Specifications.pdf
PDF 1 MB Posted
- Solicitation number
- 140P5426R0002
About this file
This is a Project Specifications document for the National Park Service's replace roofs and paint building exteriors project at Pine Island Maintenance Yard in Everglades National Park (PMIS No. 329159). The project encompasses eight buildings requiring roofing replacement, exterior painting, and selective structural repairs. The roofing work includes removal of existing materials, replacement of deteriorated sheathing (approximately 25% of roof square footage) and trim (approximately 25% of perimeter linear feet), installation of 1-inch tapered insulation with coverboard, 2-ply modified bitumen roofing systems with base and cap sheets, seamless gutters and downspouts, and reinstallation of appurtenances. Building 116 requires special attention with removal of an existing barn door, construction of a fully enclosed wall compliant with building codes, and repair of adjacent walls addressing multiple leaks. All exterior building surfaces, including soffits, fascia, and trim, must be prepared and painted to match existing finishes. Building 113 features a standing seam metal roof, while buildings 114, 115, 116, 140, 158, 164, and 186 all utilize 2-ply modified bitumen roofing systems. The specifications include comprehensive requirements for quality assurance, submittals, project management and coordination, construction schedules using Critical Path Method (CPM), safety protocols, historic preservation procedures for contributing properties, temporary facilities and controls, and closeout procedures including warranties and maintenance manuals.
The specifications establish detailed execution standards across 26 divisions covering general requirements, site construction, metals, wood and composite materials, thermal and moisture protection, finishes, electrical systems, and related work. Key requirements include submittal procedures with specific forms (CM-16 transmittal forms), pre-construction conferences, weekly progress meetings with schedule updates, coordination with the National Park Service to minimize disruptions (with 72 hours' notice for activities affecting operations), and compliance with environmental regulations including waste management with a 60% diversion goal from landfills. All roofing work must comply with manufacturer specifications and include 20-year warranties on materials and 2-year warranties on installation. Contractors must maintain comprehensive documentation including project record drawings, photographic evidence, operation and maintenance manuals, warranties, and certificates of insurance. The project emphasizes historic preservation treatment procedures for buildings with contributing historic status, requiring specialized expertise and documentation of all repair methodologies and material selections.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Specifications
National Park Service
Replace Roofs and Paint Building Exteriors - Pine Island Maintenance Yard
EVERGLADES NATIONAL PARK
PMIS NO: 329159
Date: May 2, 2025
Table of Contents 000110 - 1
Everglades National Park (EVER) PMIS: 329159 Replace Roofs and Paint Building Exteriors–P.I Maintenance Yard
TABLE OF CONTENTS
SECTION TITLE
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY 1 - 3
013100 PROJECT MANAGEMENT AND COORDINATION 1 - 9
013216 CONSTRUCTION SCHEDULE 1 - 10
013233 PHOTO DOCUMENTATION 1 - 2
013300 SUBMITTAL PROCEDURES 1 - 6
013523 SAFETY REQUIREMENTS 1 - 5
013591 HISTORIC PRESERVATION TREATMENT PROCEDURES 1 - 8
015000 TEMPORARY FACILITIES AND CONTROLS 1 - 4
016000 PRODUCT REQUIREMENTS 1 - 4
017300 EXECUTION 1 - 5
017329 CUTTING AND PATCHING 1 - 4
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 1 - 8
017700 CLOSEOUT PROCEDURES 1 - 5
DIVISION 02 - SITE CONSTRUCTION
024119 SELECTIVE DEMOLITION 1 - 5
DIVISION 05 METALS
053000 METAL DECKING 1 - 3
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061053 MISCELLANEOUS ROUGH CARPENTRY 1 - 3
061600 SHEATHING 1 - 3
061920 PREFABRICATED WOOD TRUSSES 1 - 4
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
070150 PREPARATION FOR REROOFING 1 - 4
072100 THERMAL INSULATION 1 - 3
074113 STANDING SEAM METAL ROOF PANELS 1 - 10
074116 FORMED METAL ROOF PANELS 1 - 6
074646 FIBER-CEMENT SIDING Hardy Board 1 - 3
075216 SBS-MODIFED BITUMINOUS MEMBRANE ROOFING 1 - 14
076200 SHEET METAL FLASHING AND TRIM 1 - 8
079200 JOINT SEALANTS 1 - 4
Table of Contents 000110 - 2
Everglades National Park (EVER)
TABLE OF CONTENTS
SECTION TITLE
DIVISION 09 - FINISHES
092400 CEMENT PLASTERING 1 - 4
092900 GYPSUM BOARD 1 - 2
099100 PAINTING 1 - 7
DIVISION 26 - ELECTRICAL
260519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 1 - 7
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEM 1 - 3
264113 LIGHTNING PROTECTION FOR STRUCTURES 1 - 3
265619 LED EXTERIOR LIGHTING 1 - 6
APPENDICIES
DRAWINGS
END OF TABLE OF CONTENTS
Everglades National Park (EVER)
Paint Building Exteriors–P.I Maintenance Yard
Summary 011000 - 3
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Use of premises.
