seven pounds per square feet of winter rye with a purity of 95 percent with 90 percent germination.

b. From March 2 to September 14, seeding shall be with hulled Bermuda at a rate of two pounds per 1,000 square feet with a purity of 95 percent and 85 percent germination.

2. Hydromulch Seeding

a. From September 15 to March 1, seeding shall be with a combination of one pound per 1,000 square feet of unhulled Bermuda and seven pounds per 1,000 square feet of winter rye with a purity of 95 percent with 90 percent germination.

b. From March 2 to September 14, seeding shall be with hulled Bermuda at a rate of one pound per 1,000 square feet with a purity of 95 percent and 85 percent germination.

E. The seed shall be furnished and delivered premixed in the proportions specified above. A manufacturer’s certificate of compliance to the specified mixes shall be submitted for each seed type. These certificates shall include the guaranteed percentages of purity, weed content and germination of the seed, and also the net weight and date of shipment. No seed may be sown until the Contractor has submitted the certificates.

F. Seed shall be delivered in sealed containers bearing the dealer’s guaranteed analysis.

G. Landscaped areas determined by the Engineer to be revegetated shall be sodded with Bermuda grass.

02490-3

H. Mulch shall be a specially processed cellulose fiber containing no growth or germination-inhibiting factors. It shall be manufactured in such a manner that after addition and agitation in slurry tanks with water, the fibers in the material become uniformly suspended to form a homogeneous slurry. When sprayed on the ground, the material shall allow absorption and percolation of moisture. Each package of the cellulose fiber shall be marked by the manufacturer to show the air-dry weight content and not contain in excess of 10 percent moisture.

PART 3 EXECUTION

3.01 APPLICATION

A. Unless otherwise shown on the Plans, topsoil shall be placed to a minimum compacted depth of 6-in on all parts of the site not covered with structures, pavement, or existing woodland.

B. For broad cast seeded area:

1. Fertilizer shall be pelleted or granular slow release with an analysis of 10-20-10 to be applied once at planting and once during the period of establishment at a rate of one pound per 1,000 square feet or as determined by the soil test.

2. Seed shall be applied at the rate of five pounds per 1,000 square feet.

3. Fiber mulch shall be applied at the rate of forty-five pounds per 1,000 square feet.

C. For hydromulch seeded area:

1. Fertilizer shall be water soluble fertilizer with an analysis of 10-20-10 at the rate of 1.5 pounds per 1,000 square feet.

2. Mulch type used shall be hay, straw, or mulch applied at a rate of 45 pounds per 1,000 square feet, with soil tackifier at a rate of 1.4 pounds per 1,000 square feet.

3. Fiber mulch shall be applied at the rate of forty-five pounds per 1,000 square feet.

D. After the topsoil is placed and before it is raked to true lines and rolled, limestone shall be spread evenly over the loam surface and thoroughly incorporated by heavy raking to at least one half the depth of topsoil.

E. The application of fertilizer may be performed hydraulically in one operation with hydroseeding and fiber mulching. The Contractor is responsible for cleaning all structures and paved areas of unwanted deposits of the hydroseeded mixture.

3.02 INSTALLATION

A. Previously established grades, as shown on Plans shall be maintained in a true and even condition.

B. Subgrade shall be prepared by tilling prior to topsoil placement to obtain a more satisfactory bond between the two layers. Tillage operations shall be across the slope.

02490-4

Tillage shall not take place on slopes steeper than 2 horizontal to 1 vertical or where tillage equipment cannot be operated. Tillage shall be accomplished by disking or harrowing to a depth of 9-in parallel to contours. Tillage shall not be performed when the subgrade is frozen, excessively wet, extremely dry, or in other conditions which would not permit tillage. The subgrade shall be raked and all rubbish, sticks, roots and stones larger than 2-in shall be removed. Subgrade surfaces shall be raked or otherwise loosened immediately prior to being covered with loam.

