Specifications.pdf
PDF 9 MB Posted
- Attached to
- Stabilize and Repair Blackstone House
- Solicitation number
- 140P6425B0012
About this file
This document is a comprehensive project specification for the Stabilize and Repair Blackstone House project at Hopewell Culture National Historic Park in Chillicothe, Ohio. The project involves exterior stabilization and repair of the Blackstone Main House, Smokehouse, and Milk House, with an estimated project magnitude between $500,000 and $1,000,000. The main scope of work for the Main House includes roof replacement, new gutters and downspouts, masonry repair to stone foundation and brick walls, wood repairs to trim and siding, window and door repairs, installation of new storm windows and door, and chimney repairs. For the Smokehouse and Milk House, the work encompasses roof repairs, new gutters and downspouts, masonry repairs, and new plywood door covers.
The solicitation (140P6425B0012) is a firm-fixed price contract set aside 100% for Total Small Businesses under NAICS Code 236118, with a size standard of $45.0 million. Construction Wage Rate Requirements for Ross County, OH will apply. Potential bidders must have a UEI number and be registered and active in the System for Award Management (SAM). The project is being issued by the Department of the Interior National Park Service Midwest Region, with the objective of addressing high-priority deficiencies that threaten the long-term preservation of the Blackstone homestead. Specific details about evaluation factors are to be found in the full solicitation document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P6425B0012_Amd_0003.pdf | ||
| Updated_Questions_and_Answers_0003.pdf | ||
| Sol_140P6425B0012_Amd_0002.pdf | ||
| Revised_Drawings_0002.pdf | ||
| Revised_Specifications_0002.pdf | ||
| Sol_140P6425B0012_Amd_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Sol_140P6425B0012.pdf | ||
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| Drawings.pdf | ||
| Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Submittal_List.xlsx | XLSX spreadsheet | |
| DOL_Wage_Determination.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIV. 1 V. 2025-02-03 01 10 00 - 1
HOCU - 239486
Hopewell Culture National Historical Park
Seip Earthworks Unit, Bainbridge, OH 45612
STABILIZE AND REPAIR BLACKSTONE HOUSE
PMIS 239486
Drawing No: 353-80057
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
04.15.2025
DIV. 1 V. 2025-02-03 01 10 00 - 2
This page intentionally left blank.
DIV. 1 V. 2025-02-03 01 10 00 - 3
TABLE OF CONTENTS
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01 10 00 Division 1 Short Form General Requirements 22
01 35 91 Historic Treatment Procedures 10
01 73 29 Cutting and Patching 4
01 74 19 Construction Waste Management and Disposal 8
01 78 39 Project Record Documents 4
DIVISION 2 - SITEWORK
02 41 19 Selective Demolition 6
02 42 96 Historic Removal and Dismantling 6
DIVISION 4 - MASONRY
04 01 20.63 Masonry Repair 8
04 03 10 Historic Masonry Cleaning 8
04 03 23 Historic Stone Unit Masonry Repointing 8
04 03 42 Historic Stone Masonry Repair 16
DIVISION 6 - WOOD AND PLASTICS
06 03 12 Historic Wood Repair 8
06 20 13 Exterior Finish Carpentry 6
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Reroofing 4
07 31 13 Asphalt Shingles 10
07 56 00 Fluid-Applied Roofing 8
07 62 00 Sheet Metal Flashing and Trim 10
07 71 00 Roof Specialties 6
07 92 00 Joint Sealants 8
DIVISION 8 – DOORS AND WINDOWS
08 03 52 Historic Treatment of Wood Windows 12
08 42 13 Aluminum-Framed Storm Door 4
08 56 19 Custom Aluminum Storm Windows 4
DIVISION 9 - FINISHES
09 91 13 Exterior Painting 8
APPENDICES
Appendix A: Geotechnical Report
Appendix B: Hot Work Policy
DIV. 1 V. 2025-02-03 01 10 00 - 4
DRAWINGS
G001 COVER
G002 SITE PLAN
ARCHITECTURAL: BLACKSTONE HOUSE
AX103 DEMOLITION ROOF PLAN
AX200 DEMOLITION ELEVATIONS
AX201 DEMOLITION ELEVATIONS
A005 WINDOWS AND DOORS TREATMENT
A101 TREATMENT FIRST FLOOR PLAN
A103 TREATMENT ROOF PLAN
A104 ROOF DETAILS – DORMERS
A105 ROOF DETAILS – CHIMNEYS
A200 TREATMENT ELEVATION NORTH
A201 TREATMENT ELEVATION EAST
A202 TREATMENT ELEVATION SOUTH
A203 TREATMENT ELEVATION WEST
ARCHITECTURAL: MILK HOUSE
A400 MILK HOUSE TREATMENT
ARCHITECTURAL: SMOKEHOUSE
A500 SMOKEHOUSE TREATMENT
STRUCTURAL
S101 STRUCTURAL FRAMING PLANS
S501 TYPICAL DETAILS
SECTION 01 10 00
DIV. 1 V. 2025-02-03 01 10 00 - 5
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The circa 1857 Blackstone House is a one and one-half story structure with an L-shaped plan. Despite later modifications to the rear porch, the Georgian Revival style house has retained many of its original features and materials. For more than 150 years, the house and outbuildings have been part of the cultural landscape of the Seip Earthworks. The Blackstone property is historically significant as an intact example of mid-nineteenth century residential and agricultural architecture.
