SPECS ARQS DEP25-100 AML-Valley Camp Mine Facilities.pdf

PDF 1 MB Posted

Attached to
AML-Valley Camp Mine Facilities
Solicitation number
ARFQ-0313-DEP2500000066-2
Issued by
Monongalia County, West Virginia

About this file

These construction specifications are for the Valley Camp Mine Facilities project, issued by the West Virginia Department of Environmental Protection's Division of Land Restoration and Office of Abandoned Mine Lands & Reclamation. The project is located in Ohio County, West Virginia, and involves comprehensive site restoration and demolition work. Key scope elements include mobilization and demobilization, construction layout, site preparation, erosion and sediment control, structure demolition (including a 140' tall concrete silo), gravel road rehabilitation, temporary access roads, installation of erosion control measures, repaving, revegetation, and final site cleanup. The project will require detailed video documentation, careful environmental management, and adherence to strict state and federal environmental regulations.

The project will be funded through the state's environmental protection budget, with a comprehensive payment structure that breaks down costs across multiple line items including site preparation (not to exceed 10% of total bid), quality control (not to exceed 3%), and administration (not to exceed 5%). Contractors must provide detailed documentation, including soil tests, material certifications, and comply with NPDES stormwater permit requirements. The project emphasizes environmental restoration, with specific requirements for revegetation, sediment control, and minimizing ecological disruption. Bidders must demonstrate significant experience in large-scale environmental remediation, particularly in handling complex demolition and reclamation projects in abandoned mine lands.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SPECIFICATIONS

Valley Camp Mine Facilities

Ohio County, West Virginia

West Virginia Department of Environmental Protection

Division of Land Restoration

Office of Abandoned Mine Lands & Reclamation

December 2024

TABLE OF CONTENTS

SECTION PAGE

Contents

I. SPECIAL PROVISIONS

1.0 LOCATION / SITE DESCRIPTION

2.0 SCOPE OF WORK

3.0 BORROW (DISPOSAL) AREAS

4.0 DISPOSAL OF UNSUITABLE MATERIAL

5.0 PERMITS, LICENSES, AND FEES

6.0 NPDES STORMWATER REQUIREMENTS

7.0 CONSTRUCTION SIGN

8.0 CONTRACTOR INFORMATION FORM (AVS)

II. TECHNICAL SPECIFICATIONS

1.0 MOBILIZATION AND DEMOBILIZATION

1.1 Description

1.2 Method of Measurement and Basis of Payment

1.3 Pay Item

2.0 CONSTRUCTION LAYOUT

2.1 Description

2.2 Materials

2.3 Construction Methods

2.4 Method of Measurement and Basis of Payment

2.5 Pay Item

3.0 QUALITY CONTROL

3.1 Description

3.2 Materials

3.3 Construction Methods

3.4 Method of Measurement and Basis of Payment

3.5 Pay Item

4.0 SITE PREPARATION

4.1 Description

4.2 Materials

4.3 Construction Methods

4.4 Method of Measurement and Basis of Payment

TABLE OF CONTENTS

SECTION PAGE

4.5 Pay Items

5.0 EROSION & SEDIMENT CONTROL

5.1 Description

5.2 Materials

5.3 Maintenance

5.4 Installation

5.5 Removal

5.6 Method of Measurement and Basis of Payment

5.7 Pay Items

6.0 REVEGETATION

6.1 Description

6.2 Materials

6.3 Construction Methods

6.4 Method of Measurement and Basis of Payment

6.5 Pay Item

7.0 VIDEO DOCUMENTATION

7.1 Description

7.2 Quality Assurance

7.3 Materials

7.4 Methods of Measurement and Basis of Payment

7.5 Pay Items

8.0 ASPHALT PAVING

8.1 Description

8.2 Materials

8.3 Method of Measurement and Basis of Payment

8.4 Pay Items

9.0 ADMINISTRATION

9.1 Description

9.2 Summary

9.3 Method of Measurement and Basis of Payment

9.4 Pay Items

VALLEY CAMP MINE FACILITIES

I. SPECIAL PROVISIONS

1.0 LOCATION / SITE DESCRIPTION

The project is located within Ohio County, West Virginia in Wheeling near the community of Valley Camp. The site was the previous location of the mining operations preparation plant. The only remaining facilities visible are an approximately 140’ tall by 80’ diameter concrete silo, the circular foundation and wall remains of another tank or silo, and a water pump structure and shaft. According to historic aerial photographs, it appears that the silo was constructed sometime between 1957 and 1966. The rest of the plant was demolished and removed between 1982 and 1997.

Directions to Site:

From Washington, Pa, take I-70 West to the Dallas Pike Exit. Turn right at the end of the exit ramp and go South on the Dallas Pike. At the bottom of the hill at the "T" intersection turn left on the National Road/ Rt.40, travel about a mile, Liberty Distribution building on the left. The access road to the vacant mine property is on the left beside a row of blue storage buildings. The locked access road is across a metal bridge.

GPS Coordinates for the Concrete Silo is:

40.063157°, -80.611199°

Approximate GPS Coordinates for Foundation Remains and Ruins is:

40.063294°, -80.610239°

Approximate GPS Coordinates for Pump Structure and Shaft is:

40.063865°, - 80.607638°

2.0 SCOPE OF WORK

The Work consists of furnishing all labor, plant, power, equipment, supplies, and performing all operations necessary for the completion of the project. The Contractor shall perform all operations necessary for:

• Mobilization and Demobilization

• Survey and Construction Layout

• Quality Control

• Site Preparation

• Gravel Road Rehabilitation

• Temporary Access Roads

• Structure Demolition

• Installation and Maintenance of Erosion and Sediment (E&S) Controls

• Repaving and Refinishing of Existing Paved Road, at the direction of the

Engineer.