C. Topsoil shall be placed over approved areas to a depth sufficiently greater than required so that after natural settlement and light rolling, the complete work will conform to the lines, grades and elevations indicated. No loam shall be spread in water or while frozen or muddy.

D. After topsoil has been spread, it shall be carefully prepared by scarifying or harrowing and hand raking. All stiff clods, lumps, roots, litter and other foreign material shall be removed from the loamed area and disposed of by the Contractor. The areas shall also be free of smaller stones in excessive quantities, as determined by the Engineer. The entire surface shall then be rolled with a hand roller weighing not more than 100 pounds per foot of width.

During the rolling, all depressions caused by settlement of rolling shall be filled with additional loam and the surface shall be regraded and rolled until a smooth and even finished grade is created.

E. Seeding, sodding, mulching and conditioning shall only be performed during those periods that are normal for such work as determined by the weather and locally accepted practice, or approved by the Engineer. The Contractor shall not hydroseed during high winds.

F. Schedules for seeding and fertilizing must be submitted to the Engineer for approval prior to the work. Seeding as specified herein shall be accomplished from March 1st to June 1st.

Seeding during the period from October 1st to March 1st shall only be undertaken after approval by the Engineer. Seeding during the period from June 1st to October 1st shall only be performed if irrigation is provided.

G. Seeding or sodding shall be done within ten days following soil preparation. Seed shall be applied hydraulically at the rates and percentages indicated. Spraying equipment and mixtures shall be so designed that when the mixture is sprayed over an area, the grass seed and mulch shall be equal in quality to the specified rates. Prior to the start of work, the Contractor shall furnish the Engineer with a certified statement as to the number of pounds of materials to be used per 100 gallons of water. This statement shall also specify the number of square feet of seeding that can be covered with the quantity of solution in the Contractor’s hydroseeder. Upon completion of seeding operations, the Contractor shall furnish the Engineer with a certified statement on the actual quantity of solution applied.

H. In order to prevent unnecessary erosion, the Contractor shall carry out seeding and mulching as soon as they have satisfactorily completed that unit or portion of the project.

I. When topsoil and seed cannot be applied to newly graded areas because of season or weather conditions, and will remain exposed for more than 30 days, the Contractor shall protect those areas against erosion and washouts by whatever means necessary. This includes methods such as straw applied with a tar tack, wood chips, or by other measures as approved by the Engineer. Prior to application of topsoil, any such materials applied for

02490-5 erosion control shall be thoroughly incorporated into the subgrade by disking. Fertilizer shall be applied prior to spreading of topsoil.

J. On slopes, the Contractor shall provide measures to prevent washouts by an approved method. Any washout which occurs shall be regraded and reseeded at the Contractor’s expense until vegetation is established.

3.03 MAINTENANCE AND PROVISIONAL ACCEPTANCE

A. The Contractor shall keep all seeded areas watered and mowed, if necessary, and reseed all seeded areas as necessary until a good, healthy, uniform growth is established and provisionally accepted by the Engineer.

B. The Engineer and/or Owner will inspect all work for provisional acceptance at the end of the ten-week maintenance period. The Contractor shall request inspection a minimum of ten days prior to the anticipated inspection date. The maintenance period must occur during the growing season between March 15th and October 1st and shall include a minimum of three mowings.

C. A satisfactory stand will be defined as a section of turf of 10,000 square feet or larger that has:

1. No bare spots larger than three square feet.

2. No more than ten percent of total area with bare spots larger than one square foot.

3. Not more than fifteen percent of total area with bare spots larger than 6-in square.

D. After the inspection has occurred but prior to provisional acceptance, a soil test shall be performed to determine if additional soil fertilization should occur. If necessary, additional fertilizer not to exceed 30 lbs per 1,000 square feet of 20-10-10 shall be applied as directed by the Engineer.

E. The Contractor shall furnish full and complete written instructions for maintenance of the seeded areas to the Owner at the time of provisional acceptance.

