Specifications.pdf
PDF 247 KB Posted
- Attached to
- Concrete Federal contract opportunity
- Solicitation number
- 140P6426Q0070
About this file
This document is a Specifications file for a concrete supply contract for Canyonlands National Park in Moab, Utah, dated April 27, 2026, with PMIS# 339016.
The National Park Service requires supply and delivery of concrete to the Grand View Point Area in the Island in the Sky District for use in constructing a sidewalk, curb along an expanded parking lot, and an accessible walkway to toilet facilities. The vendor must deliver a total of 120 cubic yards of concrete: 110 cubic yards of Davis 5084 integral color concrete and 10 cubic yards of grey concrete. The concrete must meet specific technical requirements including a minimum 28-day compressive strength of 4,000 psi, air entrainment of 5% ± 1.5%, water-cement ratio between 0.35 and 0.45, slump of 4 to 6 inches, maximum aggregate size of 1 inch, and temperature not exceeding 90°F. Type I or II cement per ASTM C150 is required. Concrete delivery trucks must be a minimum of 10 cubic yards with front discharge chutes only; rear discharge chutes are prohibited.
The contract specifies a 240-day period of performance from the award effective date, with deliveries not to exceed 15 total trips scheduled by the park with minimum 4-day notification. Delivery is FOB destination with costs included in the per-cubic-yard pricing. The vendor must allow 6 minutes per cubic yard for unloading at no cost, with documented hourly rates applicable for excess time not to exceed 120 minutes total. Optional concrete admixtures (ice, delay set, fly ash, hot water, calcium chloride, and fiber mesh) may be required for weather conditions at the park's discretion, with total additive usage capped at $6,225 without Contracting Officer approval. The park will handle all concrete forming, placing, and finishing. Standard manufacturer's one-year warranty on concrete materials is required. Submittals must include electronic cut sheets in PDF format documenting product specifications and 28-day compressive strength certification. The delivery location is approximately 45 miles from Moab, Utah.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6426Q0070_Amd_0001.pdf | ||
| Clause_Package_-_Revised_0001.pdf | ||
| Sol_140P6426Q0070.pdf | ||
| Price_Schedule.xlsx | XLSX spreadsheet | |
| Price_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONCRETE SUPPLY PMIS# 339016
CANYONLANDS NATIONAL PARK 1 | P a g e
Canyonlands National Park Moab, UT
Specifications:
Concrete Supply
DATED:
April 27th, 2026
NATIONAL PARK
SERVICE INTERIOR
REGIONS 6/7/8
CANYONLANDS NATIONAL PARK 2 | P a g e
SPECIFICATIONS
1. DESCRIPTION:
A. Synopsis. Supply and deliver concrete to the Grand View Point Area in the Island in the
Sky District located within Canyonlands National Park. The Vendor shall also provide various concrete admixtures as requested and listed in this specification. The quantities of the admixtures will be proportional to the amount of concrete that is ordered.
B. Concrete supplies are needed for the sidewalk and curb along the expanded parking lot and for the accessible walkway linking to the toilets.
C. This is for the delivery of Concrete Supplies only. NPS staff will be responsible for forming, placing and finishing all concrete supplied under this requirement.
2. SITE CONDITIONS:
A. Onsite Services:
1. Park provided Phones are not available to the Vendor.
2. Restrooms are available for Vendor use at the Visitor Center, the Grand View
Point area and at various locations within the Park.
B. Road access: Asphalt paved roadways to site. Heavy visitor traffic is possible at times.
3. DELIVERY DAYS AND HOURS:
A. Concrete delivery shall be as scheduled by the Park. No deliveries can be made during weekends or Federal Holidays.
B. All deliveries shall be coordinated with the Project Crew at (435) 719-2157 throughout the scheduling and delivery process.
C. Park shall provide vendor minimum of 4 days notification prior to delivery date.
CANYONLANDS NATIONAL PARK 3 | P a g e
4. DELIVERY LOCATION:
Delivery location is at the Island in the Sky District, 10 miles north on U.S. Highway 191 from Moab, Utah and then southwest 22 miles on Route 313.
1. Grand View Point Area is located approximately 45 miles from Moab, UT.
The delivery location is approximately 13 miles from the entrance station using Grand View Point Drive. Travel south 6 miles on the Drive and continue south past Mesa Arch for 6 more miles. GPS coordinates: latitude: 38.311404°, longitude: -109.856799°. Attachment A: location map.
5. PERIOD OF PERFORMANCE:
A. The period of performance is 240 days after contract Award effective date.
6. SUBMITTALS:
A. Submittals. Provide electronic cut sheets, preferably in PDF format, that document that the concrete mixture and associated admixture products meet the requirements of 2.1 Products and 1.1D Warranty. Provide certification of competency for manufacturer’s concrete mixture 28-day compressive strength. This information must be included with the quote, even if an approved product is being supplied.
7. PRODUCTS SPECIFICATIONS:
7.1 - Concrete Requirements:
A. Concrete Truck: The concrete supply truck shall be a minimum 10 cubic yard (CY) truck.
The concrete truck shall have a front discharge chute that can be controlled by the driver.
Rear discharge chutes will not be allowed.
B. Measurement: Products will be measured and paid according to the certified weigh tickets converted to cubic yards. Payment will be made on the actual quantity of concrete delivered.
C. The Concrete shall be grey or the integral color concrete. The color shall be Davis 5084.
Other brands of similar color may be used. Color shall be added to the mix design at 12 lbs. of color per cubic yard of concrete. Quantities: Colored: 110 CY, Grey: 10 CY.
D. Air Entrainment: 5% ± 1.5%. ASTM C260 specification.
E. 28 Day Compressive Strength: ≥ 4,000 psi mix design. ASTM C873 specification.
F. Cement: Type I or II. ASTM C150 specification.
CANYONLANDS NATIONAL PARK 4 | P a g e
G. Water-Cement Ratio: 0.35 ≤ W/C ≤ 0.45.
H. Slump at Maximum W/C Ratio: 4 to 6 inches. ASTM C143 specification.
I. Maximum Aggregate Size: 1 inch. ASTM C33 specification.
J. Temperature: ≤ 90°F. ASTM C1094 specification.
7.1 - Requirements for Optional Concrete Admixtures for Hot or Cold Weather:
A. Concrete may require additional admixtures to allow hot or cold weather placement.
These additives are ice, hot water, calcium chloride, fly ash, microfibers and/or delay set up to 2 hours.
1. Ice: Add ice at 15 lbs. per cubic yard if requested by the Park.
2. Delay Set: Add delay set if requested by the Park for delay up to 2 hours. ASTM C1017 specification. The Park may order less delay time but will pay for 2 hours.
3. Fly Ash: Option if requested by the Park for substituting 10-25% of required cement amount with fly ash by weight. ASTM A618 specification.
4. Hot Water: Substitute Hot Water in Mix Design for cold weather concrete.
5. Calcium Chloride: 0.5% to 2.0% if requested.
6. Fiber Mesh: Option if requested for microfibers normally added at 1.5lbs/ft3.
B. Due to weather variability, the use of these additives may be necessary. The Park will determine if these additives are required on the day that the concrete order is placed.
C. Additional concrete admixtures are optional. Payment will be made according to actual usage and will be based on the quoted price per Cubic Yard for each additive as established in the Price Schedule submitted with quote. Total additive usage shall not exceed $6,225.00 dollars total without approval from Contracting Officer.
CANYONLANDS NATIONAL PARK 5 | P a g e
8. CONCRETE DELIVERY REQUIREMENTS:
A. NPS will schedule the exact time and date of delivery with the Vendor.
B. Concrete delivery shall not exceed 15 total delivery trips.
C. Delivery is FOB destination. Delivery cost shall be included in pricing for each Cubic Yard of concrete.
D. Vendor shall coordinate delivery with the Park to the areas specified by the park at the Grand View Point Area location.
E. The Park will form, place, and finish all delivered concrete.
F. The Vendor shall allow 6 minutes per cubic yard unloading time with no additional costs.
The Vendor may charge the Park for unloading time in excess of 6 minutes per cubic yard, at the Vendor’s documented hourly rate as established on the Price Schedule submitted with quote. Total excess time shall not exceed 120 minutes total without approval from Contracting Officer.
G. The Park will provide an area for washing out the truck drum after delivery at the site.
9. SAFETY:
A. The work site shall always be maintained to protect visitor, employee and Vendor safety.
10. WARRANTY:
A. Standard manufacturer’s one year warranty on concrete materials.
| 1. DESCRIPTION: |
| A. Synopsis. Supply and deliver concrete to the Grand View Point Area in the Island in the Sky District located within Canyonlands National Park. The Vendor shall also provide various concrete admixtures as requested and listed in this specification... |
| 2. SITE CONDITIONS: |
| 6. SUBMITTALS: |