• Revegetation

• Final Site Cleanup and Removal of E&S Controls

Specifically, the Contractor will be installing their E&S Controls, establishing access to the Equipment / Storage Area, clearing and grading the site as needed to provide space to Work, and any other applicable Site Preparation.

The Contractor is to install Gravel Rehabilitation to repair or reconstruct any existing graveled areas damaged during the Work by the Contractor to a quality consistent with these Specifications and to a quality at least what was present before the Work started, at the Contractor’s expense, except as otherwise specified or approved.

The existing bridge structure at the site is owned by the Ohio County Commission. The

Contractor shall have the option to utilize the existing bridge structure to the site or to install a temporary crossing for access. To utilize the existing bridge, the Contractor shall evaluate the structure based upon the size and weight of the proposed equipment to be used. This evaluation shall include the replacement cost of the structure in the case that it is damaged beyond repair during construction. If the structure is found to be adequate to provide access, then the Contractor shall reach a signed agreement with the Ohio

County Commission to utilize the bridge. The Contractor shall have in place a bond for the use of the bridge for a total of $1,500,000 or the replacement cost of the bridge from the evaluation, whichever is greater. This bond will act as a surety in the event that the bridge is damaged and the damages are not rectified by the Contractor.

If the Contractor decides to install a temporary crossing into the site, then they will be responsible for all design, permitting, and installation of that structure and the temporary access roads necessary to accommodate entry.

The Contractor shall demolish the existing concrete silo on the project site. This shall be accomplished by either blasting or by demolition equipment. If equipment is used, then demolition shall be completed from the top of the structure down.

The Contractor is to install a 2-inch type 1 hot mix asphalt wearing course to any existing paved areas that are damaged during work at the direction of the Engineer. The expectation is that, if the pavement is damaged, that the pavement would be, at a minimum, cleaned and prepped, have tack coat applied, and resurface areas as deemed necessary by the engineer. If damage protrudes into the base or aggregate layer of the existing asphalt, then a full depth repair will be necessary. This will be determined as directed by the Engineer. If nothing is damaged during the Work, then no replacements would be necessary.

Contractor is responsible for leaving the site and surrounding area in original condition or better. This includes picking up and disposing of any trash or litter the Work generates in accordance with these Specifications.

Contractor will IMMEDIATELY clean any mud off roadways that the State reasonably believes to be project related.

Contractor is responsible for engaging in soil disturbance only within the Limits of

Disturbance shown on the Plans.

The Contractor shall also be responsible for surveying, including establishing construction baseline, measuring and developing all completed quantities on the job, and the ordering, purchase and delivery of any and all materials required for construction or required for development of support areas. The Contractor shall perform all other operations as incidental to the program as specified herein. The Contractor is responsible to verify all surveying, measurements, estimates, or any other information provided by the State for accuracy.

Any deviation from the Plans or Specifications, not approved in writing by the State

Engineer or Contract Administrator, are at Contractor risk. State reserves the right to require Contractor to correct back to Plans – at Contractor cost – any unapproved condition at any time.

3.0 BORROW (DISPOSAL) AREAS

All borrow (disposal) areas must be approved by the State. The Contractor shall be responsible to obtain from the property owner(s) of the borrow areas, all necessary rights of entry, including rights of entry for the State and OSMRE for inspection purposes. The said rights of entry agreement must state that the property owner(s) indemnify and hold harmless the State for Contractor’s action for any injury or damages whatsoever resulting from the use of the property.

The Contractor also shall submit a borrow / disposal area reclamation plan for prior approval by the State. The Contractor shall observe the following NEPA compliance schedule relative to selecting and utilizing any off site borrow areas and / or any waste disposal areas:

• No borrow (disposal) site operations will affect a site listed in, eligible for, or proposed to be listed in the National Register of Historic Places.

• No borrow (disposal) operations will be located within one-quarter mile of any Federally listed, established, or prospective component of the National

Wild and Scenic River System under 16 USC 1274 and 1276.

• Borrow (disposal) site operations will not cause a significant encroachment within the base floodplain (CE.O. 11988: Floodplain Management).

• Borrow (disposal) site operations will not be located in or affect a critical habitat of a Federally listed endangered or threatened species under 16 USC

1531, et. seq.

• No borrow (disposal) operations will occur in wetland areas which are designated by appropriate agencies.

• Borrow (disposal) site operations will be consistent with any approved plans governing ambient air quality.

• Adherence to these mitigation measures does not relieve the Contractor of the obligation or responsibility to obtain any other Federal, State, or Local approvals required to use borrow (disposal) areas and conduct such activities.

• Documentation: Copies of borrow (disposal) site approvals and concurrences will be submitted to the State prior to the commencement of reclamation activities.

• Site Monitoring: Borrow (disposal) activities will be monitored by the State to ensure compliance with contractual requirements, applicable Federal, State, and Local laws, and any permit conditions.

4.0 DISPOSAL OF UNSUITABLE MATERIAL

All waste areas shall be obtained in accordance with these Specifications. All unsuitable materials (wood, trash, debris, and garbage), as determined by the State, shall be wasted by the Contractor outside the limits of work conforming to the requirements of these

Specifications at the Contractor’s expense. Wood may be burned, if in conformity with these Specifications and any applicable Federal, State, and Local laws, and any permit conditions. Uncontaminated wood may also be chipped with the chips either buried or broadcasted across the site.