F. The inspection by the Engineer and/or Owner will determine whether maintenance shall continue in any area or manner.

G. After all necessary corrective work and clean-up has been completed, and maintenance instructions have been received by the Owner, the Engineer and/or Owner will certify in writing the provisional acceptance of the lawn areas. The Contractor’s responsibility for maintenance of lawns, or parts of lawns shall cease on receipt of provisional acceptance.

3.04 GUARANTEE PERIOD AND FINAL ACCEPTANCE

A. All seeded areas shall be guaranteed by the Contractor for not less than one full year from the time of provisional acceptance.

B. At the end of the guarantee period, inspection will be made by the Engineer and/or Owner upon written request submitted by the Contractor at least ten days before the anticipated

02490-6 date. Seeded areas not demonstrating satisfactory stands as outlined above, as determined by the Engineer and/or Owner, shall be renovated, reseeded and maintained meeting all requirements as specified herein.

C. After all necessary corrective work has been completed, the Engineer and/or Owner shall certify in writing the final acceptance of the seeded areas.

END OF SECTION 02490

Miscellaneous Work and Cleanup 02901-1

SECTION 02901

MISCELLANEOUS WORK AND CLEANUP

PART 1 GENERAL

1.01 SCOPE OF WORK

A. Furnish all labor, materials, equipment and incidentals required to do the miscellaneous work not specified in other sections but necessary for the proper completion of the work as shown on the Plans.

B. When applicable, the Contractor will perform the work in accordance with other sections of this Specification. When no applicable Specification exists, the Contractor shall perform the work in accordance with the best modern practice and/or as directed by the Engineer and/or Owner.

C. The work of this section includes, but is not limited to, the following:

1. Crossing and Relocating Existing Utilities

2. Restoring of Driveways, Fences, and Curbing

3. Site Cleaning

4. Restoring Easements and Rights-of-Way

1.02 CROSSING AND RELOCATING EXISTING UTILITIES

A. This item includes any extra work required in crossing culverts, water courses including streams and drainage ditches, drains, gas lines, water lines and water services and other utilities. This work shall include but is not limited to the following: bracing, hand excavation, and backfill (except screened gravel) or any other work required for crossing the utility or obstruction not included for payment in other items of this Specification.

Notification of utility companies shall be the Contractor’s responsibility.

B. In locations where existing utilities cannot be crossed without interfering with the construction of the work as shown on the Plans, the Contractor shall coordinate with the utility owner for the relocation of the utility.

C. At pipe crossings and where designated by the Engineer, the Contractor shall furnish and place crushed stone bedding to support the existing pipe the entire exposed length. The bedding shall extend to the mid-diameter of the pipe crossed.

1.03 RESTORING OF DRIVEWAYS AND FENCES

A. Existing driveways disturbed by the water line construction shall be replaced. Gravel dirt roads and drives shall be replaced and regraded. Notice shall be required at least five days prior to disturbance of driveway access and temporary access shall be provided.

B. Fences shall be protected from damage under this item. If damaged, fences shall be replaced in condition equal to condition prior to being damaged.

Miscellaneous Work and Cleanup 02901-2

1.04 CLEANING UP

The Contractor shall remove all construction material, excess excavation, buildings, equipment and other debris remaining on the job as a result of construction operations and shall restore the site of the work to a neat and orderly condition.

1.05 RESTORING EASEMENTS AND RIGHTS-OF-WAYS

A. The Contractor shall be responsible for all damage to private property due to the Work. He shall protect from damage of all walls, fences, cultivated shrubbery and vegetables, trees, pavement, and underground facilities such as water pipes, septic systems, leach fields, and utilities.