4. Work restrictions.
5. Closeout procedures.
1.2 PROJECT INFORMATION
A. Project Identification:
1. Project Name: Replace Roofs and Paint Building Exteriors - Pine Island
Maintenance Yard
2. Project Number: PMIS 329159.
3. Project Region: Everglades National Park, Homestead, Florida.
B. Owner: The United States of America, as represented by the U. S. Department of the Interior, National Park Service, Everglades National Park referred to in the Specifications as the Owner.
1. Contracting Officer: A Contracting Officer (CO) will represent the Owner with respect to the Contract.
a. The Contracting Officer may delegate certain administrative and technical responsibilities to a Contracting Officer’s Representative (COR).
C. Architect-Engineer: N/A or TBD
D. This project will be solicited as a single prime contract.
1. Contractor: TBD
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. This project consists of replacing roofs that have exceeded their useful lifespan for buildings within the maintenance yard at Everglades National Park Pine. The Work is defined by the Contract Documents and, in general, includes the following:
B.
1. Itemized roof shop drawings per structure
2. Remove existing roofing material
3. Replace deteriorated sheathing/deck boards (approx. 25% of roof sqft)
4. Replace deteriorated trim (approx.25% of perimeter linear feet)
5. Replace deteriorated fascia (approx.25% of perimeter linear feet)
6. Install 1" Tapered Insulation and ½” coverboard (For 2Ply Modified Bitumen Roof)
Paint Building Exteriors–P.I Maintenance Yard
011000 - 4
7. Install 2-ply modified bitumen roofing system, including base and cap sheets, in strict accordance with the manufacturer's published guidelines, local building codes, and relevant project requirements to ensure system integrity and warranty compliance.
8. Seamless Gutters and Downspouts, 4-inch, 20 gauge
9. Reinstall appurtenances and paint all soffit, fascia and trim
10. Building 116 - Pine Island Storage Bay/AC/Carpenter:
• Remove the existing barn door and construct a fully enclosed wall in compliance with applicable building codes. Ensure that both interior and exterior finishes match existing.
• Repair the adjacent wall as specified in the drawings, addressing multiple leaks. All repairs shall be completed to meet industry standards and match existing finishes.
11. Prepare and paint all exterior building surfaces, including soffits, fascia, and trim, in accordance with specified coating systems (match existing)
Pine Island Maintenance Yard
Building Roof Type SQFT
* Contractor to field verify
Perimeter Historic Status
1 113 Pine Island IT Telecom
Standing Seam Metal
1,643 SQFT 177 LF Contributing
2 114 Pine Island Supply Building
2plyModified Bitumen
3,652 SQFT 274 LF Contributing
3 115 Pine Island 2plyModified 6,292.75 380.5 LF Contributing
Paint Building Exteriors–P.I Maintenance Yard
011000 - 5
Maintenance Office Bitumen SQFT
4 116 Pine Island storage Bay/AC/Carpenter
2plyModified Bitumen
5,710.5 SQFT 337 LF Contributing
5 140 Pine Island Storage Building
2plyModified Bitumen
5,710.5 SQFT 337 LF Contributing
6 158 Pine Island Generator Building
2plyModified Bitumen
266 SQFT 66 LF Contributing
7 164 Pine Island Ranger Station
2plyModified Bitumen
6,543.75
SQFT
452 LF Contributing
8 186 FPMA Building (The Association)
2plyModified Bitumen
4,555.5 SQFT 297 LF Non Contributing
*Contributing: A building, structure, or site within a historic district that adds to the district’s overall historical significance. While it may not be individually eligible for the National Register of Historic Places (NRHP), it plays a role in maintaining the district’s character and historical integrity. Contributing properties help define the district’s period of significance and architectural cohesion.
C. All work must be coordinated with the Contracting Officer. All work performed will be subject to requirements of the Contracting Officer to minimize disruptions.
D. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 USE OF PREMISES
A. General: Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits.
B. Limits on Use of Site: Limit use of Project site to Work in areas designated by the Contracting Officer. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Revegetate site damaged by trucks or heavy equipment during construction operations, including staging.