The Contractor shall observe the NEPA compliance schedule relative to selecting and utilizing any off-site disposal areas in accordance with these Specifications.

5.0 PERMITS, LICENSES, AND FEES

The Contractor shall procure all permits and licenses, pay all charges and fees, and give all notices necessary and incidental to the due and lawful prosecution of the Work.

Permits required for this project may include but not be limited to: Water Quality

Certification from WVDEP and burning permits from WVDNR and WVDEP Office of

Air Quality. A copy of the permit/permits as procured shall be furnished to the State prior to initiation of the Work under this Contract. The State will obtain the Permits from

WVDOH and NPDES from WVDEP, if required. Contractor shall be responsible for any Stream Activity Permits necessary to complete the project Work.

6.0 NPDES STORMWATER REQUIREMENTS

The WVDEP-AML has obtained a Construction Storm Water General Permit for this project from the WVDEP Division of Water and Waste Management (WVDEP

DWWM). The registration for this reclamation project will be modified to include the

Contractor as Co-Applicant #1, with the WVDEP-AML being Co-Applicant #2. As such, the Contractor shall assume responsibility for compliance with the terms and conditions of the permit including modifications and any future correspondence such as registration renewal invoices, inspection reports, and notices of violation shall be forwarded to the Contractor. Upon award of the contract, the Contractor shall complete a Co-Applicant #1 signature page and submit the completed form to WVDEP-AML prior to scheduling a Pre-Construction Conference.

Upon receipt of the completed form, WVDEP-AML will request the WVDEP DWWM to modify the existing NPDES registration for this project to make the Contractor the

Co-Applicant #1 to the permit.

The WVDEP DWWM will notify the Contractor and WVDEP-AML when the successful transfer of registration under WV/NPDES Storm Water Construction

General Permit (No. WV0115924) is completed. A Notice to Proceed will not be issued until the contractor signs the co-applicant form and submits to the Office of

Abandoned Mine Lands. Once the transfer has been completed, the WVDEP will continue to be responsible for any modification fees and annual renewal fees incurred up until the date of the final inspection of the project that occurs after completion of construction activities at the site. The Contractor shall be responsible for any and all costs associated with violations and fines assessed against the project that are a result of the Contractor’s negligence, carelessness, or failure to install permanent controls as part of the work as scheduled.

The WVDEP shall apply for a Notice of Termination (NOT) from WVDEP DWWM via the Construction Storm Water website.

https://dep.wv.gov/WWE/Programs/stormwater/csw/Pages/home.aspx upon completion of construction activities at the site. The NOT shall be issued by

WVDEP DWWM upon completion of the project. The Contractor will continue to be bound by the terms and conditions of the permit until the NOT has been approved by

WVDEP DWWM. Once the project is complete, the Contractor will still bear responsibility for the NPDES registration until a NOT is received from the WVDEP

DWWM.

Co-Applicant #1 Signature Page

Co-Applicant #1: _____________________________________________

New and/or Modification of NPDES Storm Water of Construction Project Name:

BY COMPLETING AND SUBMITTING THIS APPLICATION, I HAVE REVIEWED AND UNDERSTAND

AND AGREE TO THE TERMS AND CONDITIONS OF THE GENERAL PERMIT (WV0115924) ISSUED ON

MARCH 6, 2024, WITH AN EFFECTIVE DATE OF APRIL 6, 2024, AND EXPIRATION DATE OF APRIL 5, 2029. I UNDERSTAND THAT PROVISIONS OF THE PERMIT ARE ENFORCEABLE BY LAW, VIOLATION

OF ANY TERM AND CONDITION OF THE GENERAL PERMIT AND /OR OTHER APPLICABLE LAW OR

REGULATIONS CAN LEAD TO ENFORCEMENT ACTION.

I CERTIFY UNDER PENALTY OF LAW THAT I HAVE PERSONALLY EXAMINED AND AM FAMILIAR

WITH THE INFORMATION SUBMITTED ON THIS FORM AND ALL ATTACHMENTS AND THAT, BASED

ON MY INQUIRING OF THOSE INDIVIDUALS IMMEDIATELY RESPONSIBLE FOR OBTAINING THE

INFORMATION. THE INFORMATION SUBMITTED IS, TO THE BEST OF MY KNOWLEDGE AND

BELIEF, TRUE, ACCURATE, AND COMPLETE. I AM AWARE THAT THERE ARE SIGNIFICANT

PENALTIES FOR SUBMITTING FALSE INFORMATION, INCLUDING THE POSSIBILITY OF FINE AND

IMPRISONMENT.

(CO-APPLICANT #1 SIGNATURE) DATE

Print Name: ___________________________________________

Print Title: ___________________________________________

Address: ___________________________________________

City: _____________________State: _______ Zip:___________

Telephone Number: (_____ )________-____________________

Email: ______________________________________________

FEIN: ______________________________________________

7.0 CONSTRUCTION SIGN

The work to be performed under this Section consists of providing all labor, material, and equipment necessary to install a project sign as indicated on the detail included herein and as specified herein.

Sign face shall be 3/4" thick Marine Exterior plywood or aluminum or composite material. Posts and cross-brace shall be No. 2 Grade Pine or Fir: kiln dried and pressure treated.

All hardware shall be manufactured from good, commercial-quality material and meet all applicable ASTM standards. Spikes and nails shall be common wire-type and shall meet AISI steel specifications 1010 or 1020. All hardware shall be hot-dip galvanized in accordance with ASTM A-153.

The sign face shall be cut to the dimensions shown on the detail herein. The sign shall be painted with one (1) coat of primer and two (2) coats of white enamel. All exterior cut edges shall be smooth sanded, prior to painting. All edges shall be double primed.