B. Existing lawns damaged by construction shall be replaced. The Contractor may cut and replace the lawn, or he may restore the areas with an equivalent depth and quality of loam, seeded and fertilized as specified in Section 02490, Loaming and Hydroseeding. These areas shall be maintained and reseeded, if necessary, until all work under the Contract has been completed and accepted. The Contractor shall perform any additional work required to restore easements to their original condition.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION

DIVISION 03

CONCRETE

Concrete 03000-1

SECTION 03000

CONCRETE

PART 1 GENERAL

1.01 GENERAL

A. Concrete consisting of Portland cement, concrete aggregate, sand and water will be designated by the symbol consisting of two numbers. The first number will be the number of sacks of cement per cubic yard, and the last number the compressive strength at 28 days expressed in pounds per square inch. A sack of cement shall be defined as 94 pounds. The concrete shall be 6.0-4000 unless otherwise specified. Compressive strength tests where otherwise specified herein, shall be performed in accordance with ASTM C-39.

B. The Contractor shall be responsible for providing the mix design to the Engineer for approval.

1.02 SCOPE

This section of the Specifications shall include all labor and materials to construct all concrete work as shown on the Plans, herein specified, or both including the following:

A. All footings, slabs, floors, walls, beams, supports, walks, pedestals, curbs, vaults, and other concrete items, complete with metal reinforcement.

B. All formwork, formwork supports, formwork coatings and soaking, screens and levels required, and formwork removal.

C. Installing all inserts, grounds, dowels, blocks, sleeves and anchors, and safety treads as shown and/or specified in this or other sections.

PART 2 PRODUCTS

2.01 PORTLAND CEMENT

A. All cement to be used or furnished shall be Type I, Portland cement, conforming to ASTM C-150 unless otherwise specified. The Contractor shall furnish a certificate of compliance signed by the manufacturer identifying the cement and stating that the cement delivered conforms to ASTM C-150.

B. Whenever suitable facilities are available for handling and weighing bulk cement, such facilities shall be used. Otherwise, the cement shall be delivered in original unopened sacks that have been filled by the manufacturer. They shall be plainly marked with the manufacturer’s name or brand and cement type. Each sack shall contain 94 pounds of cement.

C. Cement shall be stored in such a manner as to permit ready access for the purpose of inspection and sampling, and suitable protected against contamination or moisture. Should any cement show evidence of contamination, or be otherwise unsuitable, it shall not be used.

03000-2

D. All Portland cement used in concrete for any individual structure shall be of the same brand and type unless otherwise approved by the Engineer.

2.02 AGGREGATES

A. Aggregates shall be sand and concrete aggregates conforming to the requirements prescribed in ASTM C-33 coarse aggregate gradation size number 467 and shall be approved by the Engineer prior to use.

B. Methods of handling materials resulting in segregation, degradation or the combining of materials, which result in any stockpile failing to meet specifications, shall not be permitted.

C. Aggregates which are found to have a silica-released alkali-reduced ratio greater than one, when tested in accordance with ASTM C289, may be used only when approved by the Engineer and provided low-alkali cement is used.

2.03 WATER

A. Water used for concrete shall be clear and free from oil, vegetable matter and other deleterious substances. Water shall not contain an amount of impurities that will cause a change in the time of setting of Portland cement or more than 25 percent nor a reduction in the compressive strength of mortar at fourteen days of more than 5% compared to results obtained with distilled water.

B. In conventionally reinforced concrete work, water shall not contain more than 1,000 ppm of chloride calculated as Cl, or more than 1,000 ppm of sulfates calculated as SO4.

C. In non-reinforced concrete work, water shall not contain more than 2,000 ppm of chloride calculated as Cl, no more than 1,500 ppm of sulfate calculated as SO4.

2.04 ADMIXTURES

A. Air entrainment shall be required on exposed plant walls or as directed by the Engineer.

The air content shall not be less than 3% nor more than 6%. Admixtures shall conform to ASTM C-260. Test shall be conducted in accordance with C-231, 233 or 173. Water reducer-set retarder shall be 75 degrees F. or more per ASTM C-494.