The Seip Earthworks were built at a monumental scale by an indigenous tradition, presently referred to as the Hopewell Culture. The complex includes a large circle, just over 1500 feet in diameter, which intersects a smaller circle, approximately 750 feet across, and a square which intersects a smaller circle, approximately 750 feet across, and a square which is approximately
1080 feet across. The house was built on part of the large circle of the prehistoric earthworks. It is on the north edge of the large circle. The portion of the large circle occupied by the house is believed to be one of the least-disturbed sections of the earthworks at the site; it was described as the only unrestored or unexcavated portions of the earthworks system.
1.2 Work Covered by the Contract Documents:
A. Project Location: Hopewell Culture National Historical Park, Seip Earthworks Unit, 7058 US Highway 50, Bainbridge, OH 45612, Ross County.
1. Work consists of: The project is an exterior stabilization and repair project for the Blackstone Main House, Smokehouse, and Milk House. The objective is to address high-priority deficiencies that threaten the long-term preservation of the Blackstone homestead. The project scope of work for the Main House includes roof replacement, new gutters and downspouts, masonry repair to the stone foundation and brick walls, wood repairs to trim and siding, wood repairs to windows and doors, new storm windows and door, and chimney repairs. The project scope for the Smokehouse and Milk House includes roof repairs, new gutters and downspouts, masonry repairs, and new plywood door covers.
All work must meet the secretary of the interior's standards for the treatment of historic properties, specifically for rehabilitation. These standards can be found at www.nps.gov/tps/standards/rehabilitation.htm
B. All work will be performed under a single contract.
C. Period of performance: Work shall be completed within 180 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, http://www.nps.gov/tps/standards/rehabilitation.htm
DIV. 1 V. 2025-02-03 01 10 00 - 6
anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Preservation Act of 1974 (AHPA) and the
Archaeological Resource Protection Act (ARPA) provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the
Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting
Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure involved in the work of this Contract is located on earthworks that are part of the designated UNESCO World Heritage Site, and the Blackstone House is potentially eligible for the National Register of Historic Places. Every precaution shall be taken by the
Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the
Contractor’s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
i. Should Contractor’s operations or employees uncover or find any historic artifacts or archeological remains not specifically noted within the contract, the Contractor shall suspend operations at the site of discovery; notify the Contracting Officer immediately
DIV. 1 V. 2025-02-03 01 10 00 - 7
of the findings and continue operations in other areas outside a 50 foot radius of discovery.
C. Protection of Landscaping and Surrounding Structures: The Contractor and their subcontractor do not have permission to complete any ground disturbance on the site.
Ground disturbance at this project shall only be completed by National Park staff and must have oversite by a Park provided Archeologist. Coordinate schedules as required. The
Contractor shall take all necessary measures to provide protection for all trees, fencing, walks and other landscape features and surrounding structures near the work site as noted with the contract. Any such surrounding features damaged, scarred or broken as a result of the
Contractor’s operations at the site outside of agreed upon documented extents, shall be treated, repaired or replaced in kind to the satisfaction of the Contracting Officer at no additional expense to the Government.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: The existing electrical is running the building security system.
The COR approval is required for shutdowns. Shutdowns shall not exceed 2 to 3 hours.
Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the Contractor shall conduct their operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park
Service, and applicable park rules and regulations prescribed by the Park Superintendent. Click or tap here to enter text.