The letters, border, and strips shall be painted as shown on the detail drawing. Posts and cross-brace shall be painted with two (2) finished coats of brown enamel.

The Contractor shall bolt the sign to posts and provide the required cross-bracing. The posts shall be set in gravel base and sign erected, as shown on the drawing. One (1) sign is required and is to be located at the discretion of the Inspector.

Payment for the Work, which shall include installation of the project sign, shall be part of the lump-sum bid for "Mobilization” and Demobilization”.

8.0 CONTRACTOR INFORMATION FORM (AVS)

Vendor must complete the Contractor Information Form (AVS) to request an eligibility evaluation from the Office of Surface Mining Reclamation and Enforcement

(https://www.osmre.gov/programs/regulating-coal-mines/avs). This requirement applies to Contractors and their Sub-contractors and is found under OSMRE’s regulations at CFR

Title 30, Chapter VII, Subchapter R, Part 874.16:

https://www.ecfr.gov/current/title-30/chapter-VII/subchapter-R/part-874

Vendors should submit the most recent version with their bid documents. Form must be signed and dated within the last 30 days for vendors' bid to be considered for any current solicitation.

II. TECHNICAL SPECIFICATIONS

1.0 MOBILIZATION AND DEMOBILIZATION

1.1 Description

This Work shall consist of the performance of construction preparatory operations, including the movement of personnel and equipment to the project sites and for the establishment of the Contractor’s offices, buildings and other facilities including the construction of all temporary access roads as necessary to begin work on a substantial phase of the contract. The location of the Contractor’s office to be established shall be approved by the State. It also shall include all demobilization activities involving the removal from the sites of all plant, equipment, supplies and personnel after completion of the work, including cleanup of all rubbish and waste materials generated during the construction of this project and restoration of any damage to existing site improvements resulting from the Contractor’s activities at the site. This item shall also include the installation of the project sign at the beginning of the project and the removal of the sign, prior to the Final Inspection. All equipment and material storage areas shall be approved by the State.

Upon receipt of a notice to proceed, the Contractor shall initiate and complete measures necessary to commence the Work. Mobilization shall also consist of delivering to the site and assembling in working order all necessary equipment, materials, and supplies to be furnished by the Contractor to complete the work. Demobilization shall consist of the removal from the site of all the Contractor’s equipment and materials after completion of the work and cleanup of the site. Work shall be performed to the satisfaction of the State to be considered complete.

1.2 Method of Measurement and Basis of Payment

There shall be no measurement for the “Mobilization and Demobilization” item as it shall be lump sum. Said lump sum cannot be more than 10% of the TOTAL AMOUNT BID for the project. Partial payments will be as follows:

One-half of the amount bid will be released to the Contractor with the first estimate payable, not less than 15 days after the start of Work at the project site.

The final one-half of the amount bid shall be released with the last estimate payable after the work is accepted by the State and after all Final Inspection submittals are received and approved by the State.

Nothing herein shall be construed to limit or preclude partial payments otherwise provided for by the contract. Neither deduction nor increase will be made in the lump sum

“Mobilization and Demobilization” item amount regardless of decreases or increases in the final total contract amount or for any other cause.

1.3 Pay Item

Item 1.0, “Mobilization and Demobilization”, per lump sum cannot be more than 10% of the TOTAL AMOUNT BID for the project.

2.0 CONSTRUCTION LAYOUT

2.1 Description

This item consists of furnishing, placing, and maintaining construction layout stakes, (based on the original baselines and/or control points in the plans), necessary for the proper performance of the work under this contract including borrow/waste areas. Construction limits must be clearly flagged, and Pre-Construction cross sections must be provided and approved prior to any disturbance or “unclassified excavation”. It shall further consist of determining the exact units of measure for payment. It also consists of checking and making any field adjustment to the plan alignment, grades and elevations as considered necessary by the Engineer. Additionally, this item shall also include the preparation of “As-Built”

Plans, including the Reclamation Plan and any others specifically requested by the State.

All “As-Built” Plans shall be provided for review and acceptance prior to the Final

Inspection Meeting.

This item will be paid according to the following schedule: 25% initial layout and LODs, 50% for layout throughout/end of construction, and 25% on the acceptance of as-builts.

This layout shall include location stakes and cut-fill lines marked on the stakes for each pre-manufactured or formed on site structures (manholes, drop inlets, headwalls, etc.). The layout shall also include centerline stakes with cut-fill lines for each channel and any areas of excavation and re-grade. The certified layout and cross-sections surveyed must be submitted to the State for approval prior to beginning construction for each item. Work shall be performed to the satisfaction of the State to be considered complete.

2.2 Materials

Conventional survey stakes, hubs, batter boards, flagging, templates, straightedges, and other devices necessary for laying out all parts of the work.

2.3 Construction Methods

The Contractor shall be responsible for the proper layout of the Work. The State will provide the Contractor with survey information regarding the baselines and the existing surface features shown on the Construction Drawings. The Contractor shall make all calculations involved and shall furnish and place all layout stakes. The Contractor is responsible to verify all surveying, measurements, estimates, or any other information provided by the State for accuracy.

The Contractor shall provide field forces and shall set all additional stakes as needed, such as offset stakes, reference point stakes, slope stakes, grade stakes, stakes for drainage, or other structures, supplementary benchmarks, and any other horizontal or vertical controls necessary to secure a correct layout of the Work, including the re-establishment of the survey and construction baselines (as necessary), as shown on the Construction Drawings.