B. No other admixtures of any type shall be used unless authorized by the Engineer. When an admixture is permitted or specified, it shall be measured accurately into each batch or load in liquid form by a mechanical dispensing device and method approved by the Engineer.

2.05 PROPORTIONING

A. Aggregates and cement shall be proportioned by weight.

B. Proportioning shall consist of combining the aggregates, each stored in a separate bin in the various gradations prescribed, with cement and water. Weigh hoppers shall be charged from bins located directly over them or from conveyor belts. When conveyor belts are used, separate belts shall be provided for each size aggregate. There shall be an approved moisture meter installed to indicate the moisture in the sand.

03000-3

C. Bulk cement shall be weighed in an individual hopper and shall be kept separate from the aggregate until the batch ingredients are discharge into the mixer drum. The cement hopper shall be attached to a separate scale for individual weighing.

D. The amount of water to be added to the mixture shall be measured and discharged rapidly into the mixing drum through a valve with a positive cut-off. When water is measured by weight, it shall be weighed on a separate scale.

E. All weighing or metering devices, except moisture meters, used for proportioning materials shall be accurate to within one percent. They shall be sealed and certified by the recognized, legal Sealer of Weights and Measures. These certifications shall be dated within the past 12 months and shall be renewed whenever required by the Engineer. The moisture meter shall be accurate to within ½ of the one percent moisture. Whenever portable bunkers are set up at a new location, the scale assemblies shall be inspected and certified regardless of the date of scales were last tested.

F. Scales utilized in proportioning shall be either springless dial or multiple beam type. Scale graduations shall be no greater than the following:

Aggregate Scales 25 lbs.

Cement Scales 5 lbs.

Water Scales 5 lbs.

G. All scales shall be of such size and so arranged that they may be read easily from the operator’s platform. If a multiple beam type scale is used, the scale shall be provided with an indicator operated by the main beam, which will give positive visible evidence of over or under weight. The indicator shall be so designed that it will operate during the addition of the last 400 pounds of any weighing. The other travel of the indicator hand shall be at least one-third of the loading travel. Indicators shall be enclosed against moisture and dust.

H. Weighing equipment shall be insulated against vibration and movement of the other operating equipment in the plant. When the entire plant is running, the scale reading at cut-off shall not vary from the weight designated by the Engineer by more than one percent (1%) for cement, one percent for the total aggregate in any batch.

2.06 MIXING

A. Machine mixing will be required in all cases other than those in which it would obviously prove to be impractical, in which event hand mixing will be permitted. Mixing shall be commenced as soon as possible after the cement is placed in contact with the aggregates, but at no time shall the intervening period exceed 30 minutes.

B. All concrete mixers shall be of such design and construction and so operated as to provide thoroughly and properly mixed concrete in which the ingredients are uniformly distributed.

Mixers shall be maintained in proper and serviceable working condition, and any part or portion thereof that is out of order or becomes worn to such extent as to detrimentally affect the quality of mixing, shall be promptly repaired or replaced.

03000-4

2.07 CONCRETE CONSISTENCY

A. The amount of water added at the mixer shall be regulated to take into account the free water in the aggregates. Free water is defined as the total water minus the water absorbed by the aggregate in a saturated surface-dry condition.

B. The amount of water used in the mixture shall not exceed the minimum amount necessary to permit practical placement and consolidation of the concrete, and shall be that required to produce concrete with a slump within the range shown as nominal in the following table:

Type of Work Nominal Slump (inches) Maximum Slump (inches) Concrete Pavement 0-2 4 Non-reinforced Concrete 0-3 4 Reinforced Concrete Structures

Heavy Sections 0-3 7 Thin Sections & Columns 0-4 7

Concrete Place Under Water 6-8 9

C. The concrete used in the work shall not have a slump greater that shown as maximum above, nor a free water content reading more than 312 pounds per cubic yard of concrete.