1.5 WORK RESTRICTIONS
A. On-Site Work Hours: Limit work to normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated.
1. A written request for permission to work outside of these hours must be submitted to the Contracting Officer at least five working days prior to the date the contractor desires to deviate from the normal hours.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated.
1. The contractor shall notify the Contracting Officer not less than two days in advance of proposed utility interruptions.
Paint Building Exteriors–P.I Maintenance Yard
011000 - 6
2. Do not proceed with utility interruptions without Contracting Officer’s written permission. The maximum permissible outage time for proposed utility interruptions is two hours unless a greater outage time (not to exceed four hours) is required for necessary inspections and utility service restoration and is acceptable to the Contracting Officer.
1.6 CLOSEOUT PROCEDURES
A. Submit the items specified herein prior to application for final payment.
B. Maintenance Manuals: Assemble operation and maintenance data and copies of warranties into manuals, organized by system components as appropriate and using specification numbers where applicable.
1. Directory: Names, addresses, telephone numbers, of all design and construction entities, including subcontractors and suppliers, with names of products supplied.
a. Record Drawings: Bound into manuals, folded to size of binder. Also provide updated CAD files demonstrating the as-built construction.
b. Product Listing: Manufacturer’s brand name and data for each major product actually installed, in alphabetical order by generic product name.
c. Warranties: Originals, bound separately. Mount a framed copy at the main access point to each applicable roof area.
2. Roofing system manufacturer’s inspection reports.
3. Proof of Warranty Payment: Provide documentation showing that the roof warranty has been paid in full.
C. Provide electronic copies (two thumb drives) to the Contracting Officer’s Representative
(COR).
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
Project Management and Coordination 013100 - 1
Everglades National Park (EVER)
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 013216 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
013100 - 2
Everglades National Park (EVER)
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements.
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.3 SUBMITTALS
A. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre-Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or
013100 - 3
Everglades National Park (EVER) interpretation of Contract Documents, Contractor shall prepare and submit an RFI.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts
Contract Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product
Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract
Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
013100 - 4
Everglades National Park (EVER)
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. NPS Final Accessibility Inspection
20. Environmental requirements
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Value engineering
26. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Meeting agenda will include:
013100 - 5
Everglades National Park (EVER)
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method
(CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting.
Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
013100 - 6
Everglades National Park (EVER)
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
6. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
7. Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
1.6 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
1. Electrical Utility Hookup.
2. Construction trailer, Utilities hookup permit.
3. Stormwater Pollution Prevention Permit.
C. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
013100 - 7
Everglades National Park (EVER)
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Send permits to COR when permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100
Construction Schedule 013216 - 1
Everglades National Park (EVER)
SECTION 013216 - CONSTRUCTION SCHEDULE
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
013216 - 2
Everglades National Park (EVER)
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
A. Electronic Copies: Schedules and reports shall be emailed in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit three paper copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data. Provide two paper copies.
F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit two paper copies of a Time Impact Analysis.
013216 - 3
Everglades National Park (EVER)
1.4 QUALITY ASSURANCE
A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:
1. Verify availability of qualified personnel needed to develop and update schedule.
2. Discuss constraints, including phasing, interim milestones and partial
Government occupancy/substantial completions.
3. Review delivery dates for Government-furnished products.
4. Review schedule for work of separate Government contracts.
5. Review time required for review of submittals and re-submittals and RFI’s.
6. Review requirements for tests and inspections by independent testing and inspecting agencies.
7. Review time required for completion and startup procedures.
8. Review time required for obtaining and activating permits.
9. Review and finalize list of construction activities to be included in schedule.
10. Review baseline schedule comments, resolve issues and progress on incorporating them.
11. Review procedures for updating schedule.
12. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
013216 - 4
Everglades National Park (EVER)
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
013216 - 5
Everglades National Park (EVER)
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the Critical Path Method schedule within the limitations of the Contract Time.
4. Show sequence and interdependence of activities required for completion of work. Ensure work sequences are logical and Construction Baseline Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include personnel by labor category and equipment type and capacity proposed to complete the activity in duration shown.
6. Consider seasonal weather conditions in planning and scheduling work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of work within contract time.
7. Time Frame: Proposed duration assigned to each activity shall be Contractor's best estimate of time required to complete activity considering the scope and resources planned for activity.
a. An early finish date may be shown but the late finish date shall be same date as last day of contract period. An early completion schedule shall contain:
1) Insert an activity titled "Project Float" as a successor to last activity in early project completion schedule network.
2) Add a milestone titled "Contract End Date" as a successor to the activity "Project Float".