The Contractor shall be responsible for assuring the layout staking work is in conformance to the lines, grades, elevations, dimensions, and locations shown on the Construction

Drawings, or as required by the Engineer. The Contractor shall furnish a copy of their survey records for review by the Engineer and for the State’s permanent file. These records shall be furnished as they are completed during the progress of the Work.

Any inspection or review of the Contractor's layout by the Engineer and the acceptance of all or any part of it shall not relieve the Contractor of their responsibility to secure the proper dimensions, grades, and elevations of the Work.

The Contractor shall exercise care in the preservation of stakes, monuments, and benchmarks, including existing property line markers, and shall have them reset at their expense if any are damaged, lost, displaced, or removed. The Contractor shall use competent personnel and suitable equipment for the layout work required and shall provide that it be done under the supervision of, or directed by, a Professional Surveyor registered in the State of West Virginia. As the survey is completed, the Professional Surveyor shall certify that the site layout is complete; this includes, at a minimum, all necessary grades (both cut and fill), location and grades of all ditches, and all cross-sections related to cut and fill where grade lines are necessary for construction and or billing. This layout shall include location stakes and cut-fill lines marked on the stakes for each pre-manufactured or formed on-site structures (manholes, drop inlets, headwalls, etc.). The layout shall also include centerline stake with cut-fill lines for each channel and any areas of excavation and re-grade.

The certified layout and cross-sections surveyed must be submitted to the State for approval prior to beginning construction for each item.

As-Built plans shall be provided to the State prior to the Final Invoicing. All work completed by the professional surveyor, registered in the state of West Virginia on as-built plans must be certified by said professional as to the completeness and accuracy of content on the plan submittal. The As-Builts shall be provided in two forms of electronic format in PDF and AutoCAD 2020 format or AML accepted later addition on either CD-ROM, DVD, or USB memory stick and one paper copy of the plans with the same size and scale as contained on the original plans.

The As-Builts shall include the following:

• Show all permanent Work in place, and any deviations from original plans.

• The preferred coordinate system and elevation datum by the Contractor need to be specified. The State has a preference for the US State Plane

Coordinates of 1983 West Virginia North Zone – SPCS83 Zone 4701 in feet, unless otherwise specified.

• Show all horizontal and vertical dimensions (including invert elevations) of all installed components (i.e., pipes, drop inlets, mine seals, drainage channels, splash pads, manholes, etc.), as well as surveyed locations of the installed structures. Any other items deemed necessary (provided in the contract) by the State shall be included in the As-Builts.

• Cut-fill sections shall have the area of the section marked by the section for easier calculation, if required.

• Have the lines on the plans shown in either color or line type to distinguish between the original plan lines, the contractor’s original survey lines and the final grade lines. This will apply for all cross-sections on the project, if required.

• All waste and borrow areas shall be shown and labeled.

• Revegetation that is paid for by acreage, shall be per plan view acreage and shall be shown on a separate AutoCAD layer. The enclosed areas shall not include any graveled surfaces, paved surfaces, roads, ponds, treatment components, all non-vegetated channels, buildings, etc. (non-vegetated areas are not to be included in the revegetation acreage calculation or

AutoCAD layer).

• In AutoCAD, the zero (0) layer shall not be used to draw on other than to insert blocks for future insertion on appropriate layer.

• As a standard, new baseline and final contours shall be provided with 2 feet minor contours and 10 feet major contours. Major contours shall have the elevation labeled. Contour Labels shall not break the contour line (setting in AutoCAD).

• Any control points shall be shown with coordinates and elevations labeled.

If the State has provided control points, the Contractor shall reference elevations and coordinates to them. If no control points were set, then new points shall be set and utilized.

• Any seep collectors, curtain drains, or other structures inaccessible after covering, shall be surveyed for location, prior to covering.

• Show total quantities for all items on the project. The format shall be in a tabular form (i.e., Bid Schedule or Summary of Quantities).

• Changes (deviations) should be on separate “Change” layer, not on the original layers from the original plan.

ITEMS TO BE IDENTIFIED AND LABELED

AUTOCAD LAYER

ITEMS REQUIRED?

☒ Baseline Survey after Clearing & Grubbing, if required YES

☒ Intermediate Surveys, if required YES

☒ Final Survey YES

☒ Revegetation YES

☐ Pipes, Valves, Manholes N/A

☐ Mine Seals, Bat Gates N/A

☐ Seep Collectors, Curtain Drains, Clean Outs N/A

☒ Drainage Channels & Ditches, Splash Pads, Culverts, Drop Inlets YES

☐ Ponds, Wetlands, Water Treatment Structures NO

☐ Sludge Pumps, Sludge Cells, Geo-Tube Pads, Sludge Valves NO

☒ Buildings, Residential / Commercial Structures, Concrete Pads YES

☐ Pump Vaults, Air Release Valves, Pump Line Connections NO

☒ Fencing around Structures and Property Lines YES

☒ Utilities (i.e., Overhead / Underground Electric, Gas, Water, Sewer) YES

☒ Buried Lines (i.e., Electric, Communication, Chemical, Water, Sewer) YES

☐ Gas Vents, Piezometers, Monitoring Wells, Core Drilling NO

☒ Roads, Driveways, Sidewalks YES

☒ Unforeseen Areas (i.e., Slips, Seeps, Subsidence Areas, Boreholes) YES

☐ Other, As Defined: NO

2.4 Method of Measurement and Basis of Payment

There shall be no measurement of the “Construction Layout” item, as it is a lump sum. Said lump sum bid cannot be more than 5% of the TOTAL AMOUNT BID for the project. The lump sum payment shall include furnishing, setting, maintaining, and resetting the stakes when necessary, and for furnishing all personnel, equipment, materials, and all incidentals thereto.