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
DIV. 1 V. 2025-02-03 01 10 00 - 8
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting
Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Reference drawings for allowable areas for parking. Entrances should never be blocked.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
7 a.m. to 4 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day
Martin Luther King, Jr’s Birthday
Washington’s Birthday
Memorial Day
Juneteenth National Independence Day
Independence Day
Labor Day
Columbus Day
Veterans Day
Thanksgiving Day
Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal
Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
DIV. 1 V. 2025-02-03 01 10 00 - 9
C. Do Not disturb site outside of noted disturbance area
i. Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Due to the sensitive site conditions, storing equipment near the earthworks is not allowed. Reference drawings for additional information. Contractor shall remediate soil compaction as directed to do so by the CO/COR without additional costs to the government.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
2. Water Service: Water from existing water system is not available.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. The available power is limited to a few existing outlets in the home that are 15 amp 120 v. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Waste Operation:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR. Restore damaged areas to original condition, DIV. 1 V. 2025-02-03 01 10 00 - 10 repairing or replacing damaged trees and plants, at no additional expense to the Government.
b. Provide temporary barriers to protect existing trees and plants and root zones.
c. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
d. Do not fasten ropes, cables, or guys to trees.
e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Provide temporary enclosures such as snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities. As referenced in the drawings, neither the fence nor any anchoring components can penetrate the ground due to the sensitive site conditions. The Contracting Officer must review the installation method prior to installation.
6. Site Enclosure Fence: Before construction operations begin, furnish, and install portable six (6) foot tall chain link fencing in a manner that will prevent people and animals from easily entering site and or storage areas except by entrance gates.
a. Extent of Fence: As required to enclose portion determined sufficient to accommodate construction operations and storage.
b. Locate vehicular gates to avoid interference with traffic on public thoroughfares.
c. Locate pedestrian entrance gates as required to provide controlled personnel entry.
d. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Provide CO and or COR with one set of keys or utilize double lock with NPS lock.
7. Hot Work Permit: Submit HW-1 Hot work permit form and receive approval from COR prior to Hot work activities commencing on site.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: The Blackstone House and Outbuildings were constructed on and adjacent to the Seip Earthworks that were built by an indigenous tradition, presently referred to as the Hopewell Culture. The portion of the large circle occupied by the house is believed to be one of the least-disturbed sections of the earthworks at the site; it was described as the only unrestored or unexcavated portions of the earthworks system. The Contractor and their subcontractor do not have permission to complete any ground disturbance on the site. Ground
DIV. 1 V. 2025-02-03 01 10 00 - 11
disturbance at this project shall only be completed by National Park staff and must have oversite by a Park provided Archeologist. Coordinate schedules as required.
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Partial Government Occupancy: Government will partially occupy buildings to monitor existing security system stored in the Main House during the entire contract period.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. Contractor shall be responsible for and protect the entire facility and construction site from notice to proceed through final acceptance.
2. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
DIV. 1 V. 2025-02-03 01 10 00 - 12
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government acceptance.
b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.
c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Document all roof work prior to installing the new roof cladding with photos covering enough overall field view to show location and then zoom in for details.
3. Maintain organized index for photos with date, description, etc.
4. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and
DIV. 1 V. 2025-02-03 01 10 00 - 13
submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
1. Do not exceed the following dB(A) limitations at 50 feet:
Sound Level in dB(A) Time Duration of Impact Noise
70 More than 12 minutes in any hour
80 More than 3 minutes in any hour
2. Maximum permissible construction equipment noise levels at 50 feet:
EARTHMOVING dB(A) MATERIALS HANDLING dB(A)
Compressors 75 Pneumatic Tools 80
Pumps 75 Saws 75
Generators 75 Vibrators 75
D. Ambient Noise:
1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:
a. Residential receiving area :
Daytime: 65 dB Nighttime: 45 dB
b. Commercial/Industrial receiving area:
Daytime: 67 dB Nighttime: 65 dB
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
DIV. 1 V. 2025-02-03 01 10 00 - 14
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS
Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National
Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample
JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by https://www.nps.gov/orgs/1671/do-business-with-us.htm
DIV. 1 V. 2025-02-03 01 10 00 - 15
all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA
29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park
Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
DIV. 1 V. 2025-02-03 01 10 00 - 16
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification
Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting
Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the
Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting
Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan (Reference Specification Section 017419).
9. Historic Preservation Treatment Plan Submitted to COR.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
DIV. 1 V. 2025-02-03 01 10 00 - 17
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to
Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
DIV. 1 V. 2025-02-03 01 10 00 - 18
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of
Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this
Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
DIV. 1 V. 2025-02-03 01 10 00 - 19
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting
Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting
Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
DIV. 1 V. 2025-02-03 01 10 00 - 20
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. 0001 – Roof Replacement
1. This item consists of full roof replacement of the Blackstone Main House, all new flashings, new gutter and downspouts, new chimney caps and partial removal of chimney cementious coating for proper flashing installation.
2. Payment will be made per the contract and percentage of completion level.
B. Contract Line-Item No. 0002 – Stone Foundation Repair and Repointing
1. This item consists of full repointing of all exposed mortar joints at the Main House. In the small area of already disturbed soils at the northeast corner, NPS staff will excavate this location and the Contractor is responsible for repairing/repointing all exposed foundation joints below grade. The Contractor may not alter soil around the foundation. Any site preparation for the foundation repair work (e.g. weed eating) must be completed by NPS staff and coordinated with the Contracting Officer.