D. When adverse or difficult conditions affect the placement of concrete, the Engineer may authorize a greater slump to be used, provided both the water and cement are increased.

Water shall be added at a ration not to exceed 30 pounds per sack of added cement per cubic yard of concrete, and such additional water and cement shall be at the Contractor’s expense.

E. The consistency of concrete shall be determined in accordance with ASTM C-143.

F. If slump tests of individual samples taken at approximately the ¼ and ¾ points of the discharge differ by more than two inches; the mixer will not be accepted for further use until the condition is corrected.

2.08 TRANSIT MIXERS

A. The type, capacity, and manner of operation of the mixing and transporting equipment for ready-mix concrete shall conform to the current ASTM C-94 standards; “Standards for Operation of Truck Mixers and Agitators of the National Ready-Mixed Concrete Association” and the “Truck Mixer and Agitators Standards of the Truck Mixer Manufacturers Bureau.” Transit mix concrete trucks shall be equipped with an automatic device for recording the number of revolutions of the drum during the mixing period. Each mixer and agitator shall have attached thereto in a prominent place, a metal plate or plates, installed by the manufacturer on which is plainly marked the capacity of the drum in terms of the volume of mixed concrete and the speed of rotation for the agitating and mixing speeds of the mixing drum or blades.

B. Each mixer shall have an identification number painted on the truck in such a location that it can be easily read from the batching platform.

03000-5

C. The total volume of materials introduced into the mixer shall not exceed the manufacturer’s guaranteed mixing capacity. If the concrete so mixed does not meet the uniformity requirements of this subsection, the amount of materials charged into the mixer shall be reduced.

D. The drum of the mixer shall be completely emptied of any previously mixed load. The proper proportions of aggregate, cement, and water for each load of concrete shall be placed in the mixer and shall be mixed for not less than 70, or more than the speed designated by the manufacturer of the equipment as mixing speed. Additional revolutions of the drum shall be at the speed designated by the manufacturer of the equipment as agitating speed.

The revolving of the drum shall be continuous until the concrete is completely emptied from the drum.

E. When concrete is being placed for concrete structures, all wash water shall be emptied from the mixer before any portion of the succeeding load is placed therein. For all other work, the mixer shall be empty or may carry 10 gallons of water in the drum. Adequate control of ready-mixed concrete in the drum will sometimes require that additional water be added and mixed into the batch at the point of discharge. Water so added shall be mixed 3 minutes.

Water shall not be added to the load during transit.

F. The total elapsed time between the addition of water at the batch plant and discharging the completed mix shall not exceed 90 minutes. Under conditions contributing to quick setting, the total elapse time permitted may be reduced by the Engineer.

G. The Engineer shall be provided with a legible certified weighmaster’s certificate, which shall contain the following information:

1. Name of vendor

2. Name of contractor

3. Number of cubic yards in the load

4. Actual weights of cement and of each size of aggregate

5. Amount of water added at the plant

6. Amount of water in the aggregate

7. Brand and type of cement

8. Brand and amount of admixture

9. Time and date of batching

H. Space shall be provided on the certificates so that the amount of water added on the job may be indicated.

03000-6

2.09 HAND MIXING

Hand mixed concrete shall be mixed on a watertight platform or in a mortar box in batches not to exceed 1/3 cubic yard each. The aggregates shall first be spread in a uniform layer over which the required quantity of cement shall be evenly distributed. The entire batch shall be turned with shovels until the ingredients are thoroughly blended before adding the water. After adding the proper amount of water, the batch shall again be turned with shovels until a uniform consistency is obtained. Methods of hand mixing which allow the loss of mixing water will not be permitted.

2.10 TRANSPORTING BATCHED MATERIALS AND MIXED CONCRETE

The compartments of trucks or other equipment used for the purpose of transporting proportioned dry aggregate and cement, or mixed concrete, shall be suitably constructed to adequately protect and prevent loss or leakage of the contents during charging, transit or discharging.