The lump sum payment also shall include the cost for providing the Engineer pre- and post-construction ground line cross-sections for all disturbed or re-graded areas, including borrow/waste areas and “As-Built”. All these activities shall be included within the lump sum bid for “Construction Layout”.

Neither deduction nor increase will be made in the lump sum “Construction Layout” item amount regardless of decreases or increases in the final total contract amount or for any other cause. This item will be paid according to the following schedule: 25% initial layout and LODs as outlined in these Specifications, 50% for layout throughout and at the end of construction, and 25% on the acceptance of As-Builts.

2.5 Pay Item

Item 2.0, “Construction Layout”, per lump sum cannot be more than 5% of the TOTAL

AMOUNT BID for the project.

3.0 QUALITY CONTROL

3.1 Description

This Work shall consist of testing for verification that the materials supplied, and the work performed are in accordance with these Specifications. Work shall be performed to the satisfaction of the State to be considered complete.

3.2 Materials

The Contractor shall submit a minimum of two (2) copies of shop drawings, catalog cuts and material certifications (as applicable) to the Engineer for all offsite materials to be incorporated into the Work. At least 1 copy submitted must be electronic. Written approval from the Engineer will be required prior to incorporation of these items into the Work.

The Contractor shall submit at least two (2) copies of the results of all tests conducted on in-situ material, concrete, and grout to be used in this project. At least 1 copy must be electronic.

Soil tests shall determine the optimal additives required for areas of soil disturbance to be fully re-vegetated as per Section 6.0 of this document. Normally, this includes – at a minimum – soil pH test results as well as available nutrients within the soil, including, at a minimum: nitrogen (N), phosphorus (P), potassium (K), calcium (Ca), magnesium (MG), and Sulfur (S). At a minimum, the soil testing report will recommend what soil amendments in which concentrations are ideal for regrowth. If problems with re-vegetation occur, additional, more specialized tests may be required to be performed at the Engineer’s discretion and the Contractor’s expense. All testing documentation shall be provided to the state prior to any revegetation work.

Limestone and Sandstone shall be subjected to a Sodium Sulfate test. All stone shall have a maximum weighted loss of twelve (12) percent when subjected to five (5) cycles of the

Sodium Sulfate Soundness Test – ASTM C88 (ASTM C88/C88M-24 Standard Test

Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate), as modified by the American Association of State Highway and Transportation Officials

(AASHTO) T-104. All Stone shall be commercially supplied and shall be tested for calcium carbonate.

Limestone shall be tested for calcium carbonate equivalency which must be 70% or greater and be certified as such.

Sandstone shall be certified to be non-acid producing. Sandstone to be sound, non-acid producing, durable, non-calcareous sandstone from a State approved source. Shale is not acceptable. The sandstone shall consist of particles of clean, hard, tough, durable rock, free from adherent coating. The State reserves the right to reject sandstone based on a visual inspection without waiting on testing results.

Note that the WVDOT DOH Standard Specifications for Roads and Bridges, 2023 Edition specify quality control and testing procedures that ARE REQUIRED for any applicable asphalt wearing coarse, tack coat, surface prep, etc. All asphalt work on this project shall be in accordance with Section 8.0 of these specifications.

Tests Required

Fill Compaction Testing for Backfill Material

Density

1 Lot of 5 tests per day (min) per engineer

Soil Test Varies As Needed

Material

Certification

Manufacturer Certification for all purchased materials

On or Before Delivery

Limestone Sodium Sulfate test, calcium carbonate equivalent

On or Before Delivery

Sandstone Certification that rock is non-acid producing and sodium sulfate test

On or Before Delivery

3.3 Construction Methods

The Contractor shall select an independent testing laboratory for testing. The laboratory shall be under the direct supervision of a Registered Professional Engineer or PhD. The laboratory must be approved by the State, prior to testing.

The Contractor shall furnish a certified technician to perform the required testing at the project site. The certified technician shall submit a copy of their certification, and a copy of that certification shall be submitted to State at the Pre-Construction Conference. The certified technician shall be responsible for chain of custody of any samples that leave the site.

Testing shall be performed as required by these Specifications and or as ordered by the

Engineer or State representative in writing. The Engineer will determine the locations and time of any testing herein specified and the need and extent of any testing in addition to that which is herein specified.

The Contractor shall be responsible for performing laboratory tests of the coal, mine refuse and spoil, and any natural soil to identify the compaction requirements for their use as fill and cover material, respectively. In addition, field density tests shall be performed in accordance with these Specifications. All test results shall be submitted to the Engineer for approval of compaction criteria prior to finalizing compacting the fill material and after fill material is placed to verify that the required compaction is obtained.

Only new and first-class materials, which conform to the requirements of these Specifications, shall be used unless specified otherwise. When requested by the State, the Contractor shall furnish a written statement of the origin, composition, and manufacturer of any or all materials

(manufactured or produced) that are to be used in the work. The sources of supply of each material used shall be approved by the Engineer before delivery is started. If, at any time, sources previously approved fail to produce materials acceptable to the State, the

Contractor shall furnish materials from other approved sources at no additional cost to the State.

3.4 Method of Measurement and Basis of Payment

There shall be no measurement of the “Quality Control” item as it is a lump sum. The quality control work done will be paid at the contract lump sum price bid for this item.

Said lump sum bid cannot be more than 3% of the TOTAL AMOUNT BID for the project.