C. Contract Line-Item No. 0003 – Masonry Stabilization Repairs for the Blackstone House, Smokehouse, and Milk House
1. This item consists of masonry repairs to the Blackstone Main House, Smokehouse and Milk House. The scope of work includes patching to cracked bricks, replacement of unsound masonry, repointing open mortar joints, reconstructing unstable masonry. This CLIN requires the removal of window 204 for masonry repair. The repair and reinstallation of the window are included in this scope of work.
D. Contract Line-Item No. 0004 – Woodwork Repairs at the exterior of Blackstone Main House
1. This item consists of woodwork repairs to the exterior of the Blackstone Main House including fascia board, barge board, and dormer work.
2. Payment will be made per the contract and percentage of completion level.
E. Contract Line-Item No. 0005 – Window and Door Protection
1. This item consists of installation of new aluminum storm windows, new front storefront door, and painting the exterior of all windows and doors.
DIV. 1 V. 2025-02-03 01 10 00 - 21
F. Contract Line-Item No. 0006 – Sealing Outbuilding Roofs
1. This item consists of minor areas of metal roof patching and then sealing the existing roofs.
2. Payment will be made per the contract and percentage of completion level.
G. Contract Line-Item No. 0007: Additive 1 – Main House Chimney Repairs
1. This item consists of cementious coating removal from chimneys at Blackstone Main House and repairs to masonry.
2. Payment will be made per the contract and percentage of completion level.
H. Contract Line-Item No. 0008: Additive 2 – Smokehouse and Milk House 100% Repairs to Masonry
1. This item consists of 100% repointing of mortar joints on the interior and exterior of both the Smokehouse and Milk House. This CLIN also includes replacement of brick that contain more than 40% the exterior face delaminated and patching of bricks with less than 40% of the face delaminated. This excludes those areas of masonry that are repaired under
CLIN 3.
2. Payment will be made per the contract and percentage of completion level.
I. Contract Line-Item No. 0009: Additive 3 – Main House Front Door Repairs
1. This item consists of minor repairs to the existing front door surround and painting.
2. Payment will be made per the contract and percentage of completion level.
J. Contract Line-Item No. 00010: Additive 4 – Main House Wood Window Repairs
1. This item consists of repairs to all windows (except window 204, which is being repaired in CLIN 3). The scope includes reglazing, glazing replacement, wood replacement, and painting.
END OF SECTION
DIV. 1 V. 2025-02-03 01 10 00 - 22
HISTORIC TREATMENT PROCEDURES 01 35 91 - 1
SECTION 01 35 91 - HISTORIC TREATMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section.
1.2 SUMMARY
A. Section includes general protection and treatment procedures for historic spaces, building elements, and surfaces in Project.
B. Great care shall be taken to preserve and maintain all existing historic materials and finishes. It should be assumed that all masonry, plaster, windows, doors, millwork, painting, fixtures, and other finishes are historic or important to presenting the historic story of the building and are to be protected throughout construction.
C. All work must meet the Secretary of the Interior’s Standards for the Treatment of Historic Properties. The standards may be found here https://www.nps.gov/tps/standards.htm
D. The removal of historic materials or alteration of historic finishes or features and spaces is not permitted. Deteriorated historic features shall be preserved or repaired rather than replaced.
Where the severity of deterioration requires replacement of a distinctive feature, the new feature shall match the old in design, color, texture, dimension, construction and installation methodology, and other visual qualities and, where possible, materials. Replacement of deteriorated features must be approved by the Contracting Officer Representative.
E. Related Requirements:
1. Section 024296 "Historic Removal and Dismantling" for selective demolition for historic spaces.
1.3 DEFINITIONS
A. Consolidate: To strengthen loose or deteriorated materials in place.
B. Design Reference Sample: A sample that represents Contracting Officer Representative’s selection of work to be matched; it may be existing work or work specially produced for Project.
C. Dismantle: To disassemble or detach a historic item from a surface, or a nonhistoric item from a historic surface, using gentle methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
D. Historic: Spaces, areas, rooms, surfaces, materials, finishes, features, and overall appearance that are important to the successful preservation, rehabilitation, restoration, and reconstruction as determined by Contracting Officer Representative.
https://www.nps.gov/tps/standards.htm
HISTORIC TREATMENT PROCEDURES 01 35 91 - 2
E. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, dimension, installation methodology, or finish; as approved by Contracting Officer Representative.
F. Material in Kind: Material that closely…