3) Add duration to the activity "Project Float" as required so the milestone "Contract End Date" equals the last day of Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include calendar based on a 7-day week to be used on activities based on calendar days. Apply this calendar to administrative tasks or other tasks not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include calendar based on planned work week for the project. Include Federal Holidays, weekends, and non-workdays indicated in contract documents. Apply this calendar to activities not anticipated to be affected by weather.
3) Weather Calendar: Utilize Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to Contracting Officer. Apply this calendar to activities anticipated to be affected by weather.
013216 - 6
Everglades National Park (EVER)
e. Activity Duration: Define so no activity is longer than 15 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities can include submittals, approvals, purchasing, fabrication, and delivery.
g. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
h. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Specification 017700 "Closeout Procedures.")
8. Constraints: Include constraints and work restrictions indicated in Contract Documents and as follows in schedule and show how the sequence of Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show effect of the following on the schedule:
1) Coordination with existing construction
2) Limitations of continued occupancies
3) Uninterruptible services
4) Partial occupancy before Substantial Completion
5) Use of premises restrictions
6) Provisions for future construction
7) Seasonal variations
8) Environmental control
9) Permit provisions
d. Work Stages: Indicate important stages of construction for each major portion of the Work.
1) Subcontract awards
2) Submittals
3) Purchases
4) Mockups
5) Fabrication
6) Sample testing
7) Deliveries
8) Installation
9) Tests and inspections
10) Adjusting
11) Curing
9. Milestones: Include milestones indicated in Contract Documents in schedule, including, but not limited to, Notice to Proceed, Substantial Completion.
013216 - 7
Everglades National Park (EVER)
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receiving Contractor's proposed Construction Baseline Schedule, Contracting Officer shall review initial Construction Baseline Schedule.
2. Within seven calendar days after review, Contractor shall revise and resubmit Construction Baseline Schedule in accordance with comments presented from review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by Contractor or Contracting Officer, shall be corrected by Contractor within seven calendar days and shall not affect contract period.
4. Upon acceptance of the Construction Baseline Schedule, Contracting Officer saves schedule as a baseline and updates on a monthly basis. Construction schedule update will be used to evaluate Contractor's monthly applications for payment based upon information developed at monthly Construction Schedule update meeting.
D. Cost Correlation: In the heading of the schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of Work performed as of dates used to prepare payment requests.
1. Contractor shall assign cost to construction activities on Construction Baseline Schedule. Costs shall not be assigned to submittal activities unless specified otherwise but may, with Contracting Officer’s approval, be assigned to fabrication and delivery activities. Costs shall be included for testing and commissioning activities, operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training (if applicable).
2. Each activity cost shall reflect an accurate value based on the Contract Price Schedule.
3. Total cost assigned to activities shall equal total Contract Price.
E. Recovery Schedule: When periodic schedule update indicates Work is 14 or more calendar days behind current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule shall also be submitted. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery shall be accomplished.
F. Computer Software: Prepare schedules using a program developed specifically to manage construction schedules.
1. Use Microsoft Project or Primavera, for (Windows 7 and newer.)
013216 - 8
Everglades National Park (EVER)
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a 2 week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize look-ahead schedule to facilitate and take notes on discussions held during progress meeting.
B. Monthly Schedule Updates:
1. General: Update Construction Schedule on monthly basis to reflect construction progress and activities throughout entire contract period and until project substantial completion. The status date of each schedule update shall be the 7th day preceding the progress payment request date.
2. Procedure: Contractor shall meet with Contracting Officer each month at Construction Schedule update meeting to review progress made through the status date of the Construction Schedule update, including dates activities were started or completed and percentage of work completed on each activity started or completed.
3. Reports: Concurrent schedule revisions, prepare tabulated reports showing:
a. Identification of activities that have changed
b. Changes in early and late start dates
c. Changes in early and late finish dates
d. Changes in activity durations in workdays
e. Changes in the critical path
f. Changes in total float or slack time
g. Changes in the Contract Time
4. Narrative: Report shall include a brief description of actual progress made during update period; actual and potential delaying activities; impediments to progress;
issues related to inclement weather; progress toward established milestones and project float. Report shall include a brief description of work anticipated to be performed in the next month. Minor revisions to the schedule should be identified for evaluation and acceptance or rejection.
5. As Work progresses, indicate Actual Completion percentage for each activity.
6. If schedule update shows a late finish date after contract completion date, include:
a. Known delays
b. Actions to get back on schedule
c. Pending modifications
d. Impediments or constraints affecting progress
7. Progress Payments: Monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made. If Contractor fails to provide schedule updates or revisions, a portion of the monthly payment may be retained until corrections have been made.