Nothing herein shall be construed to limit or preclude partial payments on this item up to

100% of the quality control bid amount. Neither deduction nor increase will be made in the lump sum “Quality Control” item amount regardless of decreases or increases in the final total contract amount or for any other cause.

3.5 Pay Item

Item 3.0, “Quality Control”, per lump sum cannot be more than 3% of the TOTAL

AMOUNT BID for the project.

4.0 SITE PREPARATION

4.1 Description

Clearing and Grubbing - Work performed under this section shall include the removal and disposal of all trees, stumps, shrubs, and any other vegetation along with wood, debris, or garbage of any nature. This includes those areas specified below, shown on the Plans, and any other areas as approved by the State. This work shall also include the preservation from damage for all vegetation, utilities, or any other object not being specifically removed according to the Specifications and Plans. Additionally, this work shall include stripping and stockpiling topsoil from the construction area, keeping it separated from other stockpiled soil, and using the topsoil for soil cover and revegetation at the end of the construction.

Site Bridge Access – There is an existing bridge structure that allows access to the site from U.S. Route 40. This bridge is currently owned by the Ohio County Commission. If the contractor utilizes the existing bridge structure for access to the site during construction, they shall be responsible for entering into an agreement with the County.

The contractor shall have a structural evaluation by a registered WV Professional

Engineer performed on the structure based upon the proposed equipment loads that will utilize the bridge during construction and shall be responsible for any damages that occur and will be handled between the contractor and the County. This evaluation shall include a complete replacement cost for the structure, including design, permitting, etc., and all other costs, if it is damaged during construction. The Contractor shall have in place a bond on the bridge for $1,500,000 or the complete replacement cost from the evaluation of the structure, whichever is greater. If damages occur to the structure that are not rectified by the Contractor, then the bond shall be used to repair or replace the structure to a so acceptable condition as determined and approved in writing by the county and

WVDEP AML. The Contractor will accept all responsibility for any damage(s) or defect(s) related to the use of this existing bridge structure. The WVDEP will accept no responsibility or liability for any damage(s) or defect(s) related to the use of this existing bridge structure.

Alternate Site Access- The plans indicate an alternative access location and if the contractor decides to utilize this area for access, they shall be responsible for all design, permitting, material, installation, etc. necessary to construct this access based upon the proposed crossing method and equipment. All access roads and structures associated with this access location shall be temporary and shall be removed immediately following construction. All disturbed areas shall be reclaimed and revegetated to a condition equal to or better than existing as approved by the engineer.

Site Demolition - This Work shall consist of complete demolition and removal of such buildings, mining related structures, equipment and materials, existing ruins and foundation structures and existing AML structures and systems, as are specifically designated on the Plans for removal or encountered during construction, except for the demolition of the concrete silo. Demolished concrete and cinder block structures and foundation ruins may be disposed in the concrete waste area. All demolished concrete will be crushed to a size less than 24-inches and all reinforcement not completely embedded in any piece of concrete will be removed and disposed of off-site. Any steel or burned (if authorized) wood remnants must be removed from the site. All on-site garbage (as well as all other debris of any type and quantity), mining equipment, and metal structures encountered shall be removed from the site to an off-site disposal area in accordance with these Specifications to a Landfill approved by the State to accept the applicable waste type. Certified disposal weight tickets shall be provided to the WVDEP.

The contractor is advised to perform a thorough site reconnaissance to quantify all garbage designated for removal prior to submitting a bid.

Gravel Drive Rehabilitation - The Gravel Drive Rehabilitation roads shall be covered with a layer of Class 1, 1-1/2” Crusher Run Aggregate to restore – as needed – the gravel road to “as good as” or “better” condition than existed prior to construction. In areas that will not support the stone due to soft conditions, stabilization fabric will be required. Any regrading or resurfacing necessary to restore existing roads or driveways used during construction to a condition that is equal to or better than the condition encountered before construction activities, including partial roadway section overlays and re-blending of transitions into existing gravel roadway stone placement. Gravel Drive Rehabilitation shall be utilized as specified, and as required or approved by the Engineer.

Stabilization Fabric and Stone - Stabilization Fabric and Stabilization Stone shall be placed in areas that will not support the road construction due to soft conditions. The placement of stabilization fabric and stabilization stone shall be at the discretion of Engineer and approved prior.

Access Road Construction - Access roads constructed to gain access to, travel between, or otherwise required for equipment/vehicular site access shall be kept to a minimum and only constructed where necessary upon approval from the WVDEP, where applicable. If the

Contractor constructs such travel routes, they shall be reclaimed and revegetated according to Section 6 upon completion of the construction activities, as deemed necessary by the

WVDEP, with associated costs being incidental. Any additional access shall require the

Contractor to obtain written permission from the respective landowner. The existing access roads shall be maintained during construction (except when culvert, ditch and road construction are being performed), and shall be left in a condition equal to, or better than, the existing condition upon completion of construction.

Silo Demolition - The Contractor shall have a minimum of 5 years’ experience in large reinforced concrete structure demolition to be qualified for the demolition of the concrete silo. The contractor must provide proof of acceptable experience including but not limited to references with contact information, etc. The silo demolition may be completed by either mechanically dismantling the structure from the top down or by means of explosives. Contractor shall submit a demolition plan to the WVDEP for review and acceptance prior to beginning the demolition of the silo. Contractor shall follow all relative federal, state, and/or local regulations and safety requirements pertaining to the demolition of the structure. Any damage(s) or defect(s) related to construction activities associated with the silo demolition shall be the responsibility of the contractor. The

WVDEP will accept no responsibility or liability for any damage(s) or defect(s) related to construction activities associated with the silo demolition.