2.11 MEMBRANE BARRIER

Provide a polyethylene sheeting that is at least 6 mils thick and free from visible defects as a bond breaker at the interface of the flexible base and new concrete pavement.

2.12 FLY ASH

This specification covers the general and specific requirements for two (2) classes of fly ash.

Classification will be based on chemical composition. Both classes of fly ash shall meet all requirements of the chemical and physical requirements for each class as shown in ASTM C 618 and the following tables.

Chemical Requirements Item Both Classes

Calcium Oxide (CaO), Variation in percentage points of CaO from the average of the last 10 samples (or less provided 10 have not been tested) shall not exceed plus or minus

4.0

Magnesium Oxide (MgO), maximum, percent NOTE: When the autoclave expansion or contraction limit is not exceeded, a MgO content above five (5) percent may be acceptable.

5.0

Available Alkalis, as Na2O, maximum percent (when used in conjunction with reactive or potentially reactive aggregates)

1.5

Moisture Content, maximum, percent 2.0 Loss on Ignition, maximum, percent* 3.0 *Exception will be taken to Note A under ASTM C 618, Table 1 (Allowance of 12% LOI for class F fly ash). All fly ash will meet specification requirement stated in this table.

03000-7

Physical Requirements Item Both Classes

Fineness, retained on the No. 325 (45µm) sieve 30.0 max.

Variation in percentage points retained on the No. 325 (45µm) sieve from the average of the last 10 samples (or less provided 10 have not been tested) shall not exceed plus or minus

5.0

Increase of drying shrinkage of mortar bars at 28 days, maximum, percent

0.03

Reactivity with cement alkalies, mortar expansion at 14 days, maximum, percent

0.02

Specific Gravity, maximum variation from average percent

5.0

A. Drying shrinkage shall be tested according to ASTM C 157.

B. Alkali reactivity shall be tested according to ASTM C 441.

C. Specific gravity shall be tested according to ASTM C 188.

D. All other physical requirements shall be tested according to ASTM C 311.

2.13. FIBER-REINFORCED CONCRETE FOR COLD JOINTS

The fiber-reinforced concrete made according to this Section must meet the requirements listed in Table 1. The qualification can be based on either of the test methods allowed in Table 1 (ASTM C1609 or Tex-475-A).

Material Requirements Property Test Method Specimen Age Requirement

Minimum Equivalent Flexural Strength Ratio 𝑅𝐷𝑇,150 or Minimum Equivalent Tensile Strength

Ratio

ASTM C1609

or

Tex-475-A 7 days

21% or

19%

Minimum Residual Strength at Net Deflection of L/150 𝑓𝐷150 or Minimum Residual Strength @δ=0.1

ASTM C1609

or

Tex-475-A

110 psi or

31 psi

PART 3 EXECUTION

3.01 CONCRETE CONSTRUCTION

A. General

1. Concrete chambers, vaults, walls, structural slabs, footings, foundations and similar structures shall be constructed in conformity with the plans and this sub-section. Concrete shall conform to the requirements herein.

03000-8

2. Safe and suitable ladders shall be provided to permit access to all portions of the work.

B. Subgrade for Concrete Structures

1. Earth subgrade upon which concrete is placed shall be firm and free from water.

Groundwater shall be kept below subgrade until the concrete has set. When the subgrade is dry earth, it shall be thoroughly dampened with water to ensure that no moisture will be absorbed from the fresh concrete.

2. When the design details for the project provide for the construction of filter or drain material consisting of gravel (or combination of gravel and sand), which material will be subgrade for concrete, the placing of steel reinforcement and placement of concrete shall follow the installation of the filter or drain material as closely as practical. The filter or drain material shall be kept de-watered to the extent necessary to prevent any portion of concrete materials being deposited in water.

3. When the concrete is to be deposited on rock, the rock shall be fully uncovered, cleaned, and its surface shall be removed to a depth sufficient to expose sound rock.