013216 - 9
Everglades National Park (EVER)
C. Distribution: Distribute copies of accepted schedule to Contracting Officer, Contracting Officers Representative, Construction Management Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to same parties and post in same locations. Delete parties from distribution when they have completed their assigned portion of the Work.
D. Construction Schedule Revisions:
1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents actual prosecution and progress of the work, Contracting Officer will request, and Contractor shall submit, a revision to the Construction Schedule. Contractor may also request reasonable revisions to currently accepted Construction Schedule in event the Contractor's planning for the work is revised. If Contractor desires to make changes, Contractor shall notify Contracting Officer in writing, stating reason for proposed revision. Accepted revisions shall be incorporated into currently accepted Construction Schedule for next monthly schedule update.
2. Procedure: If revision to currently accepted Construction Schedule is contemplated, Contractor or Contracting Officer shall advise the other in writing at least seven calendar days prior to next monthly schedule update meeting, describing revision and reasons for the revision. Government-requested revisions will be presented in writing to the Contractor, who shall respond in writing within seven calendar days.
3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing:
a. Identification of activities changed
b. Changes in early and late start dates
c. Changes in early and late finish dates
d. Changes in activity durations in workdays
e. Changes in critical path
f. Changes in total float or slack time
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS
AND CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays experienced, or Contractor desires to revise currently accepted Construction Schedule, Contractor shall submit to Contracting Officer a written time impact analysis illustrating the influence of modification, change, delay, or Contractor request on contract time.
013216 - 10
Everglades National Park (EVER)
2. Time Extensions: Activity delays, resulting in a late completion date projection, shall not automatically mean an extension of contract time is warranted or due to Contractor. It is possible a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in absorbing a part of available total float that may exist within an activity chain of the Schedule, not causing any effect on contract time. Time extensions will be granted in accordance with terms of contract.
3. Extension of contract time will be granted only to the extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
4. Procedure: Each time impact analysis shall be submitted within time period stated in a request for proposal, or time period designated under the clauses entitled Changes or Default. In cases where Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, time impact analysis shall be incorporated into currently accepted Construction Schedule at next monthly schedule update.
5. Contract Modifications: Prepare time-impact analysis
END OF SECTION 013216
Photo Documentation 013233 - 1
Everglades National Park (EVER)
SECTION 013233 - PHOTO DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for:
1. Existing condition images
2. Periodic construction images
B. See Section 017700 "Closeout Procedures" for a complete listing of closeout documents.
1.2 SUBMITTALS
A. Construction Images: Submit images electronically within seven days of taking the image. Include:
1. Date, time and number (sequentially number all images) in filename.
2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
3. Submit digital images exactly as originally recorded in digital camera, without alteration, or modifications using image-editing software.
B. Closeout: Submit complete set of digital image electronic files as a Project Record Document. Submit on Digital Video Disc (DVD).
1. Provide index as separate file on Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
2. Submit images that have the same aspect ratio as the sensor, un-cropped.
2.1 FORMAT REQUIREMENTS
A. Media: DVD-R Archival Gold
B. Media Labels: Archival DVD labeling markers, archival labels, or direct print.
C. Images: Provide sRGB (standard Red Green Blue) color images in JPEG (Joint Photographic Experts Group) format. Minimum sensor size of 8 megapixels, and at image resolution of not less than 3200 by 2400, and 300 dpi (dots per inch).
Photo Documentation 013233 - 2
Everglades National Park (EVER)
3.1 CONSTRUCTION IMAGES
A. General: Take digital images using the maximum range of depth of field, in-focus, to clearly show the Work. No blurry or out-of-focus areas accepted.
1. Maintain index with each set of Construction images and identify the number, date, time, and description for each.
2. Maintain one set of images accessible in field office at Project site available for reference.
B. Existing Condition Images: Before starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points.
1. Flag construction limits before recording construction images.
2. Take eight separate images to show existing conditions adjacent to property before starting Work.
3. Take eight separate images of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
C. Periodic Construction Images: Take 12 color digital images monthly, coinciding with cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last images were taken.
D. Additional Images: Contracting Officer may issue requests for additional images.
1. Three days advance, where feasible.
2. In emergency situations, take additional images within 24 hours of request.
3. Additional images include, but are not limited to:
a. Immediate follow-up when on-site events result in construction damage or losses.
b. Fabrication locations away from Project site.
c. Substantial Completion of a major phase or component of Work.
d. Extra record images at time of final acceptance.
END OF SECTION 013233
Submittal Procedures 013300 - 1
Everglades National Park (EVER)
SECTION 013300 - SUBMITTAL PROCEDURES
1.1 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that requires Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the
Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittal List: Provide submittals for review for every product. The requirements of the individual Specification Sections, terms and conditions are in the Contract.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Action…