Asbestos Material Identification and Removal (if present) - This Work shall consist of a

Contractor-provided Competent Person – as defined by Title 29, Subtitle B, Chapter XVII, Part 1926 of the CFR Code – performing a thorough search of all existing structures on the project to ensure that there are no asbestos materials present. If any areas are suspected of containing asbestos, then an inspection would need to occur – at the Contractor’s expense – by a company possessing a valid, current Asbestos Contractor License in the State of West

Virginia. Each on-site representative of the company performing the asbestos survey or mitigation would need to be a Licensed Asbestos Contractor in the State of West Virginia.

If asbestos was found, an estimate for removal and proper disposal would need to be obtained by the Contractor and submitted for the Engineer’s approval. At that point, the

Contractor would be responsible to perform all notifications as required by all Federal and

State law – particularly NESHAP as outlined in Title 40, Chapter I, Subchapter C, Part 61, Subpart M of the CFR Code. No work would be allowed at the location of the asbestos until the removal process was completed. No asbestos mitigation or removal is anticipated for this Work – if the Contractor determines asbestos is present and subsequently receives a positive test for asbestos, a Change Order would be negotiated with the State for the proper mitigation to occur through the Contractor. All mitigation by the Contractor (or their Sub-

Contractor) would need to be in accordance with all Federal, State, and Local laws.

Materials and Equipment Storage - The Contractor shall obtain approval from the Engineer for proposed materials and equipment storage areas not designated prior to use. Refueling or fuel storage should not occur within 100ft of a wetland, water body, stream, or ditch leading into the same – see additional requirements for fuel storage in the “Spill

Containment Area” below. Areas utilized shall be restored to an “as good as” or “better” condition than existed prior to construction or shall otherwise be reclaimed as directed or approved by the Engineer.

Any additional access shall require the Contractor to obtain written permission from the

State. The existing access roads shall be maintained during construction. Any regrading, stone, fabric, equipment, and any other labor or materials necessary for the construction of the additional access roads shall be incidental to the cost of the work described herein.

Note that the State has the option of leaving stoned laydown areas, stabilized construction entrances, and roads intact permanently at the State’s discretion.

4.2 Materials

Contractor to supply all equipment and construction materials required for clearing, grubbing, grading, stone placement, compaction, and any other installations or demolitions that are a part of the Work.

Contractor to supply all equipment and construction materials required for asbestos material identification and removal (if present – this is not anticipated).

Contractor to supply all equipment and construction materials required for materials and equipment storage, access road, spill containment area, and any other installations or demolitions that are a part of the Work.

Stone to be placed for Gravel Drive Rehabilitation shall conform to the requirements for

Class 1, 1-1/2” Crusher Run Aggregate. Stone to be placed for Equipment/Storage Area and the Concrete Waste Area Cap Material, shall conform to the requirements for

AASHTO #1 and 1 ½” Crusher Run. Stone to be placed for Pump Station Backfill shall conform to the requirements D50 = 6-inch RIPRAP and 3” Crusher Run Aggregate. All stone shall meet the gradation and quality requirements in Table 704.6.2A in Section 704 of the WVDOT DOH Standard Specifications Roads and Bridges, Adopted 2023. Stone to meet same certifications, testing requirements, and documentation provided to the State as “Limestone” as defined in these Specifications. Separation fabric, if required, shall be non-woven and at a minimum, meet the applicable requirements of AASHTO M288, Section 7, Class 2, such as Mirafi 160N, US Fabrics US 160NW, or approved equal.

“Stabilization Fabric” shall be woven and meet the requirements of Mirafi RS380i or approved equal. If deemed necessary as directed by the Engineer, “Road Stabilization

Stone” shall be utilized and shall conform to the requirements of AASHTO #1 Aggregate or 3 to 6-inch aggregate as approved by the Engineer.

Aggregate shall consist of sound, non-acid producing, durable limestone or sandstone from a WVDEP approved source. Shale is not acceptable. All rock riprap used throughout the project site shall consist of commercially purchased calcareous stone (except as noted otherwise) meeting the following requirements. The rock riprap shall have a maximum weighted loss of thirty percent when subjected to five (5) cycles of the Sodium Sulfate

Soundness Test – ASTM C88 (ASTM C88-05 Standard Test Method for Soundness of

Aggregates by Use of Sodium Sulfate or Magnesium Sulfate), as modified by the American

Association of State Highway and Transportation Officials (AASHTO) T-104. The use of on-site rock materials for riprap must have approval from the WVDEP and meet all standards for the riprap installation. The use of on-site stone shall be determined by the

Engineer. Limestone riprap stone required for the drainage channels shall be commercially supplied and have a calcium carbonate equivalency of 70% or greater.

4.3 Construction Methods

The specific areas to be cleared and grubbed are as shown on the Plans and are generally described as, but not limited to, those specific areas of demolition, rubble waste, laydown area, etc.

The Contractor shall clear the site within the limits of the areas to be regraded. The State shall exercise control over clearing and shall designate all trees, plants, and other objects to be removed or to remain.

Clearing and grubbing shall be completed prior to initiation of earthwork operations and only to the extent necessary to complete the work. The Contractor shall confine operations strictly to required areas. If the Contractor clears and grubs beyond the required areas, whether knowingly or accidentally, Contractor shall, at its own expense, replant and otherwise restore all areas outside the limit lines to a condition equal to or exceeding that existing prior to start of Work.

All timber to be cut shall be cut prior to grubbing operations. Timber shall be topped with the branches removed and stacked and stockpiled in an appropriate manner in an accessible location approved by the State on the property from which it